Fugitive Emissions
Management
Guideline VERSION 1.0: July 2019
Page: 2
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
About the Commission
The BC Oil and Gas Commission (Commission) is the single-window regulatory agency
with responsibilities for regulating oil and gas activities in British Columbia, including
exploration, development, pipeline transportation and reclamation.
The Commission’s core roles include reviewing and assessing applications for industry
activity, consulting with First Nations, ensuring industry complies with provincial legislation
and cooperating with partner agencies. The public interest is protected by ensuring public safety,
protecting the environment, conserving petroleum resources and ensuring equitable participation in production.
VISION
Safe and responsible energy resource development for British Columbia.
MISSION
We provide British Columbia with regulatory excellence in responsible energy resource development by
protecting public safety, safeguarding the environment and respecting those individuals and communities who
are affected.
VALUES
Transparency
Is our commitment to be open and provide clear information on decisions,
operations and actions.
Innovation
Is our commitment to learn, adapt, act and grow.
Integrity
Is our commitment to the principles or fairness, trust and accountability
Respect
Is our commitment to listen, accept and value diverse perspectives.
Responsiveness
Is our commitment to listening and timely and meaningful action.
Additional Guidance
As with all Commission documents, this manual does not take the place of applicable legislation. Readers are
encouraged to become familiar with the acts and regulations and seek direction from Commission staff for
clarification. Some activities may require additional requirements and approvals from other regulators or create
obligations under other statutes. It is the applicant and permit holder’s responsibility to know and uphold all legal
obligations and responsibilities.
Throughout the manual there are references to guides, forms, tables and definitions to assist in creating and
submitting all required information. Additional resources include:
Glossary and acronym listing on the Commission website.
Documentation and guidelines on the Commission website.
Frequently asked questions on the Commission website.
Advisories, bulletins, reports and directives on the Commission website.
Regulations and Acts listed on the Commission website
Page: 4
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Table of Contents
About the Commission ................................................................................................................................... 2
Additional Guidance....................................................................................................................................... 3
Manual Revisions .......................................................................................................................................... 5
Chapter 1: Preface......................................................................................................................................... 6
1.1 Scope ........................................................................................................................................................................... 6
1.2 How to Use This Guideline ......................................................................................................................................... 6
1.3 Acknowledgement ....................................................................................................................................................... 6
Chapter 2: Developing a Fugitive Emissions Management Plan ................................................................... 7
2.1 Accountability ............................................................................................................................................................... 7
2.2 Roles and Responsibilities .......................................................................................................................................... 7
2.3 Preventive Maintenance ............................................................................................................................................. 9
2.4 Continuous Improvement ........................................................................................................................................... 9
Chapter 3: Leak Detection Surveys ................................................................................................................... 11
3.1 Survey Frequency ..................................................................................................................................................... 11
3.1.1 Proration of Required Comprehensive Survey Frequency ................................................................ 13
3.1.2 Proration of Required Screening Survey Frequency ........................................................................ 14
3.1.3 General Comprehensive Survey Spacing Requirement ................................................................... 14
3.2 Survey Scope ............................................................................................................................................................ 15
3.3 Sources of Fugitive Emissions ................................................................................................................................. 17
3.4 Survey Procedures .................................................................................................................................................... 18
3.4.1 Comprehensive Surveys- Detection Methods ................................................................................. 18
3.4.2 Comprehensive Surveys- Measurement Methods ........................................................................... 21
3.4.3 Screening Surveys ...................................................................................................................... 23
3.4.4 Training and Competency ............................................................................................................ 24
Chapter 4: Repairs....................................................................................................................................... 26
Chapter 5: Data Management ..................................................................................................................... 28
Appendix A: Data Collection ........................................................................................................................ 30
Page: 5
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Manual Revisions
The Commission is committed to the continuous improvement of its documentation. Revisions to the
documentation are highlighted in this section and are posted to the Documentation Section of the Commission’s
website. Stakeholders are invited to provide input or feedback on Commission documentation to
[email protected] or submit feedback using the feedback form.
Version
Number
Posted
Date
Effective
Date
Chapter
Section
Summary of Revision(s)
1.0 July 18,
2019
January 1,
2020 Various
This is a new document. Users are
encouraged to review in full.
For more information, refer to INDB
2019-18 on the Commission’s
website.
Page: 6
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Chapter 1: Preface
This Fugitive Emissions Management Guideline provides regulatory requirements and guidance for fugitive
emissions management in British Columbia. The guideline applies to fugitive emissions at wellsites and facilities
regulated under the Oil and Gas Activities Act (OGAA). It does not apply to liquefied natural gas (LNG) facilities.
1.1 Scope
This guideline focuses exclusively on requirements and processes associated with the BC Oil and Gas
Commission’s (Commission) legislative authorities and does not provide information on legal responsibilities
that the Commission does not regulate. It is the responsibility of the applicant or permit holder to know and
uphold its other legal responsibilities.
1.2 How to Use This Guideline
Commission requirements and recommended practices are included within each section and subsection
throughout the guideline. “Must” indicates a requirement for which compliance is expected and may be
subject to Commission enforcement, while “recommends” or “should” indicates a best practice that should
be used by the applicable party.
