vicroads bridge technical note 2007-001v10

Upload: yyanan1118

Post on 16-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    1/10

    vicroads

    2007/001 Bridge Technical Note

    SAFETY DURING INSPECTION AND REPAIR OF

    CORROSION-DAMAGED BURIED CORRUGATED METAL

    STRUCTURES (BCMS)

    Note: BCMS is used throughout this document as an abbreviation for Buried Corrugated MetalStructure (both singular and plural) and signifies metal culverts and arches of round, elliptical or

    compound cross-section.

    1. INTRODUCTION

    In October 2006, on the basis of advice from the Principal Bridge Engineer, the Manager Corporate

    Occupational Health and Safety issued a prohibition on entry into all corrosion-damaged BCMS with the

    advice that inspection of these BCMS must be conducted from outside of the barrel. The Principal BridgeEngineer subsequently recommended that inspection from within the barrel of corrosion-damaged BCMS

    must not be attempted until a suitably qualified and experienced inspector had determined that it was safe to

    do so.

    This technical guidance note provides guidance on:

    (Particularly for those involved in Level 1 inspections) the recognition of potentially unstable

    BCMS and avoidance of exposure to dangerous workplace conditions;

    Criteria for the selection of suitably qualified and experienced inspectors who:o

    Are authorised to perform Safety Inspections (described in part 6) of severely corrosion-

    damaged, propped or deformed BCMS;

    o

    May authorise entry into the BCMS for maintenance purposes by maintenance personnel;

    o

    May determine whether it is safe for the public to continue to use a BCMS where it is

    provided for pedestrian and agricultural use;

    o

    May authorise remedial action such as propping;

    The procedure for inspection and assessment of severely corrosion-damaged BCMS;

    Actions that may be required in the event that a dangerously unstable BCMS is discovered.

    The driving principle underlying the advice given in this note is the need to ensure the safety of the public

    and the safety of those who inspect BCMS and those who may subsequently undertake rehabilitation works

    for whom BCMS are a workplace. In this respect the readers attention is drawn to the requirements of the

    Occupational Health and Safety Act 2004 and in particular sections 21 to 26 and section 28. The relevant

    sections of the Act are listed in Appendix A

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    2/10

    BTN 2007/001 Buried Corrugated Metal Structures

    It may only be possible to assess the loss of metal in the water-side (open side) surface of the BCMS walls

    around the invert and within the splash-zone above water-level. There may be significant loss of metal

    thickness to the buried (soil-side) faces of the BCMS and, unless the metal becomes visibly perforated or so

    thin that it can be pierced with a hand pick or chisel point, it will not be possible to fully assess the degree of

    corrosion on the soil-side. If a detailed assessment of soil-side corrosion is required, this can be achieved by

    cutting samples from the wall-panels or by excavation to expose the BCMS. The extent and method of

    cutting or excavation must be agreed with the Principal Bridge Engineer in order to prevent the risk of de-

    stabilising the BCMS. It may also be possible to use non-destructive methods of testing such as ultra-sound

    to measure the thickness of the metal.

    Issues that may require action to enable detailed inspection:

    The invert of the BCMS may be obscured by debris and or submerged below water-level;

    Where the BCMS is being used as a cattle underpass, the invert may be obscured by gravel and

    cattle-droppings;

    Where the BCMS is being used as a pedestrian underpass, the invert may be paved;

    Features of a potentially unstable BCMS:

    The walls may be deformed;

    The soffit may be propped;

    The invert may be severely corroded and there may be significant loss of metal;

    The backfill may be eroded or softened.

    4. SELECTION OF SUITABLY QUALIFIED AND EXPERIENCED INSPECTORSFor the purpose of this guidance note a suitably qualified and experienced inspector, who is authorised to

    determine whether it is safe to enter a corrosion-damaged (possibly propped) BCMS for inspection and

    maintenance works, is defined as a person who:

    a.

