volume ii_lot b
TRANSCRIPT
© Transmission Design Branch
CEYLON ELECTRICITY BOARD SRI LANKA
Power Sector Development Transmission Project (PSDTP) - Lot B
1. Construction of 132kV Transmission Lines from
Matugama GSS to Ambalangoda GSS
Polpithimukalana to Aniyakanda GSS
Maningala to Pannala GSS
2. Replacement of Steel Ground Wire with OPGW from
Biyagama GSS to Sapugaskanda PS
Kotugoda GSS to Kelaniya GSS
Kelaniya GSS to Kolonnnawa GSS
Chilaw GSS to Kotugoda GSS
Pannipitiya GSS to Paragastota In & Out
Panadura GSS to T – Off point
EMPLOYER’S REQUIREMENTS Part 1
VOLUME II
Transmission Division Ceylon Electricity Board, P.O. Box 540, Colombo 02, Sri Lanka. June 2004 Document – Revision 2
TABLE OF CONTENT
Pages
1 Scope of Works1.1 General Description of the project 1 61.2 Plant & Equipment Including Spare Parts 7 71.3 Civil works, installation and other services 7 7
2 Documents, Drawings and Informations to be submitted with the bid
2.1 Documents,Drawings and Information to be Submitted 8 92.2 Information to be Submitted 10 11
2.2.2 Guarantees and Factors of Safety 11 132.2.3 Technical Particulars 14 262.2.4 Site Organization 27 282.2.5 Contract Dates 28 302.2.6 Departures from the Specification 31 312.2.7 Tender's Experience (New Construction) 32 332.2.8
34 342.2.9
34 342.2.10 Schedule of Major Items of Constructional Plants 34 352.2.11 Schedule of Sub Contractors 36 362.2.12 Financial Standing of the Bidder 37 372.2.13 Current Litigation 38 382.2.14 Roles of Joint Venture Member 39 39
3 Technical Specifications (Refer separate volume - Technical Specification - Transmission Line)
EMPLOYER'S REQUIREMENTS - TRANSMISSION LINE
Volume of Construction Work in Each of the Last Five YearsDetails of Other Work in Hand & Contractual Commitments
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 1
1. SCOPE OF WORKS
1.1 GENERAL DESCRIPTION OF THE PROJECT
1.1.1 132 KV DOUBLE CIRCUIT TRANSMISSION LINES
(a) 132kV double circuit three phase transmission line of, single 400mm2 ZEBRA (61/3.18mm) ACSR with one galvanized ground wire and one optical fibre ground wire (OPGW):
(i) From Mathugama to Ambalangoda -:28 km
(ii) From Polpithimukalana to Aniyakanda including π-off connection to one circuit of the Kotugoda / Kelaniya 132 kV Transmission Line at tower No: 34 A; the T-OFF connection shall be as shown in the drawing no. TD/CE/1/44/TYP-06 and subjected to the approval of the Employer’s Representative. -: 5.5 km; however the final length of the line will be confirmed at the pre-bid meeting.
(iii) From Maningala to Pannala including π -off connection to one circuit of the Kotugoda / Puttlum 132 kV Transmission Line at tower No: 43 -: 14 km.
(b) Replacement of one galvanized steel ground wire with Optical Fiber Ground Wire (OPGW) in following existing transmission lines including erection of all necessary connectors, fittings and accessories for OPGW. Directional routing facility must be available at outdoor type Patch Panels to be located at all T-Off and π-off terminations as described below :-
(i) From Biyagama Grid Substation to Sapugaskanda Power Station-: 2 km
(ii) From Kotugoda Grid Substation to Kelaniya Grid Substation.-: 19.5 km
In order to facilitate connections to Aniyakanda Grid Substation, outdoor type Patch Panel should be provided at Polpithimukalana (tower No 34A).
(iii) From Kelaniya Grid Substation to Kolonnawa Grid Substation -: 6.5 km
(iv) From Chilaw Grid Substation to Kotugoda Grid Substation -: 49 km
In order to facilitate connections to Pannala Grid Substation and Bolawatta Grid Substation, outdoor Patch Panels should be provided at Maningala (tower No. 43) and Bolawatta (tower No. 55).
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 2
(v) From Pannipitiya Grid Substation to Tower No: 82 at Paragastota in Pannipitiya Matugama 132 kV Tr. Line -: 22 km
In order to facilitate connections to Panadura and Horana Grid Substations, outdoor Patch Panels shall be provided at T-off point at tower No:47A and π-off point at tower no. 82 respectively in Pannipitiya Matugama 132 k V Transmission Line.
(vi) From Panadura Grid Substation to T-off point at Tower No:47A of Pannipitiya Matugama 132 kV Tr. Line -: 5 km.