1.3 Acknowledgement
The Commission would like to acknowledge the Alberta Energy Regulator (AER) for their input into this
guideline through allowing the Commission to use material from Manual 16 throughout this guideline.
Contributions from industry, environmental non-governmental organizations, academia, service providers
and government are also gratefully acknowledged.
Page: 7
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Chapter 2: Developing a Fugitive Emissions Management
Plan
Fugitive Emissions Management Plans (FEMP) detail how a permit holder’s fugitive emissions will be systematically
detected, managed and reported.
Permit holders should develop a written FEMP. FEMPs and associated data should be reviewed annually and
continuous improvements to the plan should be made as appropriate.
2.1 Accountability
The FEMP should clearly identify which individual is accountable (operator representative) along with their
title and contact information. This individual should be a senior officer as defined in the Greenhouse Gas
Emission Reporting Regulation.
2.2 Roles and Responsibilities
The FEMP should document internal (e.g., individual staff, groups, departments) and external (e.g.,
contractors) resources allocated to develop, implement, maintain and update the FEMP, with their
specific responsibilities identified. Table 2.1 provides an example of how a permit holder might allocate and
document FEMP resources and responsibilities.
Page: 8
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Table 2.1. Example of how resources might be allocated and documented in a FEMP
Resource Responsibility
Corporate management Maintain corporate commitment to the FEMP.
Approve annual FEMP budget.
Review and sign annual certification statement.
FEMP management team Develop and maintain FEMP review schedule.
Create comprehensive survey and screening survey schedule.
Oversee data management system.
Submit reports to the Commission.
Assess the FEMP’s effectiveness and opportunities for continuous
improvement.
Provide updates, develop annual reports, and make
recommendations.
Fugitive emissions surveyors Maintain and calibrate test equipment.
Perform comprehensive surveys.
Perform screening surveys.
Generate individual facility/wellsite reports.
Generate summary reports.
Identify components that require repair, replacement, or retrofit.
Determine leak severity, and measure or estimate emissions rate.
Maintain electronic system to capture and retain data.
Maintain monitoring schedules.
Confirm integrity of repairs.
Field operators Provide guidance on comprehensive survey and screening survey
schedules.
Supervise surveyors and provide them with information about
facility performance and operation during comprehensive surveys
and screening surveys.
Review facility /wellsite reports and develop work plans (work
orders) to address recommendations.
Maintenance team Repair leaks or modify facilities / wellsites (e.g., install test ports,
repipe vent lines).
Close out work orders and record repair details.
Page: 9
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
2.3 Preventive Maintenance
A FEMP should indicate what preventive maintenance practices the permit holder is using to reduce or
prevent fugitive emissions. This might include checklists used by field operators during routine inspections,
regularly scheduled maintenance programs, and maintenance programs or standard operating procedures
that incorporate preventive maintenance practices.
The following preventive maintenance practices could be incorporated into operations and maintenance
practices to reduce fugitive emissions:
Tighten loose connections (especially in a vibrating service).
Plug or eliminate open-ended lines.
Inspect and confirm positive isolation capability of separator and scrubber dump valves.
Inspect and maintain pressurized pneumatic devices and pumps (e.g., controller case seals).
Fix or replace pressurized pneumatic devices and pumps that are not operating within
manufacturer written specifications.
Inspect and maintain thief hatches.
Inspect and maintain pressure relief valves (PRVs) and pressure vent relief valves (PVRVs).
Close thief hatches if found open on tanks with vent gas control.
Ensure combustion systems remain lit when facility or wellsite is pressurized and active.
Ensure control equipment (such as vapour recovery unit) is operational (except when it is down for
maintenance) and is operating and maintained as designed.
Look for and correct abnormal process events.
2.4 Continuous Improvement
The FEMP should describe how data will be used to evaluate performance and inform continuous improvement.
The following are indicators that could be used to evaluate the performance of a FEMP and to determine if any
changes are needed:
Quantified emissions reductions over time (e.g., by corporate or operating area, or by facility type or
equipment).
Cost of detection (e.g., $/kg methane detected).
Volume of gas conserved by managing fugitive emissions.
Number of leaking components over time (e.g., by corporate or operating area or by facility type or
equipment).
Specific components within facilities that are more prone to leaks.
Page: 10
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Time between leak detection and repair.
The FEMP should indicate methods used to review data, how often data are reviewed, and how changes will be
made to the FEMP following these reviews.
Page: 11
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Chapter 3: Leak Detection Surveys
This chapter provides technical guidance to permit holders on leak sources, detection and measurement technology
and methods, as well as leak detection survey timing and frequency.
3.1 Survey Frequency
The FEMP should have documented procedures and plans for meeting the required frequency of fugitive
emissions comprehensive surveys and screening surveys detailed in Tables 3.1 to 3.3 including tracking for:
Number of comprehensive surveys or screening surveys required and completed at each facility or
wellsite (Drilling and Production Regulation (DPR) Section 41.1 (2) (3)).
Results of comprehensive surveys and screening surveys and the status of all repairs (DPR
Section 41.1(7)).
Fugitive emissions comprehensive survey and screening survey requirements apply only to facilities and
wellsites with active (e.g. pressurized in part or in whole) equipment. Required comprehensive survey
frequencies vary according to facility type, control equipment present in the case of single well batteries
(controlled versus uncontrolled storage tanks of any size that store produced water, condensate, or oil), by
production type, and by the presence or absence of storage tanks. Minimum acceptable comprehensive
survey frequencies for regulatory compliance are detailed in Table 3.1.