    In the opinion of the Principal Bridge Engineer, has sufficient experience and engineering

    knowledge of the structural features of BCMS and, in particular, the possible modes of failure; and

    b. Is qualified to perform level 3 inspections as defined in the VicRoads Bridge Inspection Manual; or

    c.

    Is authorised to make an inspection by the Principal Bridge Engineer or by the Regional Director in

    consultation with the Principal Bridge Engineer;

    i.e. the inspector must satisfy either 4a and 4b or 4a and 4c

    5. RISK MANAGEMENT

    Confined Spaces Regulations

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    3/10

    BTN 2007/001 Buried Corrugated Metal Structures

    is showing signs of corrosion damage, deformation or if it has been propped (tommed). Advice is given in

    Part 6 on the procedure to be followed during inspections when there is debris obscuring the invert.

    Risk Assessment

    The inspector is advised to make a preliminary visit to the BCMS in order to assess the need for special

    means of access such as a ladder or the clearance of dense vegetation and to enable the preparation of a site-

    specific risk-assessment / Job-Safety Analysis. If a two-stage visit is impractical - due to the remoteness of

    the location for example - the inspector is advised to conduct a preliminary inspection and risk assessment on

    arrival at the BCMS and to continue with a detailed inspection only in the event that safe access is possible.

    The inspection must be aborted if there is any safety concern that cannot be managed with the available

    equipment and a further visit should be planned only when all outstanding safety concerns have been

    satisfactorily resolved. Risk assessments must be in writing and must be recorded for future reference in

    RAS and in the Principal Bridge Engineers structure file.

    A checklist of common hazards is provided in Appendix E as an aid to risk assessment.

    6. RECOMMENDED PROCEDURE FOR INSPECTION

    Note: The following advice is additional to and must be read in conjunction with the VicRoads Bridge

    Inspection Manual.

    Access to Records

    Prior to the inspection of BCMS, the inspector or the manager responsible for the inspection is advised toreview the most recent inspection reports and inform the inspection team of the last known condition of the

    BCMS together with any previously identified hazards.

    In the normal course of events a Level 3 inspection will be arranged on the basis of a previously reported

    condition 3 or 4 rating and there will be a known history of deteriorating condition. Where a BCMS is

    already known to be severely corroded with significant loss of metal to the invert, or it is deformed or

    propped, a Safety Inspection (as described below) must be arranged. In these circumstances the possibility of

    instability must be assumed. However, a corrosion-damaged BCMS may be discovered for the first timeduring a Level 1, 2 or 3 inspection. With this in mind the procedure described below is to be adopted in

    accordance with the level of the inspection.

    General Guidance Applicable to all Levels of Inspection

    Adequate lighting must be available throughout the inspection;

    In all cases an initial inspection should be conducted from outside of the BCMS to check for the

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    4/10

    BTN 2007/001 Buried Corrugated Metal Structures

    Those managing inspections must ensure that if a potentially unstable BCMS is

    identified:

    Warning signs are erected promptly;

    A Safety Inspection is arranged at the earliest opportunity;

    The need for temporary closure is addressed promptly.

    Level 1 Inspection

    The fundamental principle is that an inspection at this level must only be attempted if the BCMS is in

    condition 1 or 2 and there is no propping or deformation.

    The inspector must be suitably experienced and qualified to conduct Level 1 inspections in

    accordance with the requirements of the Bridge Inspection Manual for this level;

    The BCMS is to be inspected from outside and, if the metal is rusting and has holes or there are

    missing sections or the BCMS is propped or there is visible deformation, the inspection must be

    terminated immediately and a report made to the appropriate manager;

    If there is debris or other material obscuring the invert, the first 0.3 to 1m of the metal surface should

    be exposed without entering the BCMS and its condition assessed as before;

    If metal in the exposed area is badly rusted and there are holes or metal is missing, the inspection

    must be terminated and a report made to the appropriate manager as before;

    If the Level 1 inspection team considers the BCMS to be unsafe, they must place signs warning the

    public and other workers of the potential hazard at both ends of the BCMS;

    If invert metal is clearly visible and is sound and in good condition, clearing of debris may continue

    in 0.3 to 0.5m steps unless the condition of the corrugated metal deteriorates and holes or missing

    areas become visible - in which case the inspection must be terminated immediately and a report

    made to the appropriate manager.