The existing transmission lines where the ground wires to be replaced with OPGW , will be at energized (full hot line) state throughout the contract period and the Contractor will be expected to carry out the Works under live line condition (full hot line). The removed galvanized steel ground wire shall be neatly bundled and shall be delivered to the asset management stores along with the removed accessories as instructed by the Employer.
1.1.2 CLIMATE
The climatic data given are for the standard period for 1945-1975. This data has to be up dated with the latest available data.
The climate is that of a tropical region and the following meteorological information is set out for guidance only.
(A) AIR TEMPERATURES –
Records are available for the monthly mean daily maximum and daily minimum temperatures with offset from average. The averages are taken for the standard period 30 years and all shown in Table 1.1 and 1.2.
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 3
Table 1.1 – Mean Daily Maximum Temperature Month Mean daily Max. temp. / 0C Colombo Galle Katunayaka Rathmalana Kurunegala Jan. 30.9 29.0 32.1 31.1 30.8 Feb. 31.2 29.9 32.5 31.2 33.1 Mar. 31.7 30.6 32.7 31.8 34.4 Apr. 31.8 30.6 32.4 32.0 33.5 May 31.1 29.8 31.4 31.3 32.3 Jun. 30.4 29.0 30.7 30.5 31.0 Jul. 30.0 28.6 30.4 30.2 30.8 Aug. 30.0 28.4 30.5 30.1 31.0 Sep. 30.2 28.5 30.6 30.2 31.4 Oct. 30.0 28.7 30.5 30.1 31.2 Nov. 30.1 29.0 30.9 30.4 30.9 Dec. 30.3 29.1 31.2 30.6 31.1 Year Average 30.6 29.3 31.3 30.8 31.8
Table 1.2 - Mean Daily Miniimum Temperature
Month Mean daily Min. temp. / 0C Colombo Galle Katunayaka Ratmalana Kurunegala Jan. 22.3 22.8 21.6 21.7 20.7 Feb. 22.6 23.0 21.9 22.2 20.9 Mar. 23.7 23.9 23.1 23.2 22.4 Apr. 24.6 24.8 24.1 24.1 23.6 May 25.5 25.5 25.1 25.1 24.4 Jun. 25.5 25.2 25.1 25.2 24.3 Jul. 25.2 24.8 24.9 24.9 23.9 Aug. 25.1 24.7 24.8 24.9 23.8 Sep. 24.8 24.7 24.3 24.5 23.5 Oct. 24.0 24.1 23.5 23.7 22.8 Nov. 23.2 23.5 22.8 22.9 22.1 Dec. 22.8 23.1 22.4 22.4 21.7 Year Average
24.1 24.2 23.6 23.7 22.8
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 4
(B) RELATIVE HUMIDITY
Records are available giving the following.
(i) Monthly mean maximum and minimum wet bulb temperatures with offsets from average.
(ii) Extreme wet bulb temperature in each month.
(iii) Monthly means of the relative humidity obtained from dry and wet bulb readings at day and night (state I & II respectively) with offsets from average.
(iv) Monthly means of the relative humidity obtained from the minimum dry and maximum wet bulb readings with offsets from average.
The averages are taken for the standard period of 1945-1975 and are shown in table 1.3
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 5
Table 1.3 - % Relative Humidity Month % Relative Humidity
Colombo Galle Katunayaka Ratmalana Kurunegala Jan. I II
68 85
76 63 84
79 69
65
Feb. I II
69 87
73 65 86
80 69
59
Mar. I II
71 89
73 68 89
80 89
60
Apr. I II
75 91
76 71 89
80 73
69
May I II
78 88
80 76 87
81 76
73
Jun. I II
78 88
82 76 85
80 77
74
Jul. I II
78 87
82 76 85
80 76
73
Aug. I II
77 87
83 74 85
80 76
71
Sep. I II
77 87
81 75 87
81 76
71
Oct. I II
78 91
81 76 90
82 77
74
Nov. I II
77 92
79 73 91
82 77
74
Dec. I II
73 90
78 70 88
81 74
72
Year I Average II
75 86
79 72 87
81 76
70
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 6
(C) BAROMETRIC PRESSURES
Records are available for monthly means of the air pressure taken at 08.30 and 17.30 hours as mean sea level pressure. The averages are taken for the standard period of 1945 - 1975 and varies from 1007.1 mB to 1013.1mB.
(D) RAINFALL
The rainfall figures given in Table 1.4 are based on average rainfall.
