Page 1 of 1 VI-B State College Area School District Office of Physical Plant Ed Poprik, Director To: Board of School Directors From: Ed Poprik RE: High School project 30% document review Date: October 13, 2014 Attached are the presentation materials for the Board of School Directors preliminary review of the 30% design documents for the High School project. No action is required at this meeting. The approval and comment process for these documents is as follows: -October 9 CAC for Facilities Review -October 13 Board of School Directors Preliminary review -October 17 HS Staff Review -October 23 CAC for Facilities Add. review (if needed) -October 29 HS Student Government Review -October 29 Public Information Fair Review -November 3 Board of School Directors Work session -November 10 Board of School Directors Approve and comment

Upload: vucong

Post on 27-May-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1 of 1

VI-B State College Area School District

Office of Physical Plant Ed Poprik, Director

To: Board of School Directors From: Ed Poprik RE: High School project 30% document review Date: October 13, 2014 Attached are the presentation materials for the Board of School Directors preliminary review of the 30% design documents for the High School project. No action is required at this meeting. The approval and comment process for these documents is as follows: -October 9 CAC for Facilities Review -October 13 Board of School Directors Preliminary review -October 17 HS Staff Review -October 23 CAC for Facilities Add. review (if needed) -October 29 HS Student Government Review -October 29 Public Information Fair Review -November 3 Board of School Directors Work session -November 10 Board of School Directors Approve and comment

OCTOBER 13, 2014

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

SITE PLAN

1.01

SITE PLAN

1.02

PLANNING AND AGENCY APPROVALS

TO DATE

01 ZONING VARIANCES (PARKING RELATED) HEARING SCHEDULED OCTOBER 28TH

02 TEXT AMENDMENT (BUILDING HEIGHT) ZONING TEXT AMENDMENT REQUEST

PUBLIC HEARING DECEMBER 1ST

03 TRAFFIC IMPACT STUDY IN PROCESS (DATA COLLECTION IN

SEPTEMBER AND CURRENT)

04 PRELIMINARY LAND DEVELOPMENT PLANS WITH CONDITIONAL USE FOR

PARKING REDUCTION

TENTATIVE SUMBMISSION NOVEMBER 10TH

UPCOMING

1.03

PLANNING AND AGENCY APPROVALS

LONGER TERM APPROVALS

01 PA DEP – SEWAGE FACILITIES

PLANNING MODULE

02 PA DEP – NATIONAL POLLUTANT DISCHARGE

ELIMINATIONS SYSTEMS (NPDES) PERMIT

03 FINAL LAND DEVELOPMENT PLANS INCLUDING STORM WATER

MANAGEMENT DESIGN

START AFTER 60% SUBMISSION IN FEBRUARY

1.04

PLAZA DRIVE UPDATE

PLAZA DRIVE

OPTIONS

(REFERENDUM SCHEMATIC)

PLAZA DRIVE

(CURRENT DESIGN)

1.05

TEXT AMENDMENTS (ZONING)

1.06

TEXT AMENDMENTS (ZONING)

1.07

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

REFERENDUM TO 30% SUBMISSION

NOTE: THE BUILDING AND EDUCATIONAL MODEL FROM THE REFERENDUM HAS CONTINUED TO EVOLVE,

NOW INCORPORATING FURTHER INPUT FROM SCASD STAFF ALONG WITH ENGINEERS, CONSTRUCTION

MANAGERS, FOOD SERVICE PERSONNEL, CODE OFFICIALS, EMERGENCY SERVICES AND SPECIALTY

CONSULTANTS.

2.01

PROGRAM CONFORMANCE

DESIRED ACTUAL

NOTE: IMPLEMENTED EDUCATIONAL PROGRAM IS WITHIN 8% OF FINAL EDUCATIONAL SPECIFICATIONS

AND OVERALL BUILDING SQUARE FOOTAGE IS WITHIN 2% OF REFERENDUM DESIGN.

