ve workshop final report

Upload: bocevski

Post on 07-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Ve Workshop Final Report

    1/133

    VALUE

    ENGINEERING

    WORKSHOP

    March 28-31, 2011

    WORKSHOP

    FINAL

    REPORT

    FOR THE

    SOUTHWESTERN

    ILLINOIS FLOOD

    PREVENTION

    DISTRICT COUNCIL

    Submitted By: Campion Group, LLC

    In Association With: Thouvenot, Wade & Moerchen, Inc.

    and Shively Geotechnical, a Division of

    Environmental Operations, Inc.

  • 8/6/2019 Ve Workshop Final Report

    2/133

  • 8/6/2019 Ve Workshop Final Report

    3/133

    Doing the right things, not just doing things right!

    17 May 2011

    Mr. Les StermanChief Supervisor of Construction and the Works

    Southwestern Illinois Flood Prevention District Council

    104 United Drive

    Collinsville, Illinois 62234

    Subject: Value Engineering Workshop Report - Final

    Reference: Levee System Design and Construction

    Dear Mr. Sterman:

    I am pleased to submit the final report summarizing the Value Engineering Workshop held

    March 28-31, 2011. An electronic version of this report will also be provided.

    The workshop went very well, I believe, and the method used proved to be most productive as it

    engaged the designer not only at the opening and exit, but also during the actual value

    engineering activities. Furthermore, using the last day to seek closure on each and every item

    paid dividends and was only possible by having collaborated with the designer through written

    comments and questions to them during the workshop, and their quick responses.

    We will, with your approval, make this report available to the designer in electronic form. Please

    advise me whatever number of hard copies, if any, you may desire.

    Sincerely,

    Douglas R. Campion

    Owner/Principal

    Enclosure

    P.O. Box 31515

    St. Louis, Missouri 63131

    Phone: 314.783.7233

    E-mail:

    drca mp ion@yahoo .com

    C a m p i o n G r o u p , L L C

  • 8/6/2019 Ve Workshop Final Report

    4/133

  • 8/6/2019 Ve Workshop Final Report

    5/133

    Value Engineering Workshop Report Page 1 of 14

    C a m p i o n G r o u p , L L C

    REPORT OF THE

    VALUE ENGINEERING WORKSHOP

    Southwestern Illinois Flood Prevention District Levees

    March 28-31, 2011

    TABLE OF CONTENTS

    TITLE PAGE

    EXECUTIVE SUMMARY 2

    Findings & RecommendationsValue Engineering Team

    PROJECT DESCRIPTION & BACKGROUND 5

    VALUE ENGINEERING OBJECTIVES 7

    VALUE ENGINEERING PROCESS 7

    Information Design Documents

    Information Designer Presentation

    VE Review Team Developed Comments & Questions

    WRAP UP AND NEXT STEPS 13

    APPENDICES

    1. Workshop Agenda & Attendance sheets2. Plan sheets for each of the four principal levee distracts and

    Profiles illustrating basic features under study

    3. Preliminary cost estimate4. AMEC value engineering/design optimization items5. AMEC project overview and status presentation6. VE Team Written Comments/Questions and AMEC Responses

  • 8/6/2019 Ve Workshop Final Report

    6/133

    Value Engineering Workshop Report Page 2 of 14C a m p i o n G r o u p , L L C

    EXECUTIVE SUMMARY

    Findings & Recommendations

    The Value Engineering (VE) Team was pleased with the cooperation and collaborative and professional

    conduct exhibited by the designer, AMEC Earth & Environmental, Inc. (AMEC) through the course of theworkshop. The tone was very collegial and with the best interests of the project at the forefront.

    This report, inclusive of its Appendices, provides details on what the objectives were for the workshop

    and the findings and recommendations developed for consideration now or in the early stages of the

    final design phase. It is never too early to value engineer every project. While saying that, it is expressly

    understood that AMEC is very early into the design and it is not uncommon for further analysis to find

    reasonable alternatives that may significantly reduce scope, and costs, without harming functionality.

    Also, more detailed design will also uncover opportunities to reduce scope, and consequent costs, when

    it is clearer what solutions may accomplish the prime objective, that being certification for the 100 year

    flood level of protection rather than a higher level.

    The key recommendations from this VE Workshop include the following:

    1. Reduction and/or elimination altogether of cutoff walls. These are very expensive solutions andmay be replaced through further analysis of hybrid relief well/ seepage berm solutions, or relief

    well/ pond (water berm) solutions. This is particular the case at Wood River. The length of

    currently proposed cutoff wall solutions and depths as much as 160 feet are of concern. It is

    believed these can be reduced, at a minimum, and information already suggests a significant

    reduction in the required cutoff wall along Wood River. More analysis should be done, using 3-

    D modeling as well.

    2. A hybrid relief wells/seepage berm solution may better fit the need than the disjointed, hopscotch pattern currently laid out in many areas, thereby also reducing the amount of real estate

    acquisition otherwise required. This alternative could prove very cost-effective and still perform

    the functional requirements.

    3. In some locations, e.g., the southern flank of Prairie Du Pont/ Fish Lake, where the top stratumis very thin and the required berms are very long and/or closely spaced relief wells are used, an

    option would be to excavate a pond or lake to relieve seepage, store seepage and storm water,

    and convey water to pump stations. This was done at Earth City, Missouri. To control the exit

    gradient these ponds should be excavated into the sand aquifer. The gradient can best be

    determined using a program such as Seep/W. The water berm or permanent lake idea (like

    Earth city), not only provides seepage pressure relief, but also provides a potential location forstorm water runoff storage, a borrow source for seepage berms or clay cap fill elsewhere on the

    project, and may create new wetlands to offset wetlands losses elsewhere. The pond must be

    set back from the levee or berm to maintain an adequate slope stability factor of safety. A

    gravel filter blanket can be added to the bottom of the pond if there is a concern about small

    boils forming in the pond.

  • 8/6/2019 Ve Workshop Final Report

    7/133

    Value Engineering Workshop Report Page 3 of 14C a m p i o n G r o u p , L L C

    4. It is not too soon to begin to investigate and identify sources of material for seepage berms,especially the source(s) to obtain the clay material needed for both berms and clay caps. This

    will be a major item of expense and there are concerns about where the amount of material will

    come from, including the potential for long hauling costs.

    5. Specifications that mirror the U.S. COE specifications should wherever appropriate be adoptedand used. Where there is debate about the use of such specification, this should be resolved as

    quickly as possible by presentation of the alternate to the Corps and seeking immediate closure

    on acceptance, before design progresses too far.

    6. Cost estimating ought to immediately begin to correlate to both a definitive Work BreakdownStructured project and to proposed contractual specifications to be utilized. Without such care

    there is too much a potential to inadvertently mask scope and cost creep, as well as miss

    elements of work that costs are not developed for.

    7. There must be a reasoned cost and schedule contingency analysis developed that reflects theuncertainties inherent in such a project. Some of this contingency will be allocated to line items

    of cost or specific time to perform issues with certain construction, as it should be. But there

    also must be unallocated contingency available to handle the real unknowns that too often crop

    up on capital projects. The existing 7% total contingency (presumably both allocated and

    unallocated) is simply believed to be far too little at this early stage of design.

    Value Engineering Team

    The value engineering team was assembled by the Councils project management oversight consultant,

    Campion Group, LLC. The VE workshop was led by Douglas R. Campion, serving both as the facilitator

    and an active participant. The other members of the VE Team were:

    MEMBER/ AFFILIATION VE CONCENTRATION

    Craig D. Brauer, P.E. Environmental; Real Estate Costs

    (Thouvenot, Wade & Moerchen, Inc.)

    Paul K. Homann, P.E. Hydrology and Hydraulics

    (Thouvenot, Wade & Moerchen, Inc.)

    Suzanne Goldak, P.E. Hydrology and Hydraulics

    (Thouvenot, Wade & Moerchen, Inc.)

    John E. Shively, P.E. Geotechnical; Construction

    (Shively Geotechnical, a Division of Environmental Operations, Inc.)

    John S. Kottemann, P.E. Geotechnical

    (Shively Geotechnical, a Division of Environmental Operations, Inc.)

    Christopher B. Groves, P.E. Geotechnical; Levee Design

    (Shannon & Wilson, Inc.)

  • 8/6/2019 Ve Workshop Final Report

    8/133

    Value Engineering Workshop Report Page 4 of 14C a m p i o n G r o u p , L L C

    Gregory Bertoglio USACE Requirements; Prairie Du Pont/Fisk Lake districts

    (U.S. Army Corps of Engineers)

    James Worts USACE Requirements; Levee Construction

    (U.S. Army Corps of Engineers)

  • 8/6/2019 Ve Workshop Final Report

    9/133

    Value Engineering Workshop Report Page 5 of 14C a m p i o n G r o u p , L L C

    PROJECT DESCRIPTION AND BACKGROUND

    According to FEMA and the Corps of Engineers, five levees in the Metro East are at risk of failing due to

    structural deficiencies in the levees. These levees extend from Wood River south to Prairie Du Pont and

    Fish Lake. Most of the American Bottoms from the Mississippi River to Bluff Road is at risk. FEMAannounced that its intention is to disaccredit the five Mississippi River levees and, therefore, no longer

    certify the levees as capable of protecting the region from a 100 year flood.

    While the first concern is public safety and the

    increased risk of catastrophic flooding, there are

    significant economic consequences that will cloud

    future economic growth in a large area of

    southwestern Illinois. The 100 year flood map revision

    will determine which homes and businesses will be

    potentially subject to flooding and therefore requiredto buy costly flood insurance. The probability of levee

    decertification will cause massive costs to existing

    individuals and businesses and cripple economic

    growth and investment in our region. Federally

    regulated financial institutions may not be able to issue

    loans to homeowners or businesses that don't carry

    adequate flood insurance, and communities will need

    to adopt development ordinances that include strict

    requirements for building in flood zones. Many

    homeowners may not be able to afford floodinsurance, even at the current favorable rate, putting

    them at future financial risk.

    This potential action will affect almost a third of the

    population of the Illinois portion of the St. Louis area and many critical businesses that are the

    foundation of our local economy. The consequences will be felt not only by areas that could be in

    jeopardy of flooding, but also by all communities that have a stake in the economic vitality of our region.

    This region represents the second largest concentration of population in the Mississippi Corridor (after

    New Orleans) and a collaborative effort should be successful in obtaining the funds necessary to

    improve the levees.

    The Corps of Engineers describe their goal as to "Assess, Communicate Risk, and Solve" the problem.

    Their risk analysis looked at design height and under-seepage problems. It is the under seepage, plus old

    pumps and drainage tiles (Wood River Levee built 1938) that led the Corps to determine the levees are

    not adequate and need repair to be certified. The Corps of Engineers is still working to define actual

  • 8/6/2019 Ve Workshop Final Report

    10/133

    Value Engineering Workshop Report Page 6 of 14C a m p i o n G r o u p , L L C

    costs to improve the levees, but costs could range from $120 -150 million. Current policy of the federal

    government is that all Corps projects require a 35 percent local match.

