construction manager’s weekly progress reportdashboard.ddot.dc.gov/dtapdoc/document/99_65860_47 cm...

10
Field Office 1411 K Street, NW Suite 225 Washington, DC 20006 Phone: (202) 347-7733 K STREET NW FROM 12 TH STREET TO 21 ST STREET ADA IMPROVEMENTS Contract No.: DCKA-2012-C-0058 FAP No.: STP-1102(030) CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORT 08/18/2014 08/24/2014 Project Website: www.kstreetadaimprovements1221.com 08/19/14 Contractor works to install new block paver sidewalk to provide an accessible, compliant path at the SE corner of 21 st St., NW

Upload: others

Post on 26-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Field Office

1411 K Street, NW

Suite 225

Washington, DC 20006

Phone: (202) 347-7733

K STREET NW FROM 12TH STREET TO 21ST STREET

ADA IMPROVEMENTS

Contract No.: DCKA-2012-C-0058

FAP No.: STP-1102(030)

CONSTRUCTION MANAGER’S

WEEKLY PROGRESS REPORT

08/18/2014 – 08/24/2014

Project Website: www.kstreetadaimprovements1221.com

08/19/14 –Contractor works to install new block paver sidewalk to

provide an accessible, compliant path at the SE corner of 21st St., NW

Page 2: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 2 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 2 of 10

EXECUTIVE SUMMARY

Work under this contract consists of the construction of pedestrian facilities in compliance with

the 2010 Americans with Disabilities Act (ADA) Standards. These improvements are located at

signalized intersections and bus stops along K Street NW from the 12th Street intersection to the

21st Street intersection. The project involves reconstruction of pedestrian ramps at the signalized

intersections, addition of accessible pedestrian signals and pushbuttons at each roadway crossing,

removal, reconstruction of existing bus stops and the respective accessible pathways to the bus

stops, and removal/installation of multiple storm drains within the study limits as shown on

project plans and indicated in specifications and special provisions.

Fort Myer received the notice to proceed (NTP) on October 1, 2013, with a contract duration of

365 days.

Construction Items Completed This Week

Continued installation of 2” and 4” concrete encased PVC conduit and installation of

traffic signal foundations and bases at 17th St., NW and Connecticut Ave., NW

Continued reconstruction of accessible ramps at the SW and SE corners at 21st St., NW.

Began reconstruction of accessible ramps at the SW corner and median at 18th St., NW.

Installed various poles, fixtures and streetlights at Vermont Ave., NW, 15th St., NW, 14th

St., NW and 21st St., NW.

Upcoming Construction Activities

Continue reconstruction of accessible ramps at 18th St., NW.

Began reconstruction of accessible ramps at 14th St., NW.

Continue installation of inlets and connect pipes at 17th St., NW and begin installation at

14th St., NW

Continue to install various poles, fixtures and streetlights and work with DDOT

technicians to deactivate/activate new traffic and pedestrian signals.

Page 3: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 3 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 3 of 10

STATUS OF PROJECT SCHEDULE

Notice to Proceed Date 10/01/13

Original Contract Completion Date 09/30/14

Contract Duration (calendar days) 365

Contract Days Expended*

328

Contract Days Expended* (%)

90%

*figures are based on status as of August 24, 2014

STATUS OF CONSTRUCTION – PROGRESS SUMMARY

Intersection Ramp

Location

Curb

Ramp

Status

Comments/Issues

21st St., NW

NWC New Issue: FMCC discovered that

one cable was feeding signals at NW

corner and median as opposed to

separate lines for each signal.

Additional cable will need to be run.

Solutions are in review with DDOT

TOA.

Crews installed accessible ramps at the

SEC and SWC.

NEC Complete

SEC Complete

SWC Complete

20th St., NW

NWC Open Issue: Possible conduit

capacity issues at TC cabinet.

All poles and fixtures installed –

cannot be activated due to open issue

NEC

NEM

SEC

SWC

SWM

19th St., NW

NWC Complete Open Issue: Conduit space between

TC and P15.

NEC

NEM Complete

SEC Complete

SWC Complete

SEM

18th St., NW

NWC

NEC

NEM

SEC

SWC

SEM

Page 4: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 4 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 4 of 10

Intersection Ramp

Location

Curb

Ramp

Status

Comments/Issues

Connecticut Ave.,

NW

NWC An updated narrative will distributed

by KCI noting the changes occurring

at this intersection.

