waterview connection project (ca3466)

31
Waterview Connection Project (CA3466): Auckland Council Monthly Environmental Report Report 08 Period October 2012 Document 025-RPT-01681 21 November 2012

Upload: others

Post on 28-Mar-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Auckland Council Monthly Environmental Report, October 2012Auckland Council Monthly Environmental Report Report 08 – Period October 2012
Document 025-RPT-01681
AC Monthly Report Oct 2012.docx Page 2 21 November 2012
1. Introduction
To meet reporting requirements for the Waterview Connection, a monthly report will be prepared and
sent to AC in the 2nd week of the following month.
This report sets out the reporting requirements for the Waterview Connection for the period October
2012.
Consent Description Trigger
Maioro Street Interchange – NOR7.
Works within the designation.
inclusive).
contaminated land (that is undergoing disturbance or
remediation) (Sectors 1,3,5,6,7,8 and 9).
Land disturbance activities within areas
potentially containing contaminated
with roadworks (including dust emission).
General activities associated with the road
construction.
Maioro Street Interchange – NOR7.
Works within the designation.
inclusive)
permanent stream.
EPA 10/2.012
(ARC: 38317)
For bridges constructed over Oakley Creek – includes
Hendon Park Bridge and cycleway bridges.
Construction of Oakley Creek Bridge,
Hendon Pedestrian Bridge and cycle and
pedestrian bridges.
AC Monthly Report Oct 2012.docx Page 3 21 November 2012
Consent Description Trigger
Stormwater outfall structures for Oakley Creek.
Diversion and relocation of existing
stormwater outfalls.
EPA 10/2.016
Excavation, drilling or tunnelling or other disturbance for
the purpose of diverting a permanent river or stream to
a new course.
Creek.
Discharge to the water table of a road (Sectors 1-9).
Diversion and discharge of stormwater from
impermeable areas into the water table of a road.
Discharges from the sealed carriageway.
EPA10/2.018
Discharge to the water table of a road (Sectors 1-9).
Diversion and discharge of stormwater into any
watercourse for the purpose of draining roads.
EPA 10/2.019
(ARC 38324)
Stormwater discharge – Network Operator activities
within urban areas (Sectors 1, 3, 5, 6, 7, 9). Stormwater
discharge onto land or water.
Discharges to the permanent stormwater
system.
dust emission)
construction.
9).
a floodplain and associated diversion and
deposition of material in Sector 9.
EPA 10/2.021
contaminated land (that is undergoing. disturbance or
remediation) (Sectors 1, 3, 5, 6, 7, 8 and 9).
Land disturbance activities within areas
potentially containing contaminated
Consent Description Trigger
accessway, associated earthworks and tree
removal, and works within the dripline of
protected trees.
Auckland City District Plan.
Landuse consent for earthworks. Earthworks for carpark and playing field
outside the designation requiring resource
consents in accordance with Auckland City
District Plan.
Alan Wood Reserve.
located outside the designation requiring
resource consents in accordance with
Auckland City District Plan.
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 4 21 November 2012
Consent Description Trigger
trees associated with the creation of pedestrian
and vehicular accesses within Barrymore Road
Reserve.
designation requiring resource consents in
accordance with Auckland City District Plan.
ARC: 40097 and 40166
disturbance for construction of a Pre-Cast
Facility.
requiring resource consents in accordance
with Manukau City District Plan.
R/LUC/2012/2168
a new Project Site Office at Stoddard Rd,
including associated earthworks and parking.
Construction of project office requiring
resource consents in accordance with
Auckland City District Plan.
Regional) for the diversion and discharge of
stormwater, the discharge of contaminants from
an industrial or trade activity, the discharge of
contaminants to air and parking and vehicular
access infringements associated with the
construction and operation of a Pre-Cast
concrete facility at 53 Ormiston Road, East
Tamaki.
Tamaki Pre-Cast Yard requiring resource
consents in accordance with Manukau City
District Plan and Auckland Regional Plan: Air,
Land and Water.
The following construction works were carried out in October;
Southern Area:
Continuing construction of Richardson Road Bridge abutments and central pier,
Continuing construction of Hendon sewer realignment,
Continuing drilling and blasting basalt to excavate the Southern Approach Trench,
Continuing Southern Approach Trench piling,
Excavate and make live Stream Realignment A,
Commence construction of Oakley Creek Bridge, and
Commence construction of the Alan Wood wetland, and
Commence earthworks between Maioro Street interchange and Richardson Road
Northern Area:
Commence demolition of houses and tree clearance on Great North Road between Oakley Ave
and Cowley Street
Commence demolition of houses and tree clearance at Open Space 10 (corner of Waterbank
Crescent and Herdman Street); and
Construct noise walls between Northern Approach Trench and Waterview School
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 5 21 November 2012
4. Site Meetings and Inspections
Auckland Council’s Erosion and Sediment Control officer visited the Southern and Northern Area works
on the 5th, 11th, 18th and 26th of October.
5. Environmental Monitoring
5.1. Tree Management
Grant Sirl, Arborist – Arbor Advice Ltd (the Project Arborist) has provided the following report for the
amenity trees affected by the works;
Amenity Tree
South
522 Zelkova Within compound area adjacent north side of Richardson Rd
Good Good Protective fencing in place to exclude remaining grassed rootzone area from adjacent road and work site area. Exclusion zone free of materials. Weed/grass control measures may need to be implemented in due course.
