  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    MilestonesMilestones 359 01-Dec-14 A 01-Mar-16 0

    M1000 Contract Award 0 01-Dec-14 A

    M1035 Site & Earthwork Start 0 07-Jan-15 A

    M1025 Concrete Footings Start 0 06-May-15 22

    M1040 Stadium Enclosure Start 0 23-Jun-15 62

    M1070 Steel Erection Start 0 20-Jul-15 15

    M1055 Steel Erection Complete 0 01-Oct-15 10

    M1080 Exterior Cladding Complete 0 25-Nov-15 56

    M1050 Permanent Power 0 07-Dec-15 56

    M1060 Dry-in up to Suite Level 0 08-Dec-15 61

    M1140 Playing Field Start 0 23-Dec-15 53

    M1100 Interior Finishes Complete 0 28-Jan-16 20

    M1045 TAB & Cx Start 0 29-Jan-16 24

    M1110 INT & EXT FF&E Complete 0 02-Feb-16 21

    M1090 Playing Field Sod Start 0 08-Feb-16 17

    M1120 Contract Completion Date 0 01-Mar-16 0

    Design & EngineeringDesign & Engineering 0 08-Dec-14 A 31-Mar-15 A

    DE100 Sitework Package 0 08-Dec-14 A

    DE110 Final Construction Docs 0 27-Feb-15 A

    DE130 Addendum #1 Civ, Struc, Arch, MEP Revisions0 13-Mar-15 A

    DE140 Addendum #2 Civ, Struc, Arch, MEP Revisions0 20-Mar-15 A

    DE150 Addendum #3 Wall Sections 0 30-Mar-15 A

    DE160 Addendum #4 Add window types 0 31-Mar-15 A

    ProcurementProcurement 212 08-Dec-14 A 09-Sep-15 122

    Bid & AwardBid & Award 102 08-Dec-14 A 22-Apr-15 9

    BA1030 Sitework Bid & Award 5 08-Dec-14 A 12-Dec-14 A

    BA1050 Concrete & Rebar 26 02-Mar-15 A 07-Apr-15 6

    BA1060 Structural Steel & Misc Metals 26 02-Mar-15 A 07-Apr-15 -1

    BA1070 Waterproofing & Sealants 26 02-Mar-15 A 13-Apr-15 14

    BA1080 Framing 26 02-Mar-15 A 13-Apr-15 14

    BA1090 Roofing & Sheet metal 26 02-Mar-15 A 13-Apr-15 14

    BA1100 Masonry, Precast, Stone 26 02-Mar-15 A 13-Apr-15 14

    BA1110 Mechanical 26 02-Mar-15 A 13-Apr-15 14

    BA1120 Electrical 26 02-Mar-15 A 13-Apr-15 11

    BA1130 Plumbing 26 02-Mar-15 A 13-Apr-15 11

    BA1140 Fire Sprinklers 26 02-Mar-15 A 13-Apr-15 11

    BA1150 Doors, Frames, & Hardware 26 02-Mar-15 A 13-Apr-15 14

    BA1160 Glass & Storefronts 26 02-Mar-15 A 13-Apr-15 14

    BA1170 GWB & Ceilings 26 02-Mar-15 A 13-Apr-15 14

    BA1180 Interior Finishes - Walls & Floors 26 02-Mar-15 A 13-Apr-15 14

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    01-Mar-16, Milestones

    Contract Award

    Site & Earthwork Start

    Concrete Footings Start

    Stadium Enclosure Start

    Steel Erection Start

    Steel Erection Complete

    Exterior Cladding Complete

    Permanent Power

    Dry-in up to Suite Level

    Playing Field Start

    Interior Finishes Complete

    TAB & Cx Start

    INT & EXT FF&E Complete

    Playing Field Sod Start

    Contract Completion Date

    31-Mar-15 A, Design & Engineering

    Sitework Package

    Final Construction Docs

    Addendum #1 Civ, Struc, Arch, MEP Revisions

    Addendum #2 Civ, Struc, Arch, MEP Revisions

    Addendum #3 Wall Sections

    Addendum #4 Add window types

    09-Sep-15, Procurement

    22-Apr-15, Bid & Award

    Sitework Bid & Award

    Concrete & Rebar

    Structural Steel & Misc Metals

    Waterproofing & Sealants

    Framing

    Roofing & Sheet metal

    Masonry, Precast, Stone

    Mechanical

    Electrical

    Plumbing

    Fire Sprinklers

    Doors, Frames, & Hardware

    Glass & Storefronts

    GWB & Ceilings

    Interior Finishes - Walls & Floors

    Spirit Communications Park

    22-Apr-15 15:28

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 1 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

    Appendix A

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    BA1190 Millwork 26 02-Mar-15 A 13-Apr-15 14

    BA1200 Exterior FF&E 26 02-Mar-15 A 13-Apr-15 14

    BA1210 Interior FF&E 26 02-Mar-15 A 13-Apr-15 14

    BA1220 Sports Field & Landscape 26 02-Mar-15 A 13-Apr-15 14

    BA1230 Sports Equipment 26 02-Mar-15 A 13-Apr-15 14

    BA1960 Elevator 26 02-Mar-15 A 13-Apr-15 9

    BA1970 Kitchen / Concessions Equipment 26 02-Mar-15 A 13-Apr-15 14

    BA1240 Railings 26 02-Mar-15 A 13-Apr-15 14

    BA1250 OH Roll up Doors 26 02-Mar-15 A 13-Apr-15 9

    BA1520 GMP Approval 2 21-Apr-15* 22-Apr-15 3

    Submittal Prep, Review, ApproveSubmittal Prep, Review, Approve 52 06-Apr-15 A 17-Jun-15 122

