value and cost of distributed generation acc staff workshop #1 – may 7, 2014 docket no....
TRANSCRIPT
Value and Cost of Distributed GenerationACC Staff Workshop #1 – May 7, 2014Docket No. E-00000J-14-0023
DG Valuation ─ Lessons from the APS Distributed Energy and Net Metering Technical Conference
Bob DavisPrincipal and Executive ConsultantnFront Consulting LLC
33
APS Distributed Energy and Net Metering Technical Conference
ACC decision 73636 ordered that “APS shall conduct a multi-session technical conference to evaluate the costs and benefits of Distributed Renewable Energy and Net Metering” Six workshops and forums held February 21, 2013 through
May 28, 2013 Over 180 registered stakeholders and presenters included
representatives from local and national solar industries, environmental groups, consumer groups, regulatory interests, and electric utilities
Presentations provided by content experts enlisted by the stakeholders, APS and the conference Facilitator
Cost-benefit matrix developed summarizing stakeholder perspectives on costs and benefits of DE
Facilitator’s Report issued July 8, 2013
44
APS Distributed Energy and Net Metering Technical Conference
Major topics covered: DE and net metering activities and regulatory trends
throughout the U.S. Concepts of electric utility retail ratemaking Review of APS rates and potential cost shifting caused
by solar DE Electric utility avoided cost concepts and APS
planning for solar DE Solar DE evaluation models and approaches Stakeholder studies of costs and benefits of net
metering and DE costs and benefits for APS SAIC update of the 2009 R. W. Beck Study of DE value
55
DE Cost and Benefit CategoriesStakeholder Agreement
Stakeholders, including APS, reached agreement on categories of costs and benefits that should be considered when evaluating DE Avoided utility costs (benefits):
Fuel and purchased power Variable operations and maintenance Environmental compliance Avoided generation capacity investment Fixed operation and maintenance costs for avoided generation
capacity Electric system losses Avoided transmission and distribution investments
Incurred utility costs: Utility integration costs Program administration costs
66
DE Cost and Benefit CategoriesStakeholder Disagreement
Fuel hedging Market price mitigation Cost of ancillary services Value of ancillary services
provided by DE RES avoided costs Non-compliance
environmental impacts Decommissioning costs Ratepayer cross-
subsidization Utility systems costs
Grid security Marginal value of reduced
water consumption Health effects Economic development
and jobs Civic engagement /
conservation awareness Energy subsidies Technology synergies Ratepayer / consumer
interest
Stakeholders could not agree that the following should be included when computing utility benefits of DE
77
DE Costs and Benefits – Methodologies
Stakeholders generally did not reach agreement on methodologies for computing costs and benefits (even when agreeing on categories) Computation of avoided generation capital and fixed
O&M costs Generic or avoided planned facilities Incremental capacity reduction or size of avoided facilities Timing (current year or date of avoided facilities)
Computation of transmission and distribution avoided facilities/costs Average embedded costs/rates or avoided planned facilities Size and timing (similar to generation avoided costs) System-wide assessment or analysis of specific circuits
88
DE Costs and Benefits – Methodologies (cont.)
Stakeholders generally did not reach agreement on methodologies for computing costs and benefits (even when agreeing on categories) Avoided energy costs (simulated dispatch or market price) Electric system losses (average or marginal losses) Integration costs / ancillary services:
Incremental operating costs to respond to intermittent solar DE production
Value of voltage control from solar DE Treatment of avoided costs in current APS rates:
APS rates set through embedded not marginal cost treatment Life-cycle benefits produced by DE installations are not
permitted in rate setting
1010
Comparison of Value of Solar DE Presented at APS DE/NEM Technical Conference
Value of Solar for APS System – Expected / Base Case (¢/kWh)
Cost-Benefit CategorySAIC Update Nominal $ Crossborder
Study2014 $2020 2025
Avoided Fuel, Var. O&M, Purchase Power 3.6 4.7 7.1
Avoided Emission Costs 0.8 1.2 0.1Avoided Gen. Capacity, Fixed O&M, NG Trans. 2.8 2.3 8.3
Avoided Transmission Costs 0.0 0.0 2.1
Avoided Distribution Costs 0.0 0.0 0.2
Renewable Benefits n/a n/a 4.5
Integration Cost n/a n/a - 0.2
Total Value of Solar DE 7.2 8.2 22.1
1111
Comparison of Value of Solar DE (cont.)Differences in Assumptions and Methodology
Avoided Cost Crossborder Study SAIC Update
All Categories
Projected 20 year levelized cost Single year avoided cost
Generation Energy Costs
Market energy cost (blend of CT and CC energy costs) APS generation simulation
Emission Costs Does not include CO2 costs Includes avoided CO2 costs
Generation Capacity Costs
ELCC at 50%, 15% capacity reserves,avoided ancillary services
ELCC at 30% (2020) and 21% (2025), includes capacity reserves
Transmission Facility Cost
Assumes marginal cost of transmission all years, 50% ELCC
Small deferred expansion project in 2025
Distribution Facility Cost
Assumes marginal cost of distribution all years, 50% ELCC
No deferred expansion projects
Renewable Benefits
Includes incremental value of RPS, portfolio diversity, grid security, etc.
No incremental RPS benefits
1212
Technical Modeling Issues
Effective Load Carrying Capability (ELCC) is expected to decline with additional DE/DG installations ELCC is specific to the DE/DG technology being added Capacity reserves should be added only if ELCC approach
does not already encompass impact on reserves Avoided energy cost can be less than the average
operating cost of CT and CC resources Other lower-cost resources can contribute to a utility’s
marginal costs (e.g., coal generation, purchased power) Marginal operating costs of generating units are less than
average operating costs Significant DE/DG implementations can introduce
inefficiencies in utility operations
1313
Technical Modeling Issues (cont.)
Avoided transmission and distribution costs require detailed study Specific expansion/upgrade projects should be considered
(do projects exist that can be deferred or avoided) T&D facility costs should be segregated costs that can be
avoided (e.g., wires) and those that cannot (e.g., metering)
ELCC or Peak Load Reduction (PLR) for T&D should be evaluated by feeder or line
System reliability and security must be considered (the impact of DE/DG intermittency at a feeder level should be evaluated)
Voltage control and other distributed grid benefits of DE/DG should be investigated
2323
ELCC Decreases with Increasing Solar DE Penetration
0 500 1000 1500 2000 2500 30000%
10%
20%
30%
40%
50%
60%
Installed Solar DE
ELCC
Expected Penetrati
on in 2025
2424
Rate Design Considerations
One size does not fit all Costs and benefits of DE/DG will vary by technology and application Rate design, whether NEM or “value of” tariffs, need to
accommodate different DE/DG technologies DE/DG impacts some areas of utility operations and costs
more than others Rates (or offsets) should be matched to the value received from
DE/DG Fixed and variable costs avoided through DE/DG are more readily
assigned through energy and demand rates Unbundled rates permit more direct assignment of DE/DG benefits
Incremental impacts of DE/DG may need to be considered Future DE/DG installations may reduce utility fixed costs less than
installations made today (due to lower ELCC) Rate design will need to consider whether to treat DE/DG customers
on an average or incremental basis