Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure 2.1 Core Level 2.2 Hub Level 2.3 Campus Level 3. Upgrade Connectivity, Power, and Air Conditioning 3.1 Upgrade Fiber Connectivity 3.2 Upgrade Cabling Connectivity 3.3 Upgrade Electrical Power and Air Conditioning 4. Upgrade the Data Center Infrastructure 4.1 Build a Virtualized Server Data Center 4.2 Install a Storage Area Network (SAN) 4.3 Co-locate the Data Center at an External Facility 4.4 Build Backup, Recovery, and Business Continuity 5. Upgrade Staff’s Technology and Phone Systems 5.1 Replace Telephone System with VoIP 5.2 Replace Administrative Staff Technology 5.3 Replace Network Printers and Print Servers 6. Install Technology Infrastructure in New Schools iSphere Program Management Bond 1 Bond 2 Bond 3 Bond 4 Bond 5 Bond 6 Implementation Plans 2014 Bond Recommendations All Other 2014 Bond Information Implementation Team

Upload: others

Post on 20-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Week Ending April 3, 2015

1. Install High Speed Wireless Access Infrastructure

2. Install Network Electronics Infrastructure

2.1 Core Level

2.2 Hub Level

2.3 Campus Level

3. Upgrade Connectivity, Power, and Air Conditioning

3.1 Upgrade Fiber Connectivity

3.2 Upgrade Cabling Connectivity

3.3 Upgrade Electrical Power and Air Conditioning

4. Upgrade the Data Center Infrastructure

4.1 Build a Virtualized Server Data Center

4.2 Install a Storage Area Network (SAN)

4.3 Co-locate the Data Center at an External Facility

4.4 Build Backup, Recovery, and Business Continuity

5. Upgrade Staff’s Technology and Phone Systems

5.1 Replace Telephone System with VoIP

5.2 Replace Administrative Staff Technology

5.3 Replace Network Printers and Print Servers

6. Install Technology Infrastructure in New Schools

iSphere Program Management

Bond 1

Bond 2

Bond 3

Bond 4

Bond 5

Bond 6

Implementation Plans

2014 Bond Recommendations

All Other 2014 Bond Information

Implementation Team

Page 2: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Interesting Wireless Access Point (AP) Statistics:.Total number of indoor APs order by CFISD - 7,420 model 225

Total number of outdoor APs ordered by CFISD - 380 model 275

Bleyl AP Delivery - 3,295 indoor APs, 280 outdoor APs, plus mounts

Layer3 Warehouse - 4,125 APs, 100 outdoor APs, plus mounts

Delivery of Access Points Beginning April 1st, 2015

Bond 1.1

Table of ContentsLayer3 Personnel delivering wireless APs to Bleyl

Install High Speed Wireless Access InfrastructureCFISD Project Manager: Larry Barrios

Roland Padilla Managing AP Delivery

Layer3 began the delivery of Wireless access points (APs). Due to the significant

number of APs, the challenge was to locate a facility that could house the number of

APs ordered. Pictured below is a subset of the APs ordered that will be stored at Bleyl

Data Center, with the majority of APs stored at Layer3's warehouse.

Page 3: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Wireless Discussion PointsDense distribution of wireless access points (APs) is scheduled to begin at the high schools this month.

Prior to the initiation of this step, a naming scheme for the APs must be finalized. Below is the naming

convention being considered:

• Unique 3-letter campus variable, AP numbered identifier, and Room Number (RM) or unique location

identifier (i.e. HW…..abbreviation for Hallway).

Example #1 - CYR-AP005-RM3122 (AP #5 located in room 3122)

Example #2 - CYR-AP110-RM3122HW (AP #110 located in the Hallway outside of RM3122)

• Also under review is the Cable Identification for each AP.

Bond 1.1

Table of Contents

Install High Speed Wireless Access InfrastructureCFISD Project Manager: Larry Barrios

Cable indentification

required for APAP Label

Page 4: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

The core network infrastructure

for the network firewalls at the

ISC Data Center and

CyrusOne Data Center were

delivered on Monday, April 6,

2015. A total of eleven

firewalls are included as an

optimum design strategy for

securing the district’s network.

Plans for the final design and

implementation are underway.

