vicroads bridge technical note 2007-001v10
TRANSCRIPT
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
1/10
vicroads
2007/001 Bridge Technical Note
SAFETY DURING INSPECTION AND REPAIR OF
CORROSION-DAMAGED BURIED CORRUGATED METAL
STRUCTURES (BCMS)
Note: BCMS is used throughout this document as an abbreviation for Buried Corrugated MetalStructure (both singular and plural) and signifies metal culverts and arches of round, elliptical or
compound cross-section.
1. INTRODUCTION
In October 2006, on the basis of advice from the Principal Bridge Engineer, the Manager Corporate
Occupational Health and Safety issued a prohibition on entry into all corrosion-damaged BCMS with the
advice that inspection of these BCMS must be conducted from outside of the barrel. The Principal BridgeEngineer subsequently recommended that inspection from within the barrel of corrosion-damaged BCMS
must not be attempted until a suitably qualified and experienced inspector had determined that it was safe to
do so.
This technical guidance note provides guidance on:
(Particularly for those involved in Level 1 inspections) the recognition of potentially unstable
BCMS and avoidance of exposure to dangerous workplace conditions;
Criteria for the selection of suitably qualified and experienced inspectors who:o
Are authorised to perform Safety Inspections (described in part 6) of severely corrosion-
damaged, propped or deformed BCMS;
o
May authorise entry into the BCMS for maintenance purposes by maintenance personnel;
o
May determine whether it is safe for the public to continue to use a BCMS where it is
provided for pedestrian and agricultural use;
o
May authorise remedial action such as propping;
The procedure for inspection and assessment of severely corrosion-damaged BCMS;
Actions that may be required in the event that a dangerously unstable BCMS is discovered.
The driving principle underlying the advice given in this note is the need to ensure the safety of the public
and the safety of those who inspect BCMS and those who may subsequently undertake rehabilitation works
for whom BCMS are a workplace. In this respect the readers attention is drawn to the requirements of the
Occupational Health and Safety Act 2004 and in particular sections 21 to 26 and section 28. The relevant
sections of the Act are listed in Appendix A
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
2/10
BTN 2007/001 Buried Corrugated Metal Structures
It may only be possible to assess the loss of metal in the water-side (open side) surface of the BCMS walls
around the invert and within the splash-zone above water-level. There may be significant loss of metal
thickness to the buried (soil-side) faces of the BCMS and, unless the metal becomes visibly perforated or so
thin that it can be pierced with a hand pick or chisel point, it will not be possible to fully assess the degree of
corrosion on the soil-side. If a detailed assessment of soil-side corrosion is required, this can be achieved by
cutting samples from the wall-panels or by excavation to expose the BCMS. The extent and method of
cutting or excavation must be agreed with the Principal Bridge Engineer in order to prevent the risk of de-
stabilising the BCMS. It may also be possible to use non-destructive methods of testing such as ultra-sound
to measure the thickness of the metal.
Issues that may require action to enable detailed inspection:
The invert of the BCMS may be obscured by debris and or submerged below water-level;
Where the BCMS is being used as a cattle underpass, the invert may be obscured by gravel and
cattle-droppings;
Where the BCMS is being used as a pedestrian underpass, the invert may be paved;
Features of a potentially unstable BCMS:
The walls may be deformed;
The soffit may be propped;
The invert may be severely corroded and there may be significant loss of metal;
The backfill may be eroded or softened.
4. SELECTION OF SUITABLY QUALIFIED AND EXPERIENCED INSPECTORSFor the purpose of this guidance note a suitably qualified and experienced inspector, who is authorised to
determine whether it is safe to enter a corrosion-damaged (possibly propped) BCMS for inspection and
maintenance works, is defined as a person who:
a.
In the opinion of the Principal Bridge Engineer, has sufficient experience and engineering
knowledge of the structural features of BCMS and, in particular, the possible modes of failure; and
b. Is qualified to perform level 3 inspections as defined in the VicRoads Bridge Inspection Manual; or
c.
Is authorised to make an inspection by the Principal Bridge Engineer or by the Regional Director in
consultation with the Principal Bridge Engineer;
i.e. the inspector must satisfy either 4a and 4b or 4a and 4c
5. RISK MANAGEMENT
Confined Spaces Regulations
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
3/10
BTN 2007/001 Buried Corrugated Metal Structures
is showing signs of corrosion damage, deformation or if it has been propped (tommed). Advice is given in
Part 6 on the procedure to be followed during inspections when there is debris obscuring the invert.
Risk Assessment
The inspector is advised to make a preliminary visit to the BCMS in order to assess the need for special
means of access such as a ladder or the clearance of dense vegetation and to enable the preparation of a site-
specific risk-assessment / Job-Safety Analysis. If a two-stage visit is impractical - due to the remoteness of
the location for example - the inspector is advised to conduct a preliminary inspection and risk assessment on
arrival at the BCMS and to continue with a detailed inspection only in the event that safe access is possible.
