waterview connection project (ca3466) · 2015-06-29 · monitoring results are shown in table 2....
TRANSCRIPT
Waterview Connection Project (CA3466):
Auckland Council Monthly Environmental Report Report 39 – Period May 2015
Document 025-RPT-03750
22 June 2015
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 2 15 June 2015
Contents
1. Introduction .................................................................................................................................................. 3
2. Resource Consents ........................................................................................................................................ 3
3. Construction Works – May until August 2015 .............................................................................................. 3
4. Site Meetings and Inspections ...................................................................................................................... 4
5. Environmental Monitoring............................................................................................................................ 4
5.1. Tree Management ................................................................................................................................ 4
5.2. Noise and Vibration Monitoring ........................................................................................................... 6
5.3. Air Quality Monitoring .......................................................................................................................... 6
5.4. Ground Water Monitoring .................................................................................................................... 7
5.5. Settlement Monitoring ......................................................................................................................... 8
5.6. Water Quality and Ecological Monitoring ........................................................................................... 11
5.6.1. Water Quality .............................................................................................................................. 13
5.6.2. Ecological Monitoring & Management ....................................................................................... 16
5.7. Contaminated Soil Monitoring ............................................................................................................ 17
5.7.1. Site monitoring............................................................................................................................ 17
5.7.1. Soil disposal ................................................................................................................................. 17
5.7.2. Phyllis Reserve landfill monitoring .............................................................................................. 18
5.8. Erosion and Sediment Control Monitoring ......................................................................................... 23
5.9. Archaeological monitoring .................................................................................................................. 23
5.10. Waste Management ....................................................................................................................... 23
5.11. Hazardous Substance Management ............................................................................................... 24
6. Stakeholder Management .......................................................................................................................... 24
6.1. Stakeholders – local liaison activity .................................................................................................... 24
6.2. General Communications Activity: Overview ..................................................................................... 25
6.3. Queries, Concerns and Complaints ..................................................................................................... 26
Appendix A .......................................................................................................................................................... 28
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
1. Introduction
To meet reporting requirements for the Waterview Connection, a monthly report will be prepared and sent
to AC in the 2nd week of the following month.
This report sets out the reporting requirements for the Waterview Connection for the period May 2015.
2. Resource Consents
With the exception of Consents ARC:38325, 38326, 38327 and 38328 which relate to rock crushing and
concrete batching plant activities, all other remaining consents have been triggered by works to date.
Appendix A provides a table of all the additional resource consents obtained for the project to date.
Resource consents (R/LUC/2015/1361 (landuse) and R/REG/1321 (coastal permit) were granted on 7 May
2015 for the construction and operation of a Boardwalk at Eric Armishaw Reserve. Resource consent was
also granted on 29 2015 May for the earthworks associated with the demobilising of the pre-cast yard out at
East Tamaki.
3. Construction Works – April until July 2015
The table below details the construction works carried out in May, as well as an indicative programme which
shows the anticipated works in the coming 3 months until 31th of August 2015.
South Work Package May June July Aug
Dominion to Maioro St Earthworks, drainage, service relocations, ground improvement & structures
Maioro St to Richardson Rd
Construct cycleway (including earthworks and service installation)
Cut batter at Maioro off ramp
Construct Richardson Road Bridge Pedestrian stairway (inc piling)
Richardson Rd to cut in (SAT) Hendon Footbridge ( Ramps and foundations)
Valonia Street civil works (inc skatepark and Valonia Carpark and ablutions)
Oakley Creek Pedestrian Bridge #2
SAT cut to CY9 (inc Tunnel Civils)
TBM excavation
Load out spoil to Wiri
Tunnel Backfill/Drainage
Cross passage construction and excavation
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
North Work Package May June July Aug
Northern Approach Trench (NAT) & surrounds
NAT infill columns, beams and road deck.
Footpath construction & landscaping 23 - 33 Waterbank Cres
Waterbank Reserve – Landscape Park Areas/ Playground
Howlett Reserve Walkway
Northern Fill, Oakley Inlet (the Bog) & Ramp Construction
Beam Placement – Ramp 4
Oakley Creek Footbridge – investigation works/ site establishment
North abutment of Heritage Footbridge
Great North Rd Interchange
Cleaver –footpath and pavement construction. Landscaping.
Boomerang - Gas relocation works
Ramp 2 western abutment (median works) – piling & retaining wall
Carrington Rd Interchange
Retaining Wall 601 - Panel placement
Retaining Wall 603 – West Carrington Rd – Soil nails, bench and shotcrete
Retaining Wall 603 – East of Carrington Rd – Soil nails and piling
Retaining Wall 603 – Demolition of old wall
Retaining Wall 603 - Panel placement
4. Site Meetings and Inspections
Auckland Council Erosion and Sediment Control officers visited the Northern Area on the 28th May, which
resulted in an inspection score of 1. No Council Erosion and Sediment Control inspections were undertaken
in the South during May.
5. Environmental Monitoring
5.1. Tree Management
Grant Sirl, Arborist – Arbor Advice Ltd (the Project Arborist) assessed the site in May. His report is included
below:
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Table 1 – Amenity Trees
Amenity Tree
Species Location Health Fencing Observations/recommended actions
South
522 Zelkova Within compound area adjacent north side Richardson Rd
Good. Good
No actions required.
698 Group various native species
Alan Wood Reserve, access via Methuen Rd
Good/ fair Sound barrier wall excludes grove of vegetation from work site.
No actions required.
Group Lemonwood/ Titoki
Barrymore Rd Fair Located within road reserve
No actions required.
Group. Kowhai, Karamu, tree fern & various native & exotic species.
Southwestern side of Allan Wood Reserve
Good Good. No actions required.
Group #'s 512, 513 to 516 and 519
Titoki, Prunus, Totara, Tarata, Karaka & Cabbage
Near western apex of Allan Wood Reserve, outside designation area.
Good / fair.
Good. No actions required.
North
N/A Pohutukawa Waterview Primary School, (outside designation).
Good Sound wall separates tree from site.
No actions required.
Status quo. Overall vitality of
tree reasonably good. Deadwood
becoming more prevalent in
northern aspect of crown.
Epicormic growth established
upon reduced stems and
throughout crown.
# 811 Titoki (x2) Herdman Street - street trees
Good/ Fair
Trees excluded from construction by sound wall
No actions required.
# 247 Pohutukawa Waterview Reserve
Fair Tree relocated to reserve
No actions required.
Various Waterview Reserve
Majority good
All remaining trees within reserve ring fenced.
No actions required.
Development of reserve currently being undertaken.
#272 Totara Robinia Karaka Karaka
Star Mill site - archaeological area
Good/Fair Trees in archaeological area have been fenced off from construction
Actions required.
Extensive regrowth from Robinia
cut stumps establishing.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Amenity Tree
Species Location Health Fencing Observations/recommended
actions
#'s 804, 805, 806, 807,
808 & 809.
Kowhai, Silver Birch, Kawaka, Kahikatea, Bottlebrush. Lancewood & Cabbage Tree
23-25 Waterbank Crescent
Majority Good.
No actions Required.
Noted foliage decline prevalent over crown of Kawaka.
#790 Pine Group Oakley Creek Inlet Good Located on inlet embankment
No actions required.
Status quo.
#326 Cypress Located next to SRP14 beside a small Norfolk Island pine.
N/A N/A Action required.
Subject tree in an advanced state of decline.
(Clearance to be carried out in conjunction with pond works in area in 2016)
5.2. Noise and Vibration Monitoring
Noise monitoring has been undertaken for new plant and activities since commencement of construction in
January 2012 to assess levels against noise predictions (as per the Construction Noise and Vibration
Management Plan) and confirm compliance with the project noise criteria, specifically as relates to Consent
conditions CNV.2 for noise, CNV.3 for noise from air blast and CNV.4 and CNV.5 for vibration.
The focus for noise and vibration during May has been assessment of extended works required outside
normal working hours (07.30 – 18.00hrs Monday to Saturdays), submission of Site Specific Noise
Management Plans (SSNMPs) to Council and noise monitoring of ramp construction and tunnel operations.
Monitoring results are shown in Table 2.