    Not knowing if and when the Corps might get Congressional authorization and appropriations to

    undertake the requisite levee repairs, the region was able to secure state legislation enabling it to

    establish a .25 percent sales tax within the three affected southwestern Illinois counties. This tax went

    into effect January 1, 2009. With these funds, and other funding from the impacted levee districts, the

    Southwestern Illinois Flood Prevention District Council (SWIFPDC) was formed and staffed. Its goal is to

    investigate the levees for deficiencies, undertake the design and construction to repair them, and have

    the resultant levees certified to FEMA that they meet the 100 year flood protection requirement.

    The SWILFPDC procured the services of AMEC Earth & Environmental, Inc. (AMEC), a qualified consulting

    firm, to undertake the necessary analyses of the levees to determine where there were deficiencies,

    perform preliminary engineering and final design for repairing the levees, assist in contracting for the

    construction of the repairs, provide construction management services, and ultimately certify the

    repaired levees as able to meet the 100 year flood protection criteria of FEMA.

    The SWILFPDC also procured the services of Campion Group, LLC, to support the Councils Chief

    Supervisor of Construction and the Works by way of providing project management oversight of AMEC

    and future construction contractors through to FEMA acceptance of the levees as being 100 year flood

    protection certified.

    A key component of the project management oversight services is the conduct of a value engineering

    program, inclusive of a workshop to bring qualified technical specialists together to review the design

    plans and supporting design analysis in an attempt to both validate the proposed design solutions as

    well as strive to find less costly solutions without adversely affecting the functionality of the designed

    repairs. This report provides a summary of the Value Engineering Workshop held on March 28-31, 2011

    at which time the VE Team met and performed its review of the design progress material provided by

    AMEC.

  • 8/6/2019 Ve Workshop Final Report

    11/133

    Value Engineering Workshop Report Page 7 of 14C a m p i o n G r o u p , L L C

    VALUE ENGINEERING OBJECTIVES

    The principal objective of value engineering is the effective and efficient identification of unnecessary

    cost in a project. . It focuses the attention of engineering and purchasing on one objective equivalent

    performance for lower cost. It results in the orderly utilization of low cost alternative materials, low costalternative processes including new processes, and abilities of specialized suppliers to procure items at

    lower costs.

    In this instance, the VE Workshop was not set up to look deeply into the progress design documentation

    because it was not as far along as would provide greater details. Nor was the VE Team to look at life-

    cycle cost, an element of many such value engineering programs. Rather, the charge for this Team was

    the identification of the general validity of the design analysis program, the evidence of sound input

    data, the general review of the solutions proposed and where, the constructability of those solutions,

    and the relative cost of the proposed solutions. Also, the Team was to review the proposed contract

    packaging and the proposed delivery methods.

    From the review of material and discussions with the designer, and any desired field visits, the VE Team

    is to provide its assessment of the design analysis approach being used by AMEC, and then its

    recommendations for less costly solutions which the Council could adopt and in turn direct AMEC to

    investigate further and, provided a solution meets the functional requirements for levee repair, adopt

    for final design.

    VALUE ENGINEERING PROCESS

    INFORMATION DESIGN DOCUMENTS

    In advance of Workshop AMEC provided a progress set of drawings (plans and profiles of most, but not

    all, of the levees) depicting areas where deficiencies were found and solutions were recommended.

    Most solutions are one of three major types: relief wells, seepage berms or cutoff walls. These drawings

    were prepared and submitted to the Council on March 1, 2011.

    AMEC also provided a cost estimate for the proposed solutions; this also was provided on March 1,

    2011.

    With AMEC bringing this information in on March 1st, and its quick perusal by Les Sterman, the Councils

    Chief Supervisor of Construction and the Works and Doug Campion, Campion Group, the project

    management oversight consultant, led both to conclude that the scope of the solutions inferred a

    potential and sizable increase in cost compared with AMECs earlier, and even more preliminary,

    estimate of cost. Consequently, AMEC was advised then to initiate a more thorough review of its work

    to seek its own identification of value engineered opportunities to reduce scope and, hence, cost.

    Because of this forewarning, AMEC was also able to bring to this VE Workshop for the VE Team to

    review what it refers to as Value Engineering/Design Optimization Items.

  • 8/6/2019 Ve Workshop Final Report

    12/133

    Value Engineering Workshop Report Page 8 of 14C a m p i o n G r o u p , L L C

    The AGENDA for the workshop can be found at Appendix 1. Included here are the attendance sheets for

    each of the four workshop days.

    At Appendix 2 can be found the following material MEC provided in advance of the workshop:

    Plan sheets for each of the four principal levee distracts

    o Wood River Drainage & Levee districto Metro-East Sanitary Drainage and Levee Districto Prairie Du Pont Drainage and Levee and Fish Lake Drainage and Levee districts

    (combined)

    Profiles illustrating: basic levee with and without landside ditch; cross section depicting cutoff

    walls (shallow and deep); cross sections depicting seepage berm and a soil fill of low areas

    adjacent to levee; relief wells, types D and T; and soil fill of ditches beside railroad

    At Appendix 3 can be found the preliminary cost estimate AMEC prepared for the design solutions

    depicted in the progress drawings. Provided here are only the following pieces of an otherwise large

    electronic file which also contains back-up estimating material.

    Comparison of quantities by improvement type for the levees, with comparison being between

    what AMEC had in its proposal and where their analysis suggests quantities as of March 1, 2011.

    Construction cost escalation rate calculation

    Cost summary for each levee district and a total for all

    Detailed summary of unit cost and quantities for 57 work items across all the levees

    Levee-by-levee summaries for each principal levee district, with Prairie Du Pont and Fish Lake

    combined as one, with following breakdowns for major work:

    o Summary for total of 57 work itemso Clay caps solution, if and when applicableo Relief wells, if and applicableo Seepage berms, if and when applicableo Cutoff walls, if and when applicableo Civil improvements, if and when applicable

    At Appendix 4 can be found the AMEC value engineering/design optimization items developed ahead of

    the VE Workshop and provided to the VE Team. There is one sheet for Wood River, Metro-East, and

    Prairie Du Pont/Fish Lake.

    INFORMATION DESIGNER PRESENTATION

    On the morning and into the early afternoon of the workshops first day, AMEC managers, Messrs. Jay

    Martin, Project Manager, and Jon Omvig, both assisted by other staff via telephone, presented an

    overview of the project. At their request, the presentation did not follow precisely the Agenda but

    covered the items requested of them.

  • 8/6/2019 Ve Workshop Final Report

    13/133

    Value Engineering Workshop Report Page 9 of 14C a m p i o n G r o u p , L L C

    At Appendix 5 can be found the presentation made using PowerPoint. There are a total of 30 slides

    presented here two per sheet.

    AMEC was very open and candid in describing their work to-date and identified several issues which

    indicated both some delay in gathering all the data they needed and the status of first and second level

    analysis intended to have been done but was not. Their demeanor was and has been cooperative and inshowing they understood and appreciated the need to search for less costly solutions.

    It was pointed out and certainly agreed to by the VE Team that the design was at only a preliminary level

    of detail. Yes, most of the data needed to do the hydraulic and hydrology, and geotechnical analyses

    had been gathered and resultant first level screening produced the currently proposed solutions shown

    on the drawings and their cost in the estimate. AMEC, however, and as shown in the value

    engineering/design optimization sheets provided, has begun to look at alternative treatments for

    problems found and has initiated 3-D analyses particularly at corners.

    AMEC was responsive to questions raised so as to further develop for the VE Team the necessary

    information base upon which the workshop would proceed to evaluate. It was agreed that the VE Team

    would use the balance of this day and early next to prepare follow-up questions or requests for

    additional information. In turn, this material would e provided to AMEC and AMEC would get responses

    back as soon as practicable. AMEC staff was kept on alert so as to be able to respond quickly.

    The contract packaging and delivery methods were briefly touched upon. Essentially AMEC has

    proposed at this time that most of the work be delivered using conventional design-bid-build (D-B-B)

    method of contracting. In the case where cutoff walls remain required, they recommend using the

    design-build (D-B or D/B) contracting method. With respect to packaging the work, they are not far

    enough into design to fully lay out a specific plan at this time. It appears advisable that like-work, such

    as relief wells be packaged in large enough segments to achieve economies of scale for bidding thiswork. There is also the possibility, to avoid contractors running into each other, that some packages

    may best be put out that include a mix of work and be geographically related, e.g., relief wells, seepage

    berms, miscellaneous civil improvements.

    AMEC presented a brief discussion on its cost estimating approach and further stated its intent to vet

    the estimate as design proceeded and alternatives were identified and resolved.

    At this time it was also brought up by the VE Team and concurred in by AMEC that the cash flow funding

    capability will play a significant part in determining both packages and bidding dates, as well as

    contractual time to complete. In attendance during the presentation was the Councils financial

    consultant, Mr. Roy Toykelson, who contributed to the discussion as regards financial planning.

  • 8/6/2019 Ve Workshop Final Report

    14/133

    Value Engineering Workshop Report Page 10 of 14C a m p i o n G r o u p , L L C

    VE TEAM REVIEW COMMENTS & QUESTIONS AND DESIGNER RESPONSE

    Based on the documentation provided the VE Team in advance, the AMEC project status overview

    presentation, and the responses provide to written comments and questions developed by the Team,

    the value engineering process proceeded for two days.

    The first matters to be dealt with related to the field investigation and the analysis techniques utilized by

    AMEC. The objective here was to validate the geotechnical work and design basis used, and the

    hydrology and hydraulics design basis. Following are the VE Teams opinion on these matters.

    The issues presented in the available drawings and the 30 percent progress presentation by AMEC

    appears to indicate that under seepage is the most significant design issue. Through seepage is an issue

    at a few locations. There is no indication that slope stability is a significant issue after under seepage

    and through seepage issues are addressed.

    The under seepage issue is addressed with seepage berms, relief wells, and cutoff walls. Relief wellsappear to be the least expensive method followed by seepage berms, and finally by cutoff walls. The

    analysis performed to-date appears to use one of the above methods in most cases. A combination of

    berms and relief wells does not appear to have been used except in a few locations. The analysis might

    look at several different berm lengths and the corresponding spacing for relief wells required to control

    exit gradients. A cost study may show that there is an optimum berm length and well spacing to address

    the seepage resulting from the one percent probability flood.

    Upon review of the hydrologic/hydraulic approach taken for this project, we find it consistent with

    standard engineering practice that would be undertaken for a project of this type. The design team

    utilized the United States Army Corps of Engineers (USACE), Hydrologic Engineering Center HydrologicModeling System (HEC-HMS) to derive precipitation-runoff values for the various watersheds at the 10,

    25, 50, 100 and 500-year frequency events. The flows derived from this analysis were then calibrated

    against stream gage flows where available. The AMEC report states that the calibration of flows was

    adjusted to correspond with gage flows within a range of fifteen (15) percent.

    After development of these flows for the various storm events, the flows were then utilized within the

    USACE, Hydrologic Engineering Center River Analysis System (HEC-RAS) computer modeling system to

    derive peak water surface elevations for the 10, 25, 50, 100, and 500-year frequency events. Once again

    this methodology is consistent with standard engineering practice.

