virginia beach light rail extension to town center update...sep 01, 2015 · resource management...
TRANSCRIPT
Virginia Beach Light Rail Extension to Town Center Update
DCM Dave Hansen September 1, 2015
1
Virginia Beach Light Rail Extension to Town Center Update
I. NEPA conclusion
II. Light Rail Vehicle Purchase
III. Estimated cost savings on steel associated with Buy America
IV. Estimated cost savings on labor associated with Davis Bacon
V. Project Schedule
2
NEPA Conclusion
3
NEPA is Federal law applies to governmental agencies on projects where there is Federal funding, Federal decision, or other Federal action.
On major transit projects with Federal participation, the Federal Transit Administration (FTA)
is the lead Federal agency that must comply with NEPA. FTA requires the NEPA process to be
initiated on all transit projects where it is anticipated that Federal dollars will be required for
the completion of the construction of that project.
When the construction financing for the project is determined, if no Federal dollars are
included and there is no other Federal action required, the requirement for NEPA no longer
applies. With no FTA funding, decision, or action for that construction project, the NEPA
process is discontinued.
For the Light Rail extension into VB, it was assumed from early project stages that federal
dollars would be required for construction of the project for alternatives to Rosemont and to
the Resort Area; therefore, FTA approved the initiation of the NEPA process concurrent with
early development and design of the project.
NEPA Conclusion
4
City Council’s LPA decision limiting the scope of the project to a 3.1 mile extension on an existing
rail line prompted FTA Region III to consider whether an FEIS and ROD were required. FTA
Region III has suggested a Categorical Exclusion might be the appropriate “Class of Action” for
compliance with NEPA.
Because the funding (State and local) for the construction of the LPA no longer included Federal
funding, FTA no longer has a mandatory role in the project as defined by NEPA.
FTA has indicated an intention to discontinue the NEPA process at this time. We anticipate
receiving formal FTA correspondence confirming this decision.
If federal funding were to be requested, FTA would pursue a Class of Action known as a
Categorical Exclusion. A Categorical Exclusion would be considered and potentially issued only
after a request for federal funds was made.
If determined at a later date, based on unforeseen conditions, that Federal funds would be
required to complete the construction of the transit project, the appropriate project sponsor
would request a final determination of the Categorical Exclusion in order to complete the NEPA
process and apply for Federal funds.
Going forward the City will be required to comply with all environmental and historical permit regulations of federal, state and local jurisdictions.
NEPA Conclusion
5
Once FTA issues their process decision correspondence we expect a communication from HRT
advising how they will respond to the substantive public comments of the DEIS phase.
Use of funds to-date to advance the project development were necessary for the decision
making process that lead to the selection of the Town Center Alternative as the Locally
Preferred Alternative. On-going use of funds are necessary to advance project engineering
and other required environmental clearances such as wetland permitting. (i.e. - money wasn't
"wasted" on NEPA studies to-date as these were otherwise required for project development
and decision making)
Use of Federal funds for the purchase of the former NS ROW and use of Federal funds for
development of the project through the current design efforts have been covered under
legally separable and independent Federal decisions and independent of NEPA requirement.
Future use of Federal funds for operations and maintenance of the State/City funded project
are not jeopardized by not completing the NEPA process.
Future use of Federal funds for study or construction of follow-on extensions of transit is not
jeopardized by not completing the NEPA process for the current extension into Virginia Beach.
Source Documents
June 26, 2015 HRT letter to FTA Region III discussing NSRR ROW acquisition and
requesting clarification on the NEPA process when no Federal funding is involved with
the construction. (Attachment A)
June 30, 2015 FTA Region III response “FTA concludes that HRT’s intended use of
Federal funds for acquisition of the NSROW does not necessitate a NEPA review for a
future locally- funded transit project utilizing the same right-of way.” (Attachment B)
August 28, 2015 email from HRT asking, “Generally, would a decision to fund a transit
project entirely with State and City funds negate the need for the Federal Transit
Administration completing a NEPA review under current Federal environmental
requirements?” (Attachment C)
August 28, 2015 FTA Region III response, “FTA will not act as the lead Federal agency for
a proposed action if the project sponsor intends to fund a project entirely with State
and City funds.” (Attachment D)
6 Council Discussion on NEPA
Light Rail Vehicle Purchase
7
Study identified need for 4 additional vehicles
Estimated cost of $5.1M/vehicle for a total cost of $20.4M.
Minneapolis MetroRail has options to purchase 44 vehicles by same manufacturer (Siemens ) that built the original TIDE vehicles.
HRT/State are pursuing piggy-back option to acquire four of those vehicles.
MetroRail order cost per vehicle is $4.3M or $17.2M total for a total potential savings of $3.2M.
The option order is required to be placed by September 29, 2015 to take advantage of savings.
DRPT will fund purchase of rail vehicles.
State to hold City harmless on vehicle purchase.
September 15, 2015 City Council agenda item for approval IAW FY16 budget ordinance.