    S1260 Structural Steel & Misc Metals 30 06-Apr-15 A 01-Jun-15 0

    S1250 Concrete & Rebar 15 07-Apr-15 A 06-May-15 6

    S1270 Site Utilities 10 22-Apr-15 06-May-15 18

    S1280 Waterproofing & Sealants 10 22-Apr-15 06-May-15 40

    S1290 Framing 15 22-Apr-15 13-May-15 69

    S1300 Roofing & Sheet metal 15 22-Apr-15 13-May-15 89

    S1310 Masonry, Precast, Stone 15 22-Apr-15 13-May-15 18

    S1320 Mechanical 15 22-Apr-15 13-May-15 50

    S1330 Electrical 15 22-Apr-15 13-May-15 3

    S1340 Plumbing 15 22-Apr-15 13-May-15 3

    S1350 Fire Sprinklers 15 22-Apr-15 13-May-15 3

    S1360 Doors, Frames, & Hardware 30 22-Apr-15 03-Jun-15 14

    S1370 Glass & Storefronts 30 22-Apr-15 03-Jun-15 55

    S1380 GWB & Ceiling 30 22-Apr-15 03-Jun-15 43

    S1390 Interior Finishes - Walls & Floors 30 22-Apr-15 03-Jun-15 78

    S1400 Millwork 30 22-Apr-15 03-Jun-15 91

    S1410 Exterior FF&E 30 22-Apr-15 03-Jun-15 89

    S1420 Interior FF&E 30 22-Apr-15 03-Jun-15 115

    S1430 Sports Field & Landcape 30 22-Apr-15 03-Jun-15 78

    S1440 Sports Equipment 30 22-Apr-15 03-Jun-15 106

    S1450 Elevator 5 22-Apr-15 29-Apr-15 10

    S1460 Kitchen / Concessions Equipment 40 22-Apr-15 17-Jun-15 29

    S1470 Railings 40 22-Apr-15 17-Jun-15 96

    S1480 OH Roll up Doors 40 22-Apr-15 17-Jun-15 111

    S1770 Sports Equipment 40 22-Apr-15 17-Jun-15 96

    Fabrication & DeliveryFabrication & Delivery 123 07-Apr-15 09-Sep-15 122

    FD1570 Concrete & Rebar 30 07-Apr-15 14-May-15 6

    FD1780 Elevator 5 29-Apr-15 06-May-15 10

    FD1600 Site Utilities 10 06-May-15 20-May-15 18

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Millwork

    Exterior FF&E

    Interior FF&E

    Sports Field & Landscape

    Sports Equipment

    Elevator

    Kitchen / Concessions Equipment

    Railings

    OH Roll up Doors

    GMP Approval

    17-Jun-15, Submittal Prep, Review, Approve

    Structural Steel & Misc Metals

    Concrete & Rebar

    Site Utilities

    Waterproofing & Sealants

    Framing

    Roofing & Sheet metal

    Masonry, Precast, Stone

    Mechanical

    Electrical

    Plumbing

    Fire Sprinklers

    Doors, Frames, & Hardware

    Glass & Storefronts

    GWB & Ceiling

    Interior Finishes - Walls & Floors

    Millwork

    Exterior FF&E

    Interior FF&E

    Sports Field & Landcape

    Sports Equipment

    Elevator

    Kitchen / Concessions Equipment

    Railings

    OH Roll up Doors

    Sports Equipment

    09-Sep-15, Fabrication & Delivery

    Concrete & Rebar

    Elevator

    Site Utilities

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 2 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    FD1610 Waterproofing & Sealants 5 06-May-15 13-May-15 40

    FD1620 Framing 20 13-May-15 10-Jun-15 69

    FD1630 Roofing & Sheet metal 20 13-May-15 10-Jun-15 89

    FD1640 Masonry, Precast, Stone 20 13-May-15 10-Jun-15 18

    FD1650 Mechanical 20 13-May-15 10-Jun-15 84

    FD1660 Electrical 20 13-May-15 10-Jun-15 3

    FD1670 Plumbing 20 13-May-15 10-Jun-15 3

    FD1680 Fire Sprinklers 20 13-May-15 10-Jun-15 3

    FD1820 Structural Steel 38 01-Jun-15 20-Jul-15 0

    FD1690 Doors, Frames, & Hardware 60 03-Jun-15 26-Aug-15 14

    FD1700 Glass & Storefronts 60 03-Jun-15 26-Aug-15 55

    FD1710 GWB & Ceiling 60 03-Jun-15 26-Aug-15 43

    FD1720 Interior Finishes - Walls & Floors 60 03-Jun-15 26-Aug-15 78

    FD1730 Millwork 60 03-Jun-15 26-Aug-15 91

    FD1740 Exterior FF&E 60 03-Jun-15 26-Aug-15 108

    FD1750 Interior FF&E 60 03-Jun-15 26-Aug-15 115

    FD1760 Sports Field & Landcape 60 03-Jun-15 26-Aug-15 78

    FD1770 Sports Equipment 60 17-Jun-15 09-Sep-15 96

    FD1790 Kitchen / Concessions Equipment 60 17-Jun-15 09-Sep-15 29

    FD1800 Railings 60 17-Jun-15 09-Sep-15 96

    FD1810 OH Roll up Doors 60 17-Jun-15 09-Sep-15 111

    SiteworkSitework 77 05-Jan-15 A 16-Apr-15 22

    A1500 Site Conctractor Mobilization 2 05-Jan-15 A 06-Jan-15 A

    A1450 Clearing 9 07-Jan-15 A 16-Jan-15 A

    A1460 Abatement 12 07-Jan-15 A 21-Jan-15 A

    A1490 Grading 25 19-Jan-15 A 01-Apr-15 A

    A1470 Demolition 10 22-Jan-15 A 04-Feb-15 A

    A1530 French Drain System 5 26-Jan-15 A 28-Jan-15 A

    A1480 Dewatering 30 28-Jan-15 A 27-Mar-15 A

    A1510 Field Drainage System 5 26-Mar-15 A 16-Apr-15 22

    A1520 Ground Water Drainage System 10 06-Apr-15 A 13-Apr-15 22

    Field Level 3B CL17 to CL0Field Level 3B CL17 to CL0 189 06-May-15 01-Jan-16 46

    A1550 FTG CL14 - 0 3B field level 15 06-May-15 26-May-15 6

    A1560 FND Walls, Columns, & DO Tunnel CL 14 - 0 3B field level20 19-May-15 16-Jun-15 11