Table 1.4 - Rainfall Month Rainfall (mm) Colombo Galle Katunayaka Ratmalana Kurunegala Jan. 58.2 85.1 45.8 69.3 56.4 Feb 72.8 70.5 79.8 77.3 98.8 Mar. 128.0 111.3 132.9 141.5 139.1 Apr. 245.6 206.8 241.4 246.5 264.3 May 392.4 290.4 317.6 360.6 188.3 Jun. 184.9 188.2 177.2 198.4 153.0 Jul. 121.9 163.2 99.2 132.7 111.2 Aug. 119.5 185.9 117.6 139.3 98.0 Sep. 245.4 255.8 224.1 254.9 165.3 Oct. 365.4 322.7 389.7 371.4 354.4 Nov. 314.4 321.0 313.7 314.7 318.6 Dec. 175.3 176.9 129.7 177.8 149.0 Year Average
202 198 189 207 175
(E) WIND
One to three second gusts at 145 km per hour have been recorded with a mean speed of 27km per hour over 24 hours.
(F) STORMS
The frequency of thunder-storms is high, the isokeraunic level being approximately 60 days per annum on average for the island.
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Scope of Works Page 7
1.2 PLANT & EQUIPMENT INCLUDING SPARE PARTS
Refer Plant & Equipment including Mandatory Spare Parts from outside the Employers country and Plant & Equipment including Mandatory Spare Parts from within the Employers country in Schedules. (Section 7 of the Tender)
1.3 CIVIL WORKS , INSTALLATION AND OTHER SERVICES
1.3.1 CIVIL WORKS
Refer Civil works in Schedules. (Section 7 of the Tender). 1.3.2 INSTALLATION & OTHER SERVICES
Refer installation & other services in Schedules. Employer’s Representative Accommodation Employer’s Representative Accommodation as per third para of clause 1.6 (i) of Technical Specifications Transmission Lines with three bed rooms and telephone facility shall be available within one month from the contract commencement date for following transmission lines in the locations as specified by the Employer’s Representative.
1. Matugama - Ambalangoda 132 kV Transmission Line 2. Maningala – Pannala 132 kV Transmission Line
Transport for Employer’s Representative personnel Transport for Employer’s Representative personnel should be provided as per clause 1.6 (v) of Technical Specification -Transmission Line.
- 01 No: Sedan / Saloon - 04 Nos Off Road Vehicles
Communication Facilities for Employer’s Representative Personnel Communication facilities for Employer’s Representative personnel should be provided as per clause 1.6 (viii) of Technical Specification -Transmission Line.
- Six sets
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 8
2. DOCUMENTS, DRAWINGS AND INFORMATION TO BE SUBMITTED
2.1 DOCUMENT & DRAWINGS
2.1.1 The following drawings which are of a sufficient standard to indicate clearly all manufacturing and structural details must be prepared by Contractor and accompany each Tender:-
- Outline and general arrangement for all basic types of towers or supports, with main dimensions, steel qualities, design spans, body and leg extensions. Wire clearance diagrams for each tower type, for specified swing angle.
- Details of types of foundations for the above.
- Layout of one tower earthing system.
- Conductor dead-end assembly with jumper terminals.
- Earthwire dead-end assembly with jumper terminals.
- Conductor mid-span joints.
- Earthwire mid-span joints.
- Conductor repair sleeves.
- Earthwire repair sleeves.
- Suspension insulator strings and clamps with all fittings.
- Tension insulator strings and clamps with all fittings.
- Earthwire suspension clamps and general arrangement.
- Vibration dampers.
- Conductor spacers. (Not applicable)
- Conductor final tension charts.
- All fittings of OPGW
- Earthwire /OPGW final tension charts.
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 9
- Drawings and/or other data indicating the method of tension stringing to be adopted.
Drawings need have leading dimensions only. Tower and support drawings should have provisional dimensions of main members and should indicate the necessary clearance dimensions for structures for still air and maximum swing of insulator and jumpers called for in this Specification.
The conductor and earthwire tension charts are to show final sags and tensions for a range of equivalent spans between approximately 50 % and 200 % of the basic span in still air at maximum, everyday, and minimum temperature, and the tension at minimum temperature under full wind.
The successful Contractor will be required at the time of the letting of the Contract to supply additional copies of such drawings submitted with his Tender as may be selected by the Employer’s Representative. These drawings together with copies of the drawings originally issued with the Tender documents will then be bound up either in the Contract document or in a separate folder and will be signed both by the Employer and the Contractor for purposes of identification.
2.1.2 Independent type test certificates from a Internationally recognized testing authority for,
- Conductor, Earth wire, OPGW & Accessories.
- Insulators & Fittings.
2.1.3 General bar chart of the design, manufacturing, shipping, erection and commissioning schedule clearly showing the transmission line outages.
2.1.4 Evidence of Bidder’s experience in works similar to this.
2.1.5 Evidence of Bidder’s subcontractor’s experience in works similar to those subcontracted.
2.1.6 Certificates issued by an independent International Organization to ensure compliance with the ISO 9001 : 2000 standards by Bidder and manufacturers.