Screening surveys must be done a minimum of annually at any facility not listed in Table 3.1 (DPR Section
41.1(2)) and at any conventional wellsite (wellsite producing from a zone not listed in Schedule 2 of the
DPR) that does not have a storage tank (DPR Section 41.1(3)).
The FEMP should indicate how companies track when comprehensive or screening surveys are required
and (DPR Section 41.1 (2)(3)(4)) the procedures used to ensure that all applicable components and natural
gas driven pressurized pneumatic devices are surveyed at each site (DPR Section 41.1(2)).
Survey frequencies do not change based on the hydrogen sulphide concentration within any stream at a
facility or wellsite.
Page: 12
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Table 3.1: Minimum Acceptable Comprehensive Survey Frequencies
Facility Type Description Number of Comprehensive
Surveys Required Per Year
Gas Processing Plant As defined in the Drilling and
Production Regulation
3
Compressor Station Any facility containing a type A or
type B compressor, as defined in
the Drilling and Production
Regulation
3
Multi-well Battery Battery as defined in the Drilling
and Production Regulation with link
to more than one well
3
Single-well Battery with Controlled
Storage Tank
Battery as defined in the Drilling
and Production Regulation with link
to one well
3
Custom Treating Facility As defined in the Oil and Gas
Glossary and Definitions
1
Injection/Disposal Facility Injection station or disposal station,
as defined in the Oil and Gas
Glossary and Definitions
1
Wellsites with Unconventional
Production
Unconventional production as
defined in Schedule 2 of the Drilling
and Production Regulation
1
Facility or Well with Storage Tank Example include: Gas Dehydrator,
Fractionation Facility, Pump
Station, and Tank Terminal, as
defined in the Oil and Gas Glossary
and Definitions
1
It is expected that all co-located wellsites and facilities undergo leak detection surveys whenever any of
them is surveyed. For example, if a wellsite is co-located with a multi-well battery, each time the multi-well
battery is surveyed, the co-located wellsite would also be surveyed.
Page: 13
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
3.1.1 Proration of Required Comprehensive Survey
Frequency
The number of comprehensive surveys undertaken per calendar year at a facility may be adjusted as
indicated in Table 3.2. Minimum comprehensive survey spacing requirements are not affected by the
adjustments.
Table 3.2: Proration of Three Comprehensive Surveys per Year
Days Active (Pressurized) per
Calendar Year
Number of Comprehensive Surveys
Required per Calendar Year
0-30 0
31-121 1
122-243 2
244-365 3
The number of comprehensive surveys undertaken per calendar year at a facility or wellsite may be
adjusted as indicated in Table 3.3. Minimum comprehensive survey spacing requirements are not affected
by the adjustments.
Table 3.3: Proration of One Comprehensive Survey per Year
Days Active (Pressurized) Per
Calendar Year
Number of Comprehensive
Surveys Required Per Calendar
Year
0-90 0
91-365 1
If proration of comprehensive survey frequencies is used, records of well and/or facility operating hours must
be submitted to the Commission through eSubmission by no later than May 31 of the year after which the
proration was used.
Page: 14
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
3.1.2 Proration of Required Screening Survey
Frequency
Proration of the number of screening surveys undertaken per year at facilities and wellsites is not
permissible.
3.1.3 General Comprehensive Survey Spacing
Requirement
At facilities where more than one comprehensive survey is required per calendar year each comprehensive
survey must be conducted at least 60 days from the last comprehensive survey conducted as per Section
41.1(4)(a) of the DPR. The spacing between surveys may cross calendar years. For example, a survey at a
gas plant could be conducted in December of one year and then again in March of the following year. At
facilities where one comprehensive survey is required per calendar year each comprehensive survey must
be conducted a minimum of 9 months apart from the last comprehensive survey conducted as per Section
41.1(4)(b) of the DPR. The spacing between surveys may cross calendar years.
Facility Turnarounds
Comprehensive surveys should be conducted within 14 days after the completion of a facility turnaround.
The end of the turnaround is determined by the resumption of operations (full or partial).
Comprehensive surveys conducted after a facility turnaround apply towards the number of comprehensive
surveys required at a facility each calendar year provided they also meet the general comprehensive survey
spacing requirement.
Post Construction
Comprehensive surveys and screening surveys should be conducted within 30 days after the completion of
construction activities. This includes the construction of new facilities (greenfield), as well as any
modifications of existing (brownfield) facilities.
Pre-commissioning inspections are considered by the Commission to be a suitable alternative to post
construction surveys.
Page: 15
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
For facilities and wellsites, the start of the 30 day time period is the first day of startup.
Comprehensive surveys conducted after facility construction apply towards the number of comprehensive
surveys required at a facility each calendar year provided they also meet the general comprehensive survey
spacing requirement.
Inactive Wells and Facilities
Comprehensive surveys and screening surveys should be conducted within 14 days after the reactivation of
a facility or well. Reactivation is achieved the first day of production (wellsite) or receipts to a facility.
Comprehensive surveys and screening surveys conducted after the reactivation of a facility or well apply
towards the number of comprehensive surveys and screening surveys required at a facility or well each
calendar year provided they also meet the general comprehensive survey and screening survey spacing
requirements.