698 Various native species (group)
Alan Wood Reserve, access via Methuen Rd
Good/ fair
Sound barrier wall appropriate protection
Remaining trees of group 698 appear in reasonably good condition/health following completion of sound barrier wall construction. Area “opened up” following tree removals being infested with weed establishment (i.e. Privet, Knightshade etc). Some form of weed control measure may need to be implemented in due course. Note: A multitude of self- sown native seedlings of various species starting to establish.
512, 513 to
516 and 519
Titoki, Prunus, Totara, Tarata, Karaka & Cabbage
Near western end of Alan Wood Reserve adjacent basketball court. (outside designation).
Good/fair Totaras nearest
drainage excavation alignment
Southern side protective fencing erected/sturdy and in good condition. Fencing excludes the vegetation from immediate work site area.
Protective fencing around northern Totara resurrected and excludes tree from work site. Proposed to undertake remedial work on southern Totara tree upon completion of drainage works (small failed branch). Recommend mulch rootplate areas of the 2 Totara trees and fence around all remaining trees/vegetation within Park area from immediate construction.
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 6 21 November 2012
North
N/A Pohutukawa Waterview Primary School
Good Sound barrier wall erected eastern side of tree. (Tree within School grounds outside designation)
Minor remedial work required to eastern side crown structure that extends over alignment of south barrier wall.
Rootplate area has been mulched.
#698 & 811
Titokis Herdman Street – Street trees
Good/Fair Trees within designation area to be preserved where possible. Trees excluded from construction zone by sound wall to the north
Within existing grass berm area. Fence off individual trees if deemed necessary to preserve grass berm area and rootplate zone respectively.
5.2. Noise and Vibration Monitoring
Noise monitoring has been undertaken for new plant and activities since the start of construction works
in January 2012 to assess levels against noise predictions (As provided in the Construction Noise and
Vibration Management Plan) and to confirm compliance with the project noise criteria. Compliance has
been measured against Consent conditions CNV.2 for noise, CNV.3 for noise from air blast and CNV.4 and
CNV.5 for vibration.
The focus for noise and vibration during October has been:
Monitoring of noise and vibration for drill and blast in Southern approach trench and for
construction of Alan Wood Reserve stormwater pond.
Monitoring of noise where rock breaking for the sewer alignment (Southern area) in close
proximity to the residential properties.
Monitoring of site establishment works in northern area.
The table below shows the maximum measured noise levels for activities undertaken in October at noise
receivers. There were no measured exceedences of project noise criteria set out in CNV.2 measured at
relevant noise receivers.
Noise level LAMax (dB)
75 Hendon Avenue (1m from rear façade)
2 excavators operating behind 75/77 Hendon Avenue noise wall, two rock breakers near SAP11, piling/rock breaking/drilling in main trench
61.7 79.5
70 85
Northern area
AC Monthly Report Oct 2012.docx Page 7 21 November 2012
Date/time Location Activity Noise level LAeq (dB)
Noise level LAMax (dB)
Demolition of Kindergarten and vegetation clearance. Plant included: excavator, chainsaw, chipper. During school holiday and prior to noise wall construction.
46.7
64.9
During school holiday.
59.3
During school holiday.
58.2
Internal measurement (windows closed) Class 1 Waterview School Crusher and excavator operating behind
4m noise wall.
60.5
Project noise criteria (Apply to internal levels at school during teaching hours)
45
Table showing Measured Noise Levels
Vibration and noise monitoring for the Southern area blasts was undertaken by Styles Group. A report of
their findings during October is appended. The results showed compliance with project vibration limits set
out in CNV4 and CNV.5 and CNV3 for noise from air blast.
Three Site Specific Noise Management Plans (SSNMP) were submitted to Auckland Council and approved in
October. These were SSNMP#8, in relation to construction of temporary stormwater and sewer line under
Richardson Road, SSNMP#9, in relation to stream realignment ‘A’ tie ins and SSNMP#10, in relation to
installation of Super-T Beams for Richardson Road Bridge . These works have been completed.
In relation to noise mitigation, to date, temporary noise walls have been installed along the site boundary
at:
17-33 Whittle Place
21-33 Valonia Street
231 Richardson Road
194a-166 Methuen Road
57 -91 and 129 Hendon Avenue (Extended from 3m to 4m from 77-87 Hendon Avenue)
194-204 Methuen Road
Earth bund barriers have been installed along the boundary of 107 Hendon Avenue to 115 Hendon Avenue
to provide mitigation with the removal of these houses in September. A 3m plywood noise wall was
installed in October from 115 to 123 Hendon Avenue to complete the noise barrier along this section of
Hendon Avenue following the removal of houses.
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 8 21 November 2012
The table below shows the over pressure and maximum vibration levels recorded for each blast
undertaken in October. The monitoring was carried out at the nearest dwelling and also the nearest
occupied dwelling (closest receiver). There were two measured exceedences of the peak sound pressure
level set out in CNV.3 measured at the closest receiver (on the 23rd and 29th of October. Maximum
recorded was 124dB). There were also two measured exceedences of the peak particle velocity set out in
CNV.5 measured at the closest receiver (on the 11th and 24th of October. Maximum recorded was
11.4mm/sec).