    A3190 Dugout FTGs & Walls - 3B field level10 02-Jun-15 15-Jun-15 19

    A1580 UG MEP / Drainage - 3B field level 10 10-Jun-15 24-Jun-15 30

    A1610 Waterproofing FND walls - 3B field level3 23-Jun-15 26-Jun-15 11

    A1620 SOG - 3B field level 7 24-Jun-15 03-Jul-15 30

    A3090 Backfill FDN walls - 3B field level 3 29-Jun-15 01-Jul-15 12

    A1650 Pan Deck Above Field Level - 3B 15 03-Jul-15 24-Jul-15 30

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Waterproofing & Sealants

    Framing

    Roofing & Sheet metal

    Masonry, Precast, Stone

    Mechanical

    Electrical

    Plumbing

    Fire Sprinklers

    Structural Steel

    Doors, Frames, & Hardware

    Glass & Storefronts

    GWB & Ceiling

    Interior Finishes - Walls & Floors

    Millwork

    Exterior FF&E

    Interior FF&E

    Sports Field & Landcape

    Sports Equipment

    Kitchen / Concessions Equipment

    Railings

    OH Roll up Doors

    16-Apr-15, Sitework

    Site Conctractor Mobilization

    Clearing

    Abatement

    Grading

    Demolition

    French Drain System

    Dewatering

    Field Drainage System

    Ground Water Drainage System

    01-Jan-16, Field Level 3B CL17 to CL0

    FTG CL14 - 0 3B field level

    FND Walls, Columns, & DO Tunnel CL 14 - 0 3B field level

    Dugout FTGs & Walls - 3B field level

    UG MEP / Drainage - 3B field level

    Waterproofing FND walls - 3B field level

    SOG - 3B field level

    Backfill FDN walls - 3B field level

    Pan Deck Above Field Level - 3B

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 3 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A3230 CMU Stair & Elevator shafts -3B 15 24-Jul-15 13-Aug-15 33

    A2450 INT Stud Framing - 3B field level 5 17-Sep-15 24-Sep-15 10

    A2460 MEP R/I Walls - 3B field level 5 24-Sep-15 01-Oct-15 10

    A3100 MEP R/I Overhead - 3B field level 10 01-Oct-15 14-Oct-15 10

    A4540 Elec Rm F/P Eqpmnt pads - 3B field level5 02-Oct-15 09-Oct-15 75

    A4550 Elec RM Set switchgear/panels/transfrmers - 3B field level5 09-Oct-15 15-Oct-15 75

    A2580 GWB Hang - 3B field level 10 14-Oct-15 27-Oct-15 10

    A2600 GWB Finish - 3B field level 10 20-Oct-15 02-Nov-15 46

    A4560 Elec Rm Conduit - 3B Field level 10 20-Oct-15 02-Nov-15 72

    A1940 Prime & First Coat Paint Walls - 3B field level10 02-Nov-15 13-Nov-15 46

    A2010 Ceramic Tile / Epoxy Coat - 3B field level10 02-Nov-15 13-Nov-15 46

    A4570 Elec Rms Feeders/Terminations - 3B field level10 02-Nov-15 13-Nov-15 72

    A2000 Flooring - 3B field level 15 13-Nov-15 03-Dec-15 46

    A2120 Laundry Equipment 10 13-Nov-15 26-Nov-15 74

    A2230 Fire Ext. Cabinets - 3B field level 1 13-Nov-15 16-Nov-15 66

    A3130 Trash compactor 5 13-Nov-15 20-Nov-15 79

    A3110 Batting Tunnel Equipment 10 13-Nov-15 26-Nov-15 74

    A4580 Elec Rms Permanent Power Insp - 3B fiield level1 13-Nov-15 16-Nov-15 72

    A4590 Elec Rms Permanent Power - 3B field level1 16-Nov-15 17-Nov-15 72

    A1910 Ceiling Grid - 3B field level 10 17-Nov-15 30-Nov-15 53

    A1990 Millwork & Trim - 3B field level 16 20-Nov-15 10-Dec-15 46

    A1920 Ceiling Tiles - 3B field level 14 30-Nov-15 17-Dec-15 53

    A1980 A/V Equipment - 3B field level 15 30-Nov-15 18-Dec-15 57

    A2690 Install Interior Doors - 3B field level 8 03-Dec-15 14-Dec-15 58

    A2530 MEP Trim Out - 3B field level 8 07-Dec-15 16-Dec-15 49

    A2350 Countertops - 3B field level 5 10-Dec-15 16-Dec-15 49

    A2020 Final coat paint - 3B field level 10 10-Dec-15 24-Dec-15 46

    A2200 Toilet Partitions & Accesories - 3B field level5 16-Dec-15 23-Dec-15 49

    A2070 Signage & Graphics - 3B field level 2 24-Dec-15 25-Dec-15 46

    A2220 Lockers 2 24-Dec-15 25-Dec-15 51

    A2240 Wall & Door Protection - 3B field level1 24-Dec-15 24-Dec-15 47

    A1860 Final Clean - 3B field level 5 25-Dec-15 01-Jan-16 46

    Concourse Level 1B CL17 to CL31Concourse Level 1B CL17 to CL31 181 19-May-15 05-Jan-16 44

    A1570 FTG CL14 - 30 1B 15 19-May-15 08-Jun-15 6

    A1575 Install Strip Ftgs 1B CL 28 - 30 10 26-May-15 08-Jun-15 6

    A2080 Installl Perimeter Block CL 28 - 30 15 08-Jun-15 26-Jun-15 6

    A2370 UG MEP R/I 1st Base CL C - D.5 5 10-Jun-15 17-Jun-15 3

    A2360 SOG 1B Concourse CL C - D.5 5 17-Jun-15 23-Jun-15 3

    A1690 Interior CMU & Stair tower 1B 10 23-Jun-15 06-Jul-15 3

    A1630 Erect steel and deck CL 14 - 30 20 20-Jul-15 13-Aug-15 0

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    CMU Stair & Elevator shafts -3B