2.1.7 List of standards the Bidder intends to follow, for the electrical and for the civil works.
2.1.8 Evidence of Manufacturer’s experience in manufacturing comparable type of equipment or equivalent as offered under this contract.
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 10
2.2 INFORMATION TO BE SUBMITTED
2.2.1 MANUFACTURERS AND PLACES OF MANUFACTURE, TESTING AND INSPECTION
Item Manufacturer Place of Manufacture/ Inspection
LINE CONDUCTORS Aluminium Wires - 400mm2 ACSR, Zebra
Stranding Steel Wires
- 400mm2 ACSR, Zebra
Stranding (Complete conductor)
- 400mm2 ACSR, Zebra
LINE CONDUCTOR FITTINGS Mid-Span Joints - Conductor
Repair Sleeves
Vibration Dampers
EARTH CONDUCTORS Steel Wires 7/3.25mm
Stranding Steel Wires 7/3.25mm
EARTH CONDUCTOR FITTINGS
Clamps
Tension Clamps
Mid-span Joints
OPGW / OFAC Steel wires
Optic Fiber
Complete OPGW
Optical Fiber Approach Cable (OFAC)
Fittings & Accessories
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 11
INSULATORS AND FITTINGS
132 kV Line - 400mm2 ACSR
Suspension Insulator Discs, 120kN
Jumper Suspension Insulator Discs, 70kN
Suspension Insulator Hardware
Tension Insulator Discs, 160kN
Tension Insulator Hardware
Suspension Clamps - Conductor
Tension Clamps – Conductor
STEEL TOWERS
Steel Sections
Fabrications
Galvanising
Nuts and bolts
TESTING
Insulator string
Tower
ACSR Conductors
Earth wire
OPGW
Note : Only one manufacturer should be indicated. against each item
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 12
2.2.2 GUARANTEES AND FACTORS OF SAFETY
2.2.2.1 GUARANTEES
2.2.2.1.1 CONDUCTORS AND EARTHWIRES
Conductors Units 400mm2 ZEBRA, ACSR
Ultimate Tensile Strength N
Max. AC Resistance per km at 20oC ohms
Max. DC Resistance per km at 20oC ohms
Conductor weight per km kg
Galvanised Steel Earthwire 7/3.25mm
Ultimate Tensile Strength N
Max Resistance per km at 20oC ohms
Optical Fibre Ground Wire (OPGW)
Ultimate Tensile Strength
Max Resistance per km at 20oC
2.2.2.1.2 INSULATORS AND FITTINGS
Minimum Failing Load for Complete - 400mm2 ACSR
Normal Suspension Sets
Heavy Suspension sets
Normal Tension Sets
Light duty Tension Sets
kN
kN
kN
kN
Positive Wave Impulse Withstand Voltage for-
Normal Suspension Sets
Heavy Suspension sets
Normal Tension Sets
Light duty Tension Sets
kV peak
kV peak
kV peak
kV peak
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings & Information To be Submitted with Bid Page 13
2.2.2.2 MINIMUM FACTORS OF SAFETY
Description
Factor of Safety
Conductors, Earthwires and OPGW at Maximum Working Tension based on Ultimate Strength
2.5
Conductors and Earthwires at Everyday Temperature still Air Tension, based on Ultimate Strength
4.5
Anchor Clamps and Mid-span Joints, based on Ultimate Strength of Conductor and Earthwire
0.95
Insulator Strings and Fittings at Maximum Working Tension based on Failing Load
3.0
Straight Line Supports and Foundations under Normal Working Loads
2.0
Angle, Section and Terminal Supports and Foundations under Normal Working Loads
2.5
Towers under Broken Wire Loads 1.25
Foundations under Broken Wire Loads 1.5
Crossarms of straight line support under broken wire condition 2.0
Crossarms of angle, section and terminal support under broken wire condition
2.5
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 14
2.2.3 Technical Particulars
2.2.3.1 Conductors and Earthwires The bidder is required to fill the spaces in this schedule Description Unit Earthwire Conductor
7/3.25 mm ACSR 400 mm2
Nominal Aluminum Area of Conductor mm2 400
Actual Aluminum Area of Conductor mm2
Number and Diameter of Aluminum Wires mm2 54/3.18
Lay of Aluminum Wires - Inner Layer mm
- Middle Layer mm
- Outer Layer mm
Number and Diameter of Steel Wires 7/3.25 7/3.18
Lay of Outer Steel Wires mm
Overall Diameter mm
Cross-Sectional area (for stress calculation) mm2
Standard Mass per km kg
Greased Mass per km kg
Final Maximum Tension at Minimum Temperature with Maximum Wind Load
kN
Earthwire U.T.S. kN
Quality of Earthwire (Grade-BS183) 1000
Final Tension of Conductor at Everyday Temp.(Still Air)
kN
Description Equivalent Modules of Elasticity GPa
Equivalent Coefficient of Linear Expansion oC
Final Stress in Aluminum Wires at Everyday Temp.
kN
Final Stress in Steel Wires at Everyday Temp. kN
Maximum Length of Conductor on Drum m
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 15
Conductors and Earthwires (Continued....)