Lzpeak -2.5dB
Residents relocated for blast?
96 01.10.12 14:03 SAT4&5 35 holes. 1x4.5kg per hole. 3rd layer.
81 Hendon 116dB 2.10 @ 12.5Hz in
88 Methuen 106dB in
97 02.10.12 10:13 SAT4&5 22 holes. 1x4.5kg per hole. 3rd layer.
81 Hendon 114dB 2.66 @ 23Hz in
88 Methuen 114dB 2.30 @ 7.4Hz in
98 02.10.12 14:10 SAT1&2 10 holes. 1x3kg per hole. 2nd layer.
101 Hendon 110dB 2.65 @ 29Hz in
105 Hendon 116dB 4.02 @ 28Hz out
99 03.10.12 10:13 SAT4&5 23 holes. 1x4.5kg per hole. 3rd layer.
81 Hendon 116dB 2.07 @ 29Hz in
88 Methuen 110dB 2.29 @ 8.1Hz in
100 03.10.12 14:04 SAT4&5 20 holes. 1x3.75kg per hole. 3rd layer.
81 Hendon 113dB 2.59 @ 33Hz in
88 Methuen 111dB 1.32 @ 9.4Hz in
101 04.10.12 10:08 SAT4&5 24 holes. 1x2.25kg per hole. 3rd layer.
81 Hendon 116dB 2.24 @34Hz in
88 Methuen 110dB 3.77 @ 10.8Hz in
102 04.10.12 14:11 SAT1&2 18 holes. 1x3kg per hole. 1st layer.
101 Hendon 112dB 3.39 @ 38Hz in
105 Hendon 116dB 3.46 @ 25Hz out
116A Methuen 108dB 1.02 @ 57Hz out
103 05.10.12 10:05 SAT1&2 15 holes. 1x2.25kg per hole. 1st layer.
105 Hendon 114dB 3.19 @ 25Hz in
116A Methuen 112dB 1.98 @ 28Hz out
104 05.10.12 14:07 SAT1&2 20 holes. 1x3kg per hole. 1st layer.
101 Hendon 109dB 4.44 @ 43Hz in
105 Hendon 118dB 6.73 @ 28Hz out
116A Methuen 109dB 1.70 @ 33Hz out
105 08.10.12 14:19 SAT1&2 15 holes. 1x3kg per hole. 1st layer.
105 Hendon 115dB 4.71 @ 51Hz in
116A Methuen 111dB 2.94 @ 35Hz out
106 08.10.12 14:25 AWW 12 holes. 1x2.25kg per hole. 1st layer.
105 Hendon 100dB 1.06 @ 33Hz in
116A Methuen 113dB 4.49 @ 24Hz out
107 09.10.12 10:11 SAT1&2 24 holes. 1x3.75kg pe hole. 1st layer.
105 Hendon 115dB 8.73 @ 23Hz in
116A Methuen 114dB 2.97 @ 28Hz out
108 09.10.12 14:13 SAT1&2 19 holes. 1x3.75kg per hole. 1st layer.
101 Hendon 108dB 2.21 @ 20Hz in
116A Methuen out
109 10.10.12 14:14 SAT1&2 20 holes. 1x3.75kg per hole. 1st layer.
105 Hendon 110dB n/a in
116A Methuen out
110 10.10.12 14:10 AWW 6 holes. 1x3.75kg per hole. 1st layer.
105 Hendon 110dB 1.74 @ 31Hz in
116A Methuen 116dB out
111 11.10.12 14:11 SAT1&2 28 holes. 1x3.75kg per hole. 1st layer.
101 Hendon 112dB 11.0 @ 43Hz in
105 Hendon 120dB 7.87 @ 30Hz out
116A Methuen 111dB 4.99 @ 27Hz out
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 9 21 November 2012
112 12.10.12 14:01 SAT1&2 22 holes. 1x3.75kg per hole. 1st layer.
101 Hendon 111dB 6.6 @ 47Hz in
105 Hendon 119dB 7.2 @ 28Hz out
116A Methuen 116dB 2.48 @ 28Hz out
113 12.10.12 14:06 AWW 7 holes. 1x3kg per hole. 1st layer.
105 Hendon 110dB less than 1.0 in
116A Methuen 120dB 2.57 @ 30Hz out
114 15.10.12 14:12 SAT1&2 26 holes. 1x3.75kg per hole. 1st layer.
105 Hendon 119dB 11.7 @ 41Hz out
116A Methuen 112dB 4.06 @ 30Hz out
115 15.10.12 14:24 AWW 6 holes. 1x2.25kg per hole. 1st layer.
105 Hendon 105dB less than 1.0 in
116A Methuen 116dB 1.14 @ 19Hz out
116 16.10.12 14:10 SAT1&2 27 holes. 1x3.75kg per hole. 1st layer.
101 Hendon 109dB 6.01 @ 33Hz out
105 Hendon 115dB 14.6 @ 26Hz out
116A Methuen 116dB 3.56 @ 28Hz out
117 17.10.12 10:11 AWW 11 holes. 1x0.75kg per hole. 1st layer.
105 Hendon 100dB less than 1.0 in
116A Methuen 114dB less than 1.0 in
118 17.10.12 14:15 SAT4&5 8 holes. 1x2.25kg per hole. 3rd layer.
