DEVELOPMENT OF THE NETWORK DIAGRAM AND
CRITICAL PATHAcknowledgement - A
Practical Introduction to Management Science
4th edition
![Page 2: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/2.jpg)
BUILDING A HOUSE
2
THE NETWORK DIAGRAM IS
ABOUT CREATING
RELATIONSHIPSBETWEEN
ACTIVITIES
THE NETWORK DIAGRAM IS
ABOUT CREATING
RELATIONSHIPSBETWEEN
ACTIVITIES
![Page 3: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/3.jpg)
BUILDING A HOUSE
3
RELATIONSHIPS ARE ALSO
REFERRED TO AS DEPENDENCIES – THE MOST BASIC
IS “FINISH TO START”
RELATIONSHIPS ARE ALSO
REFERRED TO AS DEPENDENCIES – THE MOST BASIC
IS “FINISH TO START”
![Page 4: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/4.jpg)
BUILDING A HOUSE
4
THUS THE BASIC QUESTION IS
WHICH ACTIVITIES MUST
BE FINISHED BEFORE WHICH ACTIVITIES CAN
START
THUS THE BASIC QUESTION IS
WHICH ACTIVITIES MUST
BE FINISHED BEFORE WHICH ACTIVITIES CAN
START
![Page 5: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/5.jpg)
BUILDING A HOUSE
5
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
A B
Activity A Must Be Finished Before B Can Start
![Page 6: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/6.jpg)
BUILDING A HOUSE
6
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
But Activity E, F and G Don’t Have to Wait for Each Other
D
E
F
G
FrameHVAC
Rough Electric
H
Sheet Rock
![Page 7: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/7.jpg)
BUILDING A HOUSE
7
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
Note That E, F and G Don’t Have to Start and Finish At The Same Time
D
E
F
G
FrameHVAC
Rough Electric
H
Sheet Rock
![Page 8: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/8.jpg)
BUILDING A HOUSE
8
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
THE USE OF AN ARROW
(SPECIFICALLY IN THE NOTATION USED IN THIS
EXAMPLE) SHOWS THIS
RELATIONSHIP
TheY However Need to Be Finished Before H Can Start
D
E
F
G
FrameHVAC
Rough Electric
H
Sheet Rock
![Page 9: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/9.jpg)
Task 1 Is to Create These Dependencies By Indicating the Predecessors For Each Activity
![Page 10: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/10.jpg)
SUMMARY OF ACTIVITIES
10
Time ImmediateRequiredPredecessor
Activity Description (in days) ActivitiesA ExcavateB Lay foundationC Rough plumbingD FrameE Finish exteriorF Install HVACG Rough electricH Sheet rockI Install cabinetsJ PaintK Final plumbingL Final electricM Install flooring
![Page 11: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/11.jpg)
SUMMARY OF ACTIVITIES
11
Time ImmediateRequiredPredecessor
Activity Description (in days) ActivitiesA Excavate --B Lay foundation AC Rough plumbing BD Frame BE Finish exterior DF Install HVAC DG Rough electric DH Sheet rock C, E, F, GI Install cabinets HJ Paint HK Final plumbing IL Final electric JM Install flooring K, L
![Page 12: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/12.jpg)
Task 2 TEST THE LOGIC BY
CONSTRUCTING THE NETWORK DIAGRAM
![Page 13: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/13.jpg)
An Activity-On-Node (AON) Network
13
Install Cabinets
A B
C
D
E
F
G
H
I
J
K
L
M
Excavate
Lay Foundation
Rough Plumbing
Frame
Finish Exterior
HVAC
Rough Electric
Sheet Rock
Paint
Final Plumbing
Final Electric
InstallFlooring
![Page 14: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/14.jpg)
Basic Rules for Constructing the Network Diagram
•Networks typically flow from left to right;•An activity cannot begin until all of its
preceding activities are complete;•Arrows indicate precedence and flow and
can cross over each other;• Identify each activity with a unique
number; this number must be greater than its predecessors;
•Looping is not allowed;•Conditional statements are not allowed;•Use unique start and stop nodes.