Bond 2.1

INFRASTRUCTURE

CORE Install Network Electronics Infrastructure

Core LevelCFISD Project Manager: Oscar Villar

Roland Padilla and Oscar Villar

Jay Johnson, Kim Bowlin and MCAMCA unloading Fortinet Hardware

Page 5: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

The core network infrastructure hardware for the IP

addressing of the network at the ISC Data Center

and CyrusOne Data Center was delivered on

Monday, April 6, 2015. Plans for the final design

and implementation of the new IP addressing

scheme are underway.

Bond 2.1

INFRASTRUCTURE

CORE Install Network Electronics Infrastructure

Core LevelCFISD Project Manager: Oscar Villar

Roland Padilla amd MCA

COmmunications

Roland Padilla and MCA

CommunicationsTable of Contents

Page 6: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Presidio, M&S Technology, and CFISD discuss initial steps required :

1. Install second firewall at ISC

2. Upgrade firmware on existing Firewall

3. Install CyrusOne data Center Switches

Install Network Electronics Infrastructure

Core LevelCFISD Project Manager: Oscar VillarBond 2.1

INFRASTRUCTURE

CORE

Stuart Loftis and Oscar Villar Tim Ramsey, Stuart Loftis and Oscar Villar

Pictured above is the combined effort between CFISD, Presidio, and M&S Technology

defining the initial steps required. The first step outlined is to eliminate our current

production single point of failure by installing a second Fortinet firewall at ISC. The

production firewall will be updated with the most current release of firmware and the new

firewall will then be installed.

Page 7: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Upgrade Fiber ConnectivityCFISD Project Manager: Paula Ross

Bond 3.1

Fiber

Fiber Optic Cable Routes:CFISD plans for fiber optic cable routes between the

Instructional Support Center and CyrusOne. These routes will

follow diverse physical routes.

The following contract addendums are begin finalized:

1. Master Networking Service

2. Fiber Optic Network Lease

Additional Options Under Consideration:1. Additional dark fiber pair available on a month-to-month cost

until wavelength service is available.

2. Fiber pair available for Pope Elementary School

Table of Contents

Page 8: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Completed This Week:Comprehensive Walkthroughs at ALC East and Cook Middle School

Follow up Site Visits at Jersey Village High School

A preliminary walk-through schedule for the remaining middle

schools was created by iSphere and is being reviewed by the CFISD

Technology Team.

Planned Next Week:

Comprehensive Walkthroughs: Campbell Middle School, Arnold

Middle School, Aragon Middle School, Labay Middle School, Hopper

Middle School, and Thornton Middle School

Table of Contents

Upgrade Cabling ConnectivityCFISD Project Manager: Larry Barrios

Bond 3.2

Cabling

Page 9: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

VLK Architects delivered a proposed schedule for bidding the electrical and power

upgrades needed for the hub and secondary campuses. Frankie Jackson is

scheduled to discuss the details of this plan with Dillon Brady, Assistant

Superintendent of Facilities and Planning, on April 7, 2015.

Table of Contents

Anthony MS*

Goodson MS

Hamilton MS

Smith MS

Spillane MS

Aragon MS

Arnold MS

Truitt MS

Hopper MS

Kahla MS

Thornton MS

Watkins MS

Cy-Ridge HS

Cy-Falls HS

Bleyl MS

Campbell MS

Jersey Village HS

4. Cy-Ridge Router1. Cy-Woods Router 2. Berry Center Router 3. Cy-Lakes Router 5. Bleyl Router 6. Dean Router

1

2

3

Cy-Woods HS

Cy-Ranch HS

Cy-Fair HS

Langham Creek HS

Cy-Lakes HS

Cy-Springs HS

Labay MS

Cy-Creek HS

Windfern HS

Dean MS

Cook MS

Upgrade Electrical Power and Air ConditioningCFISD Project Manager: Frankie Jackson and Daniel Grosz

Bond 3.2

Site Investigation 12/22/14 - 2/6/15

District approval of

Phase 1 Scope of Work 4/3/2015

90% CD Print Date 4/10/2015

CD Review with Owner 4/14/2015

BIDDING

1st Advertisement 4/19/2015

Issue documents for

Bidding 4/20/2015

2nd Advertisement 4/26/2015

Pre-Proposal 5/5/2015

Bid Date 5/19/2015

Back-Up Due for Board Packet 5/29/2015

Committee of the Whole Meeting 6/4/2015

Board Meeting 6/8/2015

CONSTRUCTION

Notice to Proceed 5/12/2015

Page 10: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Anna Senties

Information

GatheringPlanning &

Design

RFP Submission

& Procurement

Implementation

& MigrationProject

Completion

- Vendor/Product Interviews & Research

- Current Environment Assessment Tools

- Product Matrix of Pros/Cons

- Applications Inventory & Priority

The Network Management and Operations (NMO) virtualization team

will soon finish the “Information Gathering” phase. The main focus is

now on completing the Application Inventory & Priority workbook where

Nelda Hanzi is making great progress. The virtualized design, product

selection, and possible RFP process are anticipated to start in April.