    To assess the flooding that would occur in the areas on the land side of the levee, the AMEC team

    utilized PCSWMM modeling to analyze the probable one-percent recurrence flood event. This

    methodology would be one possible alternative of assessing flooding in these areas and is a viable

    methodology.

  • 8/6/2019 Ve Workshop Final Report

    15/133

    Value Engineering Workshop Report Page 11 of 14C a m p i o n G r o u p , L L C

    Having generally satisfied itself that the design approach relative to geotechnical and hydrology and

    hydraulics was in keeping with sound engineering practice and followed accepted practice of the U.S.

    Corps of Engineers, the VE Team developed questions and comments to immediately share with the

    designer. Because AMEC had prepared and shared its value engineering/design optimization items in

    matrix format, numbered sequentially for each levee district, many questions were developed and

    correlated to those tables so as to better enable AMEC to quickly respond. In several instances

    telephone calls were placed with AMEC design staff to best ensure understanding of the comments and

    questions.

    Appendix 6 contains the written comments submitted to AMEC as well as their responses thereto within

    the time available. These were developed as:

    General Comments and Questions (13 comments/questions in total)

    MESD Comments (13 comments/questions in total)

    Wood River (10 comments/questions in total)

    Prairie Du Pont/Fish Lake (8 comments/questions n total)

    In addition to the comments and questions, the VE Team developed additional ones for follow-up by

    AMEC in the near future. Following are the observations and resulting comments/questions discussed

    by the VE Team during the course of the workshop and put into writing afterwards. In many instances,

    these were discussed with AMEC to some extent during the closing day.

    A. It appears that the impact of berm construction on wet lands may be significant. This is a concernwhere berm fill covers wet land and where borrow is required for construction of the berm.

    B. Deep cutoff walls are very expensive and the designers should look at cost issues and means tomitigate construction costs. Three dimension seepage analyses for the cutoff wall sections are

    recommended to evaluate flow around the ends of the wall and methods to tie-in the ends. Meansto mitigate the number and length of cutoff walls appears to hold the greatest potential for cost

    savings.

    C. Pump testing with the measurement of upward flow velocity in the well was recommended toevaluate the hydraulic conductivity of the foundation sand as a function of the position in the soil

    profile. This issue appears to be less significant after reviewing the D10 values and the pump test is

    no longer recommended. The D10 values appear to indicate that the most permeable sand layers

    appear to be at about mid-depth in the soil profile.

    D. In some locations where the top stratum is very thin and the required berms are very long and/orclosely spaced relief wells, one option will be to excavate a pond or lake to relieve seepage, store

    seepage and storm water, and convey water to pump stations. This is similar to what was done atEarth City, Missouri. To control the exit gradient these ponds should be excavated into the sand

    aquifer. The gradient can best be determined using a program such as Seep/W. The water berm or

    permanent lake idea (like Earth city), not only provides seepage pressure relief, but also provides a

    potential location for storm water runoff storage, a borrow source for seepage berms or clay cap fill

    elsewhere on the project, and may create new wetlands to offset wetlands losses elsewhere. The

    pond must be set back from the levee or berm to maintain an adequate slope stability factor of

  • 8/6/2019 Ve Workshop Final Report

    16/133

    Value Engineering Workshop Report Page 12 of 14C a m p i o n G r o u p , L L C

    safety. A gravel filter blanket can be added to the bottom of the pond if there is a concern about

    small boils forming in the pond.

    E. We believe a clarification should be made in regard to adjustment of computed flows versus gageflows. The AMEC summary report stated that computed flows were adjusted to the range of within

    fifteen (15) percent of gage flows. We would suggest clarification be offered as to the criteria for

    the selection of the fifteen (15) percent value.

    F. Since some of the computed flows are less than actual gage value wouldnt it be appropriate to atleast set the flows at the actual gage flow readings rather than utilize some computed flows that are

    as much as six (6) percent below the gage flows. (or are the gage readings not that accurate).

    G. We would also want to confirm that a check was made to verify that, in addition to the gage flows,the gage elevation was compared to the actual computed hydraulic grade line that was derived for

    the various frequency events.

    H. In our value engineering discussion, a geotechnical representative brought up a significant point asto where the levees would actually be overtopped in the event of a storm event greater than what is

    to be certified by the AMEC team. We understand that this is not in the scope of work that is to be

    undertaken by the AMEC team, but we believe this is an important part of the levee system

    certification to understand where the levees could be overtopped to avoid un-wanted catastrophic

    damage from overtopping of the system in an inappropriate location.

    I. In regard to flooding behind the levee system, it appears that significant fill may be required in someareas to control seepage behind the levee system. We would want to ensure that this additional fill

    is included in the analysis of the flood elevation that will be established on the land side of the levee

    system, and that this fill will not significantly increase existing flood elevations that presently occur

    in these areas.

    J. In some areas of the levee system, particularly in the MESD system from Station 1339+00 to Station1350+00, there is significant drainage piping (in this area a 12 x 5 box culvert system). We would

    like the AMEC team to look into these types of areas in depth to assess whether areas like these can

    be re-routed by ditching or other means to eliminate the cost of these expensive structures.

    K. We would suggest at the next submittal of the plans that it would be beneficial to see the actualflood elevation gradient on the river and the flood elevations behind the levee system so that these

    can be evaluated for their impact.

    L. We understand that the NIFP requires that engineering analyses be submitted to demonstrate thatno appreciable erosion of the levee embankment can be expected as a result of either currents or

    waves during the base flood, and that anticipated erosion will not result in failure of the levee. The

    analyses for any conditions that may affect the erosion of the embankment (i.e. flow velocities or

    wind and wave action) should be included.

    M. Are the levee closures owned and operated by the COE or by the levee districts? Will it benecessary to certify that the gates are adequate and operable?

    N. Given the statement that the 100 year flood levels lowered in most areas where Mississippi tailwater was not the controlling factor, are all of the improvements shown near the ends of the flank

    levees necessary for the 100 year certification?

  • 8/6/2019 Ve Workshop Final Report

    17/133

    Value Engineering Workshop Report Page 13 of 14C a m p i o n G r o u p , L L C

    WRAPUP AND NEXT STEPS

    On the closing day the VE Team met with Les Sterman, Councils Chief Supervisor of Construction and

    the Works, and AMECs Jay Martin and Jon Omvig to present the findings in person. As necessary,

    additional AMEC staff was available via telephone.

    The Team reviewed the Comments and Questions which had been written and provided AMEC, together

    with the AMEC responses thereto. (See Appendix 6). For the most part, AMEC accepted the VE Team

    comments and assured that it would address each one that had not been brought to closure in their

    responses. In several instances it was determined that items may not be any longer relevant, others will

    be revisited, and in one case the item is disagreed with by AMEC. Following is a recap of such items:

    In General Comments and Questions

    o Item # 6 is dropped. The VE Team after reviewing boring logs determined there isenough information without conducting the otherwise recommended test per ASTM

    guidelines.

    o Item # 10 will be looked into further by AMEC as it had not considered either fly ash orblast furnace slag for fill. Some concern about the environmental acceptability of fly

    ash, particularly due to U.S. EPA inclinations in this area.o Item # 12 was found to be a matter not considered by AMEC up until now, but they

    understand that haul roads not on major thoroughfares and highways will need to be

    considered and costs for repairs included in estimate during final design and

    construction planning.

    In MESD Comments

    o Item # 12 will look to see whether or not the stationing is correct and therefore whetheror not the recommended actions it proposed is appropriate here. There is possibility of

    simply a typo with respect to the stationing.

    In Wood River

    o Item # 6 will be revisited with further look at possible use French drains in certainsituations.

    In Prairie Du Pont/Fish Lake

    o Item # 2 will have AMEC sending additional information (which it did send and isincluded with Appendix 6).

    o Item # 4 has AMEC agreeing to utilize a 3-D analysis.Much of the discussion revolved around two major proposed design solutions, use of cutoff walls and

    berms. In the former, the VE Team stressed the potential of reducing if not altogether eliminating cutoff

    walls through the use of hybrid solutions wherein a combination of relief wells and seepage berms could

    be evaluated for solving the under seepage issues and thereby reduce the size of berms and

    corresponding land acquisition requirements to save cost. Another possibility, particularly at Wood

    River might be the hybrid relief wells and berms on the river flank, and a combination of relief wells and

    actual ponding (flooding) of the low area across highway 143 for the Mississippi reach rather than the

    deep cutoff walls. Already AMEC has done additional flow analysis and believes some 2,500 feet of wall

    might be eliminated along the Wood River reach. They agree this is a big ticket item and will look closer

    with 3-D analysis and see what the resultant solution could best serve the need.

    One last point on the use of the hybrid relief wells/berm was the VE Teams belief that a more

    consistent design wherein a uniform berm depth (distance from the levee) combined with relief wells

  • 8/6/2019 Ve Workshop Final Report

    18/133

    Value Engineering Workshop Report Page 14 of 14C a m p i o n G r o u p , L L C

    could be lead to a far simpler, therefore less expensive, construction. This in conjunction with reducing

    land acquisition costs.

    A good deal of time was used to address matters of cost throughout the review of comments and

    questions which AMEC addressed. It was also a point to specifically review the unit costs in the

    estimate; the Detailed Summary Wood River, MESD, PdP & Fish Lake prepared by AMEC was used (See

    Appendix 3). For the most part the unit prices have been developed in a parametric manner, though the

    background information provided does contain some bottoms up estimating, though that too relies on

    general figures arrived at from various sources. The VE Team did identify several items where the unit

    prices look to the Team as needing revision, as follows (the item numbers correlate to the AMEC

    Detailed Summary):

    Item #1 The unit of measure might better be developed as cubic yards rather than linear feet

    so as to reflect the actual design depth(s) for specific clay cap solutions.

    Item # 3 - Clearing and grubbing quantities seem to be included in other line items such as

    drainage for shallow ditch, drainage for deep ditch, and drainage for creek relocation. At the

    next submittal this should be clarified.

    Item # 13 The quantity (6,000 lf) could not be resolved; possibly a typo.

    Item # 15 The VE Team believes this item should be broken down further to reflect differentroadway work, such as new or improved roadway, repair of damaged roadways used for hauling

    material and/or equipment (local roads), etc.

    Item # 36 - The cost of rip rap bank protection seems somewhat excessive as compared to theCorps of Engineers typical cost. Please review.

    Item # 39 Right-of-way cost appears low; suggest based on VE Team knowledge that $7-7,500

    per acre may be more in line with what the land costs for agricultural property may be.

    Item # 48 The unit price for wetlands mitigation appears too much of an allowance; whether

    reasonable or not, per se, there ought to be an investigation of potential wetlands development

    in the watershed area whereby the project might be able to bid such a development to get the

    wetlands needed. Also, this line item should be broken down into sub-items, e.g., hardwood

    wetland mitigation, etc.Item # 56 The VE Team believes that mobilization should be assigned to specific work items as

    presumed to be packaged rather than as a simple multiplier across all the other cost items;

    mobilization cost will vary of course by the type of construction, access, etc., and consideration

    must also be given to demobilization, especially if weather conditions should cause stopping and

    starting, with even temporary demobilization to avoid flood waters (a risk).