14
![Page 15: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/15.jpg)
Task 3 DETERMINE DURATIONS FOR
EACH ACTIVITY
![Page 16: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/16.jpg)
SUMMARY OF ACTIVITIES
16
Time ImmediateRequiredPredecessor
Activity Description (in days) ActivitiesA Excavate 3 --B Lay foundation 4 AC Rough plumbing 3 BD Frame 10 BE Finish exterior 8 DF Install HVAC 4 DG Rough electric 6 DH Sheet rock 8 C, E, F, GI Install cabinets 5 HJ Paint 5 HK Final plumbing 4 IL Final electric 2 JM Install flooring 4 K, L
![Page 17: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/17.jpg)
Task 4FILL EACH NODE AS FOLLOWS
![Page 18: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/18.jpg)
Information Recorded for Each Node
18
i ti
ESTi EFTi
LSTi LFTi
ti = DURATION required to perform activity iESTi = earliest possible start for activity i
EFTi = earliest possible finish for activity iLSTi = latest possible start for activity i
LFTi = latest possible finish for activity i
![Page 19: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/19.jpg)
Task 5CALCULATE THE FORWARD AND
THE BACKWARD PASS
![Page 20: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/20.jpg)
•A Forward Pass through the network determines the earliest times each activity can start and finish – ALSO DETERMINE THE TOTAL DURATION OF THE PROJECT
•A Backward Pass through the network determines the latest times each activity can start and finish without delaying completion of the project – WITH THIS INFORMATION WE CAN DETERMINE WHERE WE CAN DELAY ACTIVITIES (HAVE SLACK) AND WHERE WE CANNOT
20
![Page 21: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/21.jpg)
21
The Forward Pass
•The earliest start (EST) for the initial activity in a project is “time zero”;
•The EST of an activity is equal to the latest (or maximum) early finish of the activities directly preceding it;
•The EFT of an activity is equal to its EST plus the duration required to perform the activity.
![Page 22: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/22.jpg)
22
Results of the Forward Pass
H25 33
8
E17 25
8
J33 38
5
I33 38
5 K38 42
4
L38 40
2
M42 46
4A 0 3
3
F17 21
4
G17 23
6
D7 17
10
C7 10
3
B3 7
4
Note: ESTH=MAX(EFTC,EFTE,EFTF,EFTG)=
25
![Page 23: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/23.jpg)
The Backward Pass
•The latest finish (LFT) for the final activity in a project is equal to its EFT as determined by the forward pass;
•The LFT for any other activity is equal to the earliest (or minimum) LST of the activities directly following (or succeeding) it;
•The LST of an activity is equal to its LFT minus the time required to perform the activity.
23
![Page 24: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/24.jpg)
Results of the Backward Pass
24
Note: LFTH=MIN(LSTI,LSTJ)=33
LFTD=MIN(LSTE,LSTF ,LSTG)=17
LFTB=MIN(LSTC,LSTD)=7
H25 33
8
E17 25
8
J33 38
5
I33 38
5 K38 42
4
L38 40
2
M42 46
4A 0 3
3
F17 21
4
G17 23
6
D 7 17
10
C 7 10
3
B 3 7
40 3 3 7
22 25
17 7
17 25
21 25
2519
25 33
33 38
35 40
42
4240
42 46
38
3
![Page 25: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/25.jpg)
Task 6DETERMINE THE CRITICAL PATH
![Page 26: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/26.jpg)
Determining The Critical Path
• Critical activities have zero slack and cannot be delayed without delaying the completion of the project;
• The slack for non-critical activities represents the amount of time by which the start of these activities can be delayed without delaying the completion of the entire project (assuming that all predecessor activities start at their earliest start times);
• The longest path on the network;• Could also be those activities with the least
slack.
26
![Page 27: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/27.jpg)
The Critical Path
27
Note:
Slack = LSTi-ESTi and LFTi-EFTi
H25 33
8
E17 25
8
J33 38
5
I33 38
5 K38 42
4
L38 40
2
M42 46
4A 0 3
3
F17 21
4
G17 23
6
D 7 17
10
C 7 10
3
B 3 7
40 3 3 7
22 25
17 7
17 25
21 25
2519
25 33
33 38
35 40
42
4240
42 46
38
Slack=0 Slack=0
Slack=0
Slack=15
Slack=0
Slack=4
Slack=2
Slack=0
Slack=0 Slack=0
Slack=2 Slack=2
Slack=0
![Page 28: Very Practical Network Diagram and Critical Path](https://reader036.vdocument.in/reader036/viewer/2022062307/551ed8454979592e5b8b484e/html5/thumbnails/28.jpg)
28