vihanga status as on 5th oct 2013

16
Project Progess – 05 th Oct 2013

Upload: manjumyhome

Post on 24-May-2015

312 views

Category:

Real Estate


4 download

DESCRIPTION

Vihanga status

TRANSCRIPT

Page 1: Vihanga status as on 5th oct 2013

Project Progess – 05th Oct 2013

Page 2: Vihanga status as on 5th oct 2013

CRS WALL 1M EXTENSION TOWARDS EAST SIDE IN PROGRESS

Page 3: Vihanga status as on 5th oct 2013

CRS WALL WORK IM EXTENSION TOWARDS SOUTH WEST

Page 4: Vihanga status as on 5th oct 2013

TOP VIEW OF PART-1 BLOCK 1,2,3,4 &17,18,19,20

Page 5: Vihanga status as on 5th oct 2013

PART-1/SVS WORK PROGRESS FOR BLOCKS -1,2

Page 6: Vihanga status as on 5th oct 2013

PART-2/JBEM WORK PROGRESS FOR BLOCKS -15&16

Page 7: Vihanga status as on 5th oct 2013

PART-2/JBEM WORK PROGRESS FOR BLOCKS -15 & 16

Page 8: Vihanga status as on 5th oct 2013

PART-2/JBEM WORK PROGRESS FOR BLOCKS -15 & 16

Page 9: Vihanga status as on 5th oct 2013

PART-2/JBEM WORK PROGRESS FOR BLOCKS -5&6

Page 10: Vihanga status as on 5th oct 2013

PART-3/GBL WORK PROGRESS FOR BLOCKS -13&14

Page 11: Vihanga status as on 5th oct 2013

PART-3/GBL WORK PROGRESS FOR BLOCKS -13&14 PLACING OF BOOSTERS FOR SHOTFIRE

Page 12: Vihanga status as on 5th oct 2013

PART-3/GBL WORK PROGRESS FOR BLOCKS -13&14

Page 13: Vihanga status as on 5th oct 2013

PART-3/GBL WORK PROGRESS FOR BLOCKS -7 & 8

Page 14: Vihanga status as on 5th oct 2013

PART-4/CEIPL WORK PROGRESS FOR 11 & 12

Page 15: Vihanga status as on 5th oct 2013

PART-4/CEIPL WORK PROGRESS FOR 11 & 12

Page 16: Vihanga status as on 5th oct 2013

PART-4/CEIPL WORK PROGRESS FOR 9 & 10