105 Hendon 106dB less than 1.0 in
116A Methuen 97dB less than 1.0 in
119 17.10.12 14:33 AWW 11 holes. 1x1.5kg per hole. 1st layer.
105 Hendon 109dB less than 1.0 in
116A Methuen 116dB 2.24 @ 19.3Hz in
120 18.10.12 14:15 SAT4&5 9 holes. 1x2.25kg per hole. 2nd layer.
81 Hendon 113dB 1.78 @ 9.8Hz in
88 Methuen 105dB less than 1.0 in
105 Hendon 109dB less than 1.0 in
121 18.10.12 14:36 SAT1&2 29 holes. 1x3.75kg per hole. 1st layer.
81 Hendon 95dB less than 1.0 in
105 Hendon 119dB 8.73 @ 60Hz out
116A Methuen 114dB 2.79 @ 28Hz in
122 19.10.12 14:17 SAT4&5 15 holes. 1x2.25kg per hole. 2nd layer.
81 Hendon 1.13 @ 68Hz in
88 Methuen 107dB 1.14 @ 20Hz in
105 Hendon in
123 19.10.12 14:39 AWW 17 holes. 1x1.5kg per hole. 1st layer.
81 Hendon in
105 Hendon in
24 holes. 1x3.75kg per hole. 1st layer.
105 Hendon 122dB 7.91 @ 33Hz in
116A Methuen 116dB 3.05 @ 31Hz in
125 23.10.12 14:18 SAT4&5 SAT092
16 holes. 1x3kg per hole. 2nd layer.
81 Hendon 111dB 1.15 @ 28Hz in
88 Methuen 1.63 @ 10Hz in
126 24.10.12 10:12 SAT093 SAT4&5
16 holes. 1x3kg per hole. 2nd layer.
81 Hendon 117dB less than 1.0 in
88 Methuen 1.27 @ 11Hz in
105 Hendon 104dB less than 1.0 in
127 24.10.12 10:31 AWP009 AWW
20 holes. 1x1.5kg per hole. 1st layer.
81 Hendon 92dB less than 1.0 in
105 Hendon 106dB less than 1.0 in
116A Methuen 2.03 @ 39Hz in
128 24.10.12 14:25 SAT094 SAT4&5
16 holes. 1x3kg per hole. 2nd layer.
81 Hendon 117dB less than 1.0 in
88 Methuen 1.27 @ 10Hz in
105 Hendon in
21 holes. 1x3kg per hole. 1st layer.
81 Hendon 92dB less than 1.0 in
105 Hendon 117dB 11.4 @ 26Hz in
116A Methuen 2.29 @ 51Hz in
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 10 21 November 2012
130 25.10.12 10:12 SAT095 SAT4&5
30 holes. 1x3kg per hole. 2nd layer.
89 Hendon 118dB less than 1.0 in
88 Methuen 110dB 1.53 @ 10Hz in
131 25.10.12 14:18 SAT(2)022 SAT1&2
? holes 1x3kg per hole. 1st layer.
101 Hendon 111dB 9.33 @ 37Hz out
105 Hendon 118dB 8.76 @ 43Hz out
116A Methuen 2.54 @ 27Hz in
132 26.10.12 10:18 SAT096 SAT4&5
32 holes. 1x3.75kg per hole. 2nd layer.
89 Hendon 114dB less than 1.0 in
88 Methuen 109dB 3.54 @ 8.2Hz in
133 26.10.12 14:26 AWP011 AWW
20 Holes. 1x1.5kg per hole. 3rd layer.
105 Hendon 118dB 1.79 @ 23Hz in
116A Methuen 117dB less than 1.0 out
134 26.10.12 14:23 SAT(2)023 SAT1&2
20 holes. 1x2.25kg per hole. 1st layer.
105 Hendon 116dB 3.46 @ 28Hz in
116A Methuen 106dB 1.34 @ 24Hz in
135 29.10.12 10:27 AWP012 AWW
20 holes. 1x1.5kg per hole. 2nd layer.
105 Hendon 108dB less than 1.0 in
116A Methuen 111dB 2.46 @ 26Hz in
136 29.10.12 14:47 SAT097 SAT4&5
40 holes. 1x3.75kg per hole. 2nd layer.
89 Hendon 125dB less than 1.0 out
88 Methuen 124dB 1.51 @ 8.6Hz in
137 30.10.12 10:07 SAT(2)024 SAT1&2
25 holes. 1x3.75kg per hole. 1st layer.
105 Hendon 118dB 2.63 @ 28Hz in
116A Methuen 109dB 3.69 @ 25Hz in
138 30.10.12 14:17 SAT(2)025 SAT1&2
32 holes. 1x3.75kg per hole. 1st layer.
105 Hendon 121dB 6.39 @ 51Hz out
116A Methuen 111dB 1.54 @ 21Hz in
139 31.10.12 14:13 SAT098 SAT4&5
32 holes. 1x3kg per hole. 2nd layer.
89 Hendon 113dB less than 1.0 in
88 Methuen 110dB 1.03 @ 7.8Hz in
116A Methuen less than 1.0 in
Closest occupied house
5.3. Air Quality Monitoring
Two Total Suspended Particulate (TSP) analysers and one met mast are required in the Southern Area
(Sector 9) under consent conditions AQ16 and AQ17. One TSP analyser with met mast is required in the
Northern Portal Area (sector 7) with the start of construction in October 2012.