2.02

PROGRAM CONFORMANCE PROGRAM CONFORMANCE

ACTUAL LOCATION

NOTE: EDUCATIONAL SPECIFICATIONS HAVE BEEN INCORPORATED INTO THE BUILDING DESIGN. AS

DESIGN TEAM CONTINUES TO MEET WITH ADMINISTRATION, FACULTY AND STAFF THROUGH 60% PROCESS

OVER NEXT 3-4 MONTHS, FINAL PROGRAM AND DESIGN WILL BE COMPLETED.

2.03

PROGRAM CONFORMANCE PROGRAM CONFORMANCE

LOCATION ADJUSTMENTS

NOTE: DESIGN TEAM IS CURRENTLY COMPLETING ADJUSTMENTS TO THE BUILDING DESIGN AS WE

PROCEED BEYOND 30% TO MEET THE REQUESTS FROM INTERIOR DESIGN MEETINGS WITH STAFF BUT

ALSO MAINTAIN OVERALL BUILDING SQUARE FOOTAGE.

2.04

PROGRAM CONFORMANCE

2.05

PROGRAM CONFORMANCE

2.06

DELTA PROGRAM ALTERATION

REFERENDUM

DESIGN

30% SUBMISSION

DESIGN

20,000 SF

EDUCATIONAL PROGRAM

52,000 SF

CURRENT PROGRAM (MIDDLE SCHOOL ADDITION)

NOTE: CRA HAS MET WITH DELTA ADMINISTRATION, STAFF, PARENTS AND STUDENT REPRESENTATIVES.

FURTHER EVOLUTION OF DESIGN WILL BE IMPLEMENTED WITH THEIR COMMENTS. UPON APPROVAL OF

CURRENT SCOPE OF DELTA PROGRAM, ANTICIPATED MODIFICATIONS WILL BE WITHIN 52,000 SF FOOTPRINT.

2.07

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

TERMINOLOGY MOVING FORWARD

BRAIN SPACES

TERMINOLOGY

“CORE LEARNING: TYPE A”

“CORE LEARNING: TYPE C”

“CORE LEARNING: TYPE D”

“CORE LEARNING: TYPE B”

“STUDENT COMMONS”

“ACADEMY SHOWCASE

SPACE”

PLANCON

TERMINOLOGY

“CLASSROOM”

“LARGE GROUP

INSTRUCTION”

“SMALL GROUP

INSTRUCTION”

“OPEN CLASSROOM”

“SMALL GROUP BREAKOUT”

NOTE: THOUGH THE FUNCTION WILL BE CONSISTENT AS ILLUSTRATED IN THE BRAIN SPACES

EDUCATIONAL SPECIFICATIONS, FOR MAXIMUM REIMBURSEMENT WE ARE PORTRAYING ALL AREAS THAT

CAN HOLD A CLASSROOM QUANITY OF STUDENTS “CLASSROOM”.

3.01

SOUTH – ADDITION VS RENOVATION

3.02

SOUTH – GROUND FLOOR

3.03

SOUTH – FIRST FLOOR

3.04

SOUTH – SECOND FLOOR

3.05

SOUTH – THIRD FLOOR

3.06

NORTH – FIRST FLOOR

3.07

NORTH – SECOND FLOOR

3.08

INTERIOR DESIGN

3.09

EXTERIOR

3.10

EXTERIOR

3.11

EXTERIOR

3.12

EXTERIOR ENVELOPE DESIGN

3.13

EXTERIOR ENVELOPE DESIGN

3.14

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

MECHANICAL SYSTEMS

SYSTEM RECOMMENDED

01 4 – PIPE ROOF-MOUNTED AHU

WITH ENERGY RECOVERY & HYDRONIC

REHEAT IN VAV BOXES

CHILLER WATER COOLING

02 WATER SOURCE HEAT PUMPS

WITH CLOSED CIRCUIT & GAS-FIRED BOILER

DEDICATED OUTDOOR AIR SYSTEM (DOAS)

