construction manager’s weekly progress reportdashboard.ddot.dc.gov/dtapdoc/document/99_65860_47 cm...
TRANSCRIPT
Field Office
1411 K Street, NW
Suite 225
Washington, DC 20006
Phone: (202) 347-7733
K STREET NW FROM 12TH STREET TO 21ST STREET
ADA IMPROVEMENTS
Contract No.: DCKA-2012-C-0058
FAP No.: STP-1102(030)
CONSTRUCTION MANAGER’S
WEEKLY PROGRESS REPORT
08/18/2014 – 08/24/2014
Project Website: www.kstreetadaimprovements1221.com
08/19/14 –Contractor works to install new block paver sidewalk to
provide an accessible, compliant path at the SE corner of 21st St., NW
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 2 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 2 of 10
EXECUTIVE SUMMARY
Work under this contract consists of the construction of pedestrian facilities in compliance with
the 2010 Americans with Disabilities Act (ADA) Standards. These improvements are located at
signalized intersections and bus stops along K Street NW from the 12th Street intersection to the
21st Street intersection. The project involves reconstruction of pedestrian ramps at the signalized
intersections, addition of accessible pedestrian signals and pushbuttons at each roadway crossing,
removal, reconstruction of existing bus stops and the respective accessible pathways to the bus
stops, and removal/installation of multiple storm drains within the study limits as shown on
project plans and indicated in specifications and special provisions.
Fort Myer received the notice to proceed (NTP) on October 1, 2013, with a contract duration of
365 days.
Construction Items Completed This Week
Continued installation of 2” and 4” concrete encased PVC conduit and installation of
traffic signal foundations and bases at 17th St., NW and Connecticut Ave., NW
Continued reconstruction of accessible ramps at the SW and SE corners at 21st St., NW.
Began reconstruction of accessible ramps at the SW corner and median at 18th St., NW.
Installed various poles, fixtures and streetlights at Vermont Ave., NW, 15th St., NW, 14th
St., NW and 21st St., NW.
Upcoming Construction Activities
Continue reconstruction of accessible ramps at 18th St., NW.
Began reconstruction of accessible ramps at 14th St., NW.
Continue installation of inlets and connect pipes at 17th St., NW and begin installation at
14th St., NW
Continue to install various poles, fixtures and streetlights and work with DDOT
technicians to deactivate/activate new traffic and pedestrian signals.
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 3 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 3 of 10
STATUS OF PROJECT SCHEDULE
Notice to Proceed Date 10/01/13
Original Contract Completion Date 09/30/14
Contract Duration (calendar days) 365
Contract Days Expended*
328
Contract Days Expended* (%)
90%
*figures are based on status as of August 24, 2014
STATUS OF CONSTRUCTION – PROGRESS SUMMARY
Intersection Ramp
Location
Curb
Ramp
Status
Comments/Issues
21st St., NW
NWC New Issue: FMCC discovered that
one cable was feeding signals at NW
corner and median as opposed to
separate lines for each signal.
Additional cable will need to be run.
Solutions are in review with DDOT
TOA.
Crews installed accessible ramps at the
SEC and SWC.
NEC Complete
SEC Complete
SWC Complete
20th St., NW
NWC Open Issue: Possible conduit
capacity issues at TC cabinet.
All poles and fixtures installed –
cannot be activated due to open issue
NEC
NEM
SEC
SWC
SWM
19th St., NW
NWC Complete Open Issue: Conduit space between
TC and P15.
NEC
NEM Complete
SEC Complete
SWC Complete
SEM
18th St., NW
NWC
NEC
NEM
SEC
SWC
SEM
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 4 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 4 of 10
Intersection Ramp
Location
Curb
Ramp
Status
Comments/Issues
Connecticut Ave.,
NW
NWC An updated narrative will distributed
by KCI noting the changes occurring
at this intersection.