Two E-BAM TSP monitors are currently co-located at a site in Hendon Park considered representative of
relevant exposure to the Southern area main works. The co-location of the E-BAMs has enabled
assessment of the performance of the monitors. A correlation of 0.8 has been achieved. A second site has
been set up in Alan Wood Reserve at the rear of residential properties along Hendon Avenue, as agreed
with Auckland Council. This will allow greater coverage across the Southern Area Main Works
construction activities. There are currently sewer alignment works in the area of Alan Wood Reserve
where one of the the E-BAMs will be moved to, so this will remain at Hendon Park until the sewer works
have been completed there.
The power to the Hendon Park E-BAMs was lost on 18th September 2012 with the demolition of the
adjacent housing on Hednon Avenue to enable the Watercare sewer diversion to be constructed. Power
was reinstalled on 23rd November 2012. Auckland Council have continued to be updated with progress
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 11 21 November 2012
with this and additional visual checks on dust have been made during this down time in the absence of
real time monitoring results.
The Northern area E-BAM was installed at Waterview School on the 9th October 2012. This provided data
until the 23rd October 2012 when the Waterview School Board requested it be closed down. A new site
will be installed outside the School grounds and is awaiting installation of a power line by suppliers
Vector.
E-BAM results for October are available for the Waterview School site and show levels below the project
consent limit and short-term trigger levels for TSP with the exception of the following episode.
11/10/12 13-14pm and 3-4 pm– EBAM3 showed levels of >200µg/m3 (Maximum 527 µg/m3) for
2 hours. This was during school holidays during early site clearance works and prior to
installation of the noise wall at Waterview School. No further exceedences were recorded that
day.
Maximum Hourly Average TSP
Maximum Daily Average TSP(Consent condition AQ.20 Trigger for investigation)
68 80
*Station operational 9th – 23rd Oct, therefore data capture reduced at this location.
Table showing TSP Monitoring Results
5.4. Ground Water Monitoring
Monthly monitoring for piezometers identified in Appendix A of the Groundwater Management Plan
(GWMP) is ongoing, with the exception of around 22 piezometers around the tunnel which are still to be
installed (as per the rev 4 GWMP).
Piezometers located within 150 m of the Southern Approach trench have been monitored weekly since
June (Appendix B), in advance of excavation above the water table that commenced in July. Dewatering
activities commenced in September when groundwater was encountered in the excavation (at a depth of
approximately 9 m below ground level). Accordingly more intensive monitoring of groundwater levels
around the Southern Approach Trench (twice-weekly in accordance with condition G.6) has commenced.
Piezometers in close proximity to the trench (i.e. less than 30 m distance) have recorded a drop in
groundwater level of between 2 m and 4 m, with some wells showing a slight recovery during the month
of October due to reduced dewatering in some areas. Wells that are very close to the trench (i.e. BHA4,
BHB1 and BHB4) show the effects of pumping from the low point sump, with short term peak drawdowns
of up to 5.5 m in the alluvium, 7 m in the East Coast Bays Formation rock, and up to 6 m in the basalt.
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 12 21 November 2012
At a distance of 30 m to 120 m groundwater levels have lowered by up to 2 m; beyond a distance of 120
m there is negligible drawdown. Groundwater levels for all piezometers remain above proposed trigger
levels (Figure 1).
Figure 1: Drawdown vs Distance Graph for SAT
Continuous pre-construction monitoring of Oakley Creek base flow is ongoing with data reviewed
monthly; to date, all recorded flows remaining within the expected seasonal range. Dewatering activites
will trigger 3-monthly reporting, and review of flow data by a hydrologist and freshwater ecologist in
accordance with condition G.12 in December.
5.5. Settlement Monitoring
Monthly monitoring of framework ground settlement markers identified in the Settlement Effects
Management Plan (SEMP) continues.
Framework markers within 150 m of the Southern Approach Trench have been being monitored weekly
since June (Appendix B). Recorded vertical movements are within the pre-construction seasonal range
and in many cases within the accuaracy of the survey (+/- 3 mm).
Surveyed levels for all markers are above proposed trigger levels.
5.6. Ecological and Water Quality Monitoring Oakley Creek
Construction phase water quality monitoring has been carried out monthly, as required by consent
conditions. Results for January to October 2012 are summarised in Figures 1 to 6 below. Full laboratory
reports are available on request.
Concentrations of all contaminants were consistent with those measured earlier in the construction
phase, and comparable to pre-construction baseline levels.
0
1
2
3
4
5
6
7
8
9
10
alert trigger level (basalt)
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 13 21 November 2012
0
5
10
15
20
25
30
35
WR1
WR2
WR3
WR4
WR5
Figure 1: Turbidity results from sites Figure 2: pH results from sites WR1-WR5 on WR1-WR5 on Oakley Creek. Oakley Creek.
0
5
10
15
20
25
30
35
WR1
WR2
WR3
WR4
WR5
Figure 3: Total Suspended Solids results from Figure 4: Total Copper results from sites sites WR1-WR5 on Oakley Creek. sites WR1-WR5 on Oakley Creek.
0
0.001
0.002
0.003
0.004
0.005
0.006
WR1
WR2
WR3
WR4
WR5
Figure 5: Total Lead results from sites Figure 6: Total Zinc results from sites WR1-WR5 on Oakley Creek. WR1-WR5 on Oakley Creek.