3.2 Survey Scope
Comprehensive surveys and screening surveys must include all equipment and components at a facility or
wellsite that could be a source of fugitive emissions, including pressurized pneumatic devices (Section
41.1(2) DPR) unless the components are unsafe to survey, difficult to survey or inaccessible to survey.
Unsafe, difficult or inaccessible components do not need to be included until it becomes feasible to do so.
Documentation stating why the component is unsafe, difficult or inaccessible to include in the survey must
be detailed in each survey report.
Difficult to survey components are those that cannot be surveyed without elevating the surveyor more than
two (2) metres above a supported surface or are unable to be reached via a wheeled scissor-lift or hydraulic
type scaffold that allows access to components up to 7.6 metres above the ground.
Unsafe to survey components are those that cannot be surveyed without exposing surveyor to an immediate
danger as a consequence of completing the survey. This is dependent on the survey method used.
Inaccessible to survey components are those that are buried, insulated, or obstructed by equipment or
piping that prevents access to the components by surveyor.
Survey technicians must use survey techniques that allow them to safely and effectively detect leaks at
storage tank components. When the survey method used includes optical gas imaging, if there is a
reasonable line of sight to a component, it must be surveyed.
Page: 16
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
The permit holder must survey the following:
Pressurized equipment components with hydrocarbon throughput.
Natural gas–driven pressurized pneumatic devices.
Tank-top equipment, including thief hatches and gauge-board assemblies and pressure relief
devices.
Pressure relief valves.
Equipment used to combust vent gas, including burners, flare ignitors, pilots.
Combustors.
Equipment used to conserve vent gas, including vapour recovery units and vent gas capture
systems.
It is recommended that, should liquid loading/unloading activities take place while a comprehensive survey
using an optical gas imaging camera is being conducted, that the liquid loading/unloading activities be
included within the scope of the survey.
Leaks detected as part of comprehensive surveys must be quantified by measurement (DPR Section
41.1(7)). Where quantification by measurement is not possible for safety reasons, because the leak is
inaccessible, difficult to survey or because the leak is too small or large to measure, quantification must be
done by engineering estimate or emission factor (DPR Section 41.1(7)).
Leaks detected as part of screening surveys must be quantified by either measurement, engineering
estimate, or emission factor (DPR Section 41.1(7)).
Leak rates and corresponding quantification methods must be submitted to the Commission using
eSubmission.
When leak rates are quantified by engineering estimate or emission factor a methodology that is in
accordance with the Greenhouse Gas Emission Reporting Regulation must be used. The estimation of
leaks by empirical experience is not acceptable (DPR Section 41.1(7)).
A summary of leak quantification requirements is provided in Table 3.4.
Table 3.4: Leak Quantification Requirements
Type of Survey
Type of Leak
Outside Measurement Device Range
Inaccessible, Difficult to Survey or Unsafe to
Access Other
Comprehensive Emission Factor or Engineering Estimate Measure
Screening Emission Factor, Engineering Estimate, or Measure
Page: 17
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
3.3 Sources of Fugitive Emissions
Standard Equipment Components
Fugitive emissions from standard equipment components are the result of components wearing out or
failing over time, being improperly installed, or loosening due to vibration. These fugitive emissions can
often be easily detected during a fugitive emissions comprehensive survey or screening survey, and the
component can often be immediately refitted, repaired, or replaced.
The following components are common sources of fugitive emissions:
Connections (especially threaded connections) and fittings.
Instruments and valves (e.g., pressure relief valves and control valves).
Seals and housings (e.g., pressurized pneumatic controller case seals and tank thief hatch seals).
Abnormal Processes
Fugitive emissions from abnormal processes typically result from equipment malfunctioning or becoming
inoperative, or from processes functioning abnormally. These types of emissions may be more difficult to
detect because they can be more intermittent and may require a detailed investigation before the source
can be identified and repaired.
The following abnormal processes are common sources of fugitive emissions:
Unlit flares (ignitors and pilots).
Malfunctioning pressurized pneumatic devices.
Conservation units (e.g., vapour recovery units) that have quit operating.
Equipment components emitting vent gas upstream of equipment actively controlling vent gas.
Hydrocarbon storage tanks can also be sources of fugitive emissions from abnormal processes when:
Thief hatches are open outside the time required for pressure relief.
Leaking process gas or volatile product moves past the seats of drains or blowdown valves.
Gas and liquids are separated inefficiently allowing gas to carry through.
Production changes result in high vapour carry through.
Pigging operations displace large volumes of gas to the tank.
Page: 18
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
3.4 Survey Procedures
A FEMP should describe the methods and equipment used for comprehensive surveys and screening
surveys including the make and model of the equipment used. It is not necessary to use the same type of
equipment for all comprehensive surveys and screening surveys (DPR Section 41.1 (1)).
3.4.1 Comprehensive Surveys- Detection Methods
The two leak detection survey technologies that, when they meet the minimum specifications in this
guideline and when used in accordance with the procedures in the guideline, are accepted as
comprehensive survey methods under the Drilling and Production Regulation are organic vapour analyzers
(US EPA Method 211) and optical gas imaging (OGI) cameras.
