    Work BreakdownStructure

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    2/21

    spm12 2

    What is a WBS?

    A (deliverable-oriented) hierarchicaldecomposition of the work to be executed

    by the project team to accomplish projects

    objectives and create the requireddeliverable

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    3/21

    spm12 3

    Why?

    To decompose the complexity of project workinto smaller, more manageable components.

    The lowest level is called workpackageand it

    is the point at which cost and schedule can bereliably estimated (work packages can becomposed of more elementary activities.)

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    4/21

    spm12 4

    WBS: Remarks

    Two formats Graphical tree

    Textual outline

    Uses a decimal numbering system to identify elements

    (Ex: 3.1.5) May include Development, Management, and project

    support tasks

    Shows is contained in relationships

    Does not show dependencies or durations

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    5/21

    spm12 5

    WBS Chart Example

    AccountingSystem

    ProjectManagement

    HWProcurement

    SWDevelopment

    Requirements Design Build

    DBDevelopment

    Client Web App

    Development

    Integration System Test Acceptance

    Test

    Training Deployment

    1

    1.1 1.2 1.3 1.4 1.5

    1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6

    1.3.3.1 1.3.3.2 1.3.3.3

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    6/21

    spm12 6

    WBS Outline Example

    1. Accounting System

    1.1.Project Management

    1.2.HW Procurement

    1.3.SW Development

    1.3.1.Requirements

    1.3.2.Design

    1.3.3.Build1.3.3.1.DB Development

    1.3.3.2.Client

    1.3.3.3.Web App Development

    1.3.4.Integration

    1.3.5.System Test

    1.3.6.Acceptance Test

    1.4.Training

    1.5.Deployment

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    7/21

    spm12 7

    WBS Types (1/3)

    Process WBS

    a.k.a. Activity-oriented

    Ex: Requirements, Analysis, Design, Testing

    Typically used by PM

    Product WBS

    a.k.a. Entity-oriented

    Ex: Financial engine, Interface system, DB

    Typically used by engineering manager

    Hybrid WBS: both of the above

    This is not unusual

    Ex: Life cycle phases at high level with component or feature-specificswithin phases

    Rationale: processes produce products

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    8/21

    spm12 8

    WBS Types (2/3)

    Less frequently used alternatives:

    Organizational WBS

    Research, Product Design, Engineering, Operations

    Can be useful for highly cross-functional projects

    Geographical WBS

    Can be useful with distributed teams

    NYC team, San Jose team, Off-shore team

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    9/21

    Program

    Project A Project B Project C

    System A System B

    Contract X

    Subsystem 1 Subsystem 2 Subsystem 3

    System C

    PWBS

    CWBS

    spm12

    WBS Type (3/3)

    9

    PWBS:Program

    (project) WBS, used

    to coordinate all

    projects (systems)

    CWBS:ContractWBS, basis for

    subcontracting system

    development

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    10/21

    spm12 10

    Product WBS

    SoftwareSystem

    RequirementsDocument

    ArchitectureDocument

    Front End Middleware Back End

    SQL Schema DB Data Admin Intf Site

    TemplatesWeb Pages

    DynamicPages

    StaticPages

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    11/21

    spm12 11

    Process WBS

    SystemDevelopment

    RequirementsAnalysis

    ScenariosAnalysis

    Security Req.Analysis

    SupportabilityReq. Anal.

    Analysis andDesign

    Coding Testing

    System Test AcceptanceTest

    Cycle 1 Cycle 2 Integration

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    12/21

    spm12

    WBS Rules of the Thumb

    Everything (and nothing else) is in place: The 100% rule:make sure all work items are there (product oriented WBS are

    better suited for this kind of rule)

    The ME rule (Mutually Exclusive rule):make sure there are no overlaps in the

    definition of the elements (especially workpackages)

    No need to make it balanced: all paths do not have to go to the same level

    Quality of the WBS is high (taken from ESA standards):

    Coherence:tasks within a work package should have the same goal;

    Coupling:work package dependencies should be minimised, so that

    team members can work independently;

    Continuity:production work packages should be full-time to maximise

    efficiency;

    Cost:bottom level work packages should require between one man- week and

    one man-month of effort.

