weekly construction update 06-06-2010
DESCRIPTION
KC Soccer Stadium construction update from Turner Construction.TRANSCRIPT
Building the Future
Current Activities this Week:
Mass Excavation:
Grading is ongoing in Area 3. Backfilling of on-grade
is ongoing in Area 1 and Area 2.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Sanitary Sewer Line E installation has started on east side
of France Family Dive.
Foundations:
Area 2 Concourse Level – E-Line footing installation is
ongoing E-Line wall installation has started.
Area 3 Field Level – A-Line wall installation is ongoing
Currently to Column Line 7.
Area 3 Field Level – Installation of Drilled Piers
are ongoing.
Area 4 Mezzanine Level – D-Line grade beam installation
is ongoing.
Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-5 is ongoing and
is currently to Column Line 27.
Decking/Detailing/Studs/Edge Angle is ongoing in
sequence 1-2 and 1-4.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 6.2.2010
Re: Wizards Stadium Project
Update – Week of
5.31.2010
Field Level Area 2 – Underground plumbing
pipe installed south of C-Line.
Main Concourse Area 1 – Reinforcing steel
and underslab MEP rough-in in preparation
for concrete slab placement.
Concourse Level Area 2 – E-Line wall forms
being installed from Column Lines 23-19.
Building the Future
Underground MEP:
Deep Sanitary installation is ongoing in Area 2 and Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in on Concourse Level is
ongoing and has started on Suite Level.
Projected Activities occurring next Week:
Mass Excavation:
Grading at Area 3 will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 2 Concourse Level – Footing and wall installation
will continue.
Area 3 Field Level – A-Line wall placement will continue.
Area 4 Mezzanine Level – Grade beam installation will
continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-5 will continue.
Decking/Detailing/Studs/Edge Plates will continue in
Sequence 1-4.
Area 1 – Structural Steel Erection at West
Building is ongoing in Sequence 1-5 (bays
27-32 shown).
Field Level Area 2 – Backfill of stage walls
are ongoing.
Area 1 – Rakers installed at Column Lines 28-
32 that support the precast concrete risers.
Building the Future
Additional Photos:
Field Level Area 3 – Drilled pier installation is
ongoing.
Field Level Area 2/3 – Southeast vomitory
walls and A-Line walls being installed.
Mezzanine Level Area 4 – D-Line footing
installation is ongoing from Column Line 33-
37.
Field Level Area 2 – East Stage and ramp
walls being placed.
Concourse Level Area 1 – Edge plate
installation at edge of concrete slabs
ongoing.
Suite Level Area 1 – Decking, Nelson Studs,
and Edge Plating installed.