OGI cameras must be capable under laboratory conditions of detecting 1 gram per hour of pure methane
emitted at:
A distance of 3 metres between the camera and the emission.
A difference between air temperature and background temperature of no greater than 10 degrees
Celsius.
Before using any survey equipment, the surveyor must make sure that it can be safely operated in the
area and take any necessary precautions. Before starting the survey, the surveyor should identify a
scanning path to ensure all areas of the facility are surveyed. It is usually best to follow the path of the
product from inlet to outlet. The surveyor might also conduct the survey by individual process units and then
check off each unit as it is surveyed.
Meteorological conditions, such as rain and wind, can make it more difficult to detect fugitive emissions.
For example, higher winds can distribute plumes more quickly, making them harder to detect.
Comprehensive surveys conducted during meteorological conditions that substantially compromise their
effectiveness should be avoided, were practicable (surveys done at wind speeds greater than 4 m/s, during
moderate to heavy precipitation events, at ambient temperatures below -20 degrees Celsius).
1 EPA Method 21 means the method of the Environmental Protection Agency of the United States entitled Method 21 — Determination of Volatile Organic Compound Leaks, set out in Appendix A-7 to Part 60 of Title 40, chapter I of the Code of Federal Regulations of the United States.
Page: 19
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Leaks detected as part of comprehensive surveys must be quantified as described in Table 3.4 (DPR
Section 41.1(7)).
Organic Vapour Analyzer
Organic vapour analyzers, sometimes called toxic vapour analyzers, are portable analyzers typically
equipped with photoionization detectors (PIDs) or flame ionization devices (FIDs). Other types of sensors
include catalytic oxidation or infrared absorption sensors.
When completing surveys using an organic vapour analyzer:
Manufacturer written recommendations for the specific type of equipment used must be followed
(DPR Section 41.1(1) (a)).
The tip of the analyzer’s probe must be traced along the leak interface as close as possible to the
component’s surface.
Surveyors must ensure that the analyzer reaches its full metre reading by keeping the analyzer’s
probe in place until the reading levels out or peaks.
To prevent falls when surveying elevated components, surveyors may use an extension probe on
the analyzer rather than a ladder.
When multiple components are close together, it can be difficult to identify the location of a leak.
Surveyors must take the time to ensure that the correct source is identified and may use soap
testing to help confirm the leak location.
Surveys must be conducted at a pace that is appropriate for the size of the component and its
configuration. Larger components will take more time to survey if a uniform probe speed is used.
As a general rule, a speed of 3 cm per second should be used, moving more slowly when
inspecting areas with higher potential for leaks.
Gas Imaging Cameras
Gas imaging cameras, often referred to as optical gas imaging cameras, are a tool for detecting
fugitive emission sources. These cameras provide images and video recordings of leaks that are invisible to
the human eye. In addition, they can be used when it is not practical to use an organic vapour analyzer
(e.g., when the component is hard to reach or is difficult to access with the analyzer’s probe) and can be
used to detect fugitive emissions from a distance.
The ability of an OGI camera to detect fugitive emissions depends on several factors, such as distance
from source, atmospheric conditions, thermal gradient, and surveyor competency.
When completing comprehensive surveys using an OGI camera:
Page: 20
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Manufacturer written recommendations for the specific type of equipment used must be followed.
(DPR Section 41.1(1) (a)).
Surveyors should stand 1.5 to 3 metres from the equipment being surveyed (for detection
purposes), depending on the size and accessibility of the equipment. (For quantification by
quantitative OGI, standing further back may be sometimes be appropriate.)
Surveyors should divide the field of view in the camera view finder into quadrants and scan each
quadrant to look for gas movement from each component. Gas movement might be visible only
when the gas moves from the component to the background. If contrast is low or movement is
difficult to observe, the high-sensitivity mode of the camera might help with detection.
Each piece or group of equipment should be scanned from a wide angle in order to identify any
apparent emissions. After a wide-angle scan, detailed scans should be done to identify the specific
fugitive emissions source and to detect any lower-rate fugitive emissions not visible in the wide-
angle scan. Each piece of equipment should also be scanned from at least two separate
viewpoints to increase the probability of emissions detection.
If the temperature of the leaking gas is similar to the surrounding area, surveyors should adjust the
temperature span on the camera to compensate for low thermal contrast to improve their ability to
identify a leak (e.g., when the component being surveyed is close to a heater or boiler) (DPR
Section 41.1(1) (b)).
Surveyors must consider, to the extent practicable, whether there are any factors such as ambient
weather conditions or surrounding physical structures that could affect the ability to detect the
fugitive emissions and take these into account when conducting a survey. Surveys should not be
conducted during weather conditions that undermine quality when it can be avoided (moderate and
heavy precipitation, wind speeds> 4m/s, ambient temperatures below -20 degrees Celsius).
It is difficult to see gas movement when the camera is in motion, so the camera is to be held still on
one scene for a few seconds before moving on to the next. This is so that video can be used for
quantitative OGI by the surveyors or by others after the survey is complete.
It can be challenging to distinguish between hydrocarbon gas and other hot gases, such as steam.
When viewed through a camera, steam will dissipate quickly as it cools, but a hydrocarbon gas
plume often remains visible for longer.