Mitigation has been installed on the pumps and the cooling fan at Construction Yard 9 which were identified
as the main noise sources during initial monitoring at 96 Methuen Road in April. The monitoring 28 May 2015
indicates that following mitigation, noise levels are marginally above night-time noise criteria. A SSNMP has
been submitted to Council for operation of the cooling fan at Construction Yard 9. Monitoring was also
undertaken at 188 Methuen Road following installation of cladding around the conveyor belt storage. This
indicated that noise levels are still being measured above night-time noise criteria. Additional noise
mitigation is being investigated for conveyor operation in the vicinity of the segment yard and a SSNMP will
be submitted to Council.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Table 2 - Measured Noise Levels
SSNMP Date/time Measurement location
Activity Noise level LAeq15min (dB)
Noise level LAMax (dB)
SSNMP# 61 Rev6
06/05/15 1.05am
End of Maryland Street, GNRI
Pouring barriers at ramp 3 50.3 64.6
Project noise criteria Northern area applicable if operating outside normal working hours (20.00 -07.30 ) (Apply at residential property)
60 75
n/a 07/05/15 8pm – 6am 96 Methuen Road,
1m from facade Construction yard CY9 operation (fan noise)
40-51 65
28/05/15 10pm-5am
46 -48 69
20/05/15 10pm – 5am
188 Methuen Road, first floor balcony
Tunnel operations (conveyor), segment yard
43-53 70
Project noise criteria Southern area applicable if operating outside normal working hours (20.00 -07.30 ) (Apply at residential property)
45 75
The SSNMPs submitted and approved in May 2015 pursuant to consent condition CNV13 are listed below.
Table 3 – SSNMPs submitted and approved for May
SSNMP Ref Date of Works
Night Works or Day Works
Location of Works
Description of Works
Works start time
Works end time
Date SSNMP
Submitted to Council
Date SSNMP Approved by
Council
Monitoring specified in
SSNMP
SSNMP# 52 Rev8
10/05/15-24/05/15
Night SH20 SB
Maioro on-ramp
SH20 traffic management
works 10pm 5am 4/05/15 6/05/15 No
SSNMP# 72
29/05/15 -31/10/15
Night Construction
yard 9, Southern Area
Cooling fan operation
7am 7am 29/05/15 04/06/15 Yes
SSNMP# 73
10/06/15 Night
Hendon footbridge
northern arch pad
Early morning concrete pour
3am 7.30am 29/05/15 04/06/15 No
5.3. Air Quality Monitoring
Two Total Suspended Particulate (TSP) analysers and one met mast are required in the Southern Area
(Sector 9) and one TSP analyser with met mast is required in the Northern Portal Area (sector 7) under
consent conditions AQ16 and AQ17.
On 22 December 2014 one of the analysers in the Southern Area was removed from service on agreement
with Auckland Council.
The Southern Area E-BAM is located nearby the Southern Approach Trench (EBAM2). The Northern Portal
area E-BAM is located outside the Waterview School grounds (EBAM3).
E-BAM results for May show levels below the project limits for TSP at all monitoring sites with the following
exceptions:
Southern Area (EBAM 2):
No exceedences were recorded of the hourly average TSP trigger level of 200 µg/m3 at EBAM2.
No exceedences were recorded of the daily average TSP trigger level of 80 µg/m3 at EBAM2.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
A beta count failure occurred on 28 May 2015 at 9:00 p.m. and was repaired on 29 May 2015 at
11:45 a.m. The fault later re-occurred on 29 May 2015 at 8:30 p.m. and was repaired on 30 May
2015 at 1:45 p.m.
A temperature sensor fault occurred on 30 May 2015 at 4:30 p.m. The fault was detected on 31
May 2015 however due to persistent rain, could not be attended to until 01 June 2015 at 9:45 a.m.
when the sensor was replaced.
Northern Area (EBAM 3):
One exceedence was recorded of the hourly average TSP trigger level of 200 µg/m3 at EBAM3. The
exceedance was measured on 28 May 2015 between 11:00 p.m. and 12:00 a.m. with a maximum
concentration of 233 µg/m3. The exceedance occurred at night during cold, calm weather
conditions and is likely due to humidty (dew) effects.
No exceedences were recorded of the daily average TSP consent limit of 80 µg/m3 at EBAM3.
Table 4 – TSP and PM10 Monitoring Results for May
Monitoring Period
Description EBAM % Data capture
Concentration
in µg/m3
Project criteria in
µg/m3
01/05/15-31/05/15
Maximum Hourly Average TSP 2-southern area
83% 142 200
Maximum Rolling 24-Hour Average TSP 46 80
Maximum Daily Average TSP (Consent condition AQ.20 Trigger for investigation)
36 80
01/05/15-31/05/15
Maximum Hourly Average TSP 3-northern area
100% 233 200
Maximum Rolling 24-Hour Average TSP 45 80
Maximum Daily Average TSP (Consent condition AQ.20 Trigger for investigation)
38 80
5.4. Ground Water Monitoring
Monthly monitoring for piezometers identified in Appendix A of the Groundwater Management Plan
(GWMP rev 4) is on-going; with the exception of 2 piezometers which are still to be installed. The
piezometers are located in Ngati Whatua owned land within the grounds of Unitec and in the Dorje Chang
Institute, and will be installed when landowner approvals allow. As noted below, where a piezometer is
within a zone of active excavation twice-weekly monitoring is being undertaken.
Seasonal Trends
Total rainfall in May was 140 % of mean (Figure 1), following on from a relatively dry six months, which
included a very dry January (2nd driest on record). Overall a rise in groundwater level, typically ~ 0.5 m to
1.5 m, was seen across most of the site. The rise in groundwater level was more significant around the SAT;
in some piezometers up to 3.0 m, in direct response to the sustained period of rainfall near the end of May.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Figure 1 - Auckland Monthly Rainfall Data
Southern Approach Trench
The southern approach trench extends from approximate CH10530 (to the south) to the southern portal
head wall at CH11080. Dewatering via sump pumps in the excavation and below the base slab has been
occurring since September 2012. The SAT structure has been complete since August 2013.
Drawdown in the basalt, alluvium and ECBF reached steady state conditions (between March and June
2013) and groundwater levels have since fluctuated at or about the same level in response to changing
rainfall conditions.
Piezometers around the SAT have generally recorded a rise in groundwater level since the last report
(between 0.5 m to 3.1 m but typically 1.5 m). Groundwater levels are comparable to or higher than for the
same time period last year; the only exception being the groundwater level in the residual soils at DH826
which is 1.0 m lower than for the same time period last year.
Nine (9) piezometers continue to have groundwater levels fluctuating about or below alert trigger level, as
has been the case since early 2012 with groundwater levels having reached steady state conditions
(excluding seasonal fluctuations). These piezometers also have groundwater levels that are comparable to
the same time period last year. The water level in the ECBF at BH503a remains below the alarm level as per
previous reports.
As outlined in previous reports the potential for damaging consolidation settlement is considered to be
very low and groundwater levels in all piezometers except BH503 remain well above the alarm trigger
levels. As such approval has been sought to review the alert and alarm water levels in these piezometers,
0
20
40
60
80
100
120
140
160
180
200
220
240
260
Ap
r-09
May-0
9Ju
n-0
9Ju
l-09
Au
g-09
Sep
-09
Oct-0
9N
ov-0
9D
ec-0
9Jan
-10
Feb
-10
Mar-1
0A
pr-1
0M
ay-10
Jun
-10
Jul-1
0A
ug-1
0Se
p-1
0O
ct-10
No
v-10
De
c-10
Jan-1
1Fe
b-1
1M
ar-11
Ap
r-11
May-1
1Ju
n-1
1Ju
l-11
Au
g-11
Sep
-11
Oct-1
1N
ov-1
1D
ec-1
1Jan
-12
Feb
-12
Mar-1
2A
pr-1
2M
ay-12
Jun
-12
Jul-1
2A
ug-1
2Se
p-1
2O
ct-12
No
v-12
De
c-12
Jan-1
3Fe
b-1
3M
ar-13
Ap
r-13
May-1
3Ju
n-1
3Ju
l-13
Au
g-13
Sep
-13
Oct-1
3N
ov-1
3D
ec-1
3Jan
-14
Feb
-14
Mar-1
4A
pr-1
4M
ay-14
Jun
-14
Jul-1
4A
ug-1
4Se
p-1
4O
ct-14
No
v-14
De
c-14
Jan-1
5Fe
b-1
5M
ar-15
Ap
r-15
May-1
5
Rai
nfa
ll (m
m)
Calendar Month
Auckland Monthly Rainfall Data
Whenuapai Wairau Rd Mt Albert Mt Roskill Avondale Mean Auckland Rainfall
Source: ARC Hydrotel website
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
and the draft rev 5 Groundwater Effects Management Plan has been updated accordingly. The GWEMP will
be submitted for certification this month.