WITH ENERGY RECOVERY

03 4 – PIPE CHILLED BEAMS

DOAS WITH ENERGY RECOVERY

04 4-PIPE SYSTEM WITH ROOF

MOUNTED AIR HANDLING UNITS

WITH DISPLACEMENT VENTILATION

THERMAL “ICE” STORAGE TO REDUCE

SIZE OF CHILLER EQUIPMENT

4.01

MECHANICAL SYSTEMS

SYSTEM RECOMMENDED

01 4 – PIPE ROOF-MOUNTED AHU

WITH ENERGY RECOVERY & HYDRONIC

REHEAT IN VAV BOXES

CHILLER WATER COOLING

02 WATER SOURCE HEAT PUMPS

WITH CLOSED CIRCUIT & GAS-FIRED BOILER

DEDICATED OUTDOOR AIR SYSTEM (DOAS)

WITH ENERGY RECOVERY

03 4 – PIPE CHILLED BEAMS

DOAS WITH ENERGY RECOVERY

04 4-PIPE SYSTEM WITH ROOF

MOUNTED AIR HANDLING UNITS

WITH DISPLACEMENT VENTILATION

THERMAL “ICE” STORAGE TO REDUCE

SIZE OF CHILLER EQUIPMENT

4.02

MECHANICAL SYSTEMS

WHY WATER SOURCE HEAT PUMPS

4.03

01 LOWEST FIRST COST

OF ALL OPTIONS

02 “EASY” ACCESS

TO MAINTAIN EQUIPMENT

03 ONE UNIT PER THERMAL ZONE

ONE UNIT PER CLASSROOM

WILL GROUP SIMILAR

OCCUPANCIES TOGETHER

LARGER ROOF-MOUNTED UNITS

FOR LARGE OCCUPANCY AREAS

04 DOAS W/ ENERGY RECOVERY

WHEELS

CO2 CONTROL

05 BASE-MOUNTED PUMPS FOR WATER CIRCULATION

MECHANICAL SYSTEMS

# 2

# 1

SYSTEMS SORTED BY CONSTRUCTION COST

(LOWEST TO HIGHEST)

SYSTEMS SORTED BY LIFE CYCLE

(LOWEST TO HIGHEST)

4.04

MECHANICAL SYSTEMS

PROJECT SQ FTBID

DATELOW BID

COST/

SFCONTRACTOR

# OF

BIDDERS

Average Bid

w/o Low &

High Bid

Average

Cost / SF

w/o low Bid

& High

Midd-West

High School 192,492 26-Mar-09 $ 4,130,000 $ 21.46 Silvertip, Inc. 6 $ 4,864,500 $ 25.27

Middleburg

Elementary

School

109,820 23-Nov-10 $ 2,668,000 $ 24.29 Silvertip, Inc. 5 $ 2,768,667 $ 25.21

Connellsville

Area Senior

High School

304,988 7-Apr-11 $ 8,069,000 $ 26.46 Hranec 6 $ 8,434,750 $ 27.66

Gettysburg

Area Middle

School

196,000 9-Apr-12 $ 4,318,000 $ 22.03 Master Mechanical 8 $ 4,851,333 $ 24.75

Dillsburg

Elementary

School

64,300 8-Apr-14 $ 1,788,000 $ 27.81 Frey Lutz 7 $ 1,917,200 $ 29.82

AVG. $ 24.41 $ 26.54

4.05

CRA PAST PROJECT PRECEDENTS

MECHANICAL SYSTEMS

4.06

TYP. HEAT PUMP LAYOUT

2 CLASSROOMS WITH SHARED CLOSET

MECHANICAL SYSTEMS

4.07

TYP. HEAT PUMP SECTION

PLUMBING SYSTEMS

4.08

DESIGN INTENT

01 ALL NEW PLUMBING FIXTURES

VITREOUS CHINA FIXTURES IN BATHROOMS

S/S SINKS IN VARIOUS AREAS

MANUAL FLUSH VALVES ON WATER CLOSETS

URINALS (LOW FLOW VS WATERLESS)

BATTERY OPERATED SENSOR FAUCETS

SOLIDS INTERCEPTORS IN ART SINKS

BI-LEVEL WATER COOLERS

02 ALL NEW PIPING

DOMESTIC, WASTE, VENT, GAS, ETC.

