Project ManagementProject Management9. Performance Management9. Performance Management

Page 2: Week 9-performance-management-1222266539427090-9

Week 9

Page 3: Week 9-performance-management-1222266539427090-9

Performance management

Page 4: Week 9-performance-management-1222266539427090-9

Once you have selected a project

Page 5: Week 9-performance-management-1222266539427090-9

Once you have selected a project

And planned it

Page 6: Week 9-performance-management-1222266539427090-9

Once you have selected a project

And planned it

And hired the team

Page 7: Week 9-performance-management-1222266539427090-9

Once you have selected a project

And planned it

And hired the team

And started the work

Page 8: Week 9-performance-management-1222266539427090-9

Once you have selected a project

And planned it

And hired the team

And started the work

How do you stay on track?

Page 9: Week 9-performance-management-1222266539427090-9

How do you even know if you are progressing to plan?

Page 10: Week 9-performance-management-1222266539427090-9

Gray & Larson, 2006, Ch 13.

Page 11: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 12: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System?

Page 13: Week 9-performance-management-1222266539427090-9

It involves determining what data to collect, how, when an who will collect the data; analysis of the data; and reporting progress

Monitoring System

Gather Analyse Report

Page 14: Week 9-performance-management-1222266539427090-9

You need to know what information is needed to satisfy you and your stakeholders.

Page 15: Week 9-performance-management-1222266539427090-9

Think about the Information System Structure

Page 16: Week 9-performance-management-1222266539427090-9

What data are collected?

Page 17: Week 9-performance-management-1222266539427090-9

current status of project (schedule and cost)

remaining cost to compete project

date that project will be complete

potential problems to be addressed now

out-of-control activities requiring intervention

Cost and/or schedule overruns & their reasons

Forecasting overruns at time of completion

What data are collected?

Page 18: Week 9-performance-management-1222266539427090-9

Collecting data and analysis

who will collect project data?how will data be collected?

when will the data be collected?who will compile and analyze the

data?who will receive the reports?

how will the reports be transmitted?

when will the reports be distributed?

Photo by germanium

Page 19: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 20: Week 9-performance-management-1222266539427090-9

Progress Report FormatProgress since last report

Current status of projectScheduleCostScope

Problems and issues since last report

Actions and resolution of earlier problems

New variances and problems identified

Corrective action planned

Page 21: Week 9-performance-management-1222266539427090-9

How long should a project status report be?

Page 22: Week 9-performance-management-1222266539427090-9

1 page

Page 23: Week 9-performance-management-1222266539427090-9

<example>

Page 24: Week 9-performance-management-1222266539427090-9

office.microsoft.com/en-us/templates/TC011417231033.aspx

http://saulcarliner.home.att.net/idbusiness/statusreport.htm

http://www.projectperfect.com.au/info_status_report.php

More info

www.ic.arizona.edu/~profcomm/writing/samples/stat_samp_s1.htm

www.projectconnections.com/knowhow/subsets/sample-templates/StatusReports.doc

Page 25: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 26: Week 9-performance-management-1222266539427090-9

Project Control Process

Page 27: Week 9-performance-management-1222266539427090-9

The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action

Pensiero

Page 28: Week 9-performance-management-1222266539427090-9

Project Control Steps

Set and baseline a

plan

Measuring progress and performance

Comparing the plan to the facts

Taking Action

Page 29: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 30: Week 9-performance-management-1222266539427090-9

Monitoring Time Performance

Page 31: Week 9-performance-management-1222266539427090-9

Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:

Page 32: Week 9-performance-management-1222266539427090-9

Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:

Tracking and baseline Gantt charts

show expected, actual, and trend data for event duration performance

Page 33: Week 9-performance-management-1222266539427090-9

Figure 13.1 Baseline Gantt Chart(Gray & Larson, 2006, p414)

Time

A Gantt Chart

Page 34: Week 9-performance-management-1222266539427090-9

Monitoring Time PerformanceTools used to catch negative variances from plan and communicate project schedule status:

Tracking and baseline Gantt charts

show expected, actual, and trend data for event duration performance

Control chartsplot the difference in

scheduled time on the critical path with the actual point on the critical path

Page 35: Week 9-performance-management-1222266539427090-9

Figure 13.2 Project Schedule Control Chart(Gray & Larson, 2006, p415)

A Control Chart

Page 36: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 37: Week 9-performance-management-1222266539427090-9

Monitoring Systems Disparities

Picture by Pensiero

Page 38: Week 9-performance-management-1222266539427090-9

Time-Phase Baseline Plan

Picture by Pensiero

Page 39: Week 9-performance-management-1222266539427090-9

Corrects the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget

Picture by Pensiero

Page 40: Week 9-performance-management-1222266539427090-9

Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule

Picture by Pensiero

Page 41: Week 9-performance-management-1222266539427090-9

Earned Value Cost/Schedule System

An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs

Picture by airgap

Page 42: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 43: Week 9-performance-management-1222266539427090-9

Earned Value Management

Page 44: Week 9-performance-management-1222266539427090-9

What is Earned Value Management (EVM)?