Description Unit Earthwire Conductor
7/3.25 mm ACSR 400 mm2
Maximum mass of greased conductor plus drum
kg
Assumed Maximum Continuous Load Current
A
Minimum drop point Temp. of inter-strand grease
oC
Maximum calculated resistance per km at 20oC
Ω
Individual Wires before stranding
Aluminum - Tensile Breaking Stress kN
Aluminum - Elongation on 250mm Length on breaking
mm
Steel - Tensile Breaking Stress kN
Steel - Elongation of 600mm Length on Breaking
mm
Elastic Limit of Material as % of Breaking strength
%
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 16
Conductors and Earthwires (Continued....)
Description Unit Earthwire Conductor
7/3.25 mm ACSR 400 mm2
Joints, Clamps, Compressors & Vibration dampers
Earthwire/Conductor Mid-Span Joint Type Number
Conductor Repair Sleeve Type Number
Earthwire/Conductor Dead End Clamp Type Number
Conductor Jumper Lug Type Number
Vibration Damper Type Number
Distance from mouth of Suspension or Tension Clamp to Vibration Damper
Distance between subsequent Vibration Dampers
Details and Type Number of Compression tools
Identification Numbers of Compressor Dies to be Supplied
Aluminum part - Conductor
Steel part - Conductor
Jumper Terminal - Conductor
Repair Sleeve - Conductor
Galvanized Steel - Earthwire
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 17
2.2.3.2 OPGW The bidder is required to fill the spaces in this schedule Description Unit Offered
Type of OPGW Conforming to standard (specify standard) Construction of OPGW 1) Overall
- Number of tubes - Tube diameter - Tube material - Number of fiber/tube - Length of each fiber per km of OPGW (km) - Filling compound - Central strength member - Heat resistant barrier - Material of fiber
2) Inner layer - Material - Number of wires - Diameter of wires - Cross-section - Lay ratio
3) Outer layer - Material - Number of wires - Diameter of wires - Cross-section - Lay ratio
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 18
Description Unit Offered
Total cross sectional area mm2
Rated outer diameter mm
Nominal weight kg/km
Minimum ultimate tensile strength kN
Maximum tensile strength for normal operation kN
DC resistance at 20 degree C ohm/km
Modulus of elasticity
- Initial kg/mm2
- Final kg/mm2
Coefficient of linear expansion /Deg. C
Method of creep compensation
Minimum bending radius
- Short term mm
- Long term mm
Strain margin
- Nominal %
- Maximum allowance %
Maximum allowable temperature and corresponding current
- continuous Deg. C/kA
- for short circuit Deg. C/kA
- for lightning stroke Deg. C/kA
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 19
A- Optical Wave Guides
Description Unit Qty
1) Number of optical fibers in OPGW no 2) Mode 3) Optimised wave length nm 4) Cut off wave length at; 5) Maximum attenuation per km at 1,550nm 6) Chromatic Dispersion at
Zero dispersion wave length: Dispersion slope (So-at o) Dispersion D ( ) in the operation window from 1,300nm to 1,575nm
7) Nominal zero dispersion wavelength nm 8) Refractive index
Core Cladding
9) Material used in Core Cladding Primary coating Jacket Coating
10) Optical attenuation corresponding to crush test impact test bend test sheave test
11) Mode field diameter and % deviation % 12) Mode field non-circularity
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 20
Description Unit Qty
13) Outside (clad) diameter µm
14) Tolerance in outside (clad) diameter µm
15) Core cladding concentricity error %
16) Cladding non-circularity (%) %
17) Screening level/tensile proof test
18) Loose buffer design or Tight buffer design
19) Temporary change in attenuation at 20 degree C due to
Temperature cycling dB/km
Lightning stroke dB/km
Short circuit current dB/km
20) Splicing loss dB/splice
21) Detail of color coding for fiber identification
22) Expected life time without degradation of characteristics
years
23) Maximum allowable short time temperature of fiber
Deg.C for sec.