When comprehensive surveys using optical gas imaging cameras are conducted at very cold temperatures
(below approximately -20 Celsius) physical limitations with the camera may be experienced such as LCD
screen freezing or a high battery discharge rate. Efforts to keep the camera warm such as minimizing the
time spent outside and the use of heating pads and/or blankets may be used. (DPR section 41.1(1) (b)).
Acoustic Leak Detection
Leakage from level control valves on separators and scrubbers to tankage without operating vapour
recovery or thermal control devices must be monitored as part of comprehensive surveys by using an
acoustic leak detection device as per the Greenhouse Gas Emission Reporting Regulation. Any leakage
found must be reported as a leak (DPR Section 41.1(7)).
Page: 21
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
When completing comprehensive surveys using an acoustic leak detection device follow manufacturer
written recommendations for the specific device used.
3.4.2 Comprehensive Surveys- Measurement
Methods
Commission approved leak measurement devices for comprehensive surveys are as follows:
1. Quantitative optical gas imaging.
2. High flow sampler.
3. Full flow meter.
4. Calibrated bag.
5. Other measurement devices, approved in consultation with the Commission.
Quantitative Optical Gas Imaging Camera
Quantitative Optical Gas Imaging (QOGI) is a technology that is designed to work with an optical gas
imaging camera as an add-on module. The module uses image information (pixel intensity and number of
pixels) and supplementary data (distance from camera to the plume and ambient air temperature) to
calculate the mass rate of the release. Leak video should be collected for a minimum of 120 seconds for
audit purposes (DPR Section 41.1(7)).
When measuring emissions using an optical gas imaging camera follow manufacturer written specifications
for the specific device used.
When QOGI is being used for measurement purposes, a tripod should be used to steady the camera (DPR
Section 41.1 (7)).
It is expected that leaks between 0.018 m3/hr and 18 m3/hr can be measured using QOGI2.
High Flow Sampler
A high flow sampler includes a sampling hose, an instrumentation box containing a blower and combustibles
sensors, a battery pack, and a control pad/display. The high flow sampler draws a sample of the air around
2 FAQ: Providence Photonics QL320 and QOGI
Page: 22
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
a leak and measures pressure differential across an orifice restrictor as well as methane concentration using
sensors. This information is used to calculate the leak flowrate.
It is expected that leaks between 0.085 m3/hr and 13.6 m3/hr can be measured using a high flow sampler3.
When measuring emissions using a high flow sampler follow manufacturer written recommendations for the
specific device used with the following exceptions:
High flow sampler is recommended to be calibrated daily (must be calibrated monthly).
Firmware version 3.03 or greater must be used4.
If the high flow sampler is not calibrated daily or Firmware version 3.03 or greater is not used, an additional
method of measurement should be undertaken in addition to the use of the high flow sampler (DPR 41.1
Section (7)).
Full Flow Meter
Leak flow rate can be measured with a variety of instruments such as a diaphragm flow meter, rotary meter,
orifice meters and ultrasonic flow meter.
When measuring emissions using a full flow meter written manufacturer specifications are to be followed.
Calibrated Bag
A calibrated bag is a bag for measuring the flow rate from a vent or open line. The bag
has a known volume and a neck sized to fit over openings. The leak rate is determined as
the volume of the calibrated bag divided by the fill time.
It is expected that leaks up to 408 m3/hr can be measured using a calibrated bag.5
When measuring emissions using a calibrated bag follow written manufacturer recommendations for the
specific bag used.
3 Section 8.5.2.3 Update of Equipment, Component and Fugitive Emission Factors for Alberta Upstream Oil and Gas, Alberta Energy Regulator, June 10, 2018 4 Howard, T., T. W. Ferrara, and A. Townsend-Small. 2015. Sensor transition failure in the high flow sampler: Implications for methane emission inventories of natural gas infrastructure. J. Air Waste Manag. Assoc. 65:856–862. doi:10.1080/10962247.2015.1025925 5 Section 8.5.2.1 Update of Equipment, Component and Fugitive Emission Factors for Alberta Upstream Oil and Gas, Alberta Energy Regulator, June 10, 2018
Page: 23
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Equipment Calibration and Maintenance
The FEMP should describe the methods of calibrating and practices for maintaining the survey equipment.
This should include how frequently any maintenance or calibration activities are conducted and any
procedures or tracking systems used to ensure that these activities are carried out (DPR Section 41.1(1)).
Documentation to demonstrate that equipment is being maintained and calibrated to the manufacturer’s
written specifications must be maintained.
3.4.3 Screening Surveys
The two screening survey methods that are currently approved for use by the Commission are the use of a
soap solution (bubble test) and using the senses of hearing, sight, and small (also known as Audio, Visual,
Olfactory (AVO)). Comprehensive survey methods approved by the Commission may also be used in place
of screening survey methods.
Leaks detected as part of screening surveys must be quantified as specified in Table 3.4 (DPR Section
41.1(7)).
Leak rates and the quantification methods must be submitted to the Commission using eSubmission.
Meteorological conditions, such as rain and wind, can make it more difficult to detect fugitive emissions.
Screening surveys conducted during under meteorological conditions that substantially compromise their
effectiveness (moderate or heavy precipitation, wind speeds greater than 4 m/s, ambient temperature below
-20 degrees Celsius) should be avoided, when practicable.