To respond to this, event-based water quality and/or ecological (macroinvertebrate) monitoring was
carried out at several sites on Oakley Creek (E1, E2, WR3, O4, O5, O6) on 26, 27, 29 and 31 October. The
results of this monitoring have been separately reported to Auckland Council. In summary, there is no
evidence of long-term adverse effects on water quality or macroinvertebrate communities.
Fieldwork for the second 6-monthly round of monitoring (prior to the commencement of the 2012-2013
earthworks season) was carried out in late September, and the report is currently being finalised.
Auckland Council, iwi and MFish/MPI have been notified of the Alliance’s intention to relocate fish from
the section of Oakley Creek/Te Auaunga which will be affected by the Diversion A works. This relocation
work is nearing completion (final relocation expected to happen in the week commencing 26 November).
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 14 21 November 2012
The final numbers/species relocated at Diversion A will be advised to stakeholders in due course, as
required by the MFish/MPI permits to capture and transfer.
Fortnightly monitoring of significant vegetation, including geraniums, continues to be carried out. All
translocation of geranium plants from areas that will be affected by the works has been completed. This
has included successful transplanting into the Diversion C area.
At least one pair of NZ dotterel have been found nesting on the traffic island at the Great North Road
interchange. That area of the site has been cordoned off and drillers who have been conducting
geotechnical investigations at the site have been advised to stay out of the area.
We have been advised by Friends of Oakley Creek that an arson event on 19 November caused a fire in
the Lizard Relocation Site (adjacent to Oakley Creek, behind Unitec). Approximately 25-30% of the recent
plantings have been lost, although the fire was outside the main area where logs had been placed to
provide additional lizard refugia. We are investigating whether any of the predator bait stations have
been destroyed, and what remedial action might feasibly be undertaken by Friends of Oakley Creek or the
Well-Connected Alliance.
5.7. Contaminated Soil Monitoring
Earthworks in October 2012 requiring off-site disposal of soil comprised those from the following
locations:
Watercare /Hendon sewer;
Southern Approach Trench;
Northen Portal Approach Trench.
Table 5.1 below provides a summary of the volume of spoil disposed from the Southern Area works since
the previous monitoring report. About 49,202 tonnes of soil, 38,000 tonnes of basalt rock and 3,252.68
tonnes of refuse were removed from site. They were removed to Three Kings Managed Fill site,
Greenmount Managed Fill site, Wiri Cleanfill and Redvale Landfill.
The topsoil containing slightly elevated BAPeq soil from the Valonia Wetlands works is now proposed to
be reused on site. Contaminant concentrations of the topsoil stockpiled on the site (refer Valonia 1,
Valonia 2, Stockpile 2 S1 and Stockpile 2 S2 samples in laboratory reports in Appendix A) are below
human health criteria for recreational land use and Auckland Regional Plan: Air Land and Water
permitted activity criteria. The results show that reuse is appropriate. The base of the excavation of the
slightly elevated BAPeq soil has also been validated. The validation testing (refer samples HS1 and HS2 in
the laboratory report in Appendix A) show metal and hydrocarbon concentrations within published
background concentration range for the Auckland Region.
Table 5.2 provides a summary of the volume of spoil disposed from the Northern Portal Area works which
commenced on 1 October 2012. About 520 tonnes of clay soil have been removed to Three Kings
Managed Fill site from the vicinity of the northern portal area following demolition of the houses along
Great North Road and works relating to the Waterview Reserve open space area at the corner of
Waterbank Crescent and Herdman Street.
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 15 21 November 2012
Date
Puketutu Managed Fill Site Three Kings Managed Fill Site Greenmount Managed Fill Site Wiri Disposal Site (Rock) Wiri Disposal Site (Cleanfill) Redvale Disposal Site
Volume Cummulative total Volume Cummulative total Volume** Cummulative total Volume Cummulative total Volume Cummulative total Volume Cummulative
total
Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 *
1-Oct-12 0 167212.93 98361 1232.36 1232.36 725 0 0 684.04 61942.68 36437 0 348 205 0 875.89 515
2-Oct-12 0 167212.93 98361 251.1 1483.46 873 0 0 1744.1 63686.78 37463 0 348 205 0 875.89 515