    INT Stud Framing - 3B field level

    MEP R/I Walls - 3B field level

    MEP R/I Overhead - 3B field level

    Elec Rm F/P Eqpmnt pads - 3B field level

    Elec RM Set switchgear/panels/transfrmers - 3B field level

    GWB Hang - 3B field level

    GWB Finish - 3B field level

    Elec Rm Conduit - 3B Field level

    Prime & First Coat Paint Walls - 3B field level

    Ceramic Tile / Epoxy Coat - 3B field level

    Elec Rms Feeders/Terminations - 3B field level

    Flooring - 3B field level

    Laundry Equipment

    Fire Ext. Cabinets - 3B field level

    Trash compactor

    Batting Tunnel Equipment

    Elec Rms Permanent Power Insp - 3B fiield level

    Elec Rms Permanent Power - 3B field level

    Ceiling Grid - 3B field level

    Millwork & Trim - 3B field level

    Ceiling Tiles - 3B field level

    A/V Equipment - 3B field level

    Install Interior Doors - 3B field level

    MEP Trim Out - 3B field level

    Countertops - 3B field level

    Final coat paint - 3B field level

    Toilet Partitions & Accesories - 3B field level

    Signage & Graphics - 3B field level

    Lockers

    Wall & Door Protection - 3B field level

    Final Clean - 3B field level

    05-Jan-16, Concourse Level 1B CL17 to CL31

    FTG CL14 - 30 1B

    Install Strip Ftgs 1B CL 28 - 30

    Installl Perimeter Block CL 28 - 30

    UG MEP R/I 1st Base CL C - D.5

    SOG 1B Concourse CL C - D.5

    Interior CMU & Stair tower 1B

    Erect steel and deck CL 14 - 30

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 4 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A1740 Install Stairs - 1B 5 13-Aug-15 20-Aug-15 38

    A3760 Roof Curbs Kitchen Equipment - 1B 5 13-Aug-15 20-Aug-15 64

    A1880 Install Roofing - 1B 10 18-Aug-15 31-Aug-15 66

    A2640 Pour Concrete Pans on Stairs - 1B 3 20-Aug-15 25-Aug-15 87

    A1700 EXT studs & sheathing - 1B 15 26-Aug-15 15-Sep-15 16

    A2680 Exterior Doors - 1B 5 31-Aug-15 07-Sep-15 82

    A4600 Elec Rms F/P Eqpmnt pads - 1B 5 07-Sep-15 11-Sep-15 82

    A2510 INT Stud Framing - 1B 10 08-Sep-15 21-Sep-15 37

    A1600 Kitchen Hoods install - 1B 5 09-Sep-15 16-Sep-15 48

    A4610 Elec Rms Set switchgear/panels/transfrmers - 1B10 11-Sep-15 24-Sep-15 82

    A1720 EXT Vapor Barrier - 1B 7 16-Sep-15 24-Sep-15 16

    A1820 Walls MEP R/I - 1B 7 22-Sep-15 30-Sep-15 37

    A2160 Kitchen Equipment overhead R/I - 1B7 22-Sep-15 30-Sep-15 44

    A1810 Install EXT Brick Veneer - 1B 30 22-Sep-15 30-Oct-15 21

    A4620 Elec Rms Conduit - 1B 15 24-Sep-15 14-Oct-15 82

    A1730 Above ceiling MEP R/I - 1B 10 25-Sep-15 08-Oct-15 37

    A1850 Install Windows - 1B 10 12-Oct-15 23-Oct-15 25

    A4630 Elec Rms Feeders/Terminations - 1B15 14-Oct-15 02-Nov-15 82

    A1890 GWB Hang - 1B 10 23-Oct-15 05-Nov-15 25

    A1900 GWB Finish - 1B 15 30-Oct-15 18-Nov-15 25

    A2380 Install Stucco - 1B 15 30-Oct-15 18-Nov-15 66

    A2660 Storefronts - 1B 5 30-Oct-15 05-Nov-15 86

    A4640 Elec Rms Permanent Power Insp - 1B1 02-Nov-15 03-Nov-15 82

    A4650 Elec Rms Permanent Power - 1B 1 03-Nov-15 04-Nov-15 82

    A2650 Ceramic Tile / Epoxy Coat - 1B 10 05-Nov-15 18-Nov-15 30

    A2670 Prime & 1st Coat Paint Walls - 1B 10 12-Nov-15 25-Nov-15 25

    A2720 Flooring - 1B 10 25-Nov-15 08-Dec-15 25

    A2730 Fire Ext. Cabinets - 1B 1 25-Nov-15 26-Nov-15 45

    A2710 Ceiling Grid - 1B 10 27-Nov-15 10-Dec-15 44

    A2740 Millwork & Trim - 1B 16 01-Dec-15 22-Dec-15 25

    A4520 Kitchen Equipment install - 1B 15 01-Dec-15 21-Dec-15 51

    A2060 Install Interior Doors -1B 4 08-Dec-15 14-Dec-15 59

    A1950 MEP Trim out - 1B 10 10-Dec-15 23-Dec-15 44

    A2760 Ceiling Tiles - 1B 7 10-Dec-15 18-Dec-15 54

    A2750 A/V Equipment - 1B 15 10-Dec-15 29-Dec-15 44

    A2770 Countertops - 1B 3 15-Dec-15 17-Dec-15 48

    A2780 Final coat paint - 1B 5 22-Dec-15 28-Dec-15 25

    A2170 Test & Balance HVAC - 1B 3 23-Dec-15 28-Dec-15 51

    A2700 Toilet Partitions & Accesories - 1B 5 23-Dec-15 29-Dec-15 44

    A2790 Signage & Graphics - 1B 2 29-Dec-15 30-Dec-15 48

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Install Stairs - 1B

    Roof Curbs Kitchen Equipment - 1B

    Install Roofing - 1B

    Pour Concrete Pans on Stairs - 1B

    EXT studs & sheathing - 1B

    Exterior Doors - 1B

    Elec Rms F/P Eqpmnt pads - 1B

    INT Stud Framing - 1B

    Kitchen Hoods install - 1B

    Elec Rms Set switchgear/panels/transfrmers - 1B

    EXT Vapor Barrier - 1B

    Walls MEP R/I - 1B

    Kitchen Equipment overhead R/I - 1B

    Install EXT Brick Veneer - 1B

    Elec Rms Conduit - 1B

    Above ceiling MEP R/I - 1B

    Install Windows - 1B

    Elec Rms Feeders/Terminations - 1B

    GWB Hang - 1B

    GWB Finish - 1B

    Install Stucco - 1B

    Storefronts - 1B

    Elec Rms Permanent Power Insp - 1B

    Elec Rms Permanent Power - 1B

    Ceramic Tile / Epoxy Coat - 1B

    Prime & 1st Coat Paint Walls - 1B

    Flooring - 1B

    Fire Ext. Cabinets - 1B

    Ceiling Grid - 1B

    Millwork & Trim - 1B

    Kitchen Equipment install - 1B

    Install Interior Doors -1B

    MEP Trim out - 1B

    Ceiling Tiles - 1B

    A/V Equipment - 1B

    Countertops - 1B

    Final coat paint - 1B

    Test & Balance HVAC - 1B

    Toilet Partitions & Accesories - 1B

    Signage & Graphics - 1B

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 5 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A2810 Wall & Door Protection - 1B 1 29-Dec-15 29-Dec-15 49