    Item # 57 A contingency in work such as this, and given the early design status, is likely to be

    required at much more than the 7% presumed by AMEC. Without trying to provide a specific

    figure, the VE Team recommends first that some contingency will naturally result during the

    estimating, that is, there will or should be allocated contingency to various work types and

    geographic locations of the work. Such allocated contingency should be clearly identified.

    Additional contingency will of necessity be required to really take into consideration the real

    uncertainties that may befall such a project.

    The VE Workshop adjourned with all parties comfortable that issues were out on the table and being

    further addressed immediately or planned for early action in the final design phase. As it stands, there

    may be another VE activity during the final design phase, perhaps at approximately the 60% level of

    completion, before detailed design and plans are too far along, but after contract packing and delivery

    methods identified, and real estate acquisition requirements are reasonably close to being final.

  • 8/6/2019 Ve Workshop Final Report

    19/133

    A

    PPENDIX1

  • 8/6/2019 Ve Workshop Final Report

    20/133

  • 8/6/2019 Ve Workshop Final Report

    21/133

    Agenda Rev02 Page 1

    LEVEE PROJECT VALUE ENGINEERING WORKSHOP

    March 28-31, 2011

    AGENDA

    DAY 1 (03-28-2011)

    9:30 AM I. GOALS AND OBJECTIVES OF WORKSHOP - Doug Campion

    9:45 AM II. PRESENTATION BY DESIGNER OF 30% ANALYSES & RECOMMENDATIONS - AMEC (Jon Omvig/ Jay Martin)

    - - Overview of Levee Project and Primary Objectives

    10:00 AM A. Wood River Drainage and Levee District (Wood River)

    1. Hydrologic and Hydraulic Analysis (H&H)

    2. Geotechnical Engineering Analysis

    3. Findings & Recommendations

    a. Deficiencies and Recommended Solutions

    b. Contract Packaging & Delivery Method

    c. Cost Estimate Basis,Allocated Contingency and Total Cost, by Type/Locationd. Risks Assessed

    10:30 AM 4. Q&A

    11:00 AM B. Metro-East Sanitary District (MESD)

    1. Hydrologic and Hydraulic Analysis (H&H)

    2. Geotechnical Engineering Analysis

    3. Findings & Recommendations

    a. Deficiencies and Recommended Solutions

    b. Contract Packaging & Delivery Method

    c. Cost Estimate Basis,Allocated Contingency and Total Cost, by Type/Location

    d. Risks Assessed

    11:30 AM 4. Q&A

    12:00 PM WORKING LUNCH

    12:30 PM C. Prairie du Pont Drainage and Levee District & Fish Lake Drainage and Levee District (PdP/Fish Lake)

    1. Hydrologic and Hydraulic Analysis (H&H)

    2. Geotechnical Engineering Analysis

    3. Findings & Recommendations

    a. Deficiencies and Recommended Solutions

    b. Contract Packaging & Delivery Method

    c. Cost Estimate Basis,Allocated Contingency and Total Cost, by Type/Location

    d. Risks Assessed

    1:00 PM 4. Q&A

    1:30 PM III. FIELD VISITS {Key Problem Areas ONLY}

    5:00 PM ADJOURN FOR THE DAY

  • 8/6/2019 Ve Workshop Final Report

    22/133

    Agenda Rev02 Page 2

    LEVEE PROJECT VALUE ENGINEERING WORKSHOP

    March 28-31, 2011

    AGENDA

    DAY 2 (03-29-2011)

    8:30 AM IV. V.E. PANEL DISCUSSIONS

    A. Follow- Up information/Data Needs from AMEC based on Day 1 Presentation and Field Visits

    1. Identification of information/data needed

    2. Request to be made of AMEC by DRC

    3. AMEC provides Requested Information/Data Needs of Panel by Noon today

    9:00 AM B. Levee-by-Levee: Sense of AMEC Seepage Analysis, Landside Drainage Analysis & Deficiency findings

    1. Wood River

    2. MESD

    3. PdP/Fish Lake

    12:00 PM WORKING LUNCH

    C. Understanding of proposed AMEC technical solutions to address deficiencies and theapplication appropriatness

    1. Seepage blankets (berms)

    2. Relief Wells

    3. Slurry Walls

    4. Pump Stations

    5. Gravity Drains

    6. Freeboard & Embankment Protection

    7. Other

    D. Land Acquisition requirements and issues

    1. As required for technical solution

    2. As required for Wetlands mitigation

    E. Environmental and Other matters

    1. Conformance with current commitments - Phase I assessments, Cultural resources

    2. Permitting - 404, 401

    3. Utilities - Access, relocation

    5:00 PM ADJOURN FOR THE DAY

  • 8/6/2019 Ve Workshop Final Report

    23/133

    Agenda Rev02 Page 3

    LEVEE PROJECT VALUE ENGINEERING WORKSHOP

    March 28-31, 2011

    AGENDA

    DAY 3 (03-30-2011)

    8:30 AM IV. PANEL DISCUSSIONS - REVIEW & IDENTIFY CRITICAL ISSUES/OPPORTINITIES

    F. REVIEW & IDENTIFY CRITICAL ISSUES/OPPORTINITIES

    9:15 AM V. EVALUATION OF COST ESTIMATE

    A. By Proposed Solution Type

    1. Seepage blankets (berms)

    2. Relief Wells

    3. Slurry Walls

    4. Pump Stations

    5. Gravity Drains

    6. Freeboard & Embankment Protection

    7. Other

    B. By Contract Packaging, Delivery Method and Levee

    C. V.E. Opportunities

    12:00 PM WORKING LUNCH

    12:15 PM V. EVALUATION OF COST ESTIMATE (continued)

    2:00 PM VI. V.E. TEAM RECOMMENDATIONS DEVELOPMENT

    5:00 PM ADJOURN FOR THE DAY

  • 8/6/2019 Ve Workshop Final Report

    24/133

    Agenda Rev02 Page 4

    LEVEE PROJECT VALUE ENGINEERING WORKSHOP

    March 28-31, 2011

    AGENDA

    DAY 4 (03-31-2011)

    9:00 AM VII. V.E. TEAM PRESENTATION & OPEN DISCUSSION

    A. Alternatives for Consideration

    B. Construction Implications

    C. Cost Implications

    12:00 PM WORKING LUNCH

    12:30 PM VIII. RISKS IDENTIFICATION

    A. Design phase

    B. Procurement

    C. Construction

    D. Certification

    E. Operations & Maintenance

    F. Unallowability of Expenses as Local Share

    3:00 PM IX. CONCLUSIONS

    4:00 PM X. LOOK AHEAD SCHEDULE - IMPLEMENTATION

    5:00 PM END OF WORKSHOP

  • 8/6/2019 Ve Workshop Final Report

    25/133

    AttendanceProject:Location:

    Southwestern Illinois Flood Protection District Council LeveeMetro-East Park & Recreation District

    Item:Date:

    Va I ~ e E n g i n ~ e r i . . r ! g W o r ~ s h ~ ____ ...Page: / ;,/7 I

    ...~ - - . - - ...~

    6 1 ~ Q . r -

    No. Name Company Email Telepbone NumberIUH'P ' f ~ - J'....,.., . If- " '.. . Ai 3/f ' -33t - ; , ~ 1 J ~ ~ " ~ . U/ClrL_ - :0:.1'(I/S:';_ ) ~ ~ 4 z % ; ~ ; - : ~ f S "

    I ~ r ~ 1 - - ~ - 1 Z ~ : r t \ 0 7 . J _ t : ; ; ~ ~ ; ; ; - ~ ~ e ~ 1 3 I C- ~ ~ s . . ! m ~ ~ ; J c.'j1""'_._!_ _ _ ....m___ ....__4 I 'iiwL. ; I o M l l l " : ' r J m _ ~ m ___m__ l ~ = ~ ; : ~ 6 : ' o + : ! f } l / ~ _ ~ J _ m : ~ ~ = ~ m 2 4 - ~

    I s ;m -W 8 ,v 'r ; " ' ~ 5'foldahil~ J ~ 2 : ~ __ G ~ ' - t ? - f r - - - ~ ~ ! ' : t u f ~ ~ O " ' 1 ( ' I f-m l . tM l r __ ~ __ + n r W N - W e . - - , ~ blt-Cf31-f.b!,. 0

    ! ;;"17 IV-< l i ~ ~ ~ + + - E ' A . 1 ~ " 4 i ) , ,. -3 -/~ j ) ( 1 ~ _ K orTf M f f t V . ! : : : ! ~ ____ c . ( " J i e 1 / U l d ~ ~ i r o t 1 ~ ~ M ~ S f l . < J . l , , 6 / ~ m ~ ~ x : f I 4, () ! ~ l c5krmt:t n -+R O ~ __ .._+_ ..._ ... __.J11 h . I tfvu{;t'.+ _____ ~ _ ! _ - _ - - ...--

    1 ~ t < . " J ' - - 1 , - - - - ~ - - - ~ J.------- - i , - - - - ~ - 15 I __i -- j. J J 2 _ - - J Y d L ~ - - - - - .. - - - ~ + - - - - - - ~ - - - ~ ..-16 I 10v!:J ' S ~ ~ b r L - - + ___ ~ + __ ,___ ..__m_._ - + - _ - ~ m - ....--l~ 4 J f k Y ' L Q - - ~ vk ; .. - l - - - + - - - - - - + - ~ _ ..._-m.m .... .. .......j18 I lltA 'J-L. vS

    e v e e Project V.E. Workshop Mar. 28-31, 2011,. .",-" N ; , ; .I ~ . I \ . C C ~ ~isnici~ Y V ' t SC-tp Ie ,

    'UJ kd y C ( r " ~ 11

  • 8/6/2019 Ve Workshop Final Report

    26/133

    Attendance Project: Southwestern Illinois Flood Protection District Council Levee __Location: Metro-East Park & Recreation DistrictItem: .VallIe E . ! 1 g i n ~ r i n g Workshop_ .. _ ~ ~ . _ _ _ _ . ... ._..... ...____Date: _ ~ ~ ~ L L ~ _ Page: _I.. dJ l.

