WEEKLY PROGRESS UPDATE
DECEMBER 20 TH, 2019
Progress Photos
Exterior Metal Stud Wall Installation
Metal Roof Installation
PROGRESS UPDATE 12.20.2019
• INSTALLATION OF METAL ROOF AND ROOF INSULATION – ONGOING
• INSTALLATION OF EXTERIOR METAL STUD WALLS - STARTED
• NEXT WEEK: COMPLETE METAL ROOF INSTALLATION, CONTINUE EXTERIOR METAL STUD WALL INSTALLATION.
• TOTAL WORK DAYS LOST DUE TO WEATHER – 4 DAYS• TOTAL WORK DAYS LOST DUE TO INSPECTION DELAYS – 0 DAYS