    12

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    13/21

    spm12

    WBS Dictionary

    A way to further specify the entries of a WBS

    A WBS dictionary lists and defines the WBS elements.

    It is initially prepared for the PWBS by the NASA

    project manager, and is expanded in greater detail at

    lower levels by contractors as the CWBSs aredeveloped(NASA WBS Prep. Guide)

    Rules of the thumb:

    it can be done for each entry in the tree.

    follow the definition: increase the details as you move down the

    tree

    a good practice is doing it for the leaves (work-packages)

    13

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    14/21

    spm12

    WBS Dictionary Example (EU Proposals)

    14

    Work packagenumber

    1 Start date or starti g event: Month 1

    Work packagetitle

    Case Stud Re uirements and Experimentation ite Asses ment

    Activity type RTD

    Participantnumber

    1 2 3 4 5 6 7 8

    Participantshort name

    P1 P2 P3 P3 P P5 P6 P7

    Person-monthsper participant

    1 0 0 9 6 0 2 0

    Objectives

    Description ofwork

    Task 1.

    Task 2.

    ...

    Deliverables D1.1.

    D1.2.

    Milestones M1.1.

    M1.2.

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    15/21

    spm12

    WBS Construction Techniques

    Top-down(from the top to the leaves): best for well

    know projects; used frequently (top-down

    decomposition it is in the very nature of the WBS).

    Bottom-up(from the leaves to homogeneous groups):

    best with group elicitation activities (post-it on a wall) Analogy (copy & paste): effective, if the analogy

    between existing material and the new project can

    actually be drawn

    15

    The Project Management Institute Practice Standard forWork Breakdown Structures provides guidance for thegeneration, development, and application of WBS. Thepublication contains industry-specific examples.

    Tuesday, March 13, 12

    B kd S

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    16/21

    spm12 16

    Breakdown Structures

    Breakdown structures are used for various purposes

    Organizational breakdown structure

    Bill of Material

    Risk Breakdown Structure

    Resource Breakdown Structure

    do not confuse WBS with the ones above

    Tuesday, March 13, 12

    Fi l R k

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    17/21

    spm12

    Final Remarks

    Remember to get the people who will be doing the work

    involved (buy-in matters!)

    Use a text editor or tools such as Visio, DIA, MS Project

    17

    Tuesday, March 13, 12

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    18/21

    WBS Examples

    Tuesday, March 13, 12

    WBS E l (PMBOK)

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    19/21

    spm12 19

    WBS Example (PMBOK)

    Source: PMBOK

    Aircraft

    System

    Project

    ManagementTraining Data Air Vehicle

    Support

    Equipment

    System

    Engineering

    Management

    Supporting PM

    activities

    Equipment

    Training

    Facilities

    Training

    Services

    Training

    Technical

    Orders

    Engineering

    Data

    Management

    Data

    Organizational

    level SE

    Intermediate

    level SE

    Dept level SE

    Airframe

    Engine

    Communicatio

    n systems

    Navigation

    System

    Fire Control

    System

    FacilitiesTest and

    Evaluation

    Base Building

    Mainteinance

    Facility

    Mockups

    Operational

    Test

    Developmental

    Test

    Test

    Tuesday, March 13, 12

    WBS E l (PMBOK)

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    20/21

    spm12

    WBS Example (PMBOK)

    Source: PMBOK

    20

    SoftwareProduct

    Release

    ProjectManagement

    ProductRequirement

    Detail Design ConstructIntegrationand Test

    Planning

    Meetings

    Administration

    Software

    User

    Documentation

    TrainingProgram

    Material

    Software

    User

    Documentation

    TrainingProgram

    Material

    Software

    User

    Documentation

    TrainingProgram

    Material

    Software

    User

    Documentation

    TrainingProgram

    Material

    Tuesday, March 13, 12

    Some other E amples

  • 8/10/2019 WBS or Work Breakdown Structure for a project

    21/21

    spm12

    Some other Examples

    Military: MIL-STD-881A, MIL-STD-881B, MIL-

    HDBK-881 (1998)

    Civil Engineering:http://www.csinet.org/s_csi/docs/

    15700/15694.pdf

    21