weekly construction update 06-06-2010

3
Building the Future Current Activities this Week : Mass Excavation : Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1 and Area 2. Site Utilities : Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Sanitary Sewer Line E installation has started on east side of France Family Dive. Foundations : Area 2 Concourse Level – E-Line footing installation is ongoing E-Line wall installation has started. Area 3 Field Level – A-Line wall installation is ongoing Currently to Column Line 7. Area 3 Field Level – Installation of Drilled Piers are ongoing. Area 4 Mezzanine Level – D-Line grade beam installation is ongoing. Structural Steel Erection : Area 1 – Steel Erection in sequence 1-5 is ongoing and is currently to Column Line 27. Decking/Detailing/Studs/Edge Angle is ongoing in sequence 1-2 and 1-4. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 6.2.2010 Re: Wizards Stadium Project Update – Week of 5.31.2010 Field Level Area 2 – Underground plumbing pipe installed south of C-Line. Main Concourse Area 1 – Reinforcing steel and underslab MEP rough-in in preparation for concrete slab placement. Concourse Level Area 2 – E-Line wall forms being installed from Column Lines 23-19.

Upload: kansas-city-wizards

Post on 03-Jul-2015

644 views

Category:

Sports


1 download

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

TRANSCRIPT

Page 1: Weekly Construction Update 06-06-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Grading is ongoing in Area 3. Backfilling of on-grade

is ongoing in Area 1 and Area 2.

Site Utilities:

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Sanitary Sewer Line E installation has started on east side

of France Family Dive.

Foundations:

Area 2 Concourse Level – E-Line footing installation is

ongoing E-Line wall installation has started.

Area 3 Field Level – A-Line wall installation is ongoing

Currently to Column Line 7.

Area 3 Field Level – Installation of Drilled Piers

are ongoing.

Area 4 Mezzanine Level – D-Line grade beam installation

is ongoing.

Structural Steel Erection:

Area 1 – Steel Erection in sequence 1-5 is ongoing and

is currently to Column Line 27.

Decking/Detailing/Studs/Edge Angle is ongoing in

sequence 1-2 and 1-4.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 6.2.2010

Re: Wizards Stadium Project

Update – Week of

5.31.2010

Field Level Area 2 – Underground plumbing

pipe installed south of C-Line.

Main Concourse Area 1 – Reinforcing steel

and underslab MEP rough-in in preparation

for concrete slab placement.

Concourse Level Area 2 – E-Line wall forms

being installed from Column Lines 23-19.

Page 2: Weekly Construction Update 06-06-2010

Building the Future

Underground MEP:

Deep Sanitary installation is ongoing in Area 2 and Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in on Concourse Level is

ongoing and has started on Suite Level.

Projected Activities occurring next Week:

Mass Excavation:

Grading at Area 3 will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue. Storm Line 5000 and

4000 will begin. Installation of Sanitary Line E will continue.

Deep Underground Plumbing:

Deep Sanitary installation in Area 3 will continue.

Foundations:

Area 2 Concourse Level – Footing and wall installation

will continue.

Area 3 Field Level – A-Line wall placement will continue.

Area 4 Mezzanine Level – Grade beam installation will

continue.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-5 will continue.

Decking/Detailing/Studs/Edge Plates will continue in

Sequence 1-4.

Area 1 – Structural Steel Erection at West

Building is ongoing in Sequence 1-5 (bays

27-32 shown).

Field Level Area 2 – Backfill of stage walls

are ongoing.

Area 1 – Rakers installed at Column Lines 28-

32 that support the precast concrete risers.

Page 3: Weekly Construction Update 06-06-2010

Building the Future

Additional Photos:

Field Level Area 3 – Drilled pier installation is

ongoing.

Field Level Area 2/3 – Southeast vomitory

walls and A-Line walls being installed.

Mezzanine Level Area 4 – D-Line footing

installation is ongoing from Column Line 33-

37.

Field Level Area 2 – East Stage and ramp

walls being placed.

Concourse Level Area 1 – Edge plate

installation at edge of concrete slabs

ongoing.

Suite Level Area 1 – Decking, Nelson Studs,

and Edge Plating installed.