AVO Inspections
When carrying out AVO inspections, check for the following:
Stains, wet areas, or dripping around thief hatches, pressure vacuum relief valves, and gauge
board assemblies on storage tanks.
Frosting or sweating of valves and pressure-relief devices connected to vent lines.
Visible vapour or steam plumes from components.
Normally closed valves connected to vents or open-ended lines that are not fully closed or plugged.
Components that have been temporarily removed for inspection, maintenance, or other purposes
and have not been put back in place.
Unlit pilots and flares.
Page: 24
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Odours inside buildings and downwind of piping, process equipment, and storage tanks.
Sounds indicative of a leak.
Responses on hydrocarbon detection monitors (personal monitors).
Permit holders should make screening surveys part of their routine site visits.
Soap Testing
Soap or bubble testing can be an effective method to detect smaller leaks. A sprayer or squeeze bottle is
used to apply a soapy solution to an area where a leak is suspected. If a leak is present, bubbling occurs at
the location of a leak. Soap tests may not be effective in detecting leaks from equipment that is inaccessible,
has continuously moving parts, or has a surface temperature greater than the boiling point or less than the
freezing point of the soap solution.
3.4.4 Training and Competency
The FEMP should describe any internal and external surveyor training programs, including the topics
covered and the duration of training, and relevant certifications. The FEMP must also describe the specific
training for the types of equipment being used. The FEMP should also indicate how frequently the surveyors
will be trained and how often they will be retrained or recertified (DPR Section 41.1(1)).
Training of individuals conducting fugitive emissions comprehensive surveys and screening surveys should
include, at a minimum, the following:
Principles of detecting emissions with the equipment or method.
Operation and calibration of equipment.
Sources of fugitive emissions.
Factors that affect estimates of fugitive emissions (e.g., weather, temperature) and how to account
for them.
Interpretation of results.
Surveyors must also have experience detecting, measuring, recording, and reporting fugitive emissions. If
they do not, such as in the case of a person that is being trained, the trainee must work under the direct
supervision of a trained and experienced individual (DPR Section 41.1(1)).
Page: 25
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Surveyors must have adequate training and experience with design and operation of pneumatic devices so
that any natural gas driven malfunctioning (leaking) pneumatic devices and pumps will be detected during
both comprehensive and screening surveys.
Additionally, it is expected that all surveyors will have applicable site safety training and certificates.
Page: 26
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Chapter 4: Repairs
Permit holders must have procedures to track, manage, and verify the status of repairs and repair information must
be submitted to the Commission through eSubmission (DPR Section 41.1(7)).
The FEMP should describe the data management practices and systems used to ensure that comprehensive survey
and screening survey results trigger required repairs and that the repairs are captured for reporting purposes. System
details might include the names of software programs or applications used and the type of data managed by each
system. When multiple systems are used, the FEMP should explain how data flows between systems (e.g., how data
from surveys performed by third parties are integrated into the permit holder’s internal systems to track repairs).
The first attempt to repair a leak should be made quickly after discovery, unless parts are unavailable, the equipment
requires shutdown to complete repair, or other good cause exists.
Repairs can either be completed on site during or after comprehensive surveys or screening surveys. It is
recommended that maintenance or operations staff who can perform repairs accompany surveyors to complete
repairs that can be done immediately.
If parts are unavailable, they should be ordered promptly and the repair must be made within 30 working days of
receipt of the parts (DPR Section 41.1 (5)(6)). If successful repairs cannot be completed within 30 days due to the
need to order parts an exemption request to DPR Section 41.1(5)(a) must6 be made to the Commission to avoid
noncompliance. Requests must be in writing to [email protected].
Some leaks might require a shutdown to repair them, such as leaks from components that cannot be isolated and
leaks requiring the site to be depressured. If the facility must be depressured to complete the repair, the repair may
be deferred until the next facility turnaround provided that it does not create an offsite odour or safety hazard (DPR
Section 41(1)(a)(b)) or as directed by the Commission (DPR Section 41.1(5)).
All leaks at wellsites must be repaired within 30 days regardless of the need to depressure the wellsite (DPR Section
41.1(6)).
The integrity of all repairs made must be verified using either a soap solution or an instrument based method such as
optical gas imaging (DPR Section 41.1 (5)(6)) for the repairs to be considered to be successful.
6 This statement is must because the DPR does not allow for repair times to extend beyond 30 days.
Page: 27
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
A repairable leak includes:
Any unintentional natural gas emission detected by an organic vapour analyzer with a concentration equal
to or greater than 500 parts per million.
Any unintentional natural gas emission detected by a gas imaging camera.
Information on each leak detected and repair made must be submitted to the Commission using the Commission’s
eSubmission portal (DPR Section 41.1 (7)).
Tagging
Physical tagging (tag is affixed to a leaking component that cannot be immediately repaired), is the most common
method of tagging. These tags should be hung either directly on the leaking component or in a position where it is
easy to determine the location of the leaking component. Tags should be uniquely numbered, weather resistant,
designed for high visibility, and securely hung using plastic zip ties or corrosion-resistant wire.
Alternative methods of tagging, such as geospatial identifiers, should identify fugitive emission sources
and provide sufficient information to enable repair. This information must include the date the leak was detected
(DPR Section 41.1 (7)).