Page 45: Week 9-performance-management-1222266539427090-9

What is Earned Value Management (EVM)?

A project performance measurement technique that integrates scope, time, and cost data.

Page 46: Week 9-performance-management-1222266539427090-9

What is Earned Value Management (EVM)?

A project performance measurement technique that integrates scope, time, and cost data.Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.

You must enter actual information periodically to use EVM.

Page 47: Week 9-performance-management-1222266539427090-9

What is Earned Value Management (EVM)?

A project performance measurement technique that integrates scope, time, and cost data.Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals.

You must enter actual information periodically to use EVM.

Page 48: Week 9-performance-management-1222266539427090-9

Terms to learn

PV

AC

EV

Planned Value

Actual Cost

Earned Value

CV Cost Variance

SV Schedule Variance

CPICost Performance Indicator

SPISchedule Performance Indicator

Page 49: Week 9-performance-management-1222266539427090-9

(Also called the budget)

This is that portion of the approved total cost estimate planned to be spent on an activity during a given period

PV Planned Value

Page 50: Week 9-performance-management-1222266539427090-9

The total of direct and indirect costs incurred in finishing work on an activity during a given period

AC Actual Cost

Page 51: Week 9-performance-management-1222266539427090-9

An estimate of the value of the physical work actually completedEV Earned Value

Page 52: Week 9-performance-management-1222266539427090-9

Earned value minus the actual cost. Shows the difference between the estimated cost of an activity and the actual cost of that activity

TABLE 13.1

CV Cost Variance

Page 53: Week 9-performance-management-1222266539427090-9

Earned value minus the planned value. Shows the difference between the schedule completion of an activity and the actual completion of that activity

TABLE 13.1

SV Schedule Variance

Page 54: Week 9-performance-management-1222266539427090-9

The ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project. If the CPI is equal to 1 or 100% then the planned and actual costs are equal, or the costs are as budgeted. If the CPI is less than 1 or less than 100%, the project is over budget. If the CPI is greater than 1 or more than 100%, the project is under budget

CPICost Performance Indicator

Page 55: Week 9-performance-management-1222266539427090-9

The ratio of earned value to planned value and can be used to estimate the projected time to complete the project. Similar to the CPI, an SPI of 1 or 100% means the project is on schedule. If the SPI is greater than 1 or 100% then the project is ahead of schedule. If the SPI is less than 1 or 100%, the project is behind schedule

SPISchedule Performance Indicator

Page 56: Week 9-performance-management-1222266539427090-9

TABLE 13.1

Quick EVM quizWhat can we say if CPI > 1

Page 57: Week 9-performance-management-1222266539427090-9

Quick EVM quizWhat can we say if CPI > 1

If the CPI is greater than 1 or more than 100%, the

project is under budget

Page 58: Week 9-performance-management-1222266539427090-9

Quick EVM quizWhat is EV minus AC?

Page 59: Week 9-performance-management-1222266539427090-9

Quick EVM quizWhat is EV minus AC?

EV – AC = SVEarned Value (what was done)

MinusActual Cost (what has been

paid)=

Schedule Variance

Page 60: Week 9-performance-management-1222266539427090-9
Page 61: Week 9-performance-management-1222266539427090-9

Scenario Example

Page 62: Week 9-performance-management-1222266539427090-9

“Purchasing & Installing Web Server”

Duration 1 week,

Budget $10,000.

Scenario Example

Page 63: Week 9-performance-management-1222266539427090-9

“Purchasing & Installing Web Server” Duration 1 week, Budget $10,000.