    I Company Email Telephone Numbero. Name

    1 ?lIttL hf,J/1I/Nri , /,J,._,:; 1.-::-lM!-6

  • 8/6/2019 Ve Workshop Final Report

    27/133

    AttendanceProject: Southwestern Illinois Flood Protection District Council Levee .....n . . . . . .tLocation: Metro-East Park & Recreation District Item: Date: Page: I

    INo. Name Company Email Telepbone Number

    Levee Project V.E. Workshop Mar. 28-31, 2011

  • 8/6/2019 Ve Workshop Final Report

    28/133

    AttendanceProject: Southwestern Illinois Flood Protection District Council Levee P ..........-+ Location: Me!ro:Eas! Park & Recreation District ~ ' ' ' ' e ' ...____.. ..____...___ .. Item: Value F:ngineering Workshop Date: Page:--.L_p..:1J_ ....__

    NO" Name . ~ ~ : ; - a n y ~ ~ ~ \ [ T e l e P h o n ~ ~ u m b e ~ .';-'" /1* , I.. i ~ ! y C ' t i J * 1 ' / ' O ' J @ . . .~ I ' - I . 7 ! i ' ~ , / ' . < ~ 5

    1 I {",It> utf ~ I I vt-l ..____-+ .. c6" L LC; i ' f ~ M j " V 1 . J . : ~ .._U ~ l ~ ~ ~ o l l ~ . - ...- . . I ~ ~ ~ q ' ; U : ..... l i ~ f ~ ~ I ~ ; ~ ~ - ~ " I- I cotS '11

  • 8/6/2019 Ve Workshop Final Report

    29/133

    A

    PPENDIX2

  • 8/6/2019 Ve Workshop Final Report

    30/133

  • 8/6/2019 Ve Workshop Final Report

    31/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    273+98

    260+00

    250+00

    240+00

    230+00

    220+00

    210+00

    200+00

    190+00

    550

    +00

    540+00

    530+00

    520+00

    510+00

    500

    +00

    490+00

    480+00

    470

    +00

    460+00

    450+00

    440

    +00

    430+00

    420+00

    0+00

    80+00

    70+00

    60+00

    50+00

    40+00

    30+00

    20+00

    10+00

    400+00

    390+00

    380+00

    370+00

    360+

    00

    350+00

    340+00

    330+00

    320+00

    310+00

    300+00

    290+00

    280+00

    270+00

    260+00

    250+00

    240+00

    230+00

    220+0021

    0+00200

    +00190+

    00180+

    00170

    +00160

    +00

    150+00

    140+00

    130+00

    120+00

    110+00

    100+00

    0+00

    90+00

    80+00

    70+00

    60+00

    50+00

    40+00

    30+00

    20+00

    10+00

    146+06140+

    00130+

    00109+

    00

    100+00

    700+17

    690+00

    680+00

    670+00

    660+00

    650+00

    640+00

    630+00

    620+00610+00

    600+00

    590+00

    580+00

    570+00

    560+00

    90

    +008

    0+007

    0+00

    60

    +005

    0+004

    0+00

    30

    +00

    20+00

    180

    +00

    170

    +001

    60

    +00

    150

    +00

    140

    +00

    130+

    00

    120

    +00

    110

    +00

    100

    +00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RDNASHVILLE,SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    WOOD RIVER DRAINAGE & LEVEE DISTRICT

    DRAWN BY: MDP

    MARCH 17, 2011

    WR-1

    Legend

    deep cutoff w

    shallow cutoff

    riverside clay

    new relief we

    excluded reac

    levee centerli

    seepage berm

    soil fill

    riprap

    water berm

    SHALLOW CUTOFF WALL

    SHALLOW CUTOFF WALL

    RELIEF WELLS

    RELIEF WELLS

    BERM

    RELIEF WELLS

    DEEP CUTOFF WALL

    SOIL FILL

    RELIEF WELLS &SOIL FILL

    SOIL FILL & RELIEF WELLS

    RELIEF WELLS

    EXCLUDED REACH

    UPPER WOOD RIVER

    LOWER WOOD RIVER

    EAST FORK OF WOOD RIVER(no deficiencies noted)

    RELIEF WELLS

    WATER BERM & RIPRAP

    WATER FILLED DITCH

    BERMS & RELIEF WELLS

    BERM

    RIPRAP(potential scour area)

    CLAY CAP

    SOIL FILL

    0 4,0002,000

    Feet

  • 8/6/2019 Ve Workshop Final Report

    32/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    230+00

    220+00

    210+00

    200+00

    190+00

    7+00

    90

    +00

    80

    +00

    70

    +00

    60

    +00

    50

    +00

    40

    +00

    30

    +00

    20

    +00

    10

    +00

    180

    +00

    170

    +00

    160

    +00

    150

    +00

    140

    +00

    130

    +00

    120

    +00

    110

    +00

    100

    +00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RDNASHVILLE,SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    WOOD RIVER DRAINAGE & LEVEE DISTRICT

    DRAWN BY: MDP

    MARCH 17, 2011

    WR-2

    Legend

    deep cutoff w

    shallow cutoff

    riverside clay

    new relief we

    excluded reac

    levee centerli

    seepage berm

    soil fill

    riprap

    water berm

    UPPER WOOD RIVER

    0 1,500750

    Feet

    SHALLOW CUTOFF WALLelev. 400; approx. 48' deep)

    SHALLOW CUTOFF WALL(to elev. 400; approx. 48' deep)

    11 NEW D-TYPE WELLS(in addition to 17 existingor proposed COE wells)

    MEL PRICE EXCLUDED REACH - C.O.E. CONTROL(certification must consider / approve COE solution)

    MEL PRICELOCK & DAM

    MSRIVER

    11 NEW T-TYPE WELLS

    5 NEW T-TYPE WELLS

    rely on proposed COE wells

    SEEPAGE BERM

  • 8/6/2019 Ve Workshop Final Report

    33/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    273+98

    270+00

    260+00

    250+00

    240+00

    230+00

    220+00

    210+00

    200+00

    190+00

    80+00

    70+00

    60+00

    50+00 20

    +00

    10+00

    90+00

    230+00

    220+00

    210+00

    200+00

    190+00

    180+00

    170+00

    160+00

    150+00

    140+00

    130+00

    120+00

    110+00

    100+00

    180

    +00

    +00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RDNASHVILLE,SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    WOOD RIVER DRAINAGE & LEVEE DISTRICT

    DRAWN BY: MDP

    MARCH 17, 2011

    WR-3

    Legend

    deep cutoff w

    shallow cutoff

    riverside clay

    new relief we

    excluded reac

    levee centerli

    seepage berm

    soil fill

    riprap

    water berm

    SEEPAGEBERM

    PPER WOOD RIVER

    LOWER WOOD RIVER

    0 1,500750

    Feet

    MSRIVER

    2 NEW T-TYPE WELLS

    DEEP CUTOFF WALL(avg. 160' to bedrock)

    SOIL FILL

    WOODRIVE

    R

    4 NEW D-TYPE WELLS

    rely on proposed COE wells

    ROCK FILTER / BALLAST &MAINTAIN SET WATER ELEVATION

  • 8/6/2019 Ve Workshop Final Report

    34/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    520

    +00

    510

    +00

    500

    +00

    490

    +00

    480

    +00

    470

    +00

    460

    +00

    450

    +00

    440

    +00

    430

    +00

    420

    +00

    410+00

    400+00

    390+00

    380+00

    370+00

    360+00

    350+00

    340+00

    330+00

    320+00

    310+00

    300+00

    290+00

    280+00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RDNASHVILLE,SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    WOOD RIVER DRAINAGE & LEVEE DISTRICT

    DRAWN BY: MDP

    MARCH 17, 2011

    WR-4

    Legend

    deep cutoff w

    shallow cutoff

    riverside clay

    new relief we

    excluded reac

    levee centerli

    seepage berm

    soil fill

    riprap

    water berm

    LOWER WOOD RIVER

    0 1,500750

    Feet

    MS

    RIVER

    9 NEW T-TYPE WELLS

    MAINTAIN WATER IN DITCH

  • 8/6/2019 Ve Workshop Final Report

    35/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    550

    +00

    540+00

    530

    +00

    520+00

    510

    +00

    700+17

    690+00

    680+00

    670+00

    660+00

    650+00

    640+00

    630+00

    620+00

    610+00

    600+00

    590+00

    580+00

    570+00

    560+00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RDNASHVILLE,SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    WOOD RIVER DRAINAGE & LEVEE DISTRICT

    DRAWN BY: MDP

    MARCH 17, 2011

    WR-5

    Legend

    deep cutoff w

    shallow cutoff

    riverside clay

    new relief we

    excluded reac

    levee centerli

    seepage berm

    soil fill

    riprap

    water berm

    LOWER WOOD RIVER

    0 1,500750

    Feet

    SOIL FILL

    SEEPAGE BERM &

    9 NEW T-TYPE WELLS

    5' THICK CLAY CAP FOR THROUGH SEEPAGE(intermittent as needed)4 NEW D-TYPE WELLS

    SOIL FILL IN LOW AREAS

    8 NEW D-TYPE WELLS

    SMALL SEEPAGE BERM &2 NEW T-TYPE WELLS

    SOIL FILL IN LOW AREA

    SOIL FILL BOTH RR DITCHES(so RR no longer acts as levee)

    RIPRAP (scour protection)

    SEEPAGE BERM &5 NEW T-TYPE WELLS

    SEEPAGE BERM

  • 8/6/2019 Ve Workshop Final Report

    36/133

    Scale: NoneDrawn by: MGDate: March 16, 2011AMEC File No. 5-6317-0001

    LEVEE ILLUSTRATION

    Levee

    Aquifer

    Semi-pervious

    Blanket

    Aquifer

    Semi-pervious

    Blanket

    Levee

  • 8/6/2019 Ve Workshop Final Report

    37/133

    Scale: NoneDrawn by: LSDate: March 16, 2011AMEC File No. 5-6317-0001

    WOOD RIVER

    PLANS AND CROSS SECTIONS

    CUTOFF WALLS- Narrowslots filled with slurry.

    BEDROCK

    DEEP CUTOFF WALLS-

    Penetrate through theaquifer to bedrock

    SHALLOW CUTOFF WALLS-

    Partially penetrate the aquifer

  • 8/6/2019 Ve Workshop Final Report

    38/133

    Scale: NoneDrawn by: LSDate: March 16, 2011AMEC File No. 5-6317-0001

    WOOD RIVER

    PLANS AND CROSS SECTIONS

    SEEPAGE BERM

    Adds weight to landsidesurface.Abuts the levee.Slopes away from levee.

    SOIL FILL IN LOW SPOTS

    Raises land surface.Used to fill in ditches, borrow pits etc.May not abut the levee.

  • 8/6/2019 Ve Workshop Final Report

    39/133

    Scale: NoneDrawn by: LSDate: March 16, 2011AMEC File No. 5-6317-0001

    WOOD RIVER

    PLANS AND CROSS SECTIONS

    T-TYPE RELIEF WELLS

    Water flows from the relief well to acollector pipe below ground.Collector connects several relief wells

    D-TYPE RELIEF WELLS

    Water flows directly from the relief well.

  • 8/6/2019 Ve Workshop Final Report

    40/133

    Scale: NoneDrawn by: LSDate: March 16, 2011AMEC File No. 5-6317-0001

    WOOD RIVER

    PLANS AND CROSS SECTIONS

    SOIL FILL IN DITCHES BESIDE RAILROAD

    Raises land surface above flood elevation.

