April 24, 2012 1 Wastewater Reclamation & Reuse Lincoln Wastewater System Wastewater Reclamation & Reuse Wastewater Reclamation & Reuse Presentation to Presentation to Mayor Mayor s Sustain Lincoln Plan s Sustain Lincoln Plan Blue Ribbon Committee Blue Ribbon Committee by by Lincoln Wastewater System Lincoln Wastewater System Dept. of Public Works & Utilities Dept. of Public Works & Utilities April 24, 2012 April 24, 2012

Upload: others

Post on 30-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 1Wastewater Reclamation & Reuse

Lincoln Wastewater System

Wastewater Reclamation & ReuseWastewater Reclamation & Reuse

Presentation toPresentation to

MayorMayor’’s Sustain Lincoln Plans Sustain Lincoln Plan

Blue Ribbon CommitteeBlue Ribbon Committee

byby

Lincoln Wastewater SystemLincoln Wastewater System

Dept. of Public Works & UtilitiesDept. of Public Works & Utilities

April 24, 2012April 24, 2012

Page 2: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 2Wastewater Reclamation & Reuse

Lincoln Wastewater System

Wastewater Reclamation & ReuseWastewater Reclamation & Reuse

Purpose : Current Reuse of Treated Wastewater Effluent in LincPurpose : Current Reuse of Treated Wastewater Effluent in Lincolnoln

�� LincolnLincoln’’s Two Wastewater Treatment Facilities s Two Wastewater Treatment Facilities

�� Theresa St. FacilityTheresa St. Facility

�� Northeast FacilityNortheast Facility

�� Facilities treat approx. 25 million gallons of wastewater per daFacilities treat approx. 25 million gallons of wastewater per dayy

�� Reuse at the Facilities has been occurring for more than 25 yearReuse at the Facilities has been occurring for more than 25 years.s.

Page 3: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 3Wastewater Reclamation & Reuse

Lincoln Wastewater System

Theresa St. Treatment Facility Theresa St. Treatment Facility –– 2400 Theresa St.2400 Theresa St.

Page 4: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012Wastewater Reclamation & Reuse

Lincoln Wastewater System 4

Northeast Treatment FacilityNortheast Treatment Facility

Near N. 70Near N. 70thth & Salt Creek& Salt Creek

Page 5: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 5Wastewater Reclamation & Reuse

Lincoln Wastewater System

Biological Treatment Biological Treatment -- Aeration BasinAeration Basin

Page 6: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 6Wastewater Reclamation & Reuse

Lincoln Wastewater System

Solids Removal Solids Removal

Clarifiers & Anaerobic DigestersClarifiers & Anaerobic Digesters

Page 7: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 7Wastewater Reclamation & Reuse

Lincoln Wastewater System

Ultraviolet disinfection of wastewater effluent Ultraviolet disinfection of wastewater effluent

prior to water being discharged or reusedprior to water being discharged or reused

Page 8: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 8Wastewater Reclamation & Reuse

Lincoln Wastewater System

Wastewater Reclamation & ReuseWastewater Reclamation & Reuse

Primary Reuse At Treatment FacilitiesPrimary Reuse At Treatment Facilities

�� Treatment processes Treatment processes �� Grit HandlingGrit Handling

�� Liquid Waste FacilityLiquid Waste Facility

�� Biosolids Dewatering ProcessBiosolids Dewatering Process

�� Equipment cooling Equipment cooling –– e.g. Cogeneration Units & Aeration Blowerse.g. Cogeneration Units & Aeration Blowers

�� Heating & cooling of buildings (HVAC) Heating & cooling of buildings (HVAC)

�� Irrigation of treatment facility grassed areas & groundsIrrigation of treatment facility grassed areas & grounds

�� Effluent Reuse Effluent Reuse ––�� Replaces over 305 million gallons/year of fresh water useReplaces over 305 million gallons/year of fresh water use

�� Reuse of treated effluent water Reuse of treated effluent water -- Potential Est. cost avoidance of $816,000/ yearPotential Est. cost avoidance of $816,000/ year

�� Terry Bundy Generating Station Terry Bundy Generating Station �� Uses 50 to 60 million gallons per year of treated wastewater effUses 50 to 60 million gallons per year of treated wastewater effluent from Northeast. luent from Northeast.

�� Returns approx. 20 million gallons per year of reused water to tReturns approx. 20 million gallons per year of reused water to treatment facility for reatment facility for further treatment prior to discharge.further treatment prior to discharge.