    Level 2 Inspection

    The Level 2 inspection shall be as the Level 1 inspection described above with the following additions:

    The inspector must be suitably experienced and qualified to conduct Level 2 inspections in

    accordance with the requirements of the Bridge Inspection Manual for this level;

    Provided that it is safe to do so the Level 2 inspector may probe the exposed metal surface from

    outside the BCMS and take soundings with a hammer and / or probe the metal with a pick or chisel

    point to assess the condition rating;

    If the visible part of the BCMS is in condition 1 or 2 the Level 2 inspector may enter the BCMS andcontinue to assess its condition;

    If the BCMS deteriorates to condition 3 or 4, the inspection must be aborted and a report must be

    made to the appropriate manager. It is recommended that a Safety Inspection is then arranged;

    Level 3 Inspection

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    5/10

    BTN 2007/001 Buried Corrugated Metal Structures

    Where the BCMS is used by the public (pedestrian and agricultural use for example), the inspector

    may recommend its temporary closure in the interests of safety;

    The inspector may if they consider that it is safe to do so, authorise access for maintenance and

    repair work and determine the requirement for propping;

    The propping system shall be designed by an engineer who is experienced in the design of

    temporary works and who shall either be:

    o

    qualified to Proof Engineer level in accordance with the VicRoads pre-qualification scheme;or

    o an engineer who meets with the approval of the Principal Bridge Engineer.

    7. ACTIONS

    Warning Signs

    In the event that a serious defect is discovered and it is considered to be too dangerous for the inspection to

    continue, warning signs should be erected immediately at both ends of the BCMS in order to inform both the

    public and other VicRoads personnel of the hazard. A detail for such a warning sign is given in Appendix D.

    Stability of the Highway

    In the event that the inspector considers the BCMS to be unstable and that there is a potential risk to users of

    the highway over the BCMS, the inspector must advise the Regional Director immediately.

    Barricading of Unstable BCMS

    If the inspector considers that a pedestrian underpass or a stock crossing (or any BCMS that is used for these

    purposes whether formally or informally) is considered to be unsafe for entry, this must be reported to theRegional Director immediately with the recommendation that the underpass is closed pending further

    investigation and repair. The following should be considered prior to closure:

    Consultation with users of the underpass and other affected parties (Police, catchment management

    authority and landowners for example);

    The route and signing of safe temporary diversions;

    The choice of barricade particularly where the BCMS carries water;

    Register of Occurrences and ActionsIn order to ensure that information is properly recorded for future reference, the structure record in RAS and

    in the Principal Bridge Engineers structure file should be updated with details of propping and any serious

    defect that is discovered such as deformation or severe corrosion damage together with details of any

    preventative action that is taken such as signing and barricading.

    8 REFERENCES

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    6/10

    BTN 2007/001 Buried Corrugated Metal Structures

    Approved July 2007

    GEOFF BOULLY

    Acting PRINCIPAL BRIDGE ENGINEER

    For further information please contact:

    Principal Bridge Engineer3 Prospect Hill Road Camberwell Vic 3124

    Telephone: (03) 9811 8307

    Facsimile: (03) 9811 8329

    Email: [email protected]

    Bridge Technical Notes are subject to periodic review and may be superseded

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    7/10

    BTN 2007/001 Buried Corrugated Metal Structures

    APPENDICES

    APPENDIX A

    Relevant Duties under the OHS Act 2004

    Main duties of employers

    21. Duties of employers to employees;

    23. Duties of employers to other persons;

    Duties of self-employed persons

    24. Duties of self-employed persons to other persons;

    Duties of employees

    25. Duties of employees;

    Duties of other persons

    26. Duties of persons who manage or control workplaces;

    28. Duties of designers of buildings or structures;

    APPENDIX B

    Extract from the Bridge Inspection Manual 2004

    BCMS Condition States

    This element includes all steel pipes, painted or galvanised, circular, elongated or elliptical.