Open Issue: NPS permit – cannot
work at SE corner
Open Issue: Possible conduit
capacity issues at TC cabinet
Open Issue: Snow Melting coils
located directly beneath pavers at
SW corner.
Crews began to excavate for
installation of conduit at the NEM.
NEC
NEM
SEC
SWC
SEM
17th St., NW
NWC Open Issue: NPS permit – cannot
work at SW corner
Open Issue: Possible conduit
capacity issues at TC cabinet.
NEC
SEC
SWC
6th St., NW
NWC Catch Basins at the NW and SW
median will be relocated in order to
install the TS foundations at the
appropriate location.
A narrower curb will be installed at the
SE median
DDOT advised a 28’-6” pole be
installed in lieu of a #18 pole. FMCC
to remove #18 pole and round
foundation
Installation of inlets and connect pipe
continued at the SW corner.
Open Issue: Possible conduit
capacity issues at TC cabinet.
On 7/30/14, I-7-1 was placed using
incorrect concrete mix (see Def. Rpt
#26). Structure must be removed and
replaced at no cost to the District.
NEC
SEM
SEC
SWC
SWM
NWM
15th St., NW
NWC Shallow building foundation at the SW
corner. Contractor installing structures
and ramps per drawings.
Open Issue: NPS permit – cannot
work at SE corner
NEC
SEC
SWC
SEM
NWM
Vermont Ave., NW NWC
NEC
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 5 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 5 of 10
Intersection Ramp
Location
Curb
Ramp
Status
Comments/Issues
SEC Open Issue: NPS permit – cannot
work at SW corner
Open Issue: Possible conduit
capacity issues at TC cabinet
Double Telephone vault at NE corner.
DDOT to advise on how to proceed
with ramp installation/layout
UFA approved tree pruning per letter
SWC
14th St., NW
NWC Open Issue: NPS permit – cannot
work at SE corner
Signal outage occurred on 8/8/14 while
DDOT technician was onsite working
in TC cabinet. DDOT flaggers were
onsite to direct traffic while issue was
resolved.
NEC
SEC
SWC
SWM
NWM
13th St., NW
NWC Complete Open Issue: NPS permit – cannot
work at SW corner
Installation of ADA compliant ramps
are complete (minus Open Issue
location noted above)
DDOT had expressed the desire to
remove/replace the curb ramps at the
SE corner
NEC Complete
NEM Complete
SEM Complete
SEC Complete
SWC
NWC Complete
12th St., NW
NWC Complete Open Issue: P05 cracked wall.
PEPCO crews onsite and saw cut limits
of excavation for their work.
NEC Complete
SEC
SWC Complete
Total
Complete 16 of 66 (24%)
ACCIDENTS/INCIDENTS/PUBLIC COMMENTS
Public Comments
No public comments were recorded during this period.
Accidents/Incidents
No accidents or incidents recorded during this period.
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 6 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 6 of 10
PHOTOGRAPHS
Connecticut Ave. – Crews installing 2” and 4” PVC conduit at the NE median
14th St. NW – Crews saw cutting in preparation for upcoming construction activities.
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 7 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 7 of 10
18th St., NW – Crews beginning to demolish the existing sidewalk in prepartion for new
accessible and compliant walkways
Connecticut Ave., NW – Crews installing new Streetlight pole at the NE median
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 8 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 8 of 10
21st St., NW – Crews cleaning up after installing new concrete pavers at the NE corner
18th St., NW – Crews installing concrete for ramps and PCC base at the SW corner
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 9 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 9 of 10
17th St., NW – Crews install connect pipe at the SE corner
21st St., NW – Clear Channel Outdoor crews arrive to remove the existing bus shelter.
Construction Manager Weekly Report
From 08/18/2014 to 08/24//2014
Page 10 of 10
DDOT K Street ADA Improvements – Weekly Summary Report Page 10 of 10
21st St. NW – Crews work to install pavers to compliant grades at the NE corner
18th St., NW – Crews work to install pavers to compliant grades at the SW corner