    A2820 Window Treatments - 1B 2 29-Dec-15 30-Dec-15 25

    A1590 Final Clean - 1B 5 29-Dec-15 05-Jan-16 44

    Concourse Level 3B CL17 to CL0Concourse Level 3B CL17 to CL0 174 01-Jul-15 08-Feb-16 17

    A1670 FTG CL - B at 3B 10 01-Jul-15 15-Jul-15 11

    A1640 Erect Steel CL 14 - 0 20 07-Aug-15 03-Sep-15 0

    A1710 Erect Steel & Deck CL 1 - 0 / E - B10 04-Sep-15 17-Sep-15 0

    A1070 EXT studs & sheathing - 3B concourse level15 17-Sep-15 07-Oct-15 0

    A2490 Install Stairs - 3B 10 17-Sep-15 01-Oct-15 10

    A4490 Roof Curbs Kitchen Equip. - 3B concourse level3 17-Sep-15 22-Sep-15 18

    A4510 Interior CMU 12 17-Sep-15 02-Oct-15 13

    A1660 Backfill to Concourse level 2 18-Sep-15 21-Sep-15 46

    A2630 Install Roofing - 3B 10 21-Sep-15 02-Oct-15 18

    A1930 SOG Concourse 3rd Base & SOD CL 1-0 / E-B10 22-Sep-15 05-Oct-15 46

    A1800 INT Stud Framing - 3B concourse level10 01-Oct-15 14-Oct-15 0

    A1830 Pour Concrete Pans on Stairs - 3B 2 01-Oct-15 02-Oct-15 85

    A2110 Exterior Doors - 3B 7 02-Oct-15 13-Oct-15 60

    A4500 Kitchen Hoods install - 3B Concourse level5 02-Oct-15 09-Oct-15 13

    A2500 EXT Vapor Barrier - 3B 8 07-Oct-15 16-Oct-15 11

    A4660 Elec Rms F/P Eqpmnt pads - 3B concourse level5 13-Oct-15 19-Oct-15 60

    A2540 MEP R/I walls - 3B concourse level 10 14-Oct-15 27-Oct-15 0

    A2260 Kitchen Equipment overhead R/I - 3B concourse level10 14-Oct-15 27-Oct-15 10

    A2390 Install EXT Brick Veener - 3B 30 16-Oct-15 25-Nov-15 11

    A4670 Elec Rms Set switchgear/panels/transfrmers - 3B concourse level8 19-Oct-15 29-Oct-15 60

    A3140 MEP R/I overhead - 3B concourse level10 27-Oct-15 09-Nov-15 0

    A4680 Elec Rms Conduit - 3B concourse level10 29-Oct-15 11-Nov-15 60

    A2400 Install Windows - 3B 10 05-Nov-15 18-Nov-15 76

    A2610 GWB Hang - 3B concourse level 10 09-Nov-15 20-Nov-15 0

    A4690 Elec Rms Feeders/Terminations - 3B concourse level15 11-Nov-15 30-Nov-15 60

    A3220 GWB Finish - 3B concourse level 15 13-Nov-15 03-Dec-15 0

    A2150 Storefronts - 3B 5 25-Nov-15 01-Dec-15 66

    A2410 Install Stucco - 3B 15 25-Nov-15 14-Dec-15 61

    A4700 Elec Rms Permanent Power Insp - 3B concourse level1 30-Nov-15 01-Dec-15 60

    A4710 Elec Rms Permanent Power - 3B concourse level1 01-Dec-15 02-Dec-15 60

    A2190 Elevator equipment 20 03-Dec-15 29-Dec-15 49

    A3120 Ceramic tile / epoxy coat - 3B concourse level10 03-Dec-15 16-Dec-15 0

    A3180 Prime & First Coat Paint Walls - 3B concourse level7 10-Dec-15 18-Dec-15 0

    A3210 Fire Ext. Cabinets - 3B concourse level1 18-Dec-15 21-Dec-15 24

    A3240 Ceiling Grid - 3B concourse level 7 23-Dec-15 31-Dec-15 0

    A3300 A/V Equipment - 3B concourse level20 31-Dec-15 26-Jan-16 22

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Wall & Door Protection - 1B

    Window Treatments - 1B

    Final Clean - 1B

    08-Feb-16, Concourse Level 3B CL17 to CL0

    FTG CL - B at 3B

    Erect Steel CL 14 - 0

    Erect Steel & Deck CL 1 - 0 / E - B

    EXT studs & sheathing - 3B concourse level

    Install Stairs - 3B

    Roof Curbs Kitchen Equip. - 3B concourse level

    Interior CMU

    Backfill to Concourse level

    Install Roofing - 3B

    SOG Concourse 3rd Base & SOD CL 1-0 / E-B

    INT Stud Framing - 3B concourse level

    Pour Concrete Pans on Stairs - 3B

    Exterior Doors - 3B

    Kitchen Hoods install - 3B Concourse level

    EXT Vapor Barrier - 3B

    Elec Rms F/P Eqpmnt pads - 3B concourse level

    MEP R/I walls - 3B concourse level

    Kitchen Equipment overhead R/I - 3B concourse level

    Install EXT Brick Veener - 3B

    Elec Rms Set switchgear/panels/transfrmers - 3B concourse level

    MEP R/I overhead - 3B concourse level

    Elec Rms Conduit - 3B concourse level

    Install Windows - 3B

    GWB Hang - 3B concourse level

    Elec Rms Feeders/Terminations - 3B concourse level

    GWB Finish - 3B concourse level

    Storefronts - 3B

    Install Stucco - 3B

    Elec Rms Permanent Power Insp - 3B concourse level

    Elec Rms Permanent Power - 3B concourse level

    Elevator equipment

    Ceramic tile / epoxy coat - 3B concourse level

    Prime & First Coat Paint Walls - 3B concourse level

    Fire Ext. Cabinets - 3B concourse level

    Ceiling Grid - 3B concourse level

    A/V Equipment - 3B concourse level

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 6 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A3200 Flooring - 3B concourse level 7 31-Dec-15 08-Jan-16 0