    Condition state 1. - There is no evidence of rust or corrosion and the paintwork or

    galvanising is in good condition. The line and invert of the pipe is

    straight with no water being retained in the pipe.

    Condition state 2. - Surface or spot rusting may be evident and the paint system is no

    longer effective. There is no corrosion of the metal occurring. The line

    of the pipe is straight, but minor settlement may be allowing some

    water to be retained in the pipe.

    Condition state 3. - The paint system has failed and pitting corrosion is prominent

    especially at normal water level. Loss of section has occurred but

    there is still adequate section left to not affect serviceability of the

    pipe. There may be some deviation of the line of the pipes due to local

    buckling or moderate settlement of the pipe may be allowing a

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    8/10

    BTN 2007/001 Buried Corrugated Metal Structures

    APPENDIX C

    Examples of corrosion-damaged BCMS

    SN8616 Bulleen RoadBCMS inspected on the 13

    thDecember 2006 by SW Consultants P/L and found to be unsafe for concrete

    lining unless it is propped. The upper limit of corrosion-affected metal on the water-side is clearly visible.

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    9/10

    BTN 2007/001 Buried Corrugated Metal Structures

    APPENDIX D

    WARNING SIGN

    Notes:

    Freestanding sign to comply with AS1742.3:2002;

    To be placed at each end of the BCMS;

  • 7/23/2019 VicRoads Bridge Technical Note 2007-001V10

    10/10

    APPENDIX E

    VERSION: 1.0 DATE: December 2006 Page 10

    Item Feature Hazard Risk Possible Controls

    1 Unstable BCMS- Propped (tommed)

    -

    Deformed-

    Corroded / missing areas ofmetal

    Or any of these in combination

    Collapse of the BCMSFalling objects

    Crush injuriesSuffocation

    DrowningBeing struck by falling objects

    Assess individual circumstances

    Abandon inspection

    Arrange safety inspectionReportingWarning Signs

    BarricadingPropping / temporary support

    Remedial workRecording

    2 BCMS Confined Space Poor access and egress (particularly in anemergency)

    Assess individual circumstances

    Manage in accordance with Occupational

    Health and Safety (Confined Spaces)Regulations together with VicRoads confinedspaces procedures

    3 Difficult access into BCMS Working at Height

    Uneven Surfaces (Slips, Trips and Falls)

    Falling (into water)

    Injuries to joints and limbs

    Assess individual circumstances

    Clear vegetationUse ladder

    Provide lightingUse appropriate footware

    No lone-working

    4 Water Working in near to water Drowning Assess individual circumstancesAvoid deep and / or fast flowing water

    Monitor weather conditions and avoid enteringwater-courses prone to flash-flooding

    No lone-working

    5 Corroded / missing areas of metal Sharp metal edges Laceration Assess individual circumstances

    Personal Protective Equipment

    (Gloves, boots, helmet)Provide lighting

    6 - Voids in and behind BCMS wallscaused by corrosion and erosion

    - Surrounding area

    Venomous creatures Snake or insect bites Assess individual circumstances

    No lone-working

    Provide lightingAvoid probing by hand into hidden voids / darkareas

    7 Debris or water in invert (invert

    condition obscured)

    Hidden corrosion-damaged metal surfaces As items 1 and 5 Assess individual circumstances

    Clear debris and enter in stages only if safe toproceed

    Note: This is a list of the main hazards and is not exhaustive. A Risk Assessment based on site-specific conditions is necessary in order to identify all hazards that may be present.