24) Nominal optical attenuation at 20 degree C over a period of 25 years
25) Bit error rate
26) Optical cross talks
Filling compound of OPGW
Long term effect of protection tube material on optical
wave-guide fiber performance
OPGW weight kg/km
Maximum length of OPGW in a drum km
Weight of drum with maximum length of OPGW
kg
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 21
B. Optical Fiber Approach Cable
Description Unit Qty
Cable type and model number
Conforming to standard
Nominal overall diameter mm
Optical wave-guide fibers similar to fibers in OPGW yes/no
If answer to item 4. above is no, details of fibers are provided
yes/no
Number of fibers in cable
Strength member materials kN
Tensile strength
Minimum bending radius
Short term mm
Long term mm
Outside jacket
Material mm
Thickness
Crush resistance (N/cm) at temperature deg. C
Method utilized to prevent water migration
Operating temperature range deg. C
Maximum variation in optical attenuation within operating temperature in range (item 13. above);
at 1,550nm dB/km
at 1,300nm dB/km
Cable life expectancy years
Atmospheric and sunlight degradation after Flexing over 100 cycle +/- 90 with bending radius of (mm) (yes
)
Torsional strength
Impact resistance at temperature of deg.C
Co-efficient of expansion per degree C degree/m
Suitable for laying in duct/direct burial/for both
Length markers on cable in unit length of m
Rodent attack additive provided yes/no
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 22
C: Splice Enclosure
Description Unit Qty
Manufacturers Name and address
Manufacturers type designation and model number
Standards
Number of splices 24
Number of cables 2
Maximum diameter of cable mm 30
Maximum pull on cable kg 40
2.2.3.3 Insulators and Fittings The bidder is required to fill the spaces in this schedule
132 kV Line Unit
Nor
mal
Su
spen
sion
.
Hea
vy
Susp
ensi
on
Nor
mal
Te
nsio
n
Jum
per
Susp
ensi
on
Low
dut
y Te
nsio
n U
prig
ht
Low
dut
y
Tens
ion
Inve
rted
Insulator Disc
Designation Disc Material (Toughened Glass or Ceramic)
Classification
Ball
& so
cket
Ball
& so
cket
Ball
& so
cket
Ball
& so
cket
Ball
& so
cket
Ball
& so
cket
Unit Number Maker Maximum Working Load kN Minimum Electro-mechanical Failing Load
kN
Outside Diameter of Unit mm Diameter of Insulator Pin mm
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 23
132 kV Line Unit
Nor
mal
Su
spen
sion
.
Hea
vy
Susp
ensi
on
Nor
mal
Te
nsio
n
Jum
per
Susp
ensi
on
Low
dut
y Te
nsio
n U
prig
ht
Low
dut
y
Tens
ion
Inve
rted
Protected Creepage Distance per Unit
mm
Minimum nominal Creepage Distance per Unit
Mm
Minimum 50 Hz Puncture Voltage per Unit
kV
Fittings
Material of Clamp
Length of Clamp
Material of spacers
Elastic Limit of Fittings
Insulator String
Number of Units in String Nos
Spacing of Unit in String mm
Minimum Failing Load of Complete Insulator Set
kN
Total Creepage Distance mm
Total Protected Creepage Distance
mm
Overall Length of Complete Suspension Set from Bottom of Conductor to Support Attachment Point
mm
Length from Tension Set Jumper Lug to Support Att h t P i t
mm
Mass of Complete Set with all Fittings
kg
Lift of Arcing Horn over Line End Unit
mm
Arcing Distance between Line End Horn and Earth End Cap
H
mm
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 24
132 kV Line Unit
Nor
mal
Su
spen
sion
.
Hea
vy
Susp
ensi
on
Nor
mal
Te
nsio
n
Jum
per
Susp
ensi
on
Low
dut
y Te
nsio
n U
prig
ht
Low
dut
y Te
nsio
n In
verte
d
Dry 1-minute 50 Hz Withstand of Normal Insulator Set Complete with all Fittings
Wet 1-minute 50 Hz Withstand of Normal Insulator Set Complete with all Fittings
Dry Impulse withstand Voltage (1.2/50) of Normal Insulator set complete with all fittings
Positive wave +kV peak
Negative Wave –kV peak
kV
kV
Dry Impulse withstand Voltage (1.2/50) of Normal Insulator set as above without Arc horns
Positive wave +kV peak
Negative Wave –kV peak
kV
kV
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 25
2.2.3.4 Support Steel The bidder is required to fill the spaces in this schedule.
Description Units Required Guaranteed
Steel to ISO 630 Grade E 275 :-
Minimum upper yield stress N/mm2 275
Ultimate stress in tension members N/mm2
Ultimate stress in compression members(express as a function of L/R)
N/mm2
Steel to ISO 630 Grade 50E 355 :-
Minimum upper yield stress N/mm2 355
Ultimate stress in tension members N/mm2
Ultimate stress in compression members (express as a function of L/R)
N/mm2
Ultimate shear stress on bolts N/mm2
Ultimate bearing stress in bolts N/mm2
Ultimate tensile strength of bolts N/mm2
Minimum proof stress N/mm2 640
2.2.3.5 Particulars of Towers ZEBRA
Basic Span Length m 300
Normal Minimum Ground Clearance of Line Conductor at Maximum Temperature (including 0.3m Allowance for Conductor Creep)
m
Approximate Final Sag of Line Conductor in Still Air at Maximum Temperature for Basic Span
m
Approximate Final Sag of Line in still Air at Everyday Temperature for Basic Span
m
Approximate Final Sag of Earth Conductor in Still Air at Everyday Temperature for Basic Span
m
Maximum working Tension of Line Conductor, for Tower Design Purposes
N
Maximum working Tension of Earth Conductor, for Tower Design Purposes
N
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission Line Documents, Drawings and Information To be submitted with Bid Page 26
Particulars of Towers Cont.