3-Oct-12 0 167212.93 98361 1468.48 2951.94 1736 0 0 2100.82 65787.6 38699 0 348 205 0 875.89 515
4-Oct-12 0 167212.93 98361 1661.58 4613.52 2714 0 0 2313.9 68101.5 40060 0 348 205 0 875.89 515
5-Oct-12 0 167212.93 98361 558.38 2041.84 1201 0 0 2184.44 70285.94 41345 0 348 205 0 875.89 515
6-Oct-12 0 167212.93 98361 595.64 3547.58 2087 0 0 1014.73 69116.23 40657 0 348 205 0 875.89 515
8-Oct-12 0 167212.93 98361 880.62 4428.2 2605 1486.48 1486.48 874 1465.32 70581.55 41519 0 348 205 0 875.89 515
9-Oct-12 0 167212.93 98361 1167.98 5596.18 3292 1330.64 2817.12 1657 1700.08 72281.63 42519 0 348 205 0 875.89 515
10-Oct-12 0 167212.93 98361 1262.84 6859.02 4035 736.36 3553.48 2090 1458.86 73740.49 43377 0 348 205 0 875.89 515
11-Oct-12 0 167212.93 98361 637.16 7496.18 4410 3553.48 2090 3170.84 76911.33 45242 0 348 205 0 875.89 515
12-Oct-12 0 167212.93 98361 1057.29 8553.47 5031 3553.48 2090 1368.85 78280.18 46047 1490.74 1838.74 1082 0 875.89 515
13-Oct-12 0 167212.93 98361 520.98 9074.45 5338 3553.48 2090 757.18 79037.36 46493 511.16 2349.9 1382 0 875.89 515
15-Oct-12 0 167212.93 98361 1236.52 10310.97 6065 3553.48 2090 2168.48 81205.84 47768 1809.19 4159.09 2447 0 875.89 515
16-Oct-12 0 167212.93 98361 1629.62 11940.59 7024 3553.48 2090 1318.43 82524.27 48544 1626.3 5785.39 3403 0 875.89 515
17-Oct-12 0 167212.93 98361 1476.7 13417.29 7893 3553.48 2090 1335.92 83860.19 49330 1673.66 7459.05 4388 0 875.89 515
18-Oct-12 0 167212.93 98361 743.26 14160.55 8330 3553.48 2090 1648.28 85508.47 50299 1343.08 8802.13 5178 0 875.89 515
19-Oct-12 0 167212.93 98361 1096.66 15257.21 8975 3553.48 2090 847.26 86355.73 50797 798.26 9600.39 5647 0 875.89 515
23-Oct-12 0 167212.93 98361 805.82 16063.03 9449 3553.48 2090 709.53 87065.26 51215 1418.2 11018.59 6482 0 875.89 515
24-Oct-12 0 167212.93 98361 837.68 16900.71 9942 3553.48 2090 642.6 87707.86 51593 1299.42 12318.01 7246 0 875.89 515
25-Oct-12 0 167212.93 98361 1091.06 17991.77 10583 3553.48 2090 977.08 88684.94 52168 1293.46 13611.47 8007 0 875.89 515
26-Oct-12 0 167212.93 98361 1010.3 19002.07 11178 3553.48 2090 2055.54 90740.48 53377 1789.86 15401.33 9060 0 875.89 515
27-Oct-12 0 167212.93 98361 984.72 19986.79 11757 3553.48 2090 1064.08 91804.56 54003 1279.68 16681.01 9812 0 875.89 515
29-Oct-12 0 167212.93 98361 815.36 20802.15 12237 3553.48 2090 1581.74 93386.3 54933 1371.69 18052.7 10619 0 875.89 515
30-Oct-12 0 167212.93 98361 1367.12 22169.27 13041 3553.48 2090 1784.02 95170.32 55983 1390.34 19443.04 11437 0 875.89 515
31-Oct-12 0 167212.93 98361 699.02 22868.29 13452 3553.48 2090 1890.76 97061.08 57095 1465.28 20908.32 12299 0 875.89 515
** Data incomplete
Table 5.1: Disposal location and quantity of soil disposed off site from the south
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 16 21 November 2012
Date
Puketutu Managed Fill Site Three Kings Managed Fill Site Greenmount Managed Fill
Site Wiri Disposal Site
(Cleanfill) Redvale Disposal Site
total Volume Cummulative
total Volume Cummulative
total Volume Cummulative
total
Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 * Tonnes tonnes m3 *
12-Oct-12 0 0 0 19.18 19.18 11 0 0 0 0 0 0 0 0 0
15-Oct-12 0 0 0 57.76 76.94 45 0 0 0 0 0 0 0 0 0
16-Oct-12 0 0 0 43.1 120.04 71 0 0 0 0 0 0 0 0 0
23-Oct-12 0 0 0 75.86 195.9 115 0 0 0 0 0 0 0 0 0
24-Oct-12 0 0 0 47.12 243.02 143 0 0 0 0 0 0 0 0 0
25-Oct-12 0 0 0 87.68 330.7 195 0 0 0 0 0 0 0 0 0
26-Oct-12 0 0 0 25.24 355.94 209 0 0 0 0 0 0 0 0 0
30-Oct-12 0 0 0 8.98 364.92 215 0 0 0 0 0 0 0 0 0
31-Oct-12 0 0 0 152.62 517.54 304 0 0 0 0 0 0 0 0 0
Table 5.2: Disposal location and quantity of soil disposed off site from the north
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 17 21 November 2012
Work planned for November 2012 is as follows:
South
Excavate clay from the Southern Approach Trench for disposal to Three Kings Managed Fill.
Remove basalt from the Southern Approach Trench excavation to Wiri Cleanfill and/or
stockpiled and re-used on site.
Retain any topsoil from the remaining Watercare/Hendon sewer realignment works for reuse
on site.
Extract basalt rock from the Watercare/Hendon sewer realignment and works for disposal to
Wiri Cleanfill.
Excavate topsoil and clay between Maioro Interchange and Richardson Road for motorway
alignment and retaining wall construction and reuse where possible or dispose to Three Kings,
Greenmount or Wiri Cleanfill.
North
Strip topsoil around the Waterview Reserve to construct Construction Yard 6.
Strip topsoil after demolition of houses north of Cowley Street and retain for re-use, if possible,
or remove to appropriate landfill. Soil sampling in this area has been carried out and will be
reported in the next monthly report.