    Avoids building a new levee (set-back levee)

  • 8/6/2019 Ve Workshop Final Report

    41/133

    Deep Cutoff Wall

    Shallow Cutoff Wall

    Deep Cutoff Wall

    Deep Cutoff Wall

    Clay Blanket

    Excluded Reach

    Berms

    Berms

    Relief Well

    Relief Wells

    Relief WellRelief Wells

    Berm

    Berms

    Berm

    Relief Wells

    MESD North Flank Le

    MESD River Front Levee

    MESD South Flank Levee

    Relief Wells

    Relief Wells

    Relief Wells

    Relief Wells

    Relief Wells Relief Well

    BermsBerms

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGR

    METRO EAST SANITARY DISTRICT DRAINA

  • 8/6/2019 Ve Workshop Final Report

    42/133

    [

    [

    [

    [

    [

    [

    [

    Deep Cutoff WallBeginning Station: 780+55 Ending Station: 790+67Total Length: 1012 ftDepth to Clay: 100 ft

    24 New T-Type

    9 New D-Type Wells

    6 New D-Type Wells

    1 New

    Chain of Rocks Excluded Reach - C.O.E. Control(certification to be provided by C.O.E.)

    Venice Pump

    Madison Pump

    Old U.E. Pow

    Granite Cit

    G.C.E.D. Pump Statio

    G.C.E.D. Pump Statio

    G.C.E.D. Pump Station No. 2

    900+00

    890+00

    880+00

    870+00

    850+00

    840+00

    830+00

    820+00

    810+00

    910+00

    860+00

    790+00

    780+00

    800+00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGR

    METRO EAST SANITARY DISTRICT DRAINA

  • 8/6/2019 Ve Workshop Final Report

    43/133

    [

    ShallowBeginn inTotal Len

    Seepage Berm

    North Pump St

    990+00

    980+00

    970+00

    960+00

    950+00

    940+00

    930+00

    920+00

    1050+0

    0

    1030+0

    0

    1020+0

    0

    1010+0

    0

    1040+0

    0

    1000+0

    0

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGR

    METRO EAST SANITARY DISTRICT DRAINA

  • 8/6/2019 Ve Workshop Final Report

    44/133

    [

    [

    Deep Cutoff WallBeginn ing Station : 1209+69 Ending Stat

    Total Length: 998 ftAverage Depth to Rock: 142.9 ft

    Clay Blanket

    Seepage Berm

    1 New D-Type Well

    5 New D-Type Wells

    1 New D-Type Well

    10 New D-Ty

    8 New D-Type Wells

    Seepage Berm

    Seepage Berm

    Seepage Berms

    Old Monsanto P.S.

    Phillips Reach Pump Station

    1130+0

    0

    1120+0

    0

    1260+0

    0

    1220+0

    0

    1210+0

    0

    1200+0

    0

    1190+0

    0

    1150+0

    0

    1140+0

    0

    1250+00

    1240+0

    0

    1230+0

    0

    1270+0

    0

    1180+0

    0

    1170+0

    0

    1160+00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGR

    METRO EAST SANITARY DISTRICT DRAINA

  • 8/6/2019 Ve Workshop Final Report

    45/133

    [

    [

    [

    [

    Deep Cutoff Wall

    Beginn ing Station : 1304+00 Ending Station: 1319+00Total Length: 1500 ftDepth to Rock : 125 ft

    Seepage Berms

    1 New D-Type Well

    4 New D-Type Wells

    Seepage Berms

    38 New T-Type Wells

    Cahokia Pump Station

    Seepage Berms

    Pairie Du Pont East PSFalling Springs Pump Station

    Blue Waters Ditch Pump Station136

    0+00

    1350+0

    0

    1340+0

    0

    1330+0

    0

    1320+0

    0

    1490+

    1480+0

    0147

    0+00

    1460+0

    0

    1450+0

    0

    1410+0

    0

    1400+0

    0139

    0+00138

    0+00

    1370+0

    0

    0+00

    1300+0

    0

    1290+0

    0

    1440+0

    0

    1430+0

    0

    1420+0

    0

    1280+0

    0

    1270+0

    0

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    SOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGR

    METRO EAST SANITARY DISTRICT DRAINA

  • 8/6/2019 Ve Workshop Final Report

    46/133

  • 8/6/2019 Ve Workshop Final Report

    47/133

  • 8/6/2019 Ve Workshop Final Report

    48/133

  • 8/6/2019 Ve Workshop Final Report

    49/133

  • 8/6/2019 Ve Workshop Final Report

    50/133

  • 8/6/2019 Ve Workshop Final Report

    51/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    _

    _

    _

    __

    __

    _

    _

    680+00

    670+00

    660+00

    650+00

    640+00

    630+00

    620+00

    610+00

    600+00

    590+00

    580+00

    570+00

    560+00

    550+00

    540+00

    530+00

    520+00

    510+00

    500+00

    490+00

    480+00

    470+00

    460+00

    450+00

    440+00

    430+00

    420+00

    410+00

    400+00

    390+00

    380+00

    370+00

    360+00

    350+00

    340+00

    330+00

    320+00

    310+00

    300+00

    290+00

    280+00

    270+00

    260+00

    250+00

    240+00

    230+00

    220+00

    809

    +00

    800

    +00

    790

    +00

    780

    +00

    770

    +00

    760

    +00

    750

    +00

    740

    +00

    730

    +00

    720

    +00

    710

    +00

    700

    +00

    690

    +00

    0+00 1

    0+00

    90

    +00

    80

    +00

    70

    +00

    60

    +00

    50

    +00

    40

    +00

    30

    +00

    20

    +00

    210

    +00

    200

    +00

    190

    +00

    180

    +00

    170

    +00

    160

    +00

    150

    +00

    140

    +00

    130

    +00

    120

    +00

    110+00

    100

    +00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RNASHVILLESOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    PRAIRIE Du PONT & FISH LAKE DRAINAGE AND LEVEE DISTRICTS

    DRAWN BY: MDP

    MARCH 10, 2011

    PdP-1

    Legend

    riverside clay

    new relief we

    levee centerli

    _ pump station

    seepage berm

    SEEPAGE BERM

    SEEPAGE BERMS &

    RELIEF WELLS

    RELIEF WELLS

    RELIEF WELLS &

    SEEPAGE BERMS

    RELIEF WELLS

    RELIEF WELLS

    SEEPAGE BERM

    SEEPAGE BERM

    0 5,0002,500

    Feet

    CLAY CAPS

    PRAIRIE Du PONT

    FISH LAKE

  • 8/6/2019 Ve Workshop Final Report

    52/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    _

    _

    _

    0

    310+00

    300+00

    290+00

    280+00

    270+00

    260+00

    250+00

    240+00

    230+00

    220+00

    210

    +00

    200

    +00

    190

    +00

    180

    +00

    170

    +00

    160

    +00

    150

    +00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RNASHVILLESOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    PRAIRIE Du PONT & FISH LAKE DRAINAGE AND LEVEE DISTRICTS

    DRAWN BY: MDP

    MARCH 10, 2011

    PdP-2

    Legend

    riverside clay

    new relief we

    levee centerli

    _ pump station

    seepage berm

    0 1,000500

    Feet

    SEEPAGE BERM

    SEEPAGE BERMS

    16 NEW D-TYPE WELLS

    10 NEW D-TYPE WELLS

    CLAY CAP

    17 NEW D-TYPE WELLS

    1 NEW D-TYPE WELL

    2 NEW D-TYPE WELLS

    1 NEW D-TYPE WELL

    3 NEW D-TYPE WELLS

    MSRIVE

    R

    PRAIRIE Du PONT

    EXISTING PUMP STATION(Prairie Du Pont West)

    EXISTING PUMP STATION

  • 8/6/2019 Ve Workshop Final Report

    53/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    470+00

    460+00

    450+00

    440+00

    430+00

    420+00

    410+00

    400+00

    390+00

    380+00

    370+00

    360+00

    350+00

    340+00

    330+00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RNASHVILLESOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    PRAIRIE Du PONT & FISH LAKE DRAINAGE AND LEVEE DISTRICTS

    DRAWN BY: MDP

    MARCH 10, 2011

    PdP-3

    Legend

    riverside clay

    new relief we

    levee centerli

    _ pump station

    seepage berm

    PRAIRIE Du PONT

    0 1,500750

    Feet

    CLAY CAP

    2 NEW D-TYPE WELLS

    CLAY CAP

    SEEPAGE BERMS

    SEEPAGE BERMS

    MS

    RIVER

    7 NEW D-TYPE WELLS

    5 NEW D-TYPE WELLS

    2 NEW D-TYPE WELLS

    9 NEW D-TYPE WELLS

    7 NEW D-TYPE WELLS

  • 8/6/2019 Ve Workshop Final Report

    54/133

  • 8/6/2019 Ve Workshop Final Report

    55/133

    Metro East Sa

    W

    Prairie Du Pont & Fish Lake

    _

    680+00

    670+00

    660+00

    650+00

    640+00

    630+00

    620+00

    610+00

    600+00

    590+00

    580+00

    570+00

    560+00

    770

    +00

    760

    +00

    750

    +00

    740

    +00

    730

    +00

    720

    +00

    710

    +00

    700

    +00

    690

    +00

    SOUTHWESTERN ILLINOIS FLOODPREVENTION DISTRICT COUNCIL

    3800 EZELL RNASHVILLESOUTHWESTERN ILLINOIS FLOOD PREVENTION INITIATIVE

    FEMA CERTIFICATION - PROGRESS SOLUTIONS

    PRAIRIE Du PONT & FISH LAKE DRAINAGE AND LEVEE DISTRICTS

    DRAWN BY: MDP

    MARCH 10, 2011

    PdP-5

    Legend

    riverside clay

    new relief we

    levee centerli

    _ pump station

    seepage berm

    0 1,000 2500

    Feet

    FISH LAKE

    MS

    RIVER

    12 NEW D-TYPE WELLS

    20 NEW D-TYPE WELLS

    2 NEW D-TYPE WELLS

    SEEPAGE BERM

    SEEPAGE BERM

    EXISTING PUMP STATION(Palmer Creek)

  • 8/6/2019 Ve Workshop Final Report

    56/133

  • 8/6/2019 Ve Workshop Final Report

    57/133

    A

    PPENDIX3

  • 8/6/2019 Ve Workshop Final Report

    58/133

  • 8/6/2019 Ve Workshop Final Report

    59/133

    Prelim Cost Estimate Page 1 of 1

    Improvement Type Unit Proposal

    Estimate

    30% Design

    Estimate

    Increase

    (Decrease)

    Clay Cap - Flush & Protruding LF 0 6,600 6,600

    Cutoff Wall - Shallow SF 136,000 83,500 (52,500)

    Cutoff Wall - Intermediate SF 0 0 0

    Cutoff Wall - Deep SF 773,800 880,000 106,200

    Relief Well - Existing - Rehab EA 18 6 (12)

    Relief Well - New EA 54 77 23

    Seepage Berm CY 68,000 565,940 497,940

    Improvement Type Unit Proposal

    Estimate

    30% Design

    Estimate

    Increase

    (Decrease)

    Clay Cap - Flush & Protruding LF 4,500 6,400 1,900

    Cutoff Wall - Shallow SF 109,240 105,600 (3,640)Cutoff Wall - Intermediate SF 0 95,600 95,600

