using cmar approach and envision for hardeeville wrf ......•serves two counties • public,...
TRANSCRIPT
© 2014 HDR, Inc., all rights reserved.
Designing Collaboratively Using CMAR Approach and Envision for Hardeeville WRF Upgrade and Expansion
Christopher Crotwell, P.E.
Envision
Change of Plans
Overview
Pre-Construction Coordination
BIM Models
Overview
• Serves two counties• Public, non-taxing
• Water accts: 53,000• Sewer accts: 35,000
• Hardeeville: 1,656 accts• 20 mgd of drinking water• Treats 9 mgd of wastewater• BJWSA acquired the City of
Hardeeville’s water and sewer utility in 2001
Hardeeville
Beaufort-Jasper Water & Sewer Authority (BJWSA)
0 2 4 6 8
Point South
Palm Key
Palmetto Bluff
St. Helena
Laurel Bay
Hardeeville
Cherry Point
Port Royal
BJWSA has 8 wastewater treatment plants
• 1 MGD → 2.7 MGD (4 MGD future)• Mainly greenfield expansion• Project includes:
• Headworks• Flow EQ• Oxidation ditches with anoxic zones• Secondary clarifiers• Cloth disk filters (planned)• Chlorine contact chambers• Sludge holding• Operations building
Hardeeville WRF is expanding for growth
• CMAR contract• SRF funding
• Applying for Green Funding• Envision certification
The project has unique features
• Stacked-tray grit removal system• Large bubble mixing system• Cloth disk filters • Multi-purpose ops building
The project has unique designs
• SRF funding can be used on Alternate Delivery projects in SC• CMAR can self-perform in SC (unlike NC)• Working closely with DHEC
• DHEC attended all workshops• DHEC assisted with approval schedule
• Project can be permitted at GMP stage• Green Funding: energy reduction → lower interest rate
State Revolving Fund will be used
• Selected engineer first via RFQ / RFP• Prepared RFQ for CMAR
• Shortlisted 3 CMARs for proposals, interviews. Evaluated:• Qualifications• Approach• Ability to meet SRF requirements• References• Price proposal (% fee, fixed cost GCs, pre-construction)• Interview
CMAR was selected via detailed process
Pre-Construction Coordination
• Online meetings• BJWSA, HDR, CMAR
• Reviewed design status, questions, latest BIM models
Bi-weekly progress meetings were held
Agenda Project: Hardeeville WRF Expansion (242104)
Subject: Progress Meeting
Date: Friday, January 23, 2015
Location: BJWSA Administrative Building (6 Snake Road, Okatie, SC 29909)
Attendees: David Christopher Christopher Crotwell Tracy Lewis
Review of Site Layout Options
o Switching location of EQ/headworks with aeration location. Benefits:
Shorter pipe lengths
Simpler piping with less doubling back
o Need for sludge drying beds
o Proximity of dewatering/chemicals to road
o Buffer
o RAS/WAS pump stations
o Need for intermediate pumping (hydraulic profile)
o Room for primary clarifiers/anaerobic basins
o Aeration basin configuration: U-shape vs traditional (CMAR decide?)
EQ basin use plan, lining
RAS/WAS pump layout
Filter layout
EcoVerde – how operating, anticipated hydrogen sulfide concentrations
o EQ air changes
Existing I/C and SCADA, what they will be looking for in the new system
• Held at CMAR kick-off, 30%, 60% design• Reviewed VE and constructability comments from CMAR• Reviewed BJWSA comments• Agreed upon changes for next steps in design• Used SharePoint site to share documents
Multiple workshops were held
• Provided at 30% and 60%• Initial VE → $4M reduction
• Eliminated dewatering building• Modified site layout• Changed coatings• Modified drainage• Eliminated one mechanical screen
CMAR provided value engineering comments
Ref.No.
Reportor
SpecSection
ReportPage or
SpecPara. No.
Dwg DwgSet Comment Reviewer Discipline
HDRResponse
ByHDR Response
220 17Y - 60% Can we show the Non Potable Water System on the P&ID's? RLM Inst Crotwell
We do show NPW connections to certain equipment but do not typically show the whole system
221 17Y-03 60% 12 Air Zones are show should isolation valves be provide per zone? RLM Process Crotwell No isolation valves required
between VCP and manifold
222 17Y-07 60%
At Zone 4 it shows 2 lines coming off going to the Clarifier Splitter Box. The yard pipe drawing shows one pipe and should there be yard valves installed?