8
Projects Receiving Federal Funding • Compliance with Buy America Requirements • Representative end products used in construction such as iron and steel must be produced in the United States • Includes Structures, bridges, and track work construction • Costs for materials typically higher than other sources
Non-Federally Funded Projects
• Buy America requirements not applicable • 25% Reduction in source cost of steel products may be realized • Estimated Steel Track Material Savings $3.2M • Estimated Steel Savings for structural construction $3.2M • Total Estimated Steel Material Savings $6.4M
Estimated Cost Savings on Steel
associated with Buy America
9
Projects Receiving Federal Funding • Compliance with Davis Bacon Act for projects in excess of $2,000 • Prevailing wages must be paid to laborers and mechanics • Prevailing wages are typically higher • Federal Oversight Compliance required for Contract & Program Support, Project Management Services, & Technical Review Services
Non-Federally Funded Projects
• Davis Bacon Act requirements not applicable • 22% Reduction in wages may be realized • Estimated Project Labor savings $13M • Federal Project Oversight Compliance not applicable $1.1M • Total Non-Federal Procurement Savings $14.1M
Estimated Cost Savings on Labor
associated with Davis Bacon
Total Estimated Savings to the Project
Rail Cars $ 3.2M
Buy America $ 6.4M
Davis Bacon $14.1M
TOTAL $23.7M
10
Virginia Beach Light Rail Extension to Town Center – Project Schedule
Project Schedule of Key Milestones Date(s) Agency Lead FTA Review/Approval of Draft Environmental Impact Statement (DEIS) Nov. 2014 – March 11, 2015 HRT
Final DEIS Published/NOA, Circulated & Formal Public Comment (45 days) March 20 – May 5, 2015 HRT
City Staff Briefing to City Council with Locally Preferred Alternative
Recommendation to extend The Tide LRT to Town Center (Alternative IA)
March 17, 2015 City Staff
Locally Preferred Alternative selected by City Council (LRT to Town Center) May 12, 2015 City Council
Resource Management Plan adopted including Light Rail related CIP projects May 12, 2015 City Council
Commonwealth of Virginia approves Six Year Improvement Program June 17, 2015 CTB
Preliminary Engineering 30% (60% Utilities) Design/NEPA Conclusion July 2015 – October 2016 HRT – City Staff
City-DRPT-HRT Negotiation and Execution of Memorandum of Agreement July 2015 – July 2016 City-DRPT-HRT
Light Rail Vehicle Procurement City Council Consideration September 15, 2015 City Council
Light Rail Vehicle Contract Option exercised September 29, 2015 HRT
Bridging Documents January 2016 – October 2016 City Staff
Issue Letter of Interest (LOI) to Construction Industry October 2015 City Staff
RFQ Posted and Design-Build Team RFQ Response Development December 2015 – Feb. 2016 City Staff
RFQ Process - Prequalification of Design Build Teams March 2016 – April 2016 City Staff
Resource Management Plan adopted including Light Rail related CIP projects May 10, 2016 City Council
Record of Decision November 2016 HRT
RFP Issued to Prequalified Design-Build Teams/Proposal Development Phase December 2016 – Feb. 2017 City Staff
Bid Opening of Design-Build Contractor February 2017 City Staff
RFP City Evaluation Phase February 2017 - April 2017 City Staff
City Council Closed Session Brief of Proposals Received April 2017 City Council
Design-Build Team Selection and Negotiations April 2017 to June 2017 City Staff
City Council Approval of Comprehensive Agreement June 2017 City Council
Design-Build Contract Implementation Phase July 2017 – July 2019 City Staff
System Testing and Turnover Light Rail Operation to HRT July 2019 – December 2019 HRT
The Tide Light Rail System service to Virginia Beach Town Center Open to Public December 2019 HRT 11
State/Local Cost Share Funding Schedule
12
Proposed Pay-out Schedule for Virginia Beach Light Rail Project
Fiscal Year Project Cost Funding Split State Local
FY 17 $ 77,500,000 80/20 $ 62,000,000 $ 15,500,000
FY 18 $ 77,500,000 60/40 $ 46,500,000 $ 31,000,000
FY 19 $ 77,500,000 40/60 $ 31,000,000 $ 46,500,000
FY 20 $ 77,500,000 20/80 $ 15,500,000 $ 62,000,000
Total $ 310,000,000 $ 155,000,000 $ 155,000,000
September 15, 2015
Excerpt from the FY16 Budget Ordinance
Section 14. Notwithstanding Sec. 2-154 of the City Code and although this Capital Improvement Program includes funding for such purpose, the City Manager or his designee shall not authorize or approve the use of any funds appropriated herein to pay for any portion of a light rail vehicle until such time as the City Council provides, by ordinance or resolution, approval of such order or contract. This limitation shall include the City Manager or designee authorizing such an action on the behalf or at the behest of the City by another entity or body, whether state, local, or regional in nature.
13
Council Discussion
14