week 3. electrical code 1. all electrical outlets run off a pigtail from main line 2. each circuit...
TRANSCRIPT
![Page 1: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/1.jpg)
Week 3
![Page 2: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/2.jpg)
Electrical
• Code
• 1. all electrical outlets run off a pigtail from main line
• 2. Each Circuit is wired directly into circuit panel - no junction boxes
• 3. Bathrooms must have GFCI either at panel or first outlet must be GFCI
![Page 3: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/3.jpg)
• 4. In rooms must have outlet
• a) on any wall longer than 2’
• b) no more than 6’ from any door
• c) no more than 12 feet apart along wall
• d) less than 18” off floor
![Page 4: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/4.jpg)
• 5. Kitchen
• a) Refridgerator on own circuit
• b) at least two circuits for outlets
• c) must have outlet on island if more than 6 sq ft
• d) outlets within 6 feet of sink must be GFCI
• e) all countertops must have a wall outlet
![Page 5: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/5.jpg)
• 6. Must have at least 1 outside outlet - GFCI
• 7. Don’t forget furnace
• 8. Fire detectors must be hard wired into a circuit with lights
![Page 6: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/6.jpg)
• 9. Separate circuits for: Clothes Dryer, Electric Range, Electric Ovens, Electric Hot Water Heater, Gas Range, Electric baseboard heaters
• 10. Must fill all holes between floors with a fire stop caulk
• Know local code - does all wiring have to be in conduits?
![Page 7: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/7.jpg)
Plumbing
• 1. All drain pipes must be vented
• 2. Sewer pipe must be PVC Schedule 40 or better - can use cast iron pipe
• 3. All sewer pipe joints must be welded
• 4. Minimum 3” pipe for toilets and main runs
![Page 8: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/8.jpg)
• 5. Minimum 1-1/4” pipe for sink drains
• 6. 1/2” pipe minimum for water pipes type L copper
• 7. 3/4” copper pipe for baseboard heat
![Page 9: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/9.jpg)
• 8. Gas is piped through Black Iron pipe and fittings or rolled copper tube
• 9. boilers and hot water heaters must have a pressure relief valve and piping to floor
• 10. Rough in plumbing includes setting tubs and showers - need to insulate outside walls before they are installed
![Page 10: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/10.jpg)
Large Projects
• Estimated differently than other projects– Many involve several separate construction
projects– May be large area
• Roadway• Super Walmart• Large housing development
– Have to look at project to do estimate correctly
![Page 11: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/11.jpg)
• May break project into quadrants or sections to facilitate scheduling (allows faster completion)– Need to estimate each section to get correct
quantities– Won’t be the same quantities as if doing 1
estimate
![Page 12: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/12.jpg)
Contingencies
• What is it?– Risk factor– Allows contractor to factor in the unknown– The less that is known about project – higher
the contingency– Design –Build has a high contingency at start
of project • decreases as project is built
![Page 13: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/13.jpg)
• Why do you want to minimize it?– Part of bid– Drives up final price– Need a good estimate– Contingency never equals zero
• Always something that is not known– Price fluctuation– Weather– Labor
![Page 14: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/14.jpg)
Mobilization
• How much does a piece of equipment cost– Need to include getting it to/from site– Need a truck to haul each way– Each time equipment is brought on site cost
money– Want to minimize – how– What is cost?
• Truck, driver, setup, inspection• May need equipment to set up
![Page 15: Week 3. Electrical Code 1. all electrical outlets run off a pigtail from main line 2. Each Circuit is wired directly into circuit panel - no junction](https://reader036.vdocument.in/reader036/viewer/2022082818/56649e805503460f94b84418/html5/thumbnails/15.jpg)
Unit price bid
• We have been talking about a lump sum estimate
• Unit Price estimate gives price per unit to do work– Multiply units by price to get cost– Still need a good estimate to find errors – Includes all costs associated with item
• Mob/Demob, material cost, labor cost