2014 UTPOverview and Update ProcessJessica Butler, P.E.April 5, 2013
Agenda
2
2014 UTP: Overview & Update Process
Describe 2014 UTP Update Resources & Toolkit
2014 UTP Programming Guidance
Project Ranking Tool
##
##
##
##
Summary & Action Items##
2014 UTP UPDATE OVERVIEW
3
Unified Transportation Program (UTP)
4
UTP Annual Update Cycle
5
TPP Provides Category Allocations
to Districts/Local Partners
Districts/Local Partners Program
Known Projects for All UTP Years by
Category
Review/ Comment
Period
Adjustments
UTP Approved by
TTC (typically in
August)
2013 UTP 2014 UTP
Spring – Summer 2013
2014 UTP Update: Big Picture
6
LegacySystems
New Generation
Tools & Approaches
We are here for the 2014 UTP Update
TxDOT Project Management & Programming
2014 UTP – How is It Different from 2013?
MAP-21 Funding Assumptions Listing of Known Projects in all Categories
– Except Category 1 Preventive Maintenance & Rehab Listing Major Transportation projects Ability to program 10 Years + 11PA Reflect Total Project Cost Project Ranking Projects listed only once Organized by District vs. Category
7
MAP-21 Funding Assumptions
8
MAP-21 Funding levels projected through FY 2014 Projection of MAP-21 beyond FY 2014 used to develop 11PA levels
MAP-21 SAFETEA-LU
National Highway Performance Program (NHPP) NHS, IM, & Bridge (portion)
Surface Transportation Program (STP) STP & Bridge (portion)
Congestion Mitigation & Air Quality Improvement Program (CMAQ)
CMAQ
Highway Safety Improvement Program (HSIP) HSIP (incl. High Risk Rural Roads)
Railway-Highway Grade Crossing(takedown from HSIP)
Railway Highway Grade Crossing
Transportation Alternatives TE, Recreational Trails, and Safe Routes to School
Listing of Known Projects Across All Ten Years
Excludes Category 1 Improved information on planned projects Increased flexibility to program all 10 years + 11PA
9
Unified Transportation Planning Program
(Years 1-10)
Statewide Transportation Improvement Program
(Years 1-4)
TxDOT 2-year Letting Schedule
• TxDOT commitment to explore these projects further.
• Projects represent joint commitment by TxDOTand local partners.
• Projects are likely to occur, barring unforeseen complication
Total Project Cost
Total Project Cost – the total cost of all phases associated with a project CSJ. Note: for the UTP, this is only future expenditures, not past expenditures.
Preliminary Engineering – Project development activities during which basic planning objectives are translated into specific, well-defined engineering criteria that transition a project into the final design process
ROW Purchase – Cost of any real property required to construct or implement a project
Construction Cost – Cost of the actual construction (labor and materials) Construction Engineering – Cost of the interpretation of plans and specifications
and formulation of engineering decisions Contingencies – Estimated amount of any unforeseen costs associated with a
project Indirect Cost – Expenses the provider or contractor incurs for operating its
business as a whole. Indirect cost rates for providers selected to enter into an engineering contract are obtainable from TxDOT’s Audit Office.
10
Project Ranking
New requirement under Texas Administrative Code [43 TAC §16.105] For 2014 UTP
– FOR INFORMATIONAL PURPOSES ONLY– Referenced as a sorting tool in the document
After 2014 UTP approval, TxDOT may assess the project ranking process
11
2014 UTP Development Resources
UTP Development Web Page – General Info 2014 UTP Development Timeline Draft Preliminary Funding Levels Instructions for Programming Other Helpful LinksUTP Programming Toolkit District/Division-Specific Project Programming Tool (Excel) Project Ranking Tool (SharePoint)Other Resources TxDOT UTP Staff TPP MPO Liaison Contact Info
12
2014 UTPDEVELOPMENT WEB PAGE
13
UTP Development Web Page – General Info
http://www.txdot.gov/inside-txdot/division/transportation-planning/utp-development.html
UTP 2014 Development Timeline
15
August 2013
Months April May June
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13
TPP Provides Preliminary Category Allocations to Districts/Local Partners
Districts/Local Partners Program Known Projects for All UTP Years by Category
Districts/Local Partners Rank Known Projects for All UTP Years
DCIS Fields Open
QCQA of Project Data
TxDOT Reports Preliminary Funding Levels to Commission
Project Selection Process Public Involvement & Approval
FINAL DRAFT 2014 UTP Public Involvement
Final 2014 UTP Approval by Commission
Milestone TxDOT/Local Partner Activity
August 2013
July 2013
Public Involvement
Preliminary Funding Levels
16