Markers within 100 m of the area (generally located on control sections K, L and M) have been specifically
reviewed, with movement being within the trigger levels for these areas, and in many cases within the
accuracy of the survey (i.e. no movement that can be attributed to construction).
Tunnels
Tunnelling commenced on the 14th November 2013 and the TBM broke-through the Northern Portal,
completing the first tunnel on the 29th September 2014. The TBM recommenced on 3rd December 2014
however active excavation of the ground did not commence until 7th January 2015.
Tunnelling of the second drive recommenced on 23rd April 2015. Negligible drawdown has been observed
as a result of tunnelling; however, where a piezometer is located within 30 m of the tunnel a small rise in
groundwater level, due to pressurisation of the TBM face and annulus was observed. The groundwater
level fully dissipates within a couple of days.
The TBM is now within the zone where some connection to the creek (manifesting as bubbles due to the
propagation of air from pressurisation of the TBM face and annulus) was observed during construction of
the first tunnel; as such we have reduced the face pressure. Given the proximity to buildings in this zone a
careful balance between controlling ground settlement (by a higher face pressure) and reducing the risk
connection to the creek (by a lower face pressure) is required.
Drawdown has been observed associated with exploratory probe drilling and canopy tube drilling at the
cross passage locations. At the end of April, the groundwater levels in the following piezometers in East
Coast Bays Formation rock (EU) remain at or below alert level as a result of the probe drilling.
XP03: BH1111 (EU only) and BH1112 (EU and Alluvium)
XP06: DH920a (EW only)
The rapid response to the probe and canopy tube drilling indicate that at these locations there is a direct
connectivity with low storativity fractures resulting in rapid drawdown in the rock. In all cases the
groundwater levels are comparable to the drawdowns which were experienced during the first tunnel pass,
that resulted in no adverse environmental impact and which fully recovered post tunnelling. We expect
these will also recover over the coming months. Twice weekly monitoring will continue in the interim.
Excavation has commenced at XP03 (in Alan Wood Reserve), as such piezometers within 50 m of the face
are now within a zone of “active excavation” and are being monitored twice weekly.
Five (5) piezometers located around Cradock Street continue to have groundwater levels below alert trigger
level (as a result of a head intervention undertaken in July 2014). These piezometers have shown negligible
change in level since the last report. As with piezometers in Alan Wood Reserve we anticipate that
groundwater levels in these piezometers will continue to slowly recover over a long time period. However
as the groundwater levels in these piezometers remain well above the alarm trigger levels and the
drawdown is within the ECBF rock, the potential for damaging consolidation settlement is considered to be
very low (as confirmed by on-going survey monitoring).
The groundwater level in the residual soils at DH836, reported in alert last month, has now risen by 3.0 m
and is well above the alert level; comparable to the same time period in 2013 and 2014 confirming that this
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
is a naturally occurring seasonal low level. Long term monitoring indicates a seasonal range at this location
of 7.5 m.
Northern Approach Trench
The Northern Approach Trench extends from the northern portal head wall at approximate CH13500 (to
the south) to the beginning of the Great North Road interchange at approximately CH13800. Excavation is
at final depth (and base slab constructed) over this length with active dewatering underway since August
2013.
Groundwater levels have generally been steady since March 2014 with small fluctuations in response to
rainfall. Piezometers within 150 m of the trench have recorded a small rise in groundwater level (typically
0.5 m to 1.5 m) since the last report. Groundwater levels are comparable to the same time period last year
and the groundwater level in all piezometers is within consented levels.
5.5. Settlement Monitoring
Monthly monitoring of framework ground settlement markers identified in the Settlement Effects
Management Plan (draft SEMP rev4), and additional markers installed since that time continues.
Southern Approach Trench
The majority of markers continue to show movement within +/- 3 mm of their adopted pre-construction
minimum (i.e. within the accuracy of the survey). Though some small fluctuations are seen from month to
month, overall the markers show a broad flat trend since works commenced in 2012.
Two markers (Z154 and Z155) have continued to record downward movements in the range of 10 mm to 34
mm since March 2013. These markers form a differential pair (in accordance with condition S.17);
differential settlement between the two markers is calculated to be ~1/720 therefore the potential for any
adverse effects is considered to be negligible and all other markers in this area have indicated movement of
less than 3 mm to 5 mm (well within trigger levels).
Differential movement between all other differential marker pairs is flatter than 1 in 5,000 and remains
well below trigger levels, as are assessed building damage categories in the area.
Tunnels
Markers located within 150 m of the TBM location are monitored weekly during active tunnelling.
Construction markers directly above the TBM have indicated less than 15 mm of mechanical movement
due to the TBM. This is consistent with the construction of the first tunnel.
Markers around the buildings between 1481 Great North Road and 2 Oakley Ave have recorded 5 mm to 17
mm movement since December, comparable to the seasonal trend observed last year. These markers have
shown recovery in the last eight weeks; consistent with seasonal trends observed for the same time period
last year (i.e. the movement appears to be wholly seasonal with no tunnelling influence).
Markers on the buildings at 1510 Great North Road indicate a maximum cumulative settlement (i.e. from
both tunnel drives (and without filtering of seasonal movements) of 18 mm but typically less than 10 mm.
This is well within the consent limit of 100 mm and within the Alliance’s internal design target of 35 mm.
Differential movement is typically flatter than 1/2000 as a result of a slightly wider than anticipated trough,
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
which results in reduced strains and deflections. The calculated building damage category is “0” or
negligible damage (cf. to the consented limit of “2”).
Markers on the building at 1550 Great North Road, and Unitec, have shown no movement that can be
attributed to the passing of the TBM (i.e. less than 3 mm or within the accuracy of the survey).
For all tunnel markers, maximum movements are within consented limits.
Construction monitoring arrays in Oakley Esplanade, Great North Road and in the approach to the Northern
Portal had continued to record further movement since the end of tunnelling for the first drive. The cause
of on-going movement is under investigation however it is likely to be a combination of seasonal
movement (due to the exceptionally dry summer, including the 2nd driest January on record and large soil
moisture deficits) and on-going movement due to several active landslips in the area. Markers on these
monitoring arrays were installed for construction monitoring only, are located within Oakley Esplanade (i.e.
there are no buildings directly above) and are not part of the network of compliance monitoring; regardless
we note that the movement of two markers has exceeded the consented alert limit (75 mm) for this area.
We note that monitoring in the wider area indicates seasonal / background movement of 10 mm to 25 mm
are not unexpected in this area, and monitoring of the slip at the BP indicates slope movement of 20 mm to
70 mm per year. These markers have shown 5 mm to 10 mm recovery through May, comparable to
movement observed on markers in the surrounding area.
Marker E14 located on Blockhouse Bay Road is now above the adopted trigger level, having recovered 13
mm since March, comparable to observations from the same time period last year.
Two markers (Y53 and C10) continue to show movement fluctuating at or about trigger level (i.e. 5 mm), as
they have done since June 2013. This is coincident with the introduction of the deep benchmarks. These
markers are all more than 250 m from the alignment, and markers between their localities and the
alignment show negligible movement (i.e. there is no clear spatial pattern that can be attributed to
tunnelling or other construction activities). Movement is inferred to be seasonal movement that was not
picked up until the installation of the deep benchmarks and hence isn’t reflected in the adopted trigger
levels.
Northern Approach Trench
Surveyed ground levels have generally remained steady since the end of September, with minor
fluctuations in response to rainfall.
Markers around the NAT have shown movement in the range of 1 mm to 15 mm below their adopted pre-
construction level; well within adopted trigger levels.