    A3310 MEP Trim Out - 3B concourse level 8 31-Dec-15 11-Jan-16 29

    A3290 Ceiling Tiles - 3B concourse level 7 01-Jan-16 11-Jan-16 36

    A3250 Millwork & Trim - 3B concourse level10 07-Jan-16 20-Jan-16 0

    A4530 Kitchen Equipment install - 3B concourse level20 07-Jan-16 02-Feb-16 17

    A3260 Install Interior Doors - 3B concourse level8 08-Jan-16 20-Jan-16 29

    A3320 Toilet Partitions & Accesories - 3B concourse level5 11-Jan-16 18-Jan-16 29

    A3280 Final coat paint - 3B concourse level7 20-Jan-16 28-Jan-16 0

    A3710 Test & Balance HVAC - 3B concourse level3 20-Jan-16 22-Jan-16 29

    A3270 Countertops - 3B concourse level 5 26-Jan-16 02-Feb-16 17

    A3330 Signage & Graphics - 3B concourse level2 28-Jan-16 01-Feb-16 23

    A3350 Wall & Door Protection - 3B concourse level1 28-Jan-16 29-Jan-16 24

    A3360 Window Treatments - 3B concourse level2 28-Jan-16 01-Feb-16 0

    A1780 Final Clean - 3B concourse level 5 02-Feb-16 08-Feb-16 17

    Suite Level 3B CL17 to CL4Suite Level 3B CL17 to CL4 105 17-Sep-15 28-Jan-16 24

    A2090 Precast concrete seating 3B suite level5 17-Sep-15 24-Sep-15 15

    A1680 SOD (incl set drains)) 3B suite level 7 01-Oct-15 09-Oct-15 9

    A1750 Roofing 3B suite level 10 12-Oct-15 23-Oct-15 9

    A1770 EXT studs framing 3B suite level 5 26-Oct-15 30-Oct-15 10

    A2870 INT stud framing 3B suite level 5 30-Oct-15 05-Nov-15 17

    A3150 EXT sheathing & vapor barrier 3B suite level5 30-Oct-15 05-Nov-15 10

    A2420 Install Sliding Glass Doors 3B suite level10 06-Nov-15 19-Nov-15 75

    A3030 MEP R/I walls 3B suite level 7 06-Nov-15 16-Nov-15 10

    A2620 Install stucco 3B suite level 9 06-Nov-15 18-Nov-15 61

    A3020 MEP R/I overhead 3B suite level 10 16-Nov-15 27-Nov-15 10

    A2840 Storefronts 3B suite level 10 25-Nov-15 08-Dec-15 61

    A3040 GWB hang 3B suite level 10 27-Nov-15 10-Dec-15 10

    A3160 GWB finish 3B suite level 10 10-Dec-15 23-Dec-15 10

    A2860 Prime & First Coat Paint Walls 3B suite level5 23-Dec-15 30-Dec-15 10

    A3170 Ceramic Tile & Epoxy coat 3B suite level5 23-Dec-15 30-Dec-15 24

    A2900 Ceiling Grid 3B suite level 5 30-Dec-15 05-Jan-16 19

    A2930 Millwork & Trim 3B suite level 8 30-Dec-15 08-Jan-16 10

    A2920 Fire Ext. Cabinets 3B suite level 1 30-Dec-15 31-Dec-15 17

    A2960 Countertops 3B suite level 5 05-Jan-16 12-Jan-16 19

    A2890 MEP Trim Out 3B suite level 5 05-Jan-16 12-Jan-16 19

    A2940 A/V Equipment 3B suite level 7 08-Jan-16 18-Jan-16 28

    A2970 Final coat paint 3B suite level 4 08-Jan-16 14-Jan-16 10

    A2950 Ceiling Tiles 3B suite level 5 12-Jan-16 18-Jan-16 23

    A2910 Flooring 3B suite level 5 12-Jan-16 18-Jan-16 19

    A2980 Signage & Graphics 3B suite level 1 14-Jan-16 14-Jan-16 35

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Flooring - 3B concourse level

    MEP Trim Out - 3B concourse level

    Ceiling Tiles - 3B concourse level

    Millwork & Trim - 3B concourse level

    Kitchen Equipment install - 3B concourse level

    Install Interior Doors - 3B concourse level

    Toilet Partitions & Accesories - 3B concourse level

    Final coat paint - 3B concourse level

    Test & Balance HVAC - 3B concourse level

    Countertops - 3B concourse level

    Signage & Graphics - 3B concourse level

    Wall & Door Protection - 3B concourse level

    Window Treatments - 3B concourse level

    Final Clean - 3B concourse level

    28-Jan-16, Suite Level 3B CL17 to CL4

    Precast concrete seating 3B suite level

    SOD (incl set drains)) 3B suite level

    Roofing 3B suite level

    EXT studs framing 3B suite level

    INT stud framing 3B suite level

    EXT sheathing & vapor barrier 3B suite level

    Install Sliding Glass Doors 3B suite level

    MEP R/I walls 3B suite level

    Install stucco 3B suite level

    MEP R/I overhead 3B suite level

    Storefronts 3B suite level

    GWB hang 3B suite level

    GWB finish 3B suite level

    Prime & First Coat Paint Walls 3B suite level

    Ceramic Tile & Epoxy coat 3B suite level

    Ceiling Grid 3B suite level

    Millwork & Trim 3B suite level

    Fire Ext. Cabinets 3B suite level

    Countertops 3B suite level

    MEP Trim Out 3B suite level

    A/V Equipment 3B suite level

    Final coat paint 3B suite level

    Ceiling Tiles 3B suite level

    Flooring 3B suite level

    Signage & Graphics 3B suite level

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 7 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A3000 Wall & Door Protection 3B suite level1 14-Jan-16 14-Jan-16 35

    A3010 Window Treatments 3B suite level 3 14-Jan-16 18-Jan-16 10

    A2850 INT doors & hardware 3B suite level 4 18-Jan-16 22-Jan-16 19

    A3640 Final Clean - 3B suite level 5 22-Jan-16 28-Jan-16 24

    Suite Level 1B CL17 to CL30Suite Level 1B CL17 to CL30 110 17-Sep-15 04-Feb-16 19