PV – Planned Value – for that activity for that week = $10,000

AC – Actual Cost – suppose it actually took 2 weeks and cost $20,000. Assume $15,000 were incurred in week 1, and $5,000 in week 2. These costs are the actual costs for that activity each week

EV – Earned Value – earned value after one week is $7,500. (10,000 * 75%)

Example: CP829_Lecture_Week9_EarnedValue.xls

Scenario Example

Page 64: Week 9-performance-management-1222266539427090-9
Page 65: Week 9-performance-management-1222266539427090-9
Page 66: Week 9-performance-management-1222266539427090-9

Earned Value Chart for Project after 5-MonthsEarned Value Chart for Project after 5-Months

Page 67: Week 9-performance-management-1222266539427090-9
Page 68: Week 9-performance-management-1222266539427090-9

Max WidemanMax Wideman

Page 69: Week 9-performance-management-1222266539427090-9

Rules for Earned Value Numbers

Negative numbers for cost and schedule variance indicate problems in those areas

The project is costing more than planned or taking longer than planned

CPI and SPI less than 100% indicate problems

Page 70: Week 9-performance-management-1222266539427090-9

Table 13.3 Interpretation of Indexes(Gray & Larson, 2006, p429)

Page 71: Week 9-performance-management-1222266539427090-9

An alternative

Source: http://www.mountaingoatsoftware.com/release_burndown

Page 72: Week 9-performance-management-1222266539427090-9

Week 2 lecture

Page 73: Week 9-performance-management-1222266539427090-9

So, what do you do when your plan changes?

Page 74: Week 9-performance-management-1222266539427090-9

There are methods used to revise estimates of future project costs

EVM allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate

EVM uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable

Page 75: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 76: Week 9-performance-management-1222266539427090-9

Developing an Integrated Cost/Schedule System

Page 77: Week 9-performance-management-1222266539427090-9

Compute

Calculate

Collect

Schedule

Resource plan

WBS

Budget

Plan

Mon

itor

Page 78: Week 9-performance-management-1222266539427090-9

Define the work using a WBSScopeWork packagesDeliverablesOrganization unitsResourcesBudgets

Develop work and resource schedules

Schedule resource to activities

Time-phase work packages into a network

Photo by shimonkey

Page 79: Week 9-performance-management-1222266539427090-9

Develop a time-phased budget using

work packages

included in an activity.

Accumulate budgets (PV)

At the work package level, collect the actual costs for the work performed (AC)

Multiply percent complete times original budget (EV)

Compute the schedule variance (EV-PV) and the cost variance (EV-AC)

Page 80: Week 9-performance-management-1222266539427090-9

Figure 13.3 Figure 13.3 Project Management Information Systems OverviewProject Management Information Systems Overview(Gray & Larson, 2006, p419)(Gray & Larson, 2006, p419)

Integrated Cost/ Schedul

es

Page 81: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 82: Week 9-performance-management-1222266539427090-9

Project Baselines

Page 83: Week 9-performance-management-1222266539427090-9

Week 4 lecture

Page 84: Week 9-performance-management-1222266539427090-9

a Baseline is an anchor point for measuring performance

Photo by _Robert C_ @

flickr

Page 85: Week 9-performance-management-1222266539427090-9

a planned cost and expected schedule against which actual cost

and schedule are measured

Gold by Куртис Перри

Page 86: Week 9-performance-management-1222266539427090-9

a basis for cash flows and awarding progress payments

Photo by quaziefoto @ flickr

Page 87: Week 9-performance-management-1222266539427090-9

a summation of time-phased budgets (cost accounts as summed work packages) along a project timeline

Picture by Network Osaka @ flickr

Page 88: Week 9-performance-management-1222266539427090-9
Page 89: Week 9-performance-management-1222266539427090-9

What Costs Are Included in Baselines?LaborEquipmentMaterialsProject direct overhead costs (DOC)

Page 90: Week 9-performance-management-1222266539427090-9

Figure 13.14 Scope Changes to a Baseline(Gray & Larson, 2006, p436)

Page 91: Week 9-performance-management-1222266539427090-9

What is a Project Monitoring System

Examples of Progress Reports

What is the Project Control Process and why is it useful?

How do I Monitor Time Performance

The shortcomings of monitoring Systems

Earned Value Management – a silver bullet?

Integrated Cost/Schedule System

Project Baselines

Page 92: Week 9-performance-management-1222266539427090-9

ReviewProject monitoring system include; data collection; analysis and reporting.Project control steps include; baseline plan, progress measurement, comparing actual against projected plan, and actions.Performance can be monitored using tools such as; tracking Gantts, control charts, baseline plans and earned value management.Earned value management (EVM) is a technique which incorporated scope, time and cost data to determine the health of the project.Integrated Cost/Schedule systems are developed creating; WBS, work/resource schedules, budget, and EVM.Project baselines are an anchor point for measuring performance.

Page 93: Week 9-performance-management-1222266539427090-9

ReferencesHorodyski, K. (1995). Managing and developing teams. Footscray, Vic.: Open Training Services.Greenberg, J. & Baron, R. (1993). Behavior in organizations (4th ed.). Syd., NSW: Allyn and Bacon. Robbins, S., et al. (1998). Organisational behaviour (2nd ed.). Sydney: Prentice-Hall