Markers installed to monitor the slip adjacent to the BP on Great North Road (BP10 to BP22 and Z177)
recorded downward movement of up to 75 mm between October 2013 and April 2014, coincident with an
increase in the rate of movement in the inclinometers installed in the slip. Survey monitoring over summer
2015 suggests that the slip may again be showing some accelerated rate of movement (again up to 70 mm
between October 2014 and March 2015). Since mid-March the movement has stabilised, as it did last year
with the onset of rainfall. The Alliance is continuing to share monitoring data with BP and Auckland
Transport.
Markers located around the BP building and fuel tanks, and on Great North Road between the BP and the
construction zone, have indicated less than 7 mm of movement i.e. the larger movements appear to be
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
wholly related to movement of the land slip not construction related ground settlement, and all these
markers have been steady or shown upward movement since May 2014.
Differential movement between marker pairs is flatter than 1 in 1500 in all other areas and remains well
below trigger levels, as are assessed building damage categories in the area. Markers will continue to be
monitored and reviewed weekly.
5.6. Water Quality and Ecological Monitoring
5.6.1. Water Quality
Construction phase water quality monitoring in Oakley Creek/Te Auaunga has been carried out monthly, as
required by consent conditions, with the most recent routine monitoring carried out on 16 May 2015. The
weather on the day of sampling was passing showers, with heavy rain in the few preceding days (52 mm of
rain at Auckland Airport in the five days prior). There was evidence of recent high flows with debris high up
the banks.
Pre-construction and construction phase monitoring results are shown in Figures 2 to 7 below.
Figure 2: Turbidity data from sites WR1-WR5
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Figure 3: Total suspended solids (TSS) data from sites WR1-WR5
Figure 4: pH data from sites WR1-WR5
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Figure 5: Total copper data from sites WR1-WR5
Figure 6: Total lead data from sites WR1-WR5
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Figure 7: Total zinc data from sites WR1-WR5
The May 2015 routine water quality monitoring data are summarised as follows:
Turbidity was slightly elevated at all sites compared to the April monitoring, presumably as a result of
rainfall on and prior to the day of sampling. However, suspended solids were relatively low at all
sites except WR1 (Waterview Glades), where TSS was slightly elevated compared to April, although
well within the previously measured range.
pH was near neutral at all sites.
Copper, lead and zinc were slightly elevated at all sites compared to April, although again were well
within th previously-recorded range. While zinc was slightly elevated at WR5, this site is an upstream
control site, and the raised zinc levels are unlikely to be related to WCA activities.
Overall, there is no indication of adverse water quality effects of the project.
5.6.2. Ecological Monitoring & Management
Fortnightly monitoring of significant vegetation, including geraniums, continues to be carried out. All
translocation of geranium plants from areas that will be affected by the works has been completed. This has
included successful transplanting into the Diversion B and C areas. Prolific growth of geraniums as well as
self-seeding has been recorded in both of these areas.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
5.7. Contaminated Soil Monitoring
5.7.1. Site monitoring
No unexpected contaminated soil was reported during the month of May 2015. An account of the asbestos-
contaminated soil discovered at the end of April 2015 during earthworks for the Waterview Playground and
Sports Courts is attached in Appendix B. The table of total disposed soil for April 2015 that was included in
the April Environmental Report did not include the asbestos-containing spoil from the playground works. An
updated table of total quantities of spoil disposed offsite for April 2015 is included in Appendix B.
5.7.1. Soil disposal
More than 150,000 tonnes of tunnel spoil from the southern section was disposed to Wiri in May.
Construction of the Carrington Road and Great North Road interchanges also produced small amounts of soil
requiring disposal. The daily volumes of soil disposed from the southern and northern parts of the project
during the month of May are shown on Tables 6 and 7 respectively.
Table 6: Disposal location and approximate quantity of soil disposed of off site from the south in May 2015
Volume Volume
Tonnes tonnes m3 * Tonnes tonnes m3 *
1/05/2015 312.26 109,264.56 64,273 4,897.74 1,290,323.93 759,014
2/05/2015 109,264.56 64,273 908.60 1,291,232.53 759,549
4/05/2015 109,264.56 64,273 5,666.40 1,296,898.93 762,882
5/05/2015 109,264.56 64,273 7,813.18 1,304,712.11 767,478
6/05/2015 109,264.56 64,273 5,877.60 1,310,589.71 770,935
7/05/2015 109,264.56 64,273 5,409.88 1,315,999.59 774,117
8/05/2015 109,264.56 64,273 5,566.14 1,321,565.73 777,392
9/05/2015 109,264.56 64,273 1,067.50 1,322,633.23 778,020
11/05/2015 103.08 109,367.64 64,334 5,532.80 1,328,166.03 781,274
12/05/2015 109,367.64 64,334 7,631.08 1,335,797.11 785,763
13/05/2015 109,367.64 64,334 6,960.14 1,342,757.25 789,857
14/05/2015 109,367.64 64,334 7,773.71 1,350,530.96 794,430
15/05/2015 109,367.64 64,334 8,327.97 1,358,858.93 799,329
16/05/2015 109,367.64 64,334 4,352.42 1,363,211.35 801,889
18/05/2015 109,367.64 64,334 6,380.79 1,369,592.14 805,642
19/05/2015 109,367.64 64,334 7,384.78 1,376,976.92 809,986
20/05/2015 109,367.64 64,334 8,513.94 1,385,490.86 814,995
21/05/2015 109,367.64 64,334 8,271.82 1,393,762.68 819,860
22/05/2015 109,367.64 64,334 7,966.58 1,401,729.26 824,547
23/05/2015 109,367.64 64,334 2,844.18 1,404,573.44 826,220
25/05/2015 109,367.64 64,334 6,081.42 1,410,654.86 829,797
26/05/2015 109,367.64 64,334 5,029.80 1,415,684.66 832,756
27/05/2015 109,367.64 64,334 5,270.92 1,420,955.58 835,856
28/05/2015 109,367.64 64,334 7,794.35 1,428,749.93 840,441
29/05/2015 109,367.64 64,334 6,404.55 1,435,154.48 844,209
30/05/2015 109,367.64 64,334 2,194.52 1,437,349.00 845,499
Month of May 415.34 109,367.64 64,333.91 151,922.81 1,437,349.00 845,499
Date
Three Kings Managed Fill Site
Cumulative total
Wiri Disposal Site (Cleanfill)
Cumulative total
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Table 7: Disposal location and approximate quantity of soil disposed of off site from the north in May 2015
Notes: * Estimated volume based on a soil density of 1.7 tonnes/m
3
^ Estimated volume based on 19 tonnes for an articulated truck
5.7.2. Phyllis Reserve landfill monitoring
5.7.2.1. Overview
Monitoring of landfill gas, pH and electric conductivity (eC) in selected groundwater wells at the Phyllis
Reserve commenced in October 2013 (i.e. 1 year prior to the estimated time of arrival of the tunnel boring
machine (TBM) beneath the landfill), to meet consent conditions CL.9 and CL.10. The monitoring programme
is described in Section 3.4.3 of the Contaminated Soil Management Plan Rev 4/5.
The intention of the monitoring is to establish if ground disturbance from the TBM has resulted in the release
of landfill gas or leachate into underlying groundwater.
Monitoring locations are shown on Map 5.1 below. Table 8 below provides summary information of the
groundwater wells that have been selected for pH and eC measurements.