Type of Tower Unit TDL TD1 TD3 TD6 TDT
Approximate Height of Lowest conductor above ground at Support
m
Vertical Distance between Top and Bottom Line Conductors
m
Vertical Spacing Between Earth Conductor and Top Line Conductor
m
Approximate Total Height of Tower above Ground
m
Approximate Width of Tower Body at Attachment Level of Bottom Cross arm
m
Horizontal Distance of Insulator Attachment from Tower Centre line for each Cross arm
m
Top m
Middle m
Bottom m
Approximate Overall Dimensions of Tower Base at Ground Level
m
Transverse to line m
Parallel to line m
Approximate Mass of Complete Tower Steelwork (using Concrete Block Foundations)
kg
Approximate Extra Mass of Steel for
3m Extension kg
3m Extension kg
6m Extension kg
9m Extension kg
12m Extension kg
Total Ult. Transverse Overturning Moment at Ground level under Specified Maximum Normal Working Loads for Standard Tower
Nm
Approximate Ult. Longitudinal Overturning Moment at Ground Level under Broken Wire
Nm
Loading(Standard Tower)
Approximate Ultimate Compression Load per Leg
Approximate Ultimate Uplift Load per Leg
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 27
2.2.4 SITE ORGANIZATION
2.2.4.1 Field Staff Details
Number of Survey Parties
Estimated Total Route - km Surveyed per month
Expatriate Field Staff.
Supervising Engineers
Foremen and Other Grades
Maximum Local Labour Force
Estimated Number of Foundation Gangs
Estimated Peak Total Rate of Foundations Installed per Month
Estimated Number of Tower Erection Gangs
Estimated Peak Total Rate of Towers Erected per Month
Estimated Number of Stringing Gangs
Estimated Peak Total of Stringing Line-km per Month
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 28
2.2.4.2 Key Personnel’s Details
Designation Name of
(i) Nominee
(ii) Alternate
Summary of Qualification
Experience & Present Occupation
Year of Birth
Headquarters
Project Director
Project Manager
Engineering Design Staff
Other key Staff (Give Designation)
Site Office
Project Manager
Site Manager
Deputy Site Manager
Supervising Engineers
Construction Supervisors
Other Key Staff
The Tenderer shall list in this schedule the key personnel (including first nominee and the second choice alternate) he will employ from headquarters and from site office to direct and execute the works.
2.2.5 CONTRACT DATES
The Schedule shall be completed by the contractor and the times entered shall be binding on the contractor.
The latest date by which an order must be placed to permit completion by the specified dates shall be entered, together with the guaranteed periods in weeks from placing of order to the completion of the lines. The completion time of each of the new lines and lines of which Steel Ground Wire to be replaced with OPGW should be entered in separate sheets. Also all new lines and lines of which Steel Ground Wire to be replaced with OPGW should be considered progressing parallely.
All periods shall be in weeks, calculated from the latest date for placing the order. (In addition to the following table, Gantt chart should also be attached)
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 29
2.2.5.1 Construction of new Transmission Lines
PERIODS IN WEEKS after placing order Commence Complete Survey Works
Preliminary Survey
Profile Survey
Tower location finalization
Access for Commencement of erection
Steel Structures
Submission of Suspension Tower Design
Suspension Tower Test
Suspension Tower Manufacture
Submission of all other Tower Designs
Angle Tower Test
Angle Tower Manufacture
Conductors Manufacture
Earth Wires/OPGW Manufacture
Insulator Manufacture
Insulator and Conductor Hardware Manufacture
2.2.5.2 Replacement of Steel Ground Wire with OPGW
Period in Weeks after placing order Commence Complete
Access for Commencement of erection
OPGW Manufacturer
OPGW Hardware & accessories Manufacturer
Replacement and Stringing of OPGW
Final Sagging
Testing and Commissioning
Handing Over of removed Steel Earth Wire
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 30
PERIODS IN WEEKS after placing order Commence Complete Foundation works
Tower Erection works
Stringing of conductors and Earth wire
Final Sagging
Testing and Commissioning
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 31
2.2.6 DEPARTURES FROM THE SPECIFICATION
(To be completed by the contractor)
Clause No. Departures from the requirements of this specification with details of alternative
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 32
2.2.7 TENDERER'S EXPERIENCE (New Construction)
2.2.7.1 Construction of New 132 kV Lines
(If Tenderers wish to supply details of more than one Contract additional pages should be attached).