RLM Inst CrotwellYard piping dwg is correct, two parallel pipes go from Aeration to clarifier splitter box
223 17Y-07 60%
On P&ID 17Y-07 the compressed air system shows a valve in zone 3 and on 17Y-08 there is no valve. Which one is correct? Should each header have a isolation valve?
RLM Process Crotwell Motorized valve to zone 3 should be deleted
224 17Y-08 60%
At Zone 4 it shows 2 lines coming off going to the Clarifier Splitter Box. The yard pipe drawing shows one pipe and should there be yard valves installed?
RLM Inst Crotwell
17Y-08 is not shown correctly with regards to this piping; we will update for Final Design; 04D and yard piping dwgs are correct
225 17Y-09 60% The SI (Secondary Influent) is not show on the P&IDs RLM Inst Crotwell Not sure what this means?
226 17Y-09 60%
Should the Secondary Clarifiers have Non Potable Water (NPW)? Drawing 01C-52 yard pipe shows it going to the area.
RLM Inst Crotwell Yes; we will provide more direction
227 17Y-09 60%
Should the Secondary Clarifier Splitter Box have Non Potable Water (NPW) for wash-down? Drawing 01C-52 yard pipe shows it going to the area.
RLM Inst Crotwell Yes; we will provide more direction
228 17Y-09 60%
The P&ID's show a ML assuming Mix Liquor. This is not called out in Specification 400500-14 nor is it shown on the yard pipe drawings.
RLM Inst Crotwell It should be SI for Secondary Influent
229 17Y-09 60%
Two lines are entering the Clarifier Splitter Box and show coming from 17Y-07 should one be from 17Y-07 and 17Y-08?
RLM Inst Crotwell Refer to yard piping
• Comment logs provided at 30% and 60% design• Items included:
• Structural comments to simplify number of joints, pours• Combine filter and chlorine contact chamber structures• Minimize tie-ins and construction on existing site
CMAR provided constructability reviews
BIM Models
• For design: Revit• Cost estimate take-offs• Clash detection• Biweekly meeting model review
• For sharing: Navisworks
Project was modeled in BIM
Envision Certification
• Managed by Institute for Sustainable Infrastructure (ISI)
• Facilitates and measures project sustainability during design, construction
• Recognizes transformational, collaborative approaches to assess sustainability over a project’s life cycle
• Evaluates through 60 sustainability credits, divided into five sections
Envision® is a framework
• Current U.S. infrastructure rating systems are sector-specific• No U.S. system covers all aspects of infrastructure
Envision® was developed to fill a gap
Verification is based on 90% design
Note:ISI verifies Envision projects.USGBC certifies LEED projects.
Owner, Engineer, CMAR completed initial assessment
33% of total applicable points =
Silver
• LD1.1 – Provide effective leadership and commitment
BJWSA has led the way in sustainability
• QL1.2 – Stimulate sustainable growth and development• LD2.2 – Improve infrastructure integration• RA3.1 – Protect fresh water availability
Design meets reclaimed water standards
1,149
676
253272 225113
0
200
400
600
800
1,000
1,200
1,400
UOD TSS BOD
lb/d
Permit Requirement Design Basis
30
118
10
51
0
5
10
15
20
25
30
35
TSS BOD Ammonia-Nm
g/L
Permit Requirement Design Basis
• RA2.1 – Reduce energy consumption• QL2.3 – Minimize light pollution• CR2.2 – Avoid traps and vulnerabilities
New equipment is energy-efficient
Mixers Lighting
• Could be first Envision-certified wastewater project in SCSubmitting for verification soon
Change of Plans
• CMAR coordinated bidding tasks• Relayed questions to Engineer• Developed addenda for bidders• Split project into packages for subcontractor bidding
• GMP came in significantly above 30% estimate• Difficulty getting subs to bid• Escalating labor prices• Recent flooding concern for site work and dewatering
CMAR prepared a guaranteed max price
• Ended CMAR contract after pre-construction• Project now being bid openly
• Hope to get more bidders, competitive pricing• Can defend to Board that most competitive pricing is obtained• Some design changes incorporated
Owner decided to change the contract
• Aeration basins → ox ditches• Raised hydraulic grade line by 5 ft• Abandoned existing clarifier,
installing 2 larger clarifiers• Deferring filter installation• Other miscellaneous changes
Design and scope have changed
• Registration: $1,000• Verification:
Fees depend on project size, ISI membership
Project Size ($) Non-Member ISI Member
≤ 2 M $ 3,000 $ 2,400
2 - 5 M $ 8,500 $ 7,000
5 - 25 M $17,000 $14,000
25 - 100 M $25,000 $21,000
100 - 250 M $33,000 $28,000
> 250 M Contact ISI for large or multi-phase projects