Volume Volume
Tonnes tonnes m3 * Tonnes ^ tonnes m3 *
1/05/2015 86.84 20,964.78 12,332 697.36 63,464.02 37,332
7/05/2015 128.88 21,093.66 12,408 63,464.02 37,332
8/05/2015 248.04 21,341.70 12,554 63,464.02 37,332
11/05/2015 21,341.70 12,554 315.52 63,779.54 37,517
12/05/2015 322.04 21,663.74 12,743 31.58 63,811.12 37,536
13/05/2015 256.36 21,920.10 12,894 63,811.12 37,536
15/05/2015 106.22 22,026.32 12,957 29.46 63,840.58 37,553
20/05/2015 182.34 22,208.66 13,064 63,840.58 37,553
25/05/2015 236.26 22,444.92 13,203 63,840.58 37,553
26/05/2015 108.1 22,553.02 13,266 63,840.58 37,553
28/05/2015 23.86 22,576.88 13,281 63,840.58 37,553
Month of May 1,698.94 22,576.88 13,280.52 1,073.92 63,840.58 37,553.28
Three Kings Managed Fill Site
Cumulative total
Ridge Road Disposal Site
Cumulative total
Date
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 19 15 June 2015
Map 5.1: Monitoring locations
MW4 MW3
MW1
MW2
BH709d
BH709a1
BH709a
BH709c
DH832
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 20 15 June 2015
Table 8: Groundwater well summary information
Borehole ID Location Well screen depth (m) Screened geological unit
BH709d Northern boundary of landfill 1.5 – 5 Landfill material
BH707 Western boundary of landfill 5.5 – 9 Landfill material (Now decommissioned)
BH709a1 Northern boundary of landfill 6.5 – 10.5 Landfill material
BH709a Northern boundary of landfill 15.5 – 19.5 Weathered Waitemata Group, about 7.5 m below landfill base
BH709c Northern boundary of landfill 12.3 – 16.8 Tauranga Group, about 4.8 m below landfill base
DH832d Down gradient of landfill 5.5 – 8 Tauranga Group
5.7.2.2. Landfill gas monitoring results
Landfill gas monitoring was undertaken on 29 May 2015. Results of the landfill gas monitoring are provided in Table 9. Results are within the range of the historical and baseline monitoring data.
Table 9: Methane concentrations (% vol)
MW1 MW2 MW3 MW4
(up gradient)
Historical range1 0 – 0.3 0 – 5.9 0 – 24.2 0 – 0.1
25/10/2013 0 0 48 0
15/11/2013 0.1 0 27.1 0
13/12/2013 0.1 0 7.5 0.1
9/01/2014 0 0 15.3 0
28/02/2014 0 0 22.8 0
31/03/2014 0 0 13.6 0
29/04/ 2014 0 0 15 0
30/05/2014 Not sampled2 0 12.9 0
02/07/2014 0.1 0.1 22.5 0
21/07/2014 0 0 5.2 0
30/07/2014 0 0 13.7 0
29/08/2014 0 0 0 0
30/09/2014 0 0 2.4 0
16/10/2014 0 0 2.5 0
14/11/2014 0.1 0 27.4 0
15/12/2014 0.1 0.1 18.1 0
07/01/2015 0.2 0 14.6 0
16/02/2015 0.1 0 21.5 0
19/03/2015 0.1 0 18.9 0
16/4/2015 0.5 0 18 0
29/05/2015 0 0 0 0 1 Obtained from Auckland Council data - refer Contaminated Soil Management Plan Rev 4 2 No access to sample well as new lock had been installed
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
5.7.2.3. Groundwater monitoring results
Monitoring of selected groundwater wells occurred at the landfill on 27 May 2015 and continue to show
overall similar results to April 2015, except for electrical conductivity in well 709a1_6.5-10.5 m. The
conductivity reading in the sample collected in May decreased sharply, however, the parameter in this well
has a history of variability over the monitoring period so at this stage the conductivity is considered
acceptable. Graphs of the measurements, together with water level measurements, are presented overleaf.
Water levels in all wells are generally similar to levels at the same time last year.
pH and conductivity in all monitored wells are showing similar trends and are within the
preconstruction range.
The review continues to show that there is no clear indication of any water quality degradation that
can be associated with tunnelling and TBM activities under the landfill.
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 22 15 June 2015
0
1
2
3
4
5
6
7
8
9
10
11
12
13
140
1
2
3
4
5
6
7
8
9
10
11
12
13
14
pH
GW
L (m
bgl
)
Date
BH709d_1.5-5m
Water Level PH
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
1300.0
1400.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14
20
/06
/13
20
/07
/13
20
/08
/13
20
/09
/13
20
/10
/13
20
/11
/13
20
/12
/13
20
/01
/14
20
/02
/14
20
/03
/14
20
/04
/14
20
/05
/14
20
/06
/14
20
/07
/14
20
/08
/14
20
/09
/14
20
/10
/14
20
/11
/14
20
/12
/14
20
/01
/15
20
/02
/15
20
/03
/15
20
/04
/15
20
/05
/15
20
/06
/15
Co
nd
uct
ivit
y μ
S
GW
L (m
bgl
)
Date
BH709d_1.5-5m
Water Level Conductivity μS
0
1
2
3
4
5
6
7
8
90
1
2
3
4
5
6
7
8
9
10
11
pH
GW
L (m
bgl
)
Date
BH709a1_6.5-10.5m
Water Level PH
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
1300.00
1
2
3
4
5
6
7
8
9
10
11
Co
nd
uct
ivit
y μ
S
GW
L (m
bgl
)
Date
BH709a1_6.5-10.5m
Water Level Conductivity μS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
1410
11
12
13
14
15
16
17
18
19
20
21
22
23
24
pH
GW
L (m
bgl
)
Date
BH709a_15.5-19.5m
Water Level PH
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
1300.0
1400.010
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Co
nd
uct
ivit
y μ
S
GW
L (m
bgl
)
Date
BH709a_15.5-19.5m
Water Level Conductivity μS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
140.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
14.0
15.0
16.0
17.0
pH
GW
L (m
bgl
)
Date
BH709c_12.3-16.8m
Water Level PH
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
14000.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
14.0
15.0
16.0
17.0
Co
nd
uct
ivit
y μ
S
GW
L (m
bgl
)
Date
BH709c_12.3-16.8m
Water Level Conductivity μS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
140.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
pH
GW
L (m
bgl
)
Date
DH832_5.5-8m
Water Level PH
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
1300.0
1400.00.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
Co
nd
uct
ivit
y μ
S
GW
L (m
bgl
)
Date
DH832_5.5-8m
Water Level Conductivity μS
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 23 15 June 2015
5.8. Erosion and Sediment Control Monitoring
New and amended CESCP’s submitted to and approved by Auckland Council in May include:
34 Rev 2 – Removal of SRP10
47 – Maioro St off-ramp batter remedial works
123 Rev 3 – Topsoiling at eastern end of the Boomerang
126 Rev 2 – Topsoiling in the Cleaver
129 – Ramp 2 Median Works
Regular monitoring of erosion and sediment control has been undertaken in May 2015 by the Erosion and
Sediment Control Team and Construction Teams.
5.9. Archaeological monitoring
General archaeological monitoring continues by project archaeologists Clough and Associates in accordance
with consent conditions and the following Heritage New Zealand (HNZ) Authorities:
2013/174 - General Authority for earthworks in association with Stage 3 Northern Portal Works.
2013/518 - General Authority for earthworks in association with Stage 4 Great North Road Interchange
Works.
2015/296- General Authority for earthworks in association with the Howlett Reserve Footpath
The archaeological authority for the Oakley Inlet Heritage Area (OIHA) around the site of the old Star Mill has
been accepted by Heritage New Zealand. A general authority has been granted under the id 2015/1062. An
amendment to this authority being sought to cover planting and landscaping works that were not accepted
at the time of lodgment due to insufficient informaiton. Clough and Associates are to submit a revised
Management Plan to Heritage NZ which will cover the final works.
5.10. Waste Management
Regular inspections of the Waste Storage Areas are being carried out to ensure they are kept tidy and
recyclable materials are being separated. Yards are set up with bins for wood waste, plastic waste, general
waste and steel. Office areas have co-mingled recycling bins and paper bins.
Regular audits of skips are being carried out and opportunities to reduce waste generation and to reuse
materials whenever possible are regularly investigated.
Waste tracking for the project up to the end of May shows 68.48% of waste being diverted from landfill for
recycling. A break down for the project to date is shown in Table 10.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Table 10: Waste Records Project to Date (tonnes)
Wood Gib Metal Plastics Comingle Card & Paper
Poly-styrene
Hardfill General Waste
Total
611.69 3.94 390.51 85.92 40.48 37.46 8.51 470.26 775.16 2459.06
25% 0% 16% 3% 2% 2% 0% 20% 32% 100%
5.11. Hazardous Substance Management
Monthly inspections of hazardous substance storage areas and associated controls, such as spill kits, are
identified in the Hazardous Substances Management Plan (HSMP rev4) that has been prepared to meet
condition CEMP.10, and are ongoing.