Lance Melancon

Mike Diaz

Jody Clark of VMware presented a

deep dive on NSX (virtual networking)

April 2nd to ECN. Virtual networking

will be an important consideration in

the overall design.Thomas Hollister

Jody Clark

Bond 4.1

Build a Virtualized Data CenterCFISD Project Manager: Greg Rhodes

Oscar Villar

Mike Hanson and his team from

Brocade presented their data center

and fibre channel switch solutions

March 30th.

Page 11: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Information

GatheringPlanning &

Design

RFP Submission

& Procurement

Implementation

& MigrationProject

Completion

- Vendor/Product Interviews & Research

- Current Environment Assessment Tools

- Product Matrix of Pros/Cons

The Network Management Operations (NMO) team will soon move

to the next phase of the storage area network (SAN) project.

Vendor discussions have included topics about replication and

backup. The effort is now concentrated on determining space

requirements for applications and data shares currently and for

future growth. Further assessment tools are scheduled to be run

this week. The storage design, product selection, and possible

RFP process are anticipated to start in April.

Install a Storage Area NetworkCFISD Project Manager: Greg Rhodes

Bond 4.2

Mark Csepke of EMC presented strategies for backup

and replication between sites April 1st. There were also

discussions about active/active SAN with Vplex.

NetApp is being scheduled this

next week to run their assessment

tool.

Lance Melancon

Mark Csepke

Steve Wheeler

Timothy Hamilton

Page 12: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Polly Gifford with Education Partners Solution, has been working on power budgets and rack elevations for CyrusOne. A sample rack elevation may be viewed here.

Contract execution is still pending.

John Sblendorio with CyrusOne sent their implementation process which may be viewed here.

The official kickoff meeting for CyrusOne will be scheduled once the contract is signed.

CoLocate the Data Center at an External FacilityCFISD Project Manager: Greg Rhodes

Bond 4.3

Coming Soon!

Page 13: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

The ISC data center is close to being ready for the upcoming

construction to a Tier 3 facility. One entire side of the data center

has been cleared to start the floor replacement. The project

budget is being reviewed by Evolve for possible funds to

purchase new network/server cabinets.

Mike Raspet

Tyndall Overby

Build Backup, Recovery, and Business ContinuityCFISD Project Manager: Greg Rhodes

Bond 4.4

Paula Ross

Richard Hoffman

Oscar Villar

Thomas Hollister

Tyndall Overby, the Evolve project manager, led the "Drawing Review" meeting April 2nd. Progress drawings

and equipment cutsheets have been sent to Facilities for review. After the review approval, an order will be

sent to CenterPoint for the new dedicated service entrance. Submitted drawings may be viewed through the

following links: power, electrical, and HVAC. The next data center construction meeting is

scheduled for April 8th.

Page 14: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

A final design meeting with AT&T was held on Wednesday,

April 1, 2015. Attendees from AT&T, Education Partners

Solution (EPS), Cisco, iSphere, along with the Technology

Services team met to review the network design and cost

proposal. AT&T is finalizing contracts and a Total Cost of

Ownership (TCO) presentation. The contracts will be

submitted to CFISD the week of April 6, 2015, in time to file

for 2015-2015 e-rate reimbursements.

Bond 5.1

Co-Locate the Data Center at an External FacilityCFISD Project Manager: Paula Ross

Table of Contents

Cisco, CFISD staff, EPS, eSphere, and AT&T

The proposal includes:

• Total Quantity of users 6380

• Cisco Call Center Express with 10 Agents

• Licenses - Essential, Basic and Enhanced

• SRST Routers for 101 locations for E911

and DR/Survivability

• WAN Bandwidth – 2 locations with 30Mbps

and Police Dept. 1.5Mbps

• IPFlex SIP trunk 20Mbps with 310

Concurrent Calls.

• 36 Month term with all equipment being

purchase and owned by CFISD

Cost savings:

• With this solution, 94% (estimate) of the current cost on

local voice services would be replaced. (327 Alarm and

45 Elevator lines are currently in place from total of 6380

Plexar lines)

• 100% of the long distance service as well as voicemail

services cost will be eliminated. AT&T SIP Trunking offer

provides 300 Min. of free long distance per concurrent call

per month.