Consideration should be given to leaving tags in place after repairs are made to monitor for recurrent leaks.
Page: 28
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Chapter 5: Data Management
Data management systems allow permit holders to track, manage, and analyze fugitive emissions data. These
systems should:
Track completed comprehensive, and screening surveys and repairs (including work orders).
Track scheduled comprehensive, and screening surveys and upcoming repairs (including tagging).
Track facility /wellsite and component performance data over time.
Enable data analysis to identify trends.
Generate data summaries for use in regulatory reports.
Record Keeping
Detailed records of all surveys conducted, leaks detected, and repairs made are required to be reported to the
Commission. Appendix A identifies the information that permit holders are required to either keep a record of for audit
purposes or submit to the Commission through eSubmission.
The keeping of and submission of records to the Commission, as detailed in Appendix A, is as follows:
Comprehensive surveys – required.
Screening surveys at facilities and wellsites
o Mandatory Screening Surveys: Those surveys conducted to meet the minimum
requirements of DPR Section 41.1(2) (3) – Records must be submitted to the Commission
through eSubmission.
o Voluntary Screening Surveys: Those surveys conducted in addition to those needed to meet
the minimum requirements of DPR Section 41.1(3) (b) - keep a record. Voluntary submission
can be made to the Commission through eSubmission.
An example of a mandatory screening survey is an annual screening survey at a wellsite with conventional
production (not listed in Schedule 2 of the DPR) that does not have a storage tank. If the conventional wellsite has a
storage tank, it would be subject to a minimum of one comprehensive survey per year (DPR Section 41.1(3) (a) (i))
and any screening surveys conducted at the wellsite would be considered to be voluntary.
An example of a voluntary screening survey is a daily screening survey at a compressor station. This is because
compressor stations are subject to mandatory comprehensive surveys under Section 41.1(2) (a) (ii) of the DPR.
Page: 29
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Data for each comprehensive survey and mandatory screening survey conducted must be submitted electronically to
the Commission through eSubmission by May 31 of each year for each survey conducted during the previous
calendar year. If May 31 occurs on a Saturday or a Sunday, the data are due on the following Monday (DPR Section
41.1 (7)). The first report is due by May 31, 2021.
Data for each leak found and for repairs must be submitted electronically to the Commission through eSubmission by
May 31 of each year for each survey conducted during the previous calendar year. If May 31 occurs on a Saturday or
a Sunday, the data are due on the following Monday (DPR Section 41.1 (7)). The first report is due by May 31, 2021.
Records related to leak detection, quantification, and repair must be retained for a period of not less than 7 years
after the date the leak detection, quantification, or repair was complete to meet the requirements of the Greenhouse
Gas Emission Reporting Regulation.
Data must be certified by a permit holder representative. This individual should be a senior officer as defined in the
Greenhouse Gas Emission Reporting Regulation.
Page: 30
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Appendix A: Data Collection
eSubmission
The following information is to be submitted to the Commission using eSubmission on an annual basis:
Facility/Well Data:
Commission facility / wellsite identifier.
Information on whether natural gas emitting pressurized pneumatic devices are present.
Information on whether storage tanks are present and whether or not they are controlled.
Reporting year.
Number of days facility or well was pressurized or partially pressurized.
Measurement Device Data (comprehensive surveys only):
Make.
Model.
Technician Data:
Name.
Leak Survey Data:
Date.
Ambient temperature (comprehensive surveys only).
Barometric pressure (comprehensive surveys only).
Wind speed (comprehensive surveys only).
Precipitation (comprehensive surveys only).
Information regarding whether the survey was conducted internally or by third parties.
Survey method.
Detection instrument make.
Detection instrument model.
Information regarding whether a leak or leaks were detected.
Page: 31
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Leak Data:
Information on whether or not the leak contains hydrogen sulphide.
Information on whether or not the leak is located within a building.
Process block in which the leak is located.
Leaking component type.
Leaking component service type.
Distance detection camera is located from leak (if applicable).
Distance quantification camera is located from leak (if applicable).
Leak rate.
Leak methane content.
Leak rate quantification method (if applicable).
Reason for non-measurement of leak (if applicable).
Repair Data:
Date of repair.
Information on whether the leak was repaired on the same day it was detected.
Leak repair confirmation method.
Leak repair method applied.
Basis of delay of leak (if repaired after 30 days of detection).
Information on whether the leak is scheduled to be repaired at the next turnaround (if applicable).
Anticipated date of next turnaround (if applicable).
Keep a Record
The following information is to be submitted to the Commission upon request:
Measurement Device Data:
Software version (if applicable).
Calibration date.
Maximum margin of error.
Calibration report.
Page: 32
BC Oil and Gas Commission V 1.0 published: July 2019
Uncontrolled copy once downloaded
GoTo: Table of Contents | Glossary | Legislation | BCOGC.CA
Fugitive Emissions Management Guideline
Technician Data:
Information on whether or not the technician’s employer is the site permit holder.
Employer name.
Employer business address.
Training entity name.
Training entity address.
Name of trainer.
Job title of trainer.
Training date(s).
Number of hours of training received.
Description of training received.
Leak Survey Data:
Survey report.
Leak Data:
Photograph of leak (comprehensive surveys only).
Video of leak (if applicable).
Repair Data:
Documentation verifying repair of leak.