03 GAS-FIRED HOT WATER GENERATOR

HIGH EFFICIENCY STORAGE TYPE

DISTRIBUTE 140°F WATER

MIXED DOWN AT POINT OF USE

04 FULLY SPRINKLERED BUILDING STANDPIPE SYSTEM IN 2 PODS

FIRE PUMP REQUIRED

PLUMBING SYSTEMS

4.09

DESIGN INTENT

05 ACID NEUTRALIZATION SYSTEM

OUTDOOR CONCRETE VAULT TYPE

06 LIMITED RAINWATER HARVESTING SYSTEM

10,000 GALLON STORAGE TANK

GREY-WATER USE FOR PLUMBING FIXTURES OR HVAC

MAKEUP WATER

SKID-MOUNTED PROCESSING EQUIPMENT

ELECTRICAL SYSTEMS

01 NEW ELECTRICAL SERVICES

02 NEW POWER DISTRIBUTION

03 LED LIGHTING INTERIOR

04 DIGITAL LIGHTING MANAGEMENT SYSTEM

05 EMERGENCY GENERATOR SETS

06 DATA CENTER RELOCATION

07 TYPICAL CLASSROOM SYSTEMS LAYOUT

08 BUILDING SYSTEMS

09 FIRE ALARM SYSTEM

10 SECURITY & ACCESS CONTROL SYSTEMS

4.10

DESIGN INTENT

ELECTRICAL SYSTEMS

4.11

NEW ELECTRICAL SERVICES

NORTH BUILDING

EXISTING SERVICE TO REMAIN UNLESS

OPTION 2 IS SELECTED

NEW 480/277V, 3-PHASE, 4-WIRE SERVICE

SOUTH BUILDING

TWO (2) 480/277V, 3-PHASE, 4-WIRE SERVICE

NEW POWER DISTRIBUTION SERVICES

ELECTRICAL SWITCHBOARD

FOR EACH UTILITY SERVICE FEEDING THE

BUILDING

NEW PANELBOARDS

FED FROM NEAREST SWITCHBOARD AND

THROUGHOUT BUILDING

POWER WIRING & DISCONNECTING

PROVIDED FOR HVAC, PLUMBING, & OWNER

FURNISHED EQUIPMENT

ELECTRICAL SYSTEMS

TYP. POWER LAYOUT

2 CLASSROOMS

4.12

ELECTRICAL SYSTEMS

TYP. LED LIGHTING INTERIOR

2 CLASSROOMS

4.13

ELECTRICAL SYSTEMS

LED LIGHTING INTERIOR

4.14

01 LIGHTING TO BE LED EXCEPTION SPECIALTY FIXTURES

02 2 x 2 RECESSED FIXTURES

FOR CLASSROOMS WITH AVERAGE

35 – 50 FOOTCANDLES OF ILLUMINATION

03 2 x 4 RECESSED FIXTURES

FOR CORRIDORS WITH AVERAGE

10 – 20 FOOTCANDLES OF ILLUMINATION

04 HIGH BAY STYLE LED FIXTURES FOR GYMNASIUM WITH AVERAGE

75 – 100 FOOTCANDLES OF ILLUMINATION

05 DECORATIVE FIXTURES MAY BE SELECTED FOR SPACES LIKE MAIN

ENTRY, LIBRARY AND CAFETERIA.

06 ILLUMINATING ENGINEERING

SOCIETY (IES) RECOMMENDATIONS SHALL BE MET FOR

LIGHTING LEVELS

TYP. CLASSROOM FIXTURES

ELECTRICAL SYSTEMS

DIGITAL LIGHTING MANAGEMENT SYSTEM

01 FOUR-BUTTON LOW VOLTAGE WALL STATION

FOR LIGHTING CONTROLS INCLUDING: ALL ‘ON’, ALL ‘OFF’,

A/V MODE, PLUG LOAD CONTROL

02 VACANCY SENSORS

TO PROVIDE AUTOMATIC ‘SHUT-OFF’