    Cutoff Wall - Deep SF 357,600 366,471 8,871

    Relief Well - Existing - Rehab EA 36 38 2

    Relief Well - New EA 82 107 25

    Seepage Berm CY 1,175,579 1,223,292 47,713

    Improvement Type Unit Proposal

    Estimate

    30% Design

    Estimate

    Increase

    (Decrease)

    Clay Cap - Flush & Protruding LF 0 1,700 1,700

    Cutoff Wall - Shallow SF 0 0 0Cutoff Wall - Intermediate SF 0 0 0

    Cutoff Wall - Deep SF 0 0 0

    Relief Well - Existing - Rehab EA 88 33 (55)

    Relief Well - New EA 192 133 (59)

    Seepage Berm CY 314,105 359,966 45,861

    Improvement Type Unit Proposal

    Estimate

    30% Design

    Estimate

    Increase

    (Decrease)

    Clay Cap - Flush & Protruding LF 4,500 14,700 10,200

    Cutoff Wall - Shallow SF 245,240 189,100 (56,140)Cutoff Wall - Intermediate SF 0 95,600 95,600

    Cutoff Wall - Deep SF 1,131,400 1,246,471 115,071

    Relief Well - Existing - Rehab EA 142 77 (65)

    Relief Well - New EA 328 317 (11)

    Seepage Berm CY 1,557,684 2,149,198 591,514

    QUANTITY COMPARISON

    WOOD RIVER

    MESD

    PdP & FISH LAKE

    TOTAL - WOOD RIVER, MESD, PdP & FISH LAKE

  • 8/6/2019 Ve Workshop Final Report

    60/133

    Prelim Cost Estimate Escalation Page 1 o

    Construction Cost Escalation Rate Calculation for Southwestern Illinois Flood Prevention Initiative

    Estimate Reference Date: 4/1/2011

    Mid-point of 3 years: 9/30/2012

    Assumptions:

    1. Reference year = 2011

    2. Quarterly cost indexes were taken from Table A-1 of Reference 1 assuming feature code 11 (Levees and Floodwalls)

    3. Quarterly escalation indices can be calculated for the quarter of interest by dividing its cost index by that of the preceding quarter

    2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12Jan - Mar April - Jun Jul - Sep Oct - Dec Jan - Mar April - Jun Jul - Sep

    Cost Index, Base year = 1967: 740.23 742.25 745.3 748.84 751.85 754.87 757.88

    Escalation Index: 1.00273 1.00411 1.00475 1.00402 1.00402 1.00399

    Quarter xEscalation

    Index

    4/1/2011 to 6/30/2011 1 1.00273

    7/1/2011 to 9/30/2011 1 1.00411

    10/1/2011 to 12/31/2011 1 1.00475

    1/1/2012 to 3/31/2012 1 1.00402

    4/1/2012 to 6/30/2012 1 1.00402

    7/1/2012 to 9/30/2012 1 1.00399

    Compound Escalation = 1.0238439 or 2.38%

    Reference:

    1. Civil Works Construction Cost Index System, US Army Corps of Engineers, Tables Revised as of 30 September 2010 (EM-1110-2-1304)

    Period

  • 8/6/2019 Ve Workshop Final Report

    61/133

    Prelim Cost Estimate Page 1 of 1

    Improvement SubtotalConstruction Estimate (includes

    Mobilization and Contingency)

    Clay Caps 1,626,750$ 1,789,425$

    Cutoff Walls 34,656,700$ 38,122,370$

    Relief Wells 4,288,450$ 4,717,295$

    Seepage Berms 13,659,785$ 15,025,764$

    Civil Improvements 2,528,430$ 2,781,273$

    Grand Total: 56,760,115$ 62,436,127$

    Proposal $33.7M $39.9M

    Improvement SubtotalConstruction Estimate (includes

    Mobilization and Contingency)

    Clay Caps 3,377,700$ 3,715,470$

    Cutoff Walls 26,532,217$ 29,185,439$

    Relief Wells 5,964,405$ 6,560,846$

    Seepage Berms 31,257,084$ 34,382,792$

    Civil Improvements 1,476,950$ 1,624,645$

    Grand Total: 68,608,356$ 75,469,192$

    Proposal $50.6M $59.6M

    Improvement SubtotalConstruction Estimate (includesMobilization and Contingency)

    Clay Caps 408,000$ 448,800$

    Cutoff Walls -$ -$

    Relief Wells 5,411,000$ 5,952,100$

    Seepage Berms 6,362,840$ 6,999,124$

    Civil Improvements 67,200$ 73,920$

    Grand Total: 12,249,040$ 13,473,944$

    Proposal $15.0M $17.9M

    Improvement SubtotalConstruction Estimate (includes

    Mobilization and Contingency)

    Clay Caps 5,412,450$ 5,953,695$

    Cutoff Walls 61,188,917$ 67,307,809$

    Relief Wells 15,663,855$ 17,230,241$

    Seepage Berms 51,279,709$ 56,407,679$

    Civil Improvements 4,072,580$ 4,479,838$

    Grand Total: 137,617,511$ 151,379,262$

    Proposal $99.3M $117.4M

    COST SUMMARY

    WOOD RIVER

    MESD

    PdP & FISH LAKE

    TOTAL - WOOD RIVER, MESD, PdP & FISH LAKE

  • 8/6/2019 Ve Workshop Final Report

    62/133

    Prelim Cost Estimate Page 1 of 1

    Item # Cost Item Unit Unit Cost Quantity Total

    1 Clay Cap - Flush LF 500.00$ 6,400.0 $ 3,200,000.00

    2 Clay Cap - Protruding LF 240.00$ 8,300.0 $ 1,992,000.00

    3 Clear & Grub AC 6,000.00$ 416.7 $ 2,500,200.00

    4 Cutoff Wall - Shallow SF 12.00$ 189,100.0 $ 2,269,200.00

    5 Cutoff Wall - Intermediate SF 32.00$ 95,600.0 $ 3,059,200.00

    6 Cutoff Wall - Deep SF 37.00$ 1,246,471.0 $ 46,119,427.00

    7 Cutoff Wall - Hazardous Waste Premium SF 30.00$ 215,836.0 $ 6,475,080.00

    8 Cutoff Wall - Special Waste Premium SF 15.00$ 78,634.0 $ 1,179,510.00

    9 Drainage - Enclosed - 12'W x 5'H RC Box Culvert LF 1,330.00$ 1,400.0 $ 1,862,000.00

    10 Drainage - Enclosed - 60" Pipe LF 220.00$ 1,220.0 $ 268,400.00

    11 Drainage - Enclosed - 72" Pipe LF 320.00$ 3,477.0 $ 1,112,640.00

    12 Drainage - Surface - Shallow Ditch LF 150.00$ 6,990.0 $ 1,048,500.00

    13 Drainage - Surface - Deep Ditch LF 275.00$ 6,000.0 $ 1,650,000.00

    14 Drainage - Surface - Creek Relocation LF 650.00$ 3,500.0 $ 2,275,000.00

    15 Improved Roadway LF 150.00$ 2,429.0 $ 364,350.00

    16 Potable Water Well - Raise at Berm EA 75,000.00$ 2.0 $ 150,000.00

    17 Relief Well - Existing - Abandon EA 2,000.00$ 96.0 $ 192,000.00

    18 Relief Well - Existing - Convert to Type "T" EA 6,000.00$ 62.0 $ 372,000.00

    19 Relief Well - Existing - Rehabilitate EA 12,000.00$ 77.0 $ 924,000.00

    20 Relief Well - Existing - Hazardous Waste Premium EA 48,700.00$ 3.0 $ 146,100.00

    21 Relief Well - Existing - Special Waste Premium EA 12,700.00$ 20.0 $ 254,000.0022 Relief Well - Lateral Pipe (8-Inch) LF 40.00$ 5,384.0 $ 215,360.00

    23 Relief Well - Manifold Manhole EA 6,000.00$ 28.0 $ 168,000.00

    24 Relief Well - Manifold Pipe (12-Inch) LF 50.00$ 1,980.0 $ 99,000.00

    25 Relief Well - Manifold Pipe (18-Inch) LF 60.00$ 1,820.0 $ 109,200.00

    26 Relief Well - New - Hazardous Waste Premium EA 61,950.00$ 8.0 $ 495,600.00

    27 Relief Well - New - Special Waste Premium EA 17,125.00$ 75.0 $ 1,284,375.00

    28 Relief Well - New Type "D" EA 30,000.00$ 205.0 $ 6,150,000.00

    29 Relief Well - New Type "T" EA 34,000.00$ 112.0 $ 3,808,000.00

    30 ROW Acquisition - Agricultural AC 6,500.00$ 297.6 $ 1,934,400.00

    31 ROW Acquisition - Commercial AC 30,000.00$ 12.5 $ 375,000.00

    32 ROW Acquisition - Governmental AC 25,000.00$ 0.1 $ 2,500.00

    33 ROW Acquisition - Industrial AC 30,000.00$ 62.8 $ 1,884,000.00

    34 ROW Acquisition - Residential AC 18,000.00$ 20.6 $ 370,800.0035 ROW Acquisition - Vacant/Undeveloped AC 23,000.00$ 98.0 $ 2,254,000.00