    A3650 Precast concrete seating 1B suite level5 17-Sep-15 24-Sep-15 7

    A3370 Pour SOD (incl set drains) 1B suite level7 24-Sep-15 05-Oct-15 7

    A3380 Roofing 1B suite level 7 05-Oct-15 14-Oct-15 20

    A3390 EXT stud framing 1B suite level 5 14-Oct-15 21-Oct-15 21

    A3400 INT stud framing 1B suite level 5 21-Oct-15 27-Oct-15 28

    A3410 EXT sheathing & vapor barrier 1B suite level5 21-Oct-15 27-Oct-15 21

    A3420 Install Sliding Glass Doors 1B suite level10 27-Oct-15 09-Nov-15 58

    A3500 Storefronts 1B suite level 10 27-Oct-15 09-Nov-15 59

    A3430 MEP R/I walls 1B suite level 7 27-Oct-15 04-Nov-15 21

    A4720 Elec Rm F/P Eqpmnt pads - 1B suite level5 27-Oct-15 03-Nov-15 56

    A4730 Elec Rm Set switchgear/panels/transfrmers - 1B suite level5 03-Nov-15 09-Nov-15 56

    A3450 MEP R/I overhead 1B suite level 10 04-Nov-15 18-Nov-15 21

    A3440 Install stucco 1B suite level 9 09-Nov-15 19-Nov-15 59

    A4740 Elec Rm Conduit - 1B suite level 10 09-Nov-15 20-Nov-15 56

    A3460 GWB hang 1B suite level 10 18-Nov-15 01-Dec-15 21

    A4750 Elec Rm Feeders/Terminations - 1B suite level10 20-Nov-15 03-Dec-15 56

    A3470 GWB finish 1B suite level 10 24-Nov-15 07-Dec-15 21

    A4760 Elec Rm Permanent Power Insp - 1B suite level1 03-Dec-15 04-Dec-15 56

    A4770 Elec Rm Permanent Power - 1B suite level1 04-Dec-15 07-Dec-15 56

    A3480 Prime & First Coat Paint Walls 1B suite level5 07-Dec-15 14-Dec-15 21

    A3490 Ceramic Tile & Epoxy coat 1B suite level5 07-Dec-15 14-Dec-15 53

    A3510 Ceiling Grid 1B suite level 5 14-Dec-15 18-Dec-15 33

    A3520 Millwork & Trim 1B suite level 8 14-Dec-15 23-Dec-15 21

    A3530 Toilet Partitions & Accesories 1B suite level3 14-Dec-15 16-Dec-15 53

    A3540 Fire Ext. Cabinets 1B suite level 1 14-Dec-15 15-Dec-15 30

    A3550 Countertops 1B suite level 5 18-Dec-15 25-Dec-15 21

    A3560 MEP Trim Out 1B suite level 5 18-Dec-15 25-Dec-15 33

    A3570 A/V Equipment 1B suite level 7 23-Dec-15 31-Dec-15 46

    A3590 Ceiling Tiles 1B suite level 5 25-Dec-15 31-Dec-15 36

    A3600 Flooring 1B suite level 5 25-Dec-15 31-Dec-15 33

    A3580 Final coat paint 1B suite level 4 25-Dec-15 30-Dec-15 21

    A3610 Signage & Graphics 1B suite level 1 30-Dec-15 31-Dec-15 46

    A3620 Wall & Door Protection 1B suite level1 30-Dec-15 31-Dec-15 46

    A3630 Window Treatments 1B suite level 3 30-Dec-15 04-Jan-16 21

    A3830 INT Doors & Hardware 1B suite level3 31-Dec-15 05-Jan-16 33

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Wall & Door Protection 3B suite level

    Window Treatments 3B suite level

    INT doors & hardware 3B suite level

    Final Clean - 3B suite level

    04-Feb-16, Suite Level 1B CL17 to CL30

    Precast concrete seating 1B suite level

    Pour SOD (incl set drains) 1B suite level

    Roofing 1B suite level

    EXT stud framing 1B suite level

    INT stud framing 1B suite level

    EXT sheathing & vapor barrier 1B suite level

    Install Sliding Glass Doors 1B suite level

    Storefronts 1B suite level

    MEP R/I walls 1B suite level

    Elec Rm F/P Eqpmnt pads - 1B suite level

    Elec Rm Set switchgear/panels/transfrmers - 1B suite level

    MEP R/I overhead 1B suite level

    Install stucco 1B suite level

    Elec Rm Conduit - 1B suite level

    GWB hang 1B suite level

    Elec Rm Feeders/Terminations - 1B suite level

    GWB finish 1B suite level

    Elec Rm Permanent Power Insp - 1B suite level

    Elec Rm Permanent Power - 1B suite level

    Prime & First Coat Paint Walls 1B suite level

    Ceramic Tile & Epoxy coat 1B suite level

    Ceiling Grid 1B suite level

    Millwork & Trim 1B suite level

    Toilet Partitions & Accesories 1B suite level

    Fire Ext. Cabinets 1B suite level

    Countertops 1B suite level

    MEP Trim Out 1B suite level

    A/V Equipment 1B suite level

    Ceiling Tiles 1B suite level

    Flooring 1B suite level

    Final coat paint 1B suite level

    Signage & Graphics 1B suite level

    Wall & Door Protection 1B suite level

    Window Treatments 1B suite level

    INT Doors & Hardware 1B suite level

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 8 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A2180 Test & Balance HVAC 1B & 3B Suite level5 22-Jan-16 28-Jan-16 19

    A3840 Final Clean - 1B suite level 5 29-Jan-16 04-Feb-16 19

    Seating Bowl Walls & Risers 1B CL17 to CL31Seating Bowl Walls & Risers 1B CL17 to CL31 178 08-Jun-15 20-Jan-16 31

    A3340 FTGs Seating Bowl & 1B DO walls 10 08-Jun-15 19-Jun-15 49

    A2880 Conc Walls - Seat Bowl & Terraces, & 1B DO15 15-Jun-15 02-Jul-15 49

    A2990 UG MEP / Drainage system 1B 5 05-Oct-15 12-Oct-15 10

    A3660 Backfill & grading bowl 1B 5 12-Oct-15 16-Oct-15 10

    A3670 P / P SOGs DO, Aisles, Platforms, Terraces 1B10 16-Oct-15 29-Oct-15 10

    A3720 F / P Stepped Bowl 1B 25 29-Oct-15 01-Dec-15 10

    A3680 Stairs - DO, Platforms, & Terraces 1B10 01-Dec-15 14-Dec-15 21

    A2590 Railings 1B 15 14-Dec-15 01-Jan-16 31

    A2550 Stadium Seating !B 15 01-Jan-16 20-Jan-16 31

    Seating Bowl Walls & Risers 3B CL17 to CL0Seating Bowl Walls & Risers 3B CL17 to CL0 182 16-Jun-15 02-Feb-16 21