• The solution is based on 310 Concurrent calls for the

district, which would give CFISD a total of 93,000 min in

free domestic long calling.

Currently Cypress-Fairbanks ISD utilizes on average

1500 Domestic Long Distance Minutes/month

Page 15: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Bond 5.1

Co-Locate the Data Center at an External FacilityCFISD Project Manager: Paula Ross

uuuuuATT

VPN MPLS

Site 1

10300 Jones Rd

Houston, TX

CyFair Site 2

5150 Westway Park Blvd.

Houston, TX 77041

IDC

900 Venture Dr

Allen, TX. 75013

CyFair ISDRFP 3936

Hosted UC

uuuuuIP FR SIP

310 CC’s

uuuuuCustomer

Private

Fiber

96 sites

Site 3

11200 A Telge

Cypress, TX

Cisco, CFISD staff, EPS, eSphere, and AT&T

Table of Contents

Summary

o AT&T has developed a Unified Communication (UC)

solution based on Cisco's network electronics.

o Fully Managed/Monitored 7x24x365 Solution with helpdesk

support with truck role for SRST router failure.

o Hosted UC robust and redundant design for Disaster

Recovery with 999.99% uptime.

o Session Initiated Protocol (SIP) trunk located in the Data

Center - 310 Concurrent Calls and includes 93,000

minutes of Domestic Long Distance per Month

o (2) MPLS connections to (2) CFISD locations for

redundancy.

o All IOS and Patch updates are tested before being

deployed into the network to insure systems keep working

and up to date.

o CFISD staff will be trained on the Support Portal to allow

them to enter Move, Add, Change and Delete (MACD)

requests as well as obtain engineering support via web or

phone.

o Cost proposal leverages new e-rate modernization

changes.

Page 16: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Leonard Chance, CFISD Technology

Assets Manager, compiled and verified the

“replacement data” for the instructional

campuses. Leonard has started this week

to make site visits to help the campus

technicians validated the inventories to

ensure accuracy, so an order can be

placed. This week he went to Cy Fair high

school, Cy Ranch high school, Hamiltion

middle school, and Hopper middle school.

For the administrative campuses, the

technology service technicians have

surveyed those sites to verify inventories.

The data will be reviewed and added to

the items that have been compiled from

the Instructional campuses.Service tech Chris Roberts

surveying equipment at the

Food Service facility.Leonard working with the

service techs Karen Davis and

Bradley Mulligan at Cy Ranch

HS to validated their inventory.

Replace Administrative Staff TechnologyCFISD Project Manager: Jay Johnson

Bond 5.2

Page 17: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Leonard Chance, the

Technology Assets manager,

has gathered a list of printers

by school of equipment that

is currently in need of

replacement or that will need

to be replaced within the next

five years. An analysis is

currently underway to

determine when the best time

to replace this equipment.

Leonard will visit campuses

to help determine their needs

and to prioritize the

deliveries.

Leonard met with the service

techs Andrew Lopez and

Donisha Fontenet at Cy Fair HS

to verify network printers location

Replace Network Printers and Print ServersCFISD Project Manager: Jay Johnson

Bond 5.3

Page 18: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Install Technology Infrastructure in New SchoolsCFISD Project Manager: Thomas Hollister

Bond 6.1

On Wednesday, April 1, 2015, Thomas Hollister, Roland

Padilla, and Frankie Jackson met with Becky Cook, Director

of Instructional Technology, and the Facilities Planning

department to review high school #12 at the 75% review.

High School #12

75% Review

Page 19: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Weekly Summary:

Frankie Jackson worked with the iSphere project management team to make improvements in the weekly status reporting and the monitoring of Bond projects. Improvements are currently being implemented.