Open Issue: NPS permit – cannot

work at SE corner

Open Issue: Possible conduit

capacity issues at TC cabinet

Open Issue: Snow Melting coils

located directly beneath pavers at

SW corner.

Crews began to excavate for

installation of conduit at the NEM.

NEC

NEM

SEC

SWC

SEM

17th St., NW

NWC Open Issue: NPS permit – cannot

work at SW corner

Open Issue: Possible conduit

capacity issues at TC cabinet.

NEC

SEC

SWC

6th St., NW

NWC Catch Basins at the NW and SW

median will be relocated in order to

install the TS foundations at the

appropriate location.

A narrower curb will be installed at the

SE median

DDOT advised a 28’-6” pole be

installed in lieu of a #18 pole. FMCC

to remove #18 pole and round

foundation

Installation of inlets and connect pipe

continued at the SW corner.

Open Issue: Possible conduit

capacity issues at TC cabinet.

On 7/30/14, I-7-1 was placed using

incorrect concrete mix (see Def. Rpt

#26). Structure must be removed and

replaced at no cost to the District.

NEC

SEM

SEC

SWC

SWM

NWM

15th St., NW

NWC Shallow building foundation at the SW

corner. Contractor installing structures

and ramps per drawings.

Open Issue: NPS permit – cannot

work at SE corner

NEC

SEC

SWC

SEM

NWM

Vermont Ave., NW NWC

NEC

Page 5: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 5 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 5 of 10

Intersection Ramp

Location

Curb

Ramp

Status

Comments/Issues

SEC Open Issue: NPS permit – cannot

work at SW corner

Open Issue: Possible conduit

capacity issues at TC cabinet

Double Telephone vault at NE corner.

DDOT to advise on how to proceed

with ramp installation/layout

UFA approved tree pruning per letter

SWC

14th St., NW

NWC Open Issue: NPS permit – cannot

work at SE corner

Signal outage occurred on 8/8/14 while

DDOT technician was onsite working

in TC cabinet. DDOT flaggers were

onsite to direct traffic while issue was

resolved.

NEC

SEC

SWC

SWM

NWM

13th St., NW

NWC Complete Open Issue: NPS permit – cannot

work at SW corner

Installation of ADA compliant ramps

are complete (minus Open Issue

location noted above)

DDOT had expressed the desire to

remove/replace the curb ramps at the

SE corner

NEC Complete

NEM Complete

SEM Complete

SEC Complete

SWC

NWC Complete

12th St., NW

NWC Complete Open Issue: P05 cracked wall.

PEPCO crews onsite and saw cut limits

of excavation for their work.

NEC Complete

SEC

SWC Complete

Total

Complete 16 of 66 (24%)

ACCIDENTS/INCIDENTS/PUBLIC COMMENTS

Public Comments

No public comments were recorded during this period.

Accidents/Incidents

No accidents or incidents recorded during this period.

Page 6: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 6 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 6 of 10

PHOTOGRAPHS

Connecticut Ave. – Crews installing 2” and 4” PVC conduit at the NE median

14th St. NW – Crews saw cutting in preparation for upcoming construction activities.

Page 7: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 7 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 7 of 10

18th St., NW – Crews beginning to demolish the existing sidewalk in prepartion for new

accessible and compliant walkways

Connecticut Ave., NW – Crews installing new Streetlight pole at the NE median

Page 8: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 8 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 8 of 10

21st St., NW – Crews cleaning up after installing new concrete pavers at the NE corner

18th St., NW – Crews installing concrete for ramps and PCC base at the SW corner

Page 9: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 9 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 9 of 10

17th St., NW – Crews install connect pipe at the SE corner

21st St., NW – Clear Channel Outdoor crews arrive to remove the existing bus shelter.

Page 10: CONSTRUCTION MANAGER’S WEEKLY PROGRESS REPORTdashboard.ddot.dc.gov/DTAPDOC/document/99_65860_47 CM WR W… · Construction Manager Weekly Report From 08/18/2014 to 08/24//2014 Page

Construction Manager Weekly Report

From 08/18/2014 to 08/24//2014

Page 10 of 10

DDOT K Street ADA Improvements – Weekly Summary Report Page 10 of 10

21st St. NW – Crews work to install pavers to compliant grades at the NE corner

18th St., NW – Crews work to install pavers to compliant grades at the SW corner