Excavate the Northen Portal Approach Trench for disposal to either Three Kings Managed Fill or
Wiri Cleanfill.
5.8. Erosion and Sediment Control Monitoring
The following ESC devices approved under specific CESCP were certified and as-built submitted to council:
CESCP No. 11, 16, 20 2nd October 2012
CESCP No. 101 3rd October 2012
CESCP No. 18 4th October 2012
CESCP No. 101 5th October 2012
CESCP No. 20 15th October 2012
CESCP No. 18, 101 16th October 2012
CESCP No. 11, 17, 101 24th October 2012
CESCP No. 101 26th October 2012
CESCP No. 17 29th October 2012
CESCP submitted to council were:
CESCP no. 19, Rev1 – Valonia 2nd Sports Field submitted 4th October, approved 8th October 2012
CESCP no. 21, Rev1 – Oakley Creek Bridge Stream Diversion, submitted 5th October, approved 12th
October 2012
CESCP no. 24, Rev 0 – Topsoil Stockpile – 45 Hendon Avenue, submitted 19th October, approved
30th October 2012
AC Monthly Report Oct 2012.docx Page 18 21 November 2012
Pumping was undertaken in October to dewater the excavations and other ponding areas. Pumped water
was directed into the forebay of the silt retention pond, or impoundment area. The pH and clarity data
was collated (refer to table below for data collected). Data was collated prior to the lowering of pond
decants to discharge out to receiving environment.
Pond 1 – Richardson Road Access Area
Regular site visits have been made during October by a member of the Erosion and Sediment Control
Team.
5.9. Archaeological monitoring
General archaeological monitoring of the works has been undertaken by the Project Arcaeologists from
Clough and Associates in accordance with consent conditions and the following NZ Historic Place Trust
Authorities:
• 2012/595 General Authority for earthworks in association with Stage 1 Southern Area Enabling
Works (Section 12 of the Historic Places Act).
• 2012/950 General Authority for earthworks in association with Stage 2 Southern Area Main
Works (Section 12 of the Historic Places Act).
No archaeological findings have been encountered to date.
6. Stakeholder Management
6.1. Stakeholders
We have made significant progress in terms of community engagement this last month, having increased
our staff numbers in this area. Dedicated stakeholder managers and support staff have been engaging
directly with the southern and northern sector communities most affected by the works. This face-to-face
communication has been reinforced by printed media including construction updates, signage, flyers and
local newspaper advertising and editorial.
The recent Community BBQ in Waterview was a massive success, and generated a positive response from
many of these community members. In the southern sector, our efforts remain focused around the
management of blasting and rock-breaking impacts on Hendon Ave residents.
Date Clarity (mm) pH 15th October 100 7
16th October 400 7
17th October 100 7
18th October 100 7
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 19 21 November 2012
6.2. Queries, Concerns and Complaints
In October there were 144 interactions with stakeholders.
Of the interactions, 29 were complaints from residents. A few of the issues stated were blasting noise;
speeding trucks on local roads; increased truck movements; resident at 71 Hendon continued to express
his displeasure of the noise adjacent to his residence; night works and GNR car movements in and out of
BP.
24 concerns were also reported including property damage potentially caused by blasting; trucks at night
queuing at the end of the street at night; pedestrian issues with the closure of the footpath; lighting along
GNR footpath and trees needing to be cut to improve visibility
An additional 14 queries were received including concerns with drainage off their property; potential
purchases of property asking if the tunnel would pass under their homes.
7. Works Proposed for November 2012
Construction works proposed to be carried out during November will likely include;
Southern Area:
Continue Hendon Sewer realignment,
Continue excavation for the Southern Approach Trench (including excavation via drilling and
blasting),
Commence excavation for Oakley Creek rehabilitation beneath Oakley Creek bridge,
Continue construction Oakley Creek Bridge
Continue construction of the Alan Wood Wetland (including excavation via drilling and blasting)
Commence construction of Valonia Field #2;
Commence bulk excavations between Richardson Road and Oakley Creek; and
Continue bulk excavations between Maioro Street interchange and Richardson Road.
Northern Area:
Continue demolition of houses and tree clearance on Great North Road between Oakley Ave
and Cowley Street
Commence demolition of houses and tree clearance on Cowley Street
Commence construction works for Open Space 10 (corner of Waterbank Crescent and Herdman
Street);
Commence excavation for Northern Approach Trench piling platform.
Appendix A
100 m
AC Monthly Report Oct 2012.docx Page 2 21 November 2012
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 3 21 November 2012
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 4 21 November 2012
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 5 21 November 2012
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 6 21 November 2012
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 7 21 November 2012
October 2012 Environmental Report
AC Monthly Report Oct 2012.docx Page 8 21 November 2012
-15.0
-10.0
-5.0
0.0
5.0
10.0
15.0
Sep 2010 Dec 2010 Mar 2011 Jun 2011 Sep 2011 Dec 2011 Mar 2012 Jun 2012 Sep 2012 Dec 2012
D e
fo rm
at io
n f
ro m
A d
o p
te d
P re
co n
st ru
ct io
n M
in im
u m
J7
L7
M6
M7
X13
X15
X16
X18
Z142
Z152
Z154
Z155
Z156
X25
X26
X26a
X27
Z27
Z28