Table of Contents

Project ManagementProject Managers: Larry Short and Charity Farve

Bond PM

Weekly Status

Report Ending

April 3, 2015(click here)

Page 20: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Summary Level Project Schedules

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2016 2017 2018 2019 2020

2.1 Install Network Electronics Infrastructure

3.1 Upgrade Fiber and Cabling Connectivity

4.1 Build Virtualized Server Data Center

4.2 Install a Storage Area Network (SAN)

4.3 Co-locate Data Center at CyrusOne

4.4 Build Backup, Recovery, and Business Continuity

5.1 Replace Telephone System with VoIP Communications

5.2 Replace Administrative Staff Technology

5.3 Replace Network Printers and Print Servers

1.1 Install High Speed Wireless Assess Infrastructure

3.2 Upgrade Electrical Power and Air Conditioning

6.1 Install Technology in New Schools

Page 21: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Table of Contents

Goodson MS 6/15/2015

Hamilton MS 6/15/2015

Smith MS 6/15/2015

Spillane MS 6/15/2015

Anthony MS*

Aragon MS 7/6/2015

Arnold MS 7/6/2015

Truitt MS 7/6/2015

Hopper MS 7/20/2015

Kahla MS 7/20/2015

Thornton MS 7/20/2015

Watkins MS 7/20/2015

Cy-Ridge HS 7/27/2015

Cy-Falls HS 7/27/2015

Bleyl MS 8/10/2015

Campbell MS 8/10/2015

Jersey Village HS

8/17/2015

4. Cy-Ridge HUB

July 13, 2015

1. Cy-Woods HUB

April – May 2015

2. Berry Center HUB

June 29, 2015

3. Cy-Lakes HUB

July 6, 2015

5. Bleyl HUB

July 20, 2015

6. Dean HUB

July 27, 2015

1

2

3 Cy-Woods HS 6/8/2015

Cy-Ranch HS 6/8/2015

Cy-Fair HS 6/29/2015

Langham HS 6/29/2015

Cy-Lakes HS 7/13/2015

Cy-Springs HS 7/13/2015

Labay MS 7/27/2015

Cy-Creek HS 8/10/2015

Windfern HS 8/10/2015

Dean MS 8/17/2015

Cook MS 8/17/2015

CyrusOne ( CoLocation)

June 1, 2015ISC (Data Center)

February 1, 2015

4

Summary Level Campus Deployment Schedule

Page 22: Week Ending April 3, 2015 - CFISD Technology Services · Week Ending April 3, 2015 1. Install High Speed Wireless Access Infrastructure 2. Install Network Electronics Infrastructure

Cy-Ridge Hub

CyrusOne – Core 2

(data center)

Cy-Woods HubBerry Center Hub

Cy-Lakes Hub Bleyl Hub

(data center)

ISC – Core 1

(data center)

Dean Hub

1. Cy-Woods Router

Cy-Woods HS

Carlton Center

Cy-Ranch HS

Spillane MS

Smith MS

Goodson MS

Hamilton MS

Salyards MS

Black ES

Warner ES

Keith ES

Farney ES

Robison ES

Hamilton ES

Sampson ES

Ault ES

Moore ES

Swenke ES

Chiller Plant

Carlton Center

2. Berry Ctr Router

Cy-Fair HS

Langham Creek HS

Anthony MS

Aragon MS

Arnold MS

Truitt MS

Postma ES

Birkes ES

Copeland ES

Lamkin ES

Holmsley ES

Horne ES

Millsap ES

Rennell ES

Police Station

Telge Transp.

Science Resource Ctr

Berry Center

Cy-Fair Annex

Barker Transp

Exhibit Center

3. Cy-Lakes Router

Cy-Lakes HS

Cy-Springs HS

Hopper MS

Kahla MS

ALC West

Thornton MS

Watkins MS

Andre ES

Duryea ES

McFee ES

Robinson ES

Metcalf ES

Emery ES

Hemmenway ES

Jowell ES

Lieder ES

Sheridan ES

Tipps ES

Walker ES

Wilson ES

4. Cy-Ridge Router

Cy-Ridge HS

Cy-Falls HS

Labay MS

Danish ES

Adam ES

Willbern ES

Emmott ES

Fiest ES

Hairgrove ES

Lowery ES

Owens ES

Telge Ag Barn

Eldridge Transp.

Eldridge Ag

ELC Smokey Trail

5. Bleyl Router

Bleyl MS

Cy-Creek HS

Windfern HS

ALC East

Campbell MS

Francone ES

Hancock ES

Matzke ES

Yeager ES

Pridgeon Stadium

Falcon Annex

Falcon Transp

Windfern Annex

Maintenance Ctr

6. Dean Router

Dean MS

Jersey Village HS

Cook MS

Lee ES

Bane ES

Kirk ES

Bang ES

Frazier ES

Gleason ES

Holbrook ES

Pope ES

Post ES

Reed ES

Food Ser Warehouse

Food Production Ctr

* Denotes priority campuses