The inspection must be aborted if there is any safety concern that cannot be managed with the available
equipment and a further visit should be planned only when all outstanding safety concerns have been
satisfactorily resolved. Risk assessments must be in writing and must be recorded for future reference in
RAS and in the Principal Bridge Engineers structure file.
A checklist of common hazards is provided in Appendix E as an aid to risk assessment.
6. RECOMMENDED PROCEDURE FOR INSPECTION
Note: The following advice is additional to and must be read in conjunction with the VicRoads Bridge
Inspection Manual.
Access to Records
Prior to the inspection of BCMS, the inspector or the manager responsible for the inspection is advised toreview the most recent inspection reports and inform the inspection team of the last known condition of the
BCMS together with any previously identified hazards.
In the normal course of events a Level 3 inspection will be arranged on the basis of a previously reported
condition 3 or 4 rating and there will be a known history of deteriorating condition. Where a BCMS is
already known to be severely corroded with significant loss of metal to the invert, or it is deformed or
propped, a Safety Inspection (as described below) must be arranged. In these circumstances the possibility of
instability must be assumed. However, a corrosion-damaged BCMS may be discovered for the first timeduring a Level 1, 2 or 3 inspection. With this in mind the procedure described below is to be adopted in
accordance with the level of the inspection.
General Guidance Applicable to all Levels of Inspection
Adequate lighting must be available throughout the inspection;
In all cases an initial inspection should be conducted from outside of the BCMS to check for the
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
4/10
BTN 2007/001 Buried Corrugated Metal Structures
Those managing inspections must ensure that if a potentially unstable BCMS is
identified:
Warning signs are erected promptly;
A Safety Inspection is arranged at the earliest opportunity;
The need for temporary closure is addressed promptly.
Level 1 Inspection
The fundamental principle is that an inspection at this level must only be attempted if the BCMS is in
condition 1 or 2 and there is no propping or deformation.
The inspector must be suitably experienced and qualified to conduct Level 1 inspections in
accordance with the requirements of the Bridge Inspection Manual for this level;
The BCMS is to be inspected from outside and, if the metal is rusting and has holes or there are
missing sections or the BCMS is propped or there is visible deformation, the inspection must be
terminated immediately and a report made to the appropriate manager;
If there is debris or other material obscuring the invert, the first 0.3 to 1m of the metal surface should
be exposed without entering the BCMS and its condition assessed as before;
If metal in the exposed area is badly rusted and there are holes or metal is missing, the inspection
must be terminated and a report made to the appropriate manager as before;
If the Level 1 inspection team considers the BCMS to be unsafe, they must place signs warning the
public and other workers of the potential hazard at both ends of the BCMS;
If invert metal is clearly visible and is sound and in good condition, clearing of debris may continue
in 0.3 to 0.5m steps unless the condition of the corrugated metal deteriorates and holes or missing
areas become visible - in which case the inspection must be terminated immediately and a report
made to the appropriate manager.
Level 2 Inspection
The Level 2 inspection shall be as the Level 1 inspection described above with the following additions:
The inspector must be suitably experienced and qualified to conduct Level 2 inspections in
accordance with the requirements of the Bridge Inspection Manual for this level;
Provided that it is safe to do so the Level 2 inspector may probe the exposed metal surface from
outside the BCMS and take soundings with a hammer and / or probe the metal with a pick or chisel
point to assess the condition rating;
If the visible part of the BCMS is in condition 1 or 2 the Level 2 inspector may enter the BCMS andcontinue to assess its condition;
If the BCMS deteriorates to condition 3 or 4, the inspection must be aborted and a report must be
made to the appropriate manager. It is recommended that a Safety Inspection is then arranged;
Level 3 Inspection
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
5/10
BTN 2007/001 Buried Corrugated Metal Structures
Where the BCMS is used by the public (pedestrian and agricultural use for example), the inspector
may recommend its temporary closure in the interests of safety;
The inspector may if they consider that it is safe to do so, authorise access for maintenance and
repair work and determine the requirement for propping;
The propping system shall be designed by an engineer who is experienced in the design of
temporary works and who shall either be:
o
qualified to Proof Engineer level in accordance with the VicRoads pre-qualification scheme;or
o an engineer who meets with the approval of the Principal Bridge Engineer.
7. ACTIONS
Warning Signs
In the event that a serious defect is discovered and it is considered to be too dangerous for the inspection to
continue, warning signs should be erected immediately at both ends of the BCMS in order to inform both the
public and other VicRoads personnel of the hazard. A detail for such a warning sign is given in Appendix D.
Stability of the Highway
In the event that the inspector considers the BCMS to be unstable and that there is a potential risk to users of
the highway over the BCMS, the inspector must advise the Regional Director immediately.