There are hazardous substance storage areas for the Project established within construction yards CY6, CY9
and CY10, 160 Stoddard Road Southern Area stores and at East Tamaki Precast Yard. Hazardous Substances
and New Organisms (HSNO) Act 1996 certification requirements have been identified as below for these
storage areas, in liaison with the Project’s HSNO Test Certifier Pete Roche. During May, two staff were
certified as approved handlers, bring the total to 44 that have been certified on the Project. In addition the
location test certificate for CY9 was updated to allow for additional gas storage for tunnel team operations.
Table 11: Project Test Certification
Storage Area Test Certification Date certified
CY6 Northern area
Location test certificate: 250 litres class 3.1A, 600 litres class 3.1B and 3.1C (combined).
02 August 2014 – 01 August 2015
CY9 Tunnel team
Stationary Container System test certificate: 60,000 litres Sodium silicate. Stationary Container System test certificate: 30,000 litres diesel. Location test certificate: 2000kg class 2.1.1A, 400m3 class 5.1.1.
07 November 2013 – 06 November 2015 14 May 2014 -13 May 2019. 02 August 2014 – 01 August 2015
CY10 Tunnel team
Location test certificate: 600 litres class 3.1B and 3.1C (combined).
04 April 2015– 03 April 2016
160 Stoddard Road, Southern area
Location test certificate: 500 litres class 3.1B and 3.1C (combined).
02 August 2014 – 01 August 2015
East Tamaki Precast Yard Location test certificate: 6000 litres class 3.1B and 3.1C (combined).
02 August 2014 – 01 August 2015
6. Stakeholder Management
6.1. Stakeholders – local liaison activity
We continue to enjoy a good relationship with our surrounding communities, which is founded on a
proactive approach to informing of any changes to the norm and ‘personal service’ through our dedicated
community liaison managers. Beyond our everyday interactions with residents and the delivery of monthly
project updates, below is a summary of some of our local activity in May:
Southern & Tunnel sector
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Ongoing liaison with specific residents above the tunnel alignment
Maioro Street on-ramp works notification – 5 letters in total because wet weather
Notification to residents at 23 and 33 Valonia Street properties regarding Retaining wall and fence
construction.
Notification to residents leiving near May Road regarding rock-breaking work
Liaison with Mt Roskill New World and AT Bus Depot around temporary traffic management impacts
Northern sector
Liaison with affected residents regarding upcoming and out of hours works in various places including: o Ground stabilisation on SH16 adjacent to Carrington Road Bridge and SH16 – two notices o Notification around the resumption of works on Ramp 4 o Night works notification at the Northern Approach Trench
Formal letter signed by Waterview School Principal and Board regarding the proposed construction of a permanent fence on boundary between school and project site.
Formal completion of documentation regarding St Francis School boundary fence
Site tours
There were 22 site tours during the month of March
Key visitors included o Auckand Council CEO – Stephen Town
There were 6 off site presentations to community groups
We hosted a visit to Alice the TBM for a group of TradeMe auction winners, they bid on tickets to support our Ride to Conquer Cancer team.
We hosted 20 delegates from the Asia Pacific Stormwater Conference, they visited the southern site to view the works around Oakley Creek regeneration.
6.2. General Communications Activity: Overview
We continue to get good feedback for the monthly Project Updates; these are distributed to around 5000 households each month and emailed out to thousands more. They offer updates on work, milestones reached, progress photos and a community corner. Last month we released three media releases announcing resumption of construction of GNRI ramp 4 after faulty concrete issue (this release covered in detail by NZ Herald), progress of TBM on main drive south (good coverage in the media) and Project and NZTA providing video interviews for British-based electronic magazine called Tunnel Talk about tunnel progress. We are contining work with the Ministry of Education to further advance the Engineering Challenge sponsored by the Minister of Tertiary Education. The Minister wants to use Waterview as an “Educational Tool” to encourage secondary school students to consider a career in engineering. We continue updating via Facebook, YouTube, Twitter and Instagram, all of which are gaining more followers. This month we put online the footage of a drone fly through of the project, it was a phenominal success, it was immediately shared on the NZ Herald website and Stuff.co.nz. This post had the most ‘likes’ and ‘shares’ of any of the posts to date. This also sparked a TV interview with TVOne. https://www.youtube.com/watch?v=e0Ogx3k2vBs
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Key links www.facebook.com.alicetbm www.youtube.com/wcnow http://www.nzta.govt.nz/projects/waterviewconnection twitter.com/wcnow
6.3. Queries, Concerns and Complaints
Compliments: Five compliments were received in May. Largley relating to customer satisfaction in relation to positive community relationships and social media compliments. Complaints: Eight complaints were received during the month of May 2015. Four were not related to WCA but were received via our 0508 phone number. A summary of the other four complaints received is as follows:
Dangerous driving by truck leaving a southern site access. The incident is being followed up with the subcontractor.
Two incidents of noise from a truck braking at the weighbridge disturbing residents. This was followed up with the subcontractor who identified the driver concerned.
Weeds behind a noise fence encroaching on neighbours property. Maintenance has been completed to address this.
May 2015 Report
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 27 15 June 2015
Case Title Subject Case Type Origin Area Status Owner
Actual Start Date Street Name Suburb
Concern re earthworks in Teardrop at GNRI affecting health. (Not WCA, passed to CA to address.) ENV - Dust Concern Email North Resolved Claire Cooney 4/05/2015 Alberta Street Pt Chevalier
Complaint: Worker vehicles parking across driveway (NOT WCA) GEN - Traffic Complaint Phone North Resolved Jocelyn Shaw 5/05/2015 Oakley Ave Waterview
Complaint - Stone on the motorway broke windscreen (NOT WCA) GEN - Traffic Complaint Email South Resolved Jocelyn Shaw 6/05/2015
Complaint re noise of rumbling motor (NOT WCA) ENV - Noise Complaint Phone North Resolved Claire Cooney 6/05/2015 Alverston Street Waterview
Compliment from St Francis School re boundary fence GEN - Other Compliment In Person North Resolved Claire Cooney 6/05/2015 Montrose Street Pt Chevalier
Request for information from local board member re faulty concrete GEN - Other Request Email North Resolved Jocelyn Shaw 6/05/2015 Howlett Avenue Waterview
Concern re road marking and steel mats on Waterview section of SH16. GEN - Traffic Concern Phone North Resolved Claire Cooney 8/05/2015 SH16 Motorway
Request for information on Waterview Reserve GEN - Other Request Email North Resolved Claire Cooney 8/05/2015 Waterview
Compliments on Facebook regarding the Drone footage GEN - Other Compliment Web Project Wide Resolved Claire Cooney 11/05/2015 Waterview
Complaint re noise from trucks braking at 2.00am. Also earlier shifts 5.00am instead of 6.00am ENV - Noise Complaint Phone South Resolved Leigh Tracey 12/05/2015 Whittle Place
New Windsor
Compliment: A Big Thanks to the Tunnel Team GEN - Other Compliment Email Tunnel Resolved Jocelyn Shaw 12/05/2015
Complaint - weed growing from WCA site onto his property ENV - Other Complaint Phone South Resolved Leigh Tracey 13/05/2015 Hendon Avenue Mt Roskill
Concern - Someone jumped through construction fence between 10 -12 Howlett Street GEN - Other Concern Phone North Resolved Leigh Tracey 13/05/2015 Howlett Avenue Waterview
Complaint - strong vibrations being felt at family home (Not WCA) ENV - Vibration Complaint Email North Resolved Leigh Tracey 18/05/2015 Novar Place Point Chev
Compliment: Marque Blog & Waterview resident GEN - Other Compliment Web Project Wide Resolved Jocelyn Shaw 18/05/2015
Thanks for drainage pipe off cuts delivered to resident for hobby project GEN - Other Compliment Phone North Resolved Claire Cooney 19/05/2015 Pt Chevalier Road Pt Chevalier
Enquiry into who will cover costs incurred due to faulty concrete on Ramp 4 GEN - Other Request Phone North Resolved Claire Cooney 20/05/2015 Alford Street Waterview
Complaint: Loud engine braking noise at 7pm – not related to site. ENV - Noise Complaint Phone South Resolved Jocelyn Shaw 20/05/2015
Information: Stone deflected onto car from truck merging into SH20 GEN - Traffic Suggestion In Person South Resolved Jocelyn Shaw 26/05/2015
Request for Information - Fence replacement at 17 Valonia Street GEN - Other Concern In Person South Resolved Leigh Tracey 27/05/2015 Valonia Street Mt Roskill
Suspected oil spill from site at CY9 to reserve. Investigated immediately. Bund around diesel tank intact/ no sign of spill. ENV - Spills Concern Phone South Resolved Claire Cooney 28/05/2015 Hendon Avenue Owairaka
Complaint - Dangerous driving from truck leaving site onto motorway. Being followed up with trucking company. GEN - Traffic Complaint Email South Active Leigh Tracey 28/05/2015
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 28 15 June 2015
Appendix A
Additional Consents Obtained
Additional consents obtained:
(New consents for the month shown in bold)
Consent Description Date Lodged Decision Date
R/LUC/2015/47163 Landuse consent for earthworks associated with the demobilising of the pre-cast yard at East Tamaki.