LIGHTING SHALL BE MANUAL ‘ON’, AUTO ‘OFF’

03 PHOTOSENSOR IN SELECT ROOMS

FOR DAYLIGHT HARVESTING

04 INTEGRATED CONTROL SETBACK OF HVAC IN EACH SPACE WHEN ROOM IS UNOCCUPIED

05 INTEGRATED PLUG LOAD REDUCTION DESIGNED TO SHUT OFF POWER TO SPECIFIC RECEPTACLES IN

CLASSROOMS AND OFFICES WHEN SPACE IS UNOCCUPIED.

4.15

ELECTRICAL SYSTEMS

4.16

EMERGENCY GENERATORS SETS

EACH UTILITY SERVICE TO THE BUILDING WILL

HAVE A DEDICATED GENERATOR LOCATED

OUTSIDE OF ITS RESPECTIVE MAIN

ELECTRICAL ROOM.

EACH EMERGENCY SYSTEM WILL BE

PROVIDED WITH TWO (2) NEW AUTOMATIC

TRANSFER SWITCHES, A CONTACTOR FOR

EMERGENCY ONLY LOAD, AND AN AREA

PROTECTION PANEL FOR EMERGENCY

LIGHTING CONTROL.

GENERATORS WILL POWER EGRESS

LIGHTING, EXIT SIGNS, SYSTEM HEAD END

EQUIPMENT SUCH AS FIRE ALARM,

SOUND/INTERCOM/PAGING, SECURITY

PANELS, MDF/IDF HEAD END UNITS,

FREEZER/COOLERS AND MECHANICAL

EQUIPMENT PER OWNER REQUIREMENTS.

DATA CENTER RELOCATION

EXISTING AT NORTH BUILDING

NEW RELOCATED TO SOUTH BUILDING

ELECTRICAL SYSTEMS

4.17

TYP. CLASSROOM SYSTEMS LAYOUT

ELECTRICAL SYSTEMS

VOICE OVER INTERNET PROTOCOL (VOIP)

A NEW VOIP SYSTEM WILL BE PROVIDED BASED UPON THE SCHOOL DISTRICT’S

CURRENT DISTRICT WIDE SYSTEM.

THE PHONE SYSTEM SHALL BE INTEGRATED WITH THE INTERCOM SYSTEM

ALLOWING FOR INTERCOM ACCESS VIA ANY PROGRAMMED WALL OR DESK

STATION.

INTERCOM SYSTEM

SHALL BE DESIGNED WITH THE ABILITY TO MAKE PROGRAM CHANGES VIA A

NETWORK WEB PORTAL.

ALL OCCUPIED SPACES SHALL HAVE AN INTERCOM SPEAKER.

REMOTE SOUND SYSTEM

SHALL BE PROVIDED FOR GYMNASIUM, AUDITORIUM AND CAFETERIA.

CLOCK AND PROGRAM SYSTEM

SHALL BE WIRELESS CORRECTED ANALOG CLOCKS WITH HARDWIRED

POWER.

DATA SYSTEM

COMPUTER DATA CABLING SHALL BE CATEGORY 6 RATED.

THE ENTIRE BUILDING SHALL BE PROVIDED WITH WIRELESS ACCESS POINT

CONNECTIONS USING CATEGORY 6 CABLING.

4.18

BUILDING SYSTEMS

THE FIRE ALARM SYSTEM WILL BE A DIGITAL ADDRESSABLE SYSTEM.

VISUAL/AUDIBLE AND VISUAL NOTIFICATION DEVICES SHALL BE PROVIDED AS

REQUIRED BY CODE.

SMOKE DETECTION SHALL BE PROVIDED AT ALL FIRE ALARM PANELS,

STORAGE ROOMS, FIRE DOORS, DOOR OPENS, ELEVATORS, ETC., AS

REQUIRED BY CODE.

CARBON MONOXIDE DETECTORS SHALL BE PROVIDED AT ALL ROOMS WITH A

NATURAL GAS CONNECTION.