Page 9: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 9Wastewater Reclamation & Reuse

Lincoln Wastewater System

Treated effluent Treated effluent -- used for cooling combined used for cooling combined

heat and power units that use anaerobic heat and power units that use anaerobic

digester gas for generating electricity and digester gas for generating electricity and

heating of the digestersheating of the digesters

Page 10: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 10Wastewater Reclamation & Reuse

Lincoln Wastewater System

Treated effluent Reuse Treated effluent Reuse -- Cooling aeration Cooling aeration

blowers used for the aeration basinsblowers used for the aeration basins

Page 11: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 11Wastewater Reclamation & Reuse

Lincoln Wastewater System

Treated effluent used the facility grit Treated effluent used the facility grit

handling facilities and other processes at handling facilities and other processes at

the treatment facilitiesthe treatment facilities

Page 12: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 12Wastewater Reclamation & Reuse

Lincoln Wastewater System

Treated effluent Treated effluent --used to heat and cool the used to heat and cool the

Divisional Administration BuildingDivisional Administration Building

Page 13: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 13Wastewater Reclamation & Reuse

Lincoln Wastewater System

Equipment used to transfer heat from effluent Equipment used to transfer heat from effluent

to the heat pumps in the administration to the heat pumps in the administration

buildingbuilding

Page 14: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 14Wastewater Reclamation & Reuse

Lincoln Wastewater System

Theresa St. Laboratory building uses treated Theresa St. Laboratory building uses treated

effluent for coolingeffluent for cooling

Page 15: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 15Wastewater Reclamation & Reuse

Lincoln Wastewater System

Theresa St. Theresa St. -- Operations Control Center Operations Control Center -- HVAC system being HVAC system being

retrofitted to use treated effluent for heating and coolingretrofitted to use treated effluent for heating and cooling

Page 16: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 16Wastewater Reclamation & Reuse

Lincoln Wastewater System

LES Terry Bundy Electrical Generating Station uses LES Terry Bundy Electrical Generating Station uses

treated effluent from Northeast for cooling towerstreated effluent from Northeast for cooling towers

Page 17: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 17Wastewater Reclamation & Reuse

Lincoln Wastewater System

After use, treated effluent reuse water is returned Treatment After use, treated effluent reuse water is returned Treatment

Facilities prior to discharge to Salt CreekFacilities prior to discharge to Salt Creek

Page 18: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 18Wastewater Reclamation & Reuse

Lincoln Wastewater System

Wastewater Reclamation & ReuseWastewater Reclamation & Reuse

Issues affecting Future Uses of Treated WastewaterIssues affecting Future Uses of Treated Wastewater

�� Protection of Public Health & SafetyProtection of Public Health & Safety�� Possible direct contact with treated effluents used for irrigatiPossible direct contact with treated effluents used for irrigationon

�� Additional Costs for Advanced treatment and distributionAdditional Costs for Advanced treatment and distribution

�� Additional advanced treatment requirements (e.g.)Additional advanced treatment requirements (e.g.)�� Filtering & Membrane TreatmentFiltering & Membrane Treatment

�� Greater Disinfection levelsGreater Disinfection levels�� Reduction and Removal of key bacteria & virus producing organisReduction and Removal of key bacteria & virus producing organismsms

�� Additional Regulatory requirements approaching those of Additional Regulatory requirements approaching those of Potable WaterPotable Water

Page 19: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 19Wastewater Reclamation & Reuse

Lincoln Wastewater System

Wastewater Reclamation & ReuseWastewater Reclamation & Reuse

Potential Uses of Treated WastewaterPotential Uses of Treated Wastewater

�� UNL Innovation Campus Development UNL Innovation Campus Development -- considering use of considering use of

treated effluent for heating and cooling of buildings treated effluent for heating and cooling of buildings

�� Irrigation of grassed areas Irrigation of grassed areas

�� Industrial uses for cooling and process requirementsIndustrial uses for cooling and process requirements

�� Potential reuse in Potential reuse in ““ Grey water Grey water ““ systemssystems

Page 20: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 20Wastewater Reclamation & Reuse

Lincoln Wastewater System

Nebraska Innovation Campus is considering using Nebraska Innovation Campus is considering using

recycled effluent for heating and coolingrecycled effluent for heating and cooling

Page 21: Wastewater Reclamation & ReuseReuse of treated effluent water -Potential Est. cost avoidance of $816,000/ year Terry Bundy Generating Station Uses 50 to 60 million gallons per year

April 24, 2012 21Wastewater Reclamation & Reuse

Lincoln Wastewater System

Water Water Wastewater Reclamation & ReuseWastewater Reclamation & ReuseReclamationReclamation

�� QuestionsQuestions

�� Further Information & Contact:Further Information & Contact:Lincoln Wastewater & Solid Waste SystemLincoln Wastewater & Solid Waste System

2400 Theresa St.2400 Theresa St.

Divisional Office: 402Divisional Office: 402--441441--79617961

Web Address: Web Address: http://lincoln.ne.gov/city/pworks/waste/index.htmhttp://lincoln.ne.gov/city/pworks/waste/index.htm

Gary Thalken P.E. Gary Thalken P.E. -- Sanitary EngineerSanitary Engineer

email: [email protected], (402) 441email: [email protected], (402) 441--79677967

Gary Brandt P.E. Gary Brandt P.E. -- Division Manager Division Manager –– Wastewater & Solid Waste OperationsWastewater & Solid Waste Operations

email: email: [email protected]@lincoln.ne.gov, (402) 441, (402) 441--79687968