15th
May 2015 25th
May 2015
R/LUC/2015/1316 R/REG/2015/132
Landuse consent and coastal permit for works associated with the construction and occupation of a boardwalk at Eric Armishaw reserve.
10th
April 2015 7th
May 2015
R/LUC/2015/1113 Landuse consent for the construction and operation of a ablutions block at Valonia carpark, Alan Wood Reserve.
27th
March 2015
9th
April 2015
R/LUC/2014/5226 Landuse consent for the provision of a new car park and volleyball court for Alan Wood Reserve
15th
December 2014
21st
January 2015
R/LUC/2014/4244 Land use consent to construct and establish a new coastal pathway through the Howlett and Waterview Esplanade Reserves, Waterview
7th
October 2014
5th
November 2014
R/LUC/2014/3265 & R/REG/2014/3266
Land use and discharge permits to undertake enabling earthworks (preparatory only) to re-grade the Valonia Street carpark and change facility.
6th August 2014
1st September 2014
R/LUC/2014/926 Land use consent to remove native trees within an open space reserve
12th
Mar 2014 31st
Mar 2014
R/LUC/2011/4677 35 Valonia Street, New Windsor
Land use consent for temporary carpark and access way, associated earthworks and tree removal, and works within the dripline of protected trees.
16th
Dec 2011 20th
Jan 2012
ARC: 39983 35 Valonia Street, New Windsor
Landuse consent for earthworks. 16
th Dec 2011 20
th Jan 2012
R/LUC/2012/991 Alan Wood Reserve
Removal and works within the dripline of protected trees associated with the relocation of a wastewater pipe (the Hendon Sewer) within Alan Wood Reserve.
2nd
April 2012 30th
April 2012
ARC: 40316 - Stormwater ARC: 40318 - Industrial & Trade; ARC: 40319 - Air Discharge; and ARC:40627 – Landuse 53 Ormiston Road, East Tamaki
Integrated Land use consents (District & Regional) for the diversion and discharge of stormwater, the discharge of contaminants from an industrial or trade activity, the discharge of contaminants to air and parking and vehicular access infringements associated with the construction and operation of a Pre-Cast concrete facility at 53 Ormiston Road, East Tamaki.
16th
May 2012 15th
Aug 2012
R/LUC/2012/1879 6 Barrymore Road, Owairaka
Land use consent for removal of eight protected trees associated with the creation of pedestrian and vehicular accesses within Barrymore Road Reserve.
18th
June 2012 11th
July 2012
R/LUC/2012/2168 142-160A Stoddard Rd, Mount Roskill
Land use consent for the construction and use of a new Project Site Office at Stoddard Rd, including associated earthworks and parking.
11th
July 2012 8th
Aug 2012
ARC: 40097 and 40166 53 Ormiston Road, East Tamaki
Land use consents for land modification and land disturbance for construction of a Pre-Cast Facility.
16th
July 2012 13th
April 2012
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Consent Description Date Lodged Decision Date
R/LUC/2012/2568 Installation of above ground duct containing power, water and telecommunication services
Installation of an above ground duct containing power, water and telecommunication services to provide services to Construction Yard 11
10th
Aug 2012 29th
Aug 2012
R/LUC/2012/4601 Valonia Sportsfield Lights 35 Valonia Street, New Windsor
To construct a sportsfield lighting column, with 2000 watt medium beam lights mounted on a 16.5 metre high pole, at Valonia Sports Field (Field No.2). 12
th Dec 2012 8
th Feb 2013
R/LUC/2013/646 CY11 Carpark & Storage
CY11 Carpark Extension and Storage, including associated earthworks
25th
Feb 2013 22nd
April 2013
ARC: 41436 Stormwater CY11 Carpark & Storage
CY11 Carpark Extension – associated stormwater diversion
25th
Feb 2013 22nd
April 2013
ARC: 41437 Earthworks CY11 Carpark & Storage
CY11 Carpark Extension – associated earthworks
25th
Feb 2013 22nd
April 2013
R/TRC/2013/709 Richardson Rd Tree Removal
The removal of a generally protected tree located within the road reserve of Richardson Road associated with the shared pedestrian and cycleway.
1st
March 2013 5th
March 2013
R/LUC/2013/3071 Resource Consent for Recovery of the Lost Core Barrel in Alan Wood Reserve
Resource Consent Approval for recovery of the lost core barrel in Alan Wood Reserve.
16th
Aug 2013 17th
Sept 2013
R/OPW/2013/3106 Outline Plan of Works SH20 Extension Dominion Rd to Maioro St
Approval for the Outline Plan of Works for the widening of the existing State Highway 20 northbound alignment between Dominion Road and Maioro Street. 20
th Aug 2013 13
th Sept 2013
R/LUC/2013/3363 Dominion Rd to Maioro St NES Soils Consent
Discretionary activity consent for soil disturbance pursuant to Regulation 11 of the National Environmental Standard for Assessing and Managing Effects on Human Health (NES (Soil)).
4th
Sept 2013 3rd
Oct 2013
R/LUC/2013/3513 Resource Consent for relocation of an existing gas regulator unit
Resource Consent Approval for the relocation of an existing gas regulator unit within a road reserve
12th
Sept 2013 11th
Oct 2013
R/LUC/2013/4460 Trimming of a tree and removal of another at Unitec
Resource Consent for the trimming of a tree and removal of another at the Unitec site at 1 Carrington Rd
30th
Oct 2013 20th
Nov 2013
R/LUC/2013/4534 Demolition of 27 Parr Rd South dwelling
Resource Consent Approval for the demolition of 27 Parr Rd South dwelling
7th
Nov 2013 20th
Nov 2013
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Consent Description Date Lodged Decision Date
R/OPW/2013/4455 Outline Plan of Works Southern Ventilation Building, Control Building and Stack (OPW2)
Approval for the Outline Plan of Works for the Southern Ventilation Building, Control Building and Stack (OPW2) – No requests for changes.
30th
Oct 2013 2nd
Dec 2013
Alteration to Designation: Retaining Wall 603 (Unitec)
Alteration to Designation: Retaining Wall 603 (Unitec) ‘A07-01E Motorway: Western Ring Route – Waterview Connection, Alteration to Designation A07-01 SH16 between Great North Road and St Lukes Interchange
12th
Nov2013 6th
Dec 2013
R/OPW/2014/9 Outline Plan of Works Northern Ventilation Building, Control Building and Stack (OPW1)
Approval for the Outline Plan of Works for the Northern Ventilation Building, Control Building and Stack (OPW1) – No requests for changes.
16th
Dec 2013 18
th February 2014
R/LUC/2014/926 and R/REG/2014/929 Harbutt Reserve Tree Clearances
Approval for clearing and pruning trees within Harbutt Reserve for the purposes of installing Settlement Monitoring Rods.
