ABBREVIATED RESETTLEMENT ACTION PLAN SOLENTEGRE ENERJİ YATIRIMLARI TİCARET A.Ş. 1. Information About Project Name &Location of Sub- project SOLENTEGRE SPP is located in center district of Elazığ province Project Sponsor SOLENTEGRE Enerji Yatırımları Ticaret A.Ş. Project Cost 11.903.350 USD Installed Generation Capacity 8 MW Key Dates of Implementation Totally 160,097.2 m² area is utilized by SOLENTEGRE Enerji Yatırımları Ticaret A.Ş. for th power plant.The company has received preliminary permits for all of the land belonging to the Treasury. 10.260 TL was paid as a preliminary permit. Route of power transmission line passes through private lands. Expropriation will be done for the parts of the lands where the line passes. . Project Components& Land Requirements Project components include solar panels, inverters, transformer substation, cabling systems and a camera system. All components of the project will be located on 160,097.2 m² area. Transmission line corridor (km):8,2 km 2.Inventory of Land & Assets Acquired from Private Owners (Completely Volunteer Purchased)(*) Name of Owners/land user Do not exist Project Component: Area(s) / plots(s) acquired (ha) - Owner’s/user’s total land holding (ha); % taken for project. - Land use: pasture, agriculture, residence, etc. - Inventory of any structures or other fixed or productive assets (wells, fences, trees, field crops, -

Upload: dinhthuy

Post on 22-May-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: english.kalkinma.com.trenglish.kalkinma.com.tr/data/file/duyurular/genel/Land... · Web viewSolentegre Enerji Yatırımları Ticaret A.Ş. , 8 MW licensed solar power plant is loacated

ABBREVIATED RESETTLEMENT ACTION PLAN SOLENTEGRE ENERJİ YATIRIMLARI TİCARET A.Ş.

1. Information About Project

Name &Location of Sub-project SOLENTEGRE SPP is located in center district of Elazığ province

Project Sponsor SOLENTEGRE Enerji Yatırımları Ticaret A.Ş.Project Cost 11.903.350 USD

Installed Generation Capacity 8 MW

Key Dates of Implementation

Totally 160,097.2 m² area is utilized by SOLENTEGRE Enerji Yatırımları Ticaret A.Ş. for th power plant.The company has received preliminary permits for all of the land belonging to the Treasury. 10.260 TL was paid as a preliminary permit.Route of power transmission line passes through private lands. Expropriation will be done for the parts of the lands where the line passes. .

Project Components& Land Requirements

Project components include solar panels, inverters, transformer substation, cabling systems and a camera system.All components of the project will be located on 160,097.2 m² area.Transmission line corridor (km):8,2 km

2.Inventory of Land & Assets Acquired from Private Owners (Completely Volunteer Purchased)(*)

Name of Owners/land user Do not exist

Project Component: Area(s) / plots(s) acquired (ha) -

Owner’s/user’s total land holding (ha); % taken for project.

-

Land use: pasture, agriculture, residence, etc. -

Inventory of any structures or other fixed or productive assets (wells, fences, trees, field crops, etc) affected.

-

Indicate if land was rented or informally used by another party.

-

Indicate if non-owner users had assets, trees, crops, etc affected

-

Indicate if land-based activity is primary source of income for owner or land user.

-

Compensation paid. -

Dates delivered. -

Impact on income of owner. -

2.1. Inventory of Land & Assets Acquired from Private Owners

Page 2: english.kalkinma.com.trenglish.kalkinma.com.tr/data/file/duyurular/genel/Land... · Web viewSolentegre Enerji Yatırımları Ticaret A.Ş. , 8 MW licensed solar power plant is loacated

Name of Owners/land user -

Project Component: Area(s) / plots(s) acquired (ha) -

Owner’s/user’s total land holding (ha); % taken for project.

-

Land use: pasture, agriculture, residence, etc. -

Inventory of any structures or other fixed or productive assets (wells, fences, trees, field crops, etc) affected.

-

Indicate if land was rented or informally used by another party.

-

Indicate if non-owner users had assets, trees, crops, etc affected

-

Indicate if land-based activity is primary source of income for owner or land user.

-

Compensation paid. -

Dates delivered. -

Impact on income of owner. -

3.Inventory of Public, Community, or State Land AcquiredLand parcels / plots acquired (ha). Treasury land : 160.097.2 m²

Land type / land use: Forest, commons for grazing, other. These lands are covered with thistle seed (thistle)

Ownership: State, community, other.Structures or other fixed assets.

T. C. Treasury

Compensation, land transfer, or other measures to mitigate impacts on land users. Specify measures and dates of delivery.

10.260 TL was paid for the Treasury land preliminary permit fee.

4.Consultations,Communications & Management of Grievances and Implementation Issues

-General Information About Project and Project Area :

Solentegre Enerji Yatırımları Ticaret A.Ş. , 8 MW licensed solar power plant is loacated in Elazığ Central district, within the boundries of Şahinkaya village, but 3.3 km away from the village settlement area.The location is 30 km away from Keban Dam .Elazig province, according to the Solar Energy Potential Atlas of General Directorate of Renewable Energy, with an annual average of 1600-1650 kWh / m² solar radiation potential, is a very suitable place for solar power plants.The company has received preliminary permits for a total of 160.097,2 m² Treasury land. 10.260 TL was

Page 3: english.kalkinma.com.trenglish.kalkinma.com.tr/data/file/duyurular/genel/Land... · Web viewSolentegre Enerji Yatırımları Ticaret A.Ş. , 8 MW licensed solar power plant is loacated

paid as a preliminary permit.

There aren’t any non-legal users of the area. During the side visit to the Project Side, a visual inspection by expert biologist was conducted and the presence of thorn was observed on the land. There are enough lands around available for being utilized as pasture, therefore the utilization of the land for SPP project will not effect the husbandary feeding of the village.

-Consultations,Communications & Management of Grievances:

The company organized a Stakeholder Consultation Meeting on 23.06.2015 at Şahinkaya Tea House.Solentegre SPP Manager Kürşat Tezkan gave information about the layout of solar panels and solar power plants in the world, accompanied by a presentation. Then a presentation was made by environmental engineer Derya Erika ÇAMURDANOĞLU of DOKAY, EIA consultant company. She evaluated the environmental and social impacts of the project.Then right to speak was given to the participants for comments, suggestions and questions. The questions asked in this section were answered by the project manager Kürşat Tezkan.He stated that, in the investment stage, it was planned to employ staff primarily from Şahinkaya village, Elazığ and surrounding areas. Also the needs of staff would be met from grocery store and other suppliers from the village. After commissioning, six staff was planned for operation. The preference would again be Şahinkaya village and the vicinity for these staff.

Corporate social responsibility:The solar power plant construction will not create negative affects to the area and to the people living around. However, under corporate social responsibility and for the purpose of establishing good relations in the region the company plans to do some aids to the village like;

-renewing the roads,-meeting some needs of the school and other public facilities.