Funding Category DRAFT 2014 UTP Funding1 - Preventative Maintenance and Rehabilitation 11,555,470,000
2 - Metro and Urban Area Corridor Projects 1,716,870,000
3 - Non-Traditional Funded Transportation Projects 6,840,130,000
4 - Statewide Connectivity Corridor Projects 0
5 - Congestion Mitigation and Air Quality Improvement 1,521,430,000
6 - Structures 2,500,000,000
7 - Metropolitan Mobility/Rehabilitation 2,835,860,000
8 - Safety 1,714,940,000
9 - Transportation Enhancements 567,030,000
10 - Supplemental Transportation Projects 747,220,000
11 - District Discretionary 624,560,000
12 - Strategic Priority 2,394,820,000
TOTAL UTP FUNDING: CATEGORIES 1-12 33,018,330,000Notes:
Category 8 total includes Prop 14 Safety Bond
Category 10 total includes Federal Earmark Match
Programming General Instructions
17
PROGRAMMINGInstructions by Category
2014 UTPPROGRAMMING TOOLKIT
18
UTP Programming ToolkitSharePoint site
19
Project Programming Toolkit Instructions
20
Project ProgrammingTOOLKIT
Instructions
PROJECT PROGRAMMING TEMPLATE
21
Project Programming
Data exported from DCIS All projects programmed in DCIS through 2023 were
included Program up to your allocations in Categories
– 10 years of work programs provided by FIN– 11PA for programming in addition to the Category allocations– Account for Inflation– Work with respective Divisions before moving Cat 6 or 8 projects – Program the projects known
If fully programmed and additional capacity in 11PA is needed, can request on project specific basis Move out projects that do not fit within 10 year plan or 11PA
allocation
22
Project Programming Template (in Toolkit)
23
Data is organized into folders accessed through SharePoint Each District/Division has a separate folder Instructions posted online Download the files from SharePoint to work on Upload back to SharePoint Use the tabs to check your work as you go Suggest ranking after your finalize your project lists After May 10th we will extract the files from SharePoint Will have QCQA time to make adjustments
Project Programming Template Instructions
24
TOOLKIT:Project Programming
TemplateInstructions
PROJECT RANKING TOOL
25
Project Ranking – A Legislative Requirement
43 TAC §16.105 amendments require TxDOT to develop criteria to rank the priority of each project listed in the UTP based on the transportation needs for the state and department goals. Projects must be ranked as Tier 1, 2 or 3 All major transportation projects will be Tier 1 and designated as highest
priority
Survey went out soliciting feedback on February 1, 2013. 39 responses total (13 MPO/20 District/6 Division) Ranking is not a replacement for current project selection processes The most important criteria for most categories were project need,
funding availability, meeting TxDOT’s goals, project readiness/phase of project, and addressing time‐sensitive critical needs.
26
Project Ranking Tool - Scoring Criteria
Project Need– Safety – Congestion – Connect Texas Communities – Become Best-In-Class State Agency
Funding Availability Project Readiness/Phase of Project
27
2014 UTP Ranking Process & Tool
28
Is Project Assigned a
Letting Date in the 2-Year
TxDOT Letting Schedule?
Rank =Tier 1
Yes
Has Project Been Identified
as a Major Transportation
Project?
Rank =Tier 1
Yes
No
2-Year Letting Schedule
Major Transportation
Project
No
Project Ranking Tool
Start Here
Project Need
Funding Availability
Project Readiness/
Phase
Score* (S1)
Score(S2)
Score(S3)
WSi = Total Score
Threshold Rank
> 75 Tier 151 - 75 Tier 2
< 50 Tier 3
Project Ranking Tool (in Toolkit)
29
Project Ranking Tool Instructions
30
TOOLKIT:Project Ranking
ToolInstructions
2014 UTP UPDATE SUMMARY
31
2014 UTP Programming Resources
UTP Development Web Page – General Info 2014 UTP Development Timeline Draft Preliminary Funding Levels Instructions for Programming Other Helpful LinksUTP Programming Toolkit District/Division-Specific Project Programming Tool (Excel) Project Ranking Tool (SharePoint)Other Resources TxDOT UTP Staff TPP MPO Liaison Contact Info
32
UTP 2014 Development: Action Items
33
August 2013
Months April May June
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13
TPP Provides Preliminary Category Allocations to Districts/Local Partners
Districts/Local Partners Program Known Projects for All UTP Years by Category
Districts/Local Partners Rank Known Projects for All UTP Years
DCIS Fields Open
QCQA of Project Data
TxDOT Reports Preliminary Funding Levels to Commission
Project Selection Process Public Involvement & Approval
FINAL DRAFT 2014 UTP Public Involvement
Final 2014 UTP Approval by Commission
Milestone TxDOT/Local Partner Activity
July 2013
Public Involvement
August 2013
34