11th
March 2014
31st
March 2014
NZHPT Authorities obtained:
Heritage New Zealand Authority – Howlett/Waterview Esplanade walkway
General Heritage New Zealand Authority for earthworks associated with the construction of Howlett/Waterview Esplanade walkway (Auth Number 2015/396)
Archaeological Authority required in accordance with Section 48 of the Heritage New Zealand Act
NZHPT Authority Southern Area Enabling Works
General NZHPT Authority for Earthworks in association with Southern Area Enabling Works
Archaeological Authority required in accordance with Section 12 of the Historic Places Act.
NZHPT Authority Southern Area Main Works
General NZHPT Authority for Earthworks in association with Southern Area Main Works
Archaeological Authority required in accordance with Section 12 of the Historic Places Act.
NZHPT Authority Northern Portal Works
General HPT Authority for Earthworks in association with Northern Portal Works
Archaeological Authority required in accordance with Section 12 of the Historic Places Act.
NZHPT Authority Great North Interchange Works
General HPT Authority for Earthworks in association with Great North Interchange Works
Archaeological Authority required in accordance with Section 14 of the Historic Places Act.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Appendix B
Summary of asbestos removal at Waterview Playground and Sports Courts
This report summarises the findings and remediation work undertaken in April 2015 at the proposed
Waterview Playground and Sports Courts area, located at the corner of Waterbank Crescent and Herdman
Street. An update to the total spoil volumes for April 2015 in the northern section is included at the end of
this appendix.
B1 Background
Asbestos-containing materials (ACM) were encountered in several areas of the proposed Waterview
Playground and Sports Courts area during excavation of surface soil at the end of April 2015 (refer Figure B1).
The ACM, based on the location where it was encountered, is likely to have been associated with either fill
material or incomplete demolition of previous structures (e.g. house cladding or roofing, or boxing of
concrete building foundations).
B2 Summary of remediation works
Remediation of the playground area was achieved by excavating and removing all ACM from the playground.
The excavation work was conducted by Nikau Demolition, supervised by a certificate of competence (CoC)
holder under the Asbestos Regulations 1998.
In all areas where ACM was discovered and including the stockpile areas, the ground was over-excavated by
a minimum of 50 mm below the last observed ACM fragments, and at least 500 mm laterally in all directions.
A visual inspection of the surface was carried out and validation samples were collected from the base of the
remediation excavation.
A total of 1,109 tonnes of ACM and associated soils were disposed of at Redvale Landfill (refer Table B3).
As a precautionary measure, and in order to progress works without waiting for the laboratory test results
for the validation samples, remediated areas were covered with bidim before the area was backfilled with
lime-stabilised clay and roller compacted. The bidim was placed to act as a visual deterrent/barrier for future
excavations, in the event that validation samples were to indicate asbestos-contaminated soils present
beneath the base of the remediation excavation. The bidim was overlapped by at least 200 mm to form a
continuous layer across the playground area and anchored with steel pins approximately every 5-10 m.
Natural East Coast Bays Formation clay, sourced from the retaining wall construction to the north of Unitec,
was placed directly on top of the bidim.
B3 Air Monitoring
Air monitoring was conducted for a minimum of 4 hours per day, each day ACM remedial works was being
undertaken (total of 6 days). Two air monitors were employed, one on the eastern and one on the western
boundary of the site (refer Figure B1). Air filters were analysed at Dowdell and Associates laboratory in
Penrose.
Air monitoring results are summarised in Table B1. Laboratory transcripts are attached. All samples were
below the laboratory detection limit and health screening level of 0.01 fibres/mL.
May 2015 Environmental Report
AC Monthly Report May 15.docx 22 June 2015
Table B1: Air monitoring results
Date Fibres in Air (fibre/mL)
Western boundary Eastern boundary
21/04/2015 <0.01 <0.01
22/04/2015 <0.01 <0.01
23/04/2015 <0.01 <0.01
24/04/2015 <0.01 <0.01
28/04/2015 <0.01 <0.01
29/04/2015 <0.01 <0.01
B4 Validation sampling and results
Validation samples were collected from the base of the remediation excavations (refer Figure B1), across the
playground. The samples were comprised of yellow-brown and orange clay with some silt.
Seven (7) samples, S1 – S7, were sent to Hill Laboratories in Hamilton to test for ACM, metals and
polyaromatic hydrocarbons (PAH). Three (3) of the seven (7) samples were analysed for total petroleum
hydrocarbons (TPH). One duplicate sample of S6 was collected for quality control and quality assurance
purposes. Another twelve (12) samples were submitted to Dowdell and Associates laboratory for qualitative
(presence/absence) ACM analysis. Full laboratory transcripts are attached.
No ACM was detected in all nineteen (19) samples sent for analysis.
Table B2 (following page) summarises the metals and PAH results, together with the assessment criteria
appropriate for the site, as follows:
NES Soil1 contaminant standards for recreational landuse; and
Permitted activity acceptance criteria for discharges outlined in the Auckland Regional Plan: Air Land and
Water (ALW Plan) and Proposed Auckland Unitary Plan (PAUP).
All samples tested for PAH and/or TPH had concentrations of these contaminants below the laboratory
detection limit. Metal concentrations were all below the NES Soil contaminant standards for recreational
land use and the permitted activity criteria for discharges in the ALW Plan and PAUP.
Conclusions
The validation programme confirms that the playground area has been successfully remediated with regards
to the proposed future land use from a ground contamination perspective.
1 Resource Management (National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect Human
Health) Regulations 2011
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 33 15 June 2015
Table B2: Soil analytical results - metals
Metal NES Soil contaminant
standards for recreational landuse
ALW Plan /PAUP permitted activity discharge criteria S1 S2 S3 S4 S5 S6 Dup (S6) S7
Total Recoverable Arsenic 80 100 < 2 < 2 4 < 2 < 2 < 2 < 2 3
Total Recoverable Cadmium 400 7.5 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium >10,000 600 6 4 16 6 5 8 7 9
Total Recoverable Copper >10,000 325 3 3 21 4 5 4 4 5
Total Recoverable Lead 880 250 8.4 7.4 136 8.9 25 159 141 11.1
Total Recoverable Nickel 1,200 105 2 < 2 11 3 3 < 2 2 5
Total Recoverable Zinc 30,000 400 11 6 70 5 18 45 48 11
Table B3: Updated daily volumes of spoil for northern section for April 2015
Volume Volume Volume
Tonnes tonnes m3 * Tonnes ^ tonnes m3 * Tonnes tonnes m3 *
1/04/2015 - 20,664.76 12,156 433.18 60,222.20 35,425 - 978.43 576
2/04/2015 - 20,664.76 12,156 30.80 60,253.00 35,443 - 978.43 576
7/04/2015 - 20,664.76 12,156 166.48 60,419.48 35,541 - 978.43 576
8/04/2015 - 20,664.76 12,156 334.30 60,753.78 35,738 - 978.43 576
9/04/2015 - 20,664.76 12,156 377.62 61,131.40 35,960 - 978.43 576
10/04/2015 - 20,664.76 12,156 508.06 61,639.46 36,259 - 978.43 576
13/04/2015 - 20,664.76 12,156 427.32 62,066.78 36,510 - 978.43 576
15/04/2015 - 20,664.76 12,156 699.88 62,766.66 36,922 - 978.43 576
17/04/2015 24.04 20,688.80 12,170 - 62,766.66 36,922 - 978.43 576
21/04/2015 - - - - 84.56 1062.99 625
22/04/2015 - - - - 270.76 1333.75 785
23/04/2015 53.34 20,742.14 12,201 - 62,766.66 36,922 226.88 1560.63 918
24/04/2015 - - - - - 165.46 1726.09 1015
28/04/2015 - - - - - - 126.16 1852.25 1090
29/04/2015 - - - - - - 184.96 2037.21 1198
30/04/2015 135.80 20,877.94 12,281 - 62,766.66 36,922 49.86 2087.07 1228
Month of April 213.18 20,877.94 12,281 2,977.64 62,766.66 36,922 1108.64 2087.07 1228
Cumulative totalDate
Three Kings Managed Fill Site
Cumulative total
Ridge Road Disposal Site
Cumulative total
Redvale Disposal Site
May 2015 Environmental Report
AC Monthly Report May 15.docx Page 34 15 June 2015