Tenderers are to complete this schedule giving details of supply and erection of transmission lines of the same type which they have completed or which are in the course of completion by them.
1 Name and Address of Client
Contact Person
Telephone and Facsimile number
2 Country
3 Voltage and Length of the line
4 Brief description of terrain
5 No. of circuits and No. and size of conductors
6 Type of Ground Wire
Steel – km
OPGW - km
7 Type of construction (e.g. vertical formation self supporting etc.)
8 Technical co-ordination by
9 Steelwork supplier
10 Conductor supplier
11 Installation of foundations by
12 Tower erection by
13 Stringing by
14 Site supervision by
15 Max. No of expatriate supervisors
16 Max. No of local employees
17 Date of award
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 33
18 Target completion date
19 Actual completion date
20 Name & address of consultant (if any)
2.2.7.2 Replacement of Steel round wire with OPGW
1 Name and Address of Client
Contact Person
Telephone and Facsimile number
2 Country
3 Voltage and Length of the line
4 Brief description of terrain
5 No. of circuits and No. and size of conductors
6 Type of construction (e.g. vertical formation self supporting etc.)
7 Replacement of Ground Wire with OPGW under full hot condition
Single Earth – km
Double Earth - km
8 Technical co-ordination by
9 Steelwork supplier
10 Conductor supplier
11 Installation of foundations by
12 Tower erection by
13 Stringing by
14 Site supervision by
15 Max. No of expatriate supervisors
16 Max. No of local employees
17 Date of award
18 Target completion date
19 Actual completion date
20 Name & address of consultant (if any)
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 34
2.2.8 VOLUME OF CONSTRUCTION WORK IN EACH OF THE LAST FIVE YEARS
2.2.8.1 Construction of New 132 kV Transmission Line
Year Description of the Work Volume of construction
work in US $
2.2.8.2 Replacement of Steel Ground Wire with OPGW
Year Description of the Work Volume of construction
work in US $
2.2.9 DETAILS OF OTHER WORK IN HAND & CONTRACTUAL COMMITMENTS
2.2.9.1 Construction of New 132 kV Transmission Line
DESCRIPTION OF OTHER WORK IN HAND
CONTRACTUAL COMMITMENTS
2.2.9.2 Replacement of Steel Ground Wire with OPGW
DESCRIPTION OF OTHER WORK IN HAND
CONTRACTUAL COMMITMENTS
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 35
2.2.10 SCHEDULE OF MAJOR ITEMS OF CONSTRUCTIONAL PLANT
As stated in the conditions of contract(volume I of 4) - Customs, the Employer shall pay Custom Duties not only for materials and equipment which is to form part or Contractual Plant but also all transport, machinery, erection equipment and materials, testing equipment which are necessary to construct and commission the plant including intermediate Temporary works. To enable the Employer to assess value of custom duties for the cash-flow purpose and evaluation of the final contract cost to the Employer, the Contractor is requested to fill the following Schedule. The total value of all equipment, tools etc. as mentioned above, declared by the Contractor for custom purpose if exceed the value stated hereinafter shall be at the Contractor’s own expense with reference to the payable custom duties. The Contractor shall enter any other equipment not listed in the foregoing Schedules which no tools is necessary for construction or commissioning purpose. For those items which the Contractor intends to hire locally no value shall be stated.
Des
crip
tion
(Typ
e, M
odel
, M
ake)
No.
of
Eac
h
Year
of
M
anuf
actu
re
New
or
Use
d
Ow
ned
(O)
or
Leas
ed (L
)
CIF
Val
ue
Est.
Pow
er
Rat
ing
Cap
acity
T
or m
3
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 36
2.2.11 SCHEDULE OF SUB CONTRACTORS
Item Element Approximate Name and address of Statement of
of work Value in percentage Sub Contractor Similar Works executed
The tenderer shall enter in this schedule a list of the sections and appropriate value of the work for which the purposes to use sub contractors, together with the names and addresses of the proposed sub contractors. The tenderer shall also enter a statement of similar works previously executed by the proposed sub contractors, including description, location and value of works, year completed, and name and addresses of the Employer Notwithstanding such information the tenderer, if awarded the contract, shall remain entirely and solely responsible for the satisfactory completion of the Works.
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 37
2.2.12 FINANCIAL STANDING OF THE BIDDER
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 38
2.2.13 CURRENT LITIGATION
Power Sector Development Transmission Project – Lot B – Rev 2 Employer’s Requirements
Transmission LineDocuments, Drawings and Information To be submitted with Bid Page 39
2.2.14 ROLES OF THE JOINT VENTURE MEMBER
Name of the JV Member Role in this Contract