ELECTRICAL SYSTEMS

ACCESS CONTROL SYSTEM WILL BE BASED UPON THE DISTRICT WIDE

SYSTEM.

ACCESS CONTROL CARD READERS WILL BE LOCATED AT AREAS AS DIRECTED

BY THE SCHOOL DISTRICT.

SECURITY SYSTEM SHALL HAVE PANIC BUTTONS LOCATED IN THE MAIN

OFFICE FOR EMERGENCY SITUATIONS.

INTERNET PROTOCOL CLOSED CIRCUIT TELEVISION (IP CCTV) COVER SHALL

BE THROUGHOUT ALL GENERAL AREAS OF THE BUILDING. 4.19

FIRE ALARM SYSTEM

SECURITY + ACCESS CONTROL SYSTEMS

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

SCHEDULE

STATE COLLEGE AREA SCHOOL DISTRICT

DESIGN SCHEDULE- State College Area High School Crabtree, Rohrbaugh & Associates Architects

Building Design

Schematic Design

Design Development

Construction Documents

30% Document Review Review

60% Document Review Review

90% Document Review Review

Faculty Interviews Preliminary Meetings Final Reviews & Sign-Off

Code Analysis Preliminary Update Final Submission

Bidding

PlanCON (PA Depart. of Ed. Reviews) Part A&B Part D Part E Part F Part G

Surveys, Building, Site & Geotechnical

Land Development Design & Preparation Prelim LD Submission Design & Preparation Final LD Submission

Zoning & Traffic Signal Permitting Design & Preparation Zoning Submission Design & Preparation

NPDES Conservation District

School Board Meetings & Review

Drawings available for Public

Construction 36-37 months

9-Oct-14

2014 2015

JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

NPDES Submission

Traffic Signal Permitting

Design & Preparation

5.01

SCHEDULE

5.02

SCHEDULE

5.03

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

PHASING

CONSIDERATIONS

01 STUDENT PEDESTRIAN SAFETY

02 CONTROLLED WORK AREA SAFETY ZONES FOR NORTH SITE & SOUTH SITE

03 TEMPORARY ON-SITE PARKING STUDENTS, STAFF, & DROP-OFFS

04 SCHOOL CALENDAR

MAXIMUM SUMMER UTILIZATION

05 TEMPORARY BAND PRACTICE AREAS

06 TEMPORARY POOL PARKING

07 BUS ACCESS + QUEUING & STUDENT

ENTRY POINTS

6.01

PHASING

CONSIDERATIONS

07 OFF-SITE PARKING ANALYSIS NOT RECOMMENDED

08 LOSS/ REPLACEMENT OF PROGRAMMING

WITH DEMO & NEW CONSTRUCTION

09 FOOD SERVICE AREAS INCLUDING EATERY, KITCHEN REPLACEMENT

& RELOCATION OF DISTRICT-WIDE KITCHEN

10 CONTRACTOR’S AREAS FIELD OFFICE & STAGING AREAS

11 COMPLETION OF SOUTH BUILDING

WHILE NORTH IS BEING COMPLETED

6.02

PHASING

6.03

PHASING

6.04

PHASE 1.1

JUNE 2015 – AUGUST 2015

6.05

PHASE 1.2

SEPTEMBER 2015 – JANUARY 2017

6.06

PHASE 2.1

JANUARY 2017 – MAY 2017

6.07

PHASE 2.2

JUNE 2017 – AUGUST 2017

6.08

PHASE 3.1

SEPTEMBER 2017 – MAY 2018

6.09

PHASE 3.2

JUNE 2018 – JULY 2018

6.10

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

COST ESTIMATING

SCASD/CRA/MCMS MEETING ON 09/30/14 DRAWING REVIEW & DESIGN INTENT DISCUSSIONS

CRA + MCMS DEVELOPING INDEPENDENT COST ESTIMATES EXCHANGE OF INFORMATION UNDERWAY

30% ESTIMATE LARGELY BASED ON $/SF COST DATA, COMPARABLE

RECENT PROJECTS AND 30% OUTLINE

GENERAL CONDITIONS ESTIMATE BASED ON PRLIM. PHASING PLANS

CURRENT NUMBER OF RECOMMENDED PRIME CONTRACTORS

(8) : GENERAL CONTRACTOR, ABATEMENT, MECHANICAL, ELECTRICAL,

PLUMBING, FIRE PROTECTION, FOOD SERVICE, TELE-DATA,

EQUIPMENT/FURNITURE

SCOPE DISCUSSION ON EXPECTED INCREASES SHOULD BE ANTICIPATED

AT THE 60% COST ESTIMATE.