Barricading of Unstable BCMS
If the inspector considers that a pedestrian underpass or a stock crossing (or any BCMS that is used for these
purposes whether formally or informally) is considered to be unsafe for entry, this must be reported to theRegional Director immediately with the recommendation that the underpass is closed pending further
investigation and repair. The following should be considered prior to closure:
Consultation with users of the underpass and other affected parties (Police, catchment management
authority and landowners for example);
The route and signing of safe temporary diversions;
The choice of barricade particularly where the BCMS carries water;
Register of Occurrences and ActionsIn order to ensure that information is properly recorded for future reference, the structure record in RAS and
in the Principal Bridge Engineers structure file should be updated with details of propping and any serious
defect that is discovered such as deformation or severe corrosion damage together with details of any
preventative action that is taken such as signing and barricading.
8 REFERENCES
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
6/10
BTN 2007/001 Buried Corrugated Metal Structures
Approved July 2007
GEOFF BOULLY
Acting PRINCIPAL BRIDGE ENGINEER
For further information please contact:
Principal Bridge Engineer3 Prospect Hill Road Camberwell Vic 3124
Telephone: (03) 9811 8307
Facsimile: (03) 9811 8329
Email: [email protected]
Bridge Technical Notes are subject to periodic review and may be superseded
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
7/10
BTN 2007/001 Buried Corrugated Metal Structures
APPENDICES
APPENDIX A
Relevant Duties under the OHS Act 2004
Main duties of employers
21. Duties of employers to employees;
23. Duties of employers to other persons;
Duties of self-employed persons
24. Duties of self-employed persons to other persons;
Duties of employees
25. Duties of employees;
Duties of other persons
26. Duties of persons who manage or control workplaces;
28. Duties of designers of buildings or structures;
APPENDIX B
Extract from the Bridge Inspection Manual 2004
BCMS Condition States
This element includes all steel pipes, painted or galvanised, circular, elongated or elliptical.
Condition state 1. - There is no evidence of rust or corrosion and the paintwork or
galvanising is in good condition. The line and invert of the pipe is
straight with no water being retained in the pipe.
Condition state 2. - Surface or spot rusting may be evident and the paint system is no
longer effective. There is no corrosion of the metal occurring. The line
of the pipe is straight, but minor settlement may be allowing some
water to be retained in the pipe.
Condition state 3. - The paint system has failed and pitting corrosion is prominent
especially at normal water level. Loss of section has occurred but
there is still adequate section left to not affect serviceability of the
pipe. There may be some deviation of the line of the pipes due to local
buckling or moderate settlement of the pipe may be allowing a
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
8/10
BTN 2007/001 Buried Corrugated Metal Structures
APPENDIX C
Examples of corrosion-damaged BCMS
SN8616 Bulleen RoadBCMS inspected on the 13
thDecember 2006 by SW Consultants P/L and found to be unsafe for concrete
lining unless it is propped. The upper limit of corrosion-affected metal on the water-side is clearly visible.
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
9/10
BTN 2007/001 Buried Corrugated Metal Structures
APPENDIX D
WARNING SIGN
Notes:
Freestanding sign to comply with AS1742.3:2002;
To be placed at each end of the BCMS;
-
7/23/2019 VicRoads Bridge Technical Note 2007-001V10
10/10
APPENDIX E
VERSION: 1.0 DATE: December 2006 Page 10
Item Feature Hazard Risk Possible Controls
1 Unstable BCMS- Propped (tommed)
-
Deformed-
Corroded / missing areas ofmetal
Or any of these in combination
Collapse of the BCMSFalling objects
Crush injuriesSuffocation
DrowningBeing struck by falling objects
Assess individual circumstances
Abandon inspection
Arrange safety inspectionReportingWarning Signs
BarricadingPropping / temporary support
Remedial workRecording
2 BCMS Confined Space Poor access and egress (particularly in anemergency)
Assess individual circumstances
Manage in accordance with Occupational
Health and Safety (Confined Spaces)Regulations together with VicRoads confinedspaces procedures
3 Difficult access into BCMS Working at Height
Uneven Surfaces (Slips, Trips and Falls)
Falling (into water)
Injuries to joints and limbs
Assess individual circumstances
Clear vegetationUse ladder
Provide lightingUse appropriate footware
No lone-working
4 Water Working in near to water Drowning Assess individual circumstancesAvoid deep and / or fast flowing water
Monitor weather conditions and avoid enteringwater-courses prone to flash-flooding
No lone-working
5 Corroded / missing areas of metal Sharp metal edges Laceration Assess individual circumstances
Personal Protective Equipment
(Gloves, boots, helmet)Provide lighting
6 - Voids in and behind BCMS wallscaused by corrosion and erosion
- Surrounding area
Venomous creatures Snake or insect bites Assess individual circumstances
No lone-working
Provide lightingAvoid probing by hand into hidden voids / darkareas
7 Debris or water in invert (invert
condition obscured)
Hidden corrosion-damaged metal surfaces As items 1 and 5 Assess individual circumstances
Clear debris and enter in stages only if safe toproceed
Note: This is a list of the main hazards and is not exhaustive. A Risk Assessment based on site-specific conditions is necessary in order to identify all hazards that may be present.