    A3730 FTGs - Seat Bowl 3B 10 16-Jun-15 29-Jun-15 43

    A3750 Conc Walls - Seat Bowl, & Terraces 3B15 22-Jun-15 10-Jul-15 43

    A3740 UG MEP / Drainage system 3B 5 05-Oct-15 12-Oct-15 7

    A3770 Backfill & grading bowl 3B 5 14-Oct-15 21-Oct-15 7

    A3780 P / P SOGs DO, Aisles, Platforms, Terraces 3B10 21-Oct-15 03-Nov-15 7

    A3790 F / P Stepped Bowl 3B 25 03-Nov-15 04-Dec-15 7

    A3800 Stairs - DO, Platforms, & Terraces 3B10 14-Dec-15 25-Dec-15 21

    A3820 Railings 3B 15 25-Dec-15 14-Jan-16 21

    A3810 Stadium Seating 3B 15 14-Jan-16 02-Feb-16 21

    Outfield Walls & Plazas CL0 to CL31Outfield Walls & Plazas CL0 to CL31 160 03-Jul-15 25-Jan-16 28

    A1760 FTG OF Walls, Scoreboard, Batters Eye15 10-Jul-15 30-Jul-15 39

    A1970 F/P OF Walls 15 23-Jul-15 12-Aug-15 43

    A2210 FTG Keystone retaining wall 10 12-Aug-15 25-Aug-15 70

    A3870 FTG OF Bar, OF Mast liights, Flag poles10 12-Aug-15 25-Aug-15 76

    A3050 Lay Keystone blocks 15 19-Aug-15 07-Sep-15 70

    A3860 Keystone wall drainage system 10 25-Aug-15 07-Sep-15 75

    A3850 Backfill Keystone wall 5 01-Sep-15 07-Sep-15 70

    A1840 Backfill OF walls 10 01-Oct-15 14-Oct-15 21

    A2140 UG MEP OF Plaza 10 14-Oct-15 28-Oct-15 30

    A1870 P / P SOG OF Concourse 15 04-Nov-15 24-Nov-15 23

    A1960 Install Light Poles 15 24-Nov-15 14-Dec-15 23

    A2130 Chain Link Fencing 10 14-Dec-15 25-Dec-15 23

    A2310 Flag Poles 3 25-Dec-15* 30-Dec-15 23

    A2320 Ornamental Fence & Gates 20 30-Dec-15 25-Jan-16 28

    ScoreboardScoreboard 90 18-Sep-15 12-Jan-16 23

    A2100 Scoreboard Steel Support 5 18-Sep-15 24-Sep-15 13

    A3880 Scoreboard UG Electric & Data 5 24-Sep-15 01-Oct-15 93

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Test & Balance HVAC 1B & 3B Suite level

    Final Clean - 1B suite level

    20-Jan-16, Seating Bowl Walls & Risers 1B CL17 to CL31

    FTGs Seating Bowl & 1B DO walls

    Conc Walls - Seat Bowl & Terraces, & 1B DO

    UG MEP / Drainage system 1B

    Backfill & grading bowl 1B

    P / P SOGs DO, Aisles, Platforms, Terraces 1B

    F / P Stepped Bowl 1B

    Stairs - DO, Platforms, & Terraces 1B

    Railings 1B

    Stadium Seating !B

    02-Feb-16, Seating Bowl Walls & Risers 3B CL17 to CL0

    FTGs - Seat Bowl 3B

    Conc Walls - Seat Bowl, & Terraces 3B

    UG MEP / Drainage system 3B

    Backfill & grading bowl 3B

    P / P SOGs DO, Aisles, Platforms, Terraces 3B

    F / P Stepped Bowl 3B

    Stairs - DO, Platforms, & Terraces 3B

    Railings 3B

    Stadium Seating 3B

    25-Jan-16, Outfield Walls & Plazas CL0 to CL31

    FTG OF Walls, Scoreboard, Batters Eye

    F/P OF Walls

    FTG Keystone retaining wall

    FTG OF Bar, OF Mast liights, Flag poles

    Lay Keystone blocks

    Keystone wall drainage system

    Backfill Keystone wall

    Backfill OF walls

    UG MEP OF Plaza

    P / P SOG OF Concourse

    Install Light Poles

    Chain Link Fencing

    Flag Poles

    Ornamental Fence & Gates

    12-Jan-16, Scoreboard

    Scoreboard Steel Support

    Scoreboard UG Electric & Data

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 9 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A2470 Install Score Board 10 30-Dec-15 12-Jan-16 23

    LF TerraceLF Terrace 19 07-Oct-15 02-Nov-15 77

    A3900 Backfill & Grading LF Terrace 3 07-Oct-15 12-Oct-15 23

    A3970 FTG LF Terrace 2 12-Oct-15 14-Oct-15 23

    A3910 UG MEP / Drainage LF Terrace 2 14-Oct-15 16-Oct-15 23

    A3920 F / P LF Terrace 5 16-Oct-15 22-Oct-15 23

    A3890 Aisle SOG LF Terrace 2 22-Oct-15 26-Oct-15 77

    A3950 F / P Steps LF Terrace 3 26-Oct-15 29-Oct-15 77

    A3930 Railings LF Terrace 2 29-Oct-15 02-Nov-15 77

    LF BermLF Berm 26 07-Oct-15 10-Nov-15 87

    A2520 Backfill & Grading LF Berm 2 07-Oct-15 09-Oct-15 28

    A3960 FTG Wallls LF Berm 2 14-Oct-15 16-Oct-15 25

    A3990 F / P Walls LF Berm 3 22-Oct-15 27-Oct-15 23

    A3940 UG MEP / Drainage LF Berm 3 27-Oct-15 30-Oct-15 90

    A4010 Railings LF Berm 2 02-Nov-15 04-Nov-15 77

    A4000 Topsoil, irrigation, sod LF berm 5 04-Nov-15 10-Nov-