Department of Watershed Management CIP Program
Valley View Water Main Replacement
Community Meeting
Scott Towler, P.E., DWM Director
Margaret Tanner, P.E., DWM Deputy Director
Tuesday, October 17, 2017 – 6:00-7:30 p.m.
October 2017 1
• Welcome
• Introductions
• Project Overview
• Contact Info
• Questions
Department of Watershed Management CIP Program
Agenda
Installation of nearly 5,000 linear feet of 8-inch pipe in the Valley View area of Dunwoody
• Part of the DeKalb County CIP project list
• Improved water service to the Valley View community
• Replace undersized lines and improve fire service
• Eliminate water main breaks
• Reduce loss of water pressure
Department of Watershed Management CIP Program
Project Rationale
PROJECT SCOPE
• Water main replacement on:o Valley View Road – 3,557 feet
o Valley View Court – 1,426 feet
• Installation of new water meters
• Installation of new hydrants
• Restoration of lawns, driveways and pavements disturbed as a result of the project
Department of Watershed Management CIP Program
Project Overview
Department of Watershed Management CIP Program
Project Overview
Department of Watershed Management CIP Program
Project Overview
Department of Watershed Management CIP Program
Project Overview
Preliminary Project Schedule:
• Late October/early November – Start of construction, site mobilization, traffic control implementation
• Early November to February/March – Water main, meter and hydrant installation
o Pressure testing
o Bacterial testing and chlorination
o New water main service connections (water shut-offs)
o Driveway restoration
• February/March to April – Lawn restoration (seeding/sod installation and watering)
Department of Watershed Management CIP Program
Project Overview
Potential Project Impacts:
• Temporary, single-lane closures; flaggers to direct traffic through construction zone
• Lawn excavations within county right-of-way to install new pipe
• Some instances of restricted driveway access as pipe is installed; prior notice to affected properties
• Temporary water shut-offs as new pipe is connected for service; prior notice to affected properties
• Possible delays due to weather
Department of Watershed Management CIP Program
Community Outreach
10/18/2017 9
• Community Meetings
• Project Bulletins and Flyers
• Email Updates
• Door Hangers
• Social Media –
HOW WE WILL KEEP YOU INFORMED
Department of Watershed Management CIP Program
Community Outreach
10/18/2017 10
• Website –www.dekalbwatershed.com
o Project Page –https://www.dekalbcountyga.gov/watershed-management/valley-view-water-main-replacement
• Contact Us:
o Email: [email protected]
o Phone: 1-800-986-1108
HOW WE WILL KEEP YOU INFORMED
Questions?
10/18/2017 11
REMINDER:Sign-up to receive project updates and
alerts via email and text!
THANK YOU!