    36 RipRap Bank Protection CY 160.00$ 7,943.0 $ 1,270,880.00

    37 Seepage Berm Fill - Dredged CY 10.00$ 1,176,055.0 $ 11,760,550.00

    38 Seepage Berm Fill - Hauled CY 12.00$ 973,142.8 $ 11,677,713.60

    39 Seeding AC 1,650.00$ 392.5 $ 647,625.00

    40 Slip-Line - 12-Inch Pipe LF 48.00$ 175.0 $ 8,400.00

    41 Slip-Line - 15-Inch Pipe LF 70.00$ 60.0 $ 4,200.00

    42 Slip-Line - 18-Inch Pipe LF 125.00$ 2,340.0 $ 292,500.00

    43 Slip-Line - 24-Inch Pipe LF 240.00$ 2,870.0 $ 688,800.00

    44 Slip-Line - 27-Inch Pipe LF 260.00$ 960.0 $ 249,600.00

    45 Slip-Line - 36-Inch Pipe LF 290.00$ 835.0 $ 242,150.00

    46 Slip-Line - 42-Inch Pipe LF 325.00$ 580.0 $ 188,500.00

    47 Slip-Line - 48-Inch Pipe LF 350.00$ 3,190.0 $ 1,116,500.00

    48 Wetland Mitigation AC 25,000.00$ 201.3 $ 5,032,250.00

    49 Pump Station Relocation (15 MGD) EA 2,500,000.00$ 1.0 $ 2,500,000.00

    50 Utility Relocation - Power Pole EA 10,000.00$ 51.0 $ 510,000.00

    51 Utility Relocation - High Tension Power (Raise) EA 200,000.00$ 9.0 $ 1,800,000.00

    52 Utility Relocation - Underground Communication LF 100.00$ 9,340.0 $ 934,000.00

    53 Utility Relocation - Underground Communications Pedestal EA 5,000.00$ 2.0 $ 10,000.00

    54 Utility Relocation - Natural Gas LF 250.00$ 7,030.0 $ 1,757,500.00

    55 Utility Relocation - Various Buried Facilities LF 250.00$ 1,450.0 $ 362,500.00

    Subtotal: 137,617,510.60$

    56 Mobilization (3%) LS 4,128,525.32$ 1.0 4,128,525.32$

    57 Contingency (7%) LS 9,633,225.74$ 1.0 9,633,225.74$

    Construction Estimate: 151,379,261.66$

    DETAILED SUMMARY - WOOD RIVER, MESD, PdP & FISH LAKE

  • 8/6/2019 Ve Workshop Final Report

    63/133

    Prelim Cost Estimate Page 1 of 1

    Item # Cost Item Unit Unit Cost Quantity Total

    1 Clay Cap - Flush LF 500.00$ 0.0 $ -

    2 Clay Cap - Protruding LF 240.00$ 6,600.0 $ 1,584,000.00

    3 Clear & Grub AC 6,000.00$ 114.7 $ 688,200.00

    4 Cutoff Wall - Shallow SF 12.00$ 83,500.0 $ 1,002,000.00

    5 Cutoff Wall - Intermediate SF 32.00$ 0.0 $ -

    6 Cutoff Wall - Deep SF 37.00$ 880,000.0 $ 32,560,000.00

    7 Cutoff Wall - Hazardous Waste Premium SF 30.00$ 6,580.0 $ 197,400.00

    8 Cutoff Wall - Special Waste Premium SF 15.00$ 26,320.0 $ 394,800.00

    9 Drainage - Enclosed - 12'W x 5'H RC Box Culvert LF 1,330.00$ 0.0 $ -

    10 Drainage - Enclosed - 60" Pipe LF 220.00$ 1,220.0 $ 268,400.00

    11 Drainage - Enclosed - 72" Pipe LF 320.00$ 3,477.0 $ 1,112,640.00

    12 Drainage - Surface - Shallow Ditch LF 150.00$ 3,190.0 $ 478,500.00

    13 Drainage - Surface - Deep Ditch LF 275.00$ 0.0 $ -

    14 Drainage - Surface - Creek Relocation LF 650.00$ 0.0 $ -

    15 Improved Roadway LF 150.00$ 1,389.0 $ 208,350.00

    16 Potable Water Well - Raise at Berm EA 75,000.00$ 2.0 $ 150,000.00

    17 Relief Well - Existing - Abandon EA 2,000.00$ 0.0 $ -

    18 Relief Well - Existing - Convert to Type "T" EA 6,000.00$ 7.0 $ 42,000.00

    19 Relief Well - Existing - Rehabilitate EA 12,000.00$ 6.0 $ 72,000.00

    20 Relief Well - Existing - Hazardous Waste Premium EA 48,700.00$ 0.0 $ -

    21 Relief Well - Existing - Special Waste Premium EA 12,700.00$ 6.0 $ 76,200.0022 Relief Well - Lateral Pipe (8-Inch) LF 40.00$ 2,209.0 $ 88,360.00

    23 Relief Well - Manifold Manhole EA 6,000.00$ 18.0 $ 108,000.00

    24 Relief Well - Manifold Pipe (12-Inch) LF 50.00$ 1,130.0 $ 56,500.00

    25 Relief Well - Manifold Pipe (18-Inch) LF 60.00$ 0.0 $ -

    26 Relief Well - New - Hazardous Waste Premium EA 61,950.00$ 0.0 $ -

    27 Relief Well - New - Special Waste Premium EA 17,125.00$ 34.0 $ 582,250.00

    28 Relief Well - New Type "D" EA 30,000.00$ 27.0 $ 810,000.00

    29 Relief Well - New Type "T" EA 34,000.00$ 50.0 $ 1,700,000.00

    30 ROW Acquisition - Agricultural AC 6,500.00$ 81.5 $ 529,750.00

    31 ROW Acquisition - Commercial AC 30,000.00$ 12.5 $ 375,000.00

    32 ROW Acquisition - Governmental AC 25,000.00$ 0.1 $ 2,500.00

    33 ROW Acquisition - Industrial AC 30,000.00$ 15.7 $ 471,000.00

    34 ROW Acquisition - Residential AC 18,000.00$ 20.6 $ 370,800.0035 ROW Acquisition - Vacant/Undeveloped AC 23,000.00$ 34.6 $ 795,800.00

    36 RipRap Bank Protection CY 160.00$ 7,943.0 $ 1,270,880.00

    37 Seepage Berm Fill - Dredged CY 10.00$ 0.0 $ -

    38 Seepage Berm Fill - Hauled CY 12.00$ 565,940.0 $ 6,791,280.00

    39 Seeding AC 1,650.00$ 114.7 $ 189,255.00

    40 Slip-Line - 12-Inch Pipe LF 48.00$ 175.0 $ 8,400.00

    41 Slip-Line - 15-Inch Pipe LF 70.00$ 60.0 $ 4,200.00

    42 Slip-Line - 18-Inch Pipe LF 125.00$ 860.0 $ 107,500.00

    43 Slip-Line - 24-Inch Pipe LF 240.00$ 1,710.0 $ 410,400.00

    44 Slip-Line - 27-Inch Pipe LF 260.00$ 960.0 $ 249,600.00

    45 Slip-Line - 36-Inch Pipe LF 290.00$ 835.0 $ 242,150.00

    46 Slip-Line - 42-Inch Pipe LF 325.00$ 270.0 $ 87,750.00

    47 Slip-Line - 48-Inch Pipe LF 350.00$ 390.0 $ 136,500.00

    48 Wetland Mitigation AC 25,000.00$ 20.3 $ 507,750.00

    49 Pump Station Relocation (15 MGD) EA 2,500,000.00$ 0.0 $ -

    50 Utility Relocation - Power Pole EA 10,000.00$ 16.0 $ 160,000.00

    51 Utility Relocation - High Tension Power (Raise) EA 200,000.00$ 5.0 $ 1,000,000.00

    52 Utility Relocation - Underground Communication LF 100.00$ 700.0 $ 70,000.00

    53 Utility Relocation - Underground Communications Pedestal EA 5,000.00$ 0.0 $ -

    54 Utility Relocation - Natural Gas LF 250.00$ 1,750.0 $ 437,500.00

    55 Utility Relocation - Various Buried Facilities LF 250.00$ 1,450.0 $ 362,500.00

    Subtotal: 56,760,115.00$

    56 Mobilization (3%) LS 1,702,803.45$ 1.0 1,702,803.45$

    57 Contingency (7%) LS 3,973,208.05$ 1.0 3,973,208.05$

    Construction Estimate: 62,436,126.50$

    WOOD RIVER - SUMMARY

  • 8/6/2019 Ve Workshop Final Report

    64/133

    Prelim Cost Estimate Page 1 of 1

    Item # Cost Item Unit Unit Cost Quantity Total

    1 Clay Cap - Flush LF 500.00$ $ -

    2 Clay Cap - Protruding LF 240.00$ 6,600.0 $ 1,584,000.00

    3 Clear & Grub AC 6,000.00$ $ -

    4 Cutoff Wall - Shallow SF 12.00$ $ -

    5 Cutoff Wall - Intermediate SF 32.00$ $ -

    6 Cutoff Wall - Deep SF 37.00$ $ -

    7 Cutoff Wall - Hazardous Waste Premium SF 30.00$ $ -

    8 Cutoff Wall - Special Waste Premium SF 15.00$ $ -

    9 Drainage - Enclosed - 12'W x 5'H RC Box Culvert LF 1,330.00$ $ -

    10 Drainage - Enclosed - 60" Pipe LF 220.00$ $ -

    11 Drainage - Enclosed - 72" Pipe LF 320.00$ $ -

    12 Drainage - Surface - Shallow Ditch LF 150.00$ $ -

    13 Drainage - Surface - Deep Ditch LF 275.00$ $ -

    14 Drainage - Surface - Creek Relocation LF 650.00$ $ -

    15 Improved Roadway LF 150.00$ $ -

    16 Potable Water Well - Raise at Berm EA 75,000.00$ $ -

    17 Relief Well - Existing - Abandon EA 2,000.00$ $ -

    18 Relief Well - Existing - Convert to Type "T" EA 6,000.00$ $ -

    19 Relief Well - Existing - Rehabilitate EA 12,000.00$ $ -

    20 Relief Well - Existing - Hazardous Waste Premium EA 48,700.00$ $ -

    21 Relief Well - Existing - Special Waste Premium EA 12,700.00$ $ -22 Relief Well - Lateral Pipe (8-Inch) LF 40.00$ $ -

    23 Relief Well - Manifold Manhole EA 6,000.00$ $ -

    24 Relief Well - Manifold Pipe (12-Inch) LF 50.00$ $ -

    25 Relief Well - Manifold Pipe (18-Inch) LF 60.00$ $ -

    26 Relief Well - New - Hazardous Waste Premium EA 61,950.00$ $ -

    27 Relief Well - New - Special Waste Premium EA 17,125.00$ $ -

    28 Relief Well - New Type "D" EA 30,000.00$ $ -

    29 Relief Well - New Type "T" EA 34,000.00$ $ -

    30 ROW Acquisition - Agricultural AC 6,500.00$ $ -

    31 ROW Acquisition - Commercial AC 30,000.00$ $ -

    32 ROW Acquisition - Governmental AC 25,000.00$ $ -

    33 ROW Acquisition - Industrial AC 30,000.00$ $ -

    34 ROW Acquisition - Residential AC 18,000.00$ $ -35 ROW Acquisition - Vacant/Undeveloped AC 23,000.00$ $ -

    36 RipRap Bank Protection CY 160.00$ $ -

    37 Seepage Berm Fill - Dredged CY 10.00$ $ -

    38 Seepage Berm Fill - Hauled CY 12.00$ $ -

    39 Seeding AC 1,650.00$ $ -

    40 Slip-Line - 12-Inch Pipe LF 48.00$ $ -

    41 Slip-Line - 15-Inch Pipe LF 70.00$ $ -

    42 Slip-Line - 18-Inch Pipe LF 125.00$ $ -

    43 Slip-Line - 24-Inch Pipe LF 240.00$ $ -

    44 Slip-Line - 27-Inch Pipe LF 260.00$ $ -

    45 Slip-Line - 36-Inch Pipe LF 290.00$ $ -

    46 Slip-Line - 42-Inch Pipe LF 325.00$ $ -

    47 Slip-Line - 48-Inch Pipe LF 350.00$ $ -

    48 Wetland Mitigation AC 25,000.00$ 1.7 $ 42,750.00

    49 Pump Station Relocation (15 MGD) EA 2,500,000.00$ $ -

    50 Utility Relocation - Power Pole EA 10,000.00$ $ -

    51 Utility Relocation - High Tension Power (Raise) EA 200,000.00$ $ -

    52 Utility Relocation - Underground Communication LF 100.00$ $ -

    53 Utility Relocation - Underground Communications Pedest