30 DAY LOOK AHEAD COST ESTIMATE

DRAFT REVIEW LATE OCTOBER WITH SCASD + CRA

PRESENT TO BOARD ON 11/03/14 WORK SESSION

7.01

ESTIMATING PROCESS

30% DOCUMENTS

COST ESTIMATE PROCESS

7.02

SEPTEMBER 26, 2014

SEPTEMBER 30, 2014

OCTOBER, 2014

LATE OCTOBER, 2014

LATE OCTOBER, 2014

NOVEMBER 3, 2014

NOVEMBER 10, 2014

30% DRAWINGS TO MASSARO

CRA/SCASD/MCMS MET TO DISCUSS 30%

CRA + MCMS INDEPENDENT COST

ESTIMATES

ANALYSIS OF COST ESTIMATES

“BELT & SUSPENDERS” APPROACH

COST ESTIMATE REVIEWED BY SCASD

COST ESTIMATE PRESENTED TO BOARD

COST ESTIMATE TENTATIVELY APPROVED

ALTERNATES

01 VEGETATED ROOF AT SOUTH BUILDING

02 SOLAR ARRAY AT SOUTH BUILDING

03 TERRAZZO IN CORRIDORS

04 UNCLASSIFIED SOILS

05 ROOFING

7.03

PRELIMINARY ALTERNATES

LIST WILL EVOLVE AS WE PROCEED TO

60% & 90% SUBMISSIONS

REIMBURSEMENT

Reimbursement Estimate

1 Project Type Secondary

2 Current Enrollment 2,387 PDE 2011-2012 report

3 Current Enrollment + 10% 2,626

4 PDE Highest Projected Enrollment (PDE 7/2011) 2,413 PDE 7/2011 report

5 Highest Projected Enrollment for Calculation 2,626 Current Enrollment + 10%

6 Planned Special Education Rooms 5 Amy Yurko Program 1/31/2013

7 Planned Special Education Capacity 125

8 Reimbursement Capacity Basis 2751

8 Rated Pupil Capacity Capacity RPC factor

9 2751 1.11 3053 RPC

Legislated Per Pupil Reimbursement Allowance $6,200

CTC FTE 462

10 Legislated Per Pupil Reimbursement Allowance $7,600

11 Maximum Eligible Reimbursement Basis High School $18,930,317 Gross

Maximum Eligible Reimbursement Basis CTC $3,511,200 Gross

Gross Total $22,441,517 Gross

12 District MVAR or CARF 0.2891 New CARF, PDE Part D

attachment C, April 8, 2013

13 Existing Building Renovation- 10% Increase $648,784

14 Sustainable Design (LEED)- 10% Increase $648,784

15 Estimated NET Reimbursement * NET

* This approximate estimate will change depending on final project scope and costs, validated by 60% Submission.

$5,500,000-$6,500,0007.04

01

02

03

04

05

06

07

08

SITE

PROGRAM

BUILDING DESIGN

ENGINEERING

SCHEDULE

PHASING

COST

LEED

LEED

NOTE: LEED CERTIFICATION MAY BE AFFECTED BY PEDA & DCED GRANTS WHICH WILL BE AWARDED IN

THE NEXT MONTH. DESIGN TEAM HAS FULLY INTEGRATED LEED CERTIFICATION PROCESS INTO DESIGN

AT THIS TIME INCLUDING INITIAL SPECIFICATIONS COMPLETED FOR THE 30% CERTIFICATION.

8.01