![Page 1: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/1.jpg)
Walk Bridge Replacement Project
A Sustainable Projectfor Norwalk &
the Northeast Corridor
Sarah Walker, AICP ENV SPHNTB Corporation
![Page 2: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/2.jpg)
Summary of Presentation1. Project Setting
2. Project Challenge
3. Innovative Construction Approach
4. Construction Coordination Plans
![Page 3: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/3.jpg)
Walk Bridge
![Page 4: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/4.jpg)
Walk Bridge: Regional & Local Significance
125,000 passengers & 175 trains daily
![Page 5: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/5.jpg)
Selected Project Design: Vertical Lift Span
• Shortest construction schedule• Lowest construction risks • Shortest period of navigational
restrictions• Least natural resources impacts• Least social & economic impacts
to Norwalk
Challenge: Maintain Commuter Rail Service & Minimize Community Impacts
![Page 6: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/6.jpg)
Integrated Design and Construction Process
• Historic Building Protection
• Business Coordination
• Marine Use
• Transportation
• Maritime Aquarium Coordination
Historic Building
Protection
Project Sustainability
Safety and Security Plans
Community-Based Protection Plans
Resource-Based Protection Plans
Construction Manager/General Contractor
![Page 7: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/7.jpg)
Innovative Construction Approach
Construction Manager/General
Contractor Alternative Delivery
DESIGNER CM/GC
PM Consultant
Independent Cost Estimator
ConnDOT
![Page 8: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/8.jpg)
Benefits of CM/GC Process• Provides advice to
designer
• Identifies innovative construction solutions
• Coordinates planning & construction operations
• Promotes collaboration & efficiency
![Page 9: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/9.jpg)
Examples of Designer-CM/GC Collaboration
Wetland Mitigation Design Bridge Component Salvage
![Page 10: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/10.jpg)
Construction Coordination Plans
• Historic Building Protection
• Business Coordination
• Marine Use
• Transportation
• Maritime Aquarium
Historic Building
Protection
• Noise and Vibration
• Air Quality
• Water Quality Control
• Materials Management
Resource Protection
Coordination Plan Types
Community Protection
Safety and Security
![Page 11: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/11.jpg)
Community-Based Plan: Historic Building Protection • Section 106 MOA Stipulation
• Protection expanded to include Zone of Influence buildings
![Page 12: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/12.jpg)
Historic Building Protection Plan
• Initial Building Condition Surveys
• Preventative Measures
• Test Pile Program Monitoring
• Pre-Construction Building Surveys & Follow-Up
![Page 13: Walk Bridge Replacement Project - American Public ......HNTB Corporation Summary of Presentation 1. Project Setting 2. Project Challenge 3. Innovative Construction Approach 4. Construction](https://reader035.vdocument.in/reader035/viewer/2022081411/60b2e9d785644223800be6d6/html5/thumbnails/13.jpg)
The New Walk Bridge - A Sustainable Solution Restore rail
infrastructure
Improve service safety & reliability
Expand & enhance service
Upgrade tracks to support local & express service CTDOT’s Goals for New York to New
Haven Corridor