weekly construction progress report · weekly construction progress report weekly construction...
TRANSCRIPT
Walden Athletic Complex
Atlanta Public Schools Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
Project: Walden Athletic Complex Week Ending: January 10, 2018 THIS WEEK:
Demolition of existing building completed
Underground Plumbing finishing
Underground Electrical finishing
Installation of lighting/netting pole bases
Backfill after demolition of existing building
Storm Sewer continuing
Floor trench drains being installed
Backfill after demolition of existing building
Underslab plumbing and electrical
Lighting/Netting Pole bases installed
Walden Athletic Complex Atlanta Public Schools
Weekly Construction Progress Report
WEEKLY CONSTRUCTION PROGRESS REPORT
NEXT WEEK – Jan 11 thru Jan 18: Prepping field house slab
Pouring field house slab
Backfill continuing
Storm and sewer work continuing
Surveying for retaining wall base Budget and Schedule Construction Budget: $7,390,000.00 Progress Earned: $0 Budget Status: On Budget Completion Date: August 8, 2018 (Substantial Completion) Schedule Status: On Schedule SCHEDULED DATE OF SUBSTANTIAL COMPLETION
August 8, 2018. PREPARED BY:
Chris Hubbard, Parrish Construction
COPIES TO:
George Harkness, APS
Michael Wright, Eberly & Associates
Scott Griffin, Eberly & Associates
John Rood, Parrish Construction
Dave Yuhas, Parrish Construction
Eric Wise, Parrish Construction
Parrish Construction – Job File