welcome! please sign in on your mobile device: http ... · construction update and milestones:...
TRANSCRIPT
Orange County Public Schools
1
SITE 207-E-W-7 New Maxey Elementary School40% Construction Community Meeting
January 22, 2018
Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris
Welcome! Please sign in
on your mobile device:
http://communitymeeting.ocps.net/
Orange County Public Schools
2
SITE 207-E-W-7 New Maxey Elementary School Meeting AgendaJanuary 22nd, 2018: Maxey Elementary School Cafeteria, 6:00 – 7:00PM
•Welcome – School Board Member: Christine Moore
•Introductions – Facilities Meeting Organizer
•Project Update – Architect:
Contractor:
•Questions and Answers
•Adjournment
Orange County Public Schools
3
Orlando International Airport
Lake Nona
Laureate Park
Eagle Creek
Nemours
North
Surrounding Context
Dillard Elementary
North
New Maxey
ES Site
Hungerford Lake
Existing Maxey ES
Downtown Winter Garden
Elk’s Lodge
Orange TechnicalCollege –Westside Campus
Maple Street
Dill
ard
Str
eet
S.R
. 429
Highway 50
9th
Str
eet
Orange County Public Schools
4
School Site
North
Wetland
Site Aerial Map
North
Orange County Public Schools
5
North
Site Plan
Parking (131 Spaces)
Elk’s Lodge
Dry Retention(1.5 ac.)
STORY ROAD
north
0’ 100’
2 STORY650 STUDENT ELEMENTARY
SCHOOLTot
Youth
CEP
FRONT DOOR
Service
Basketball Courts
Playfield Area
(+/-45,000 SF)
Right out only
9TH
STR
EET
Dry Retention(.5 ac.)
Data650 student stations
81,440 square feet
131 parking spaces116 car stacking (18%)
Planned for 5 Buses
security cameras
FENCE LINE
BikeRack
Future Expansion
BikeRack
Orange County Public Schools
6View looking towards entry
Orange County Public Schools
7View looking towards parent pick-up / drop off
Orange County Public Schools
8View looking towards covered play
Orange County Public Schools
9Logistics Map
Orange County Public Schools
10
Construction Update and Milestones:
Notice to Proceed (NTP) was July 17, 2017.
Tilt wall panels were completed on November 7, 2017.
Structural Steel Erection started on November 6, 2017 and was completed on
December 8, 2017.
Roofing work started December 11th, 2017 and will be completed early-January.
Windows install to start early-February and be completed by late February.
Interior work is in progress with framing of interior walls, and install of MEP in
wall and above ceiling rough in.
Project is 40% complete.
Project remains on schedule for Substantial Completion on May 20, 2018.
Orange County Public Schools
11Aerial Photo – Late July 2017
Orange County Public Schools
12Aerial Photo – Late August 2017
Orange County Public Schools
13Aerial Photo – Late September 2017
Orange County Public Schools
14Aerial Photo – Late October 2017
Orange County Public Schools
15Aerial Photo – Late November 2016
Orange County Public Schools
16Aerial Photo – Late December 2017
Orange County Public Schools
17
Slab Pour Tilt Panel Reinforcing
Orange County Public Schools
18
Tilt Wall Panel Pour Tilt Wall Panels Being Lifted
Orange County Public Schools
19
Set Tilt Wall Panels Interior Elevation
Orange County Public Schools
20
Setting Structural Steel Structural Steel
Orange County Public Schools
21
Steel Decking Steel Decking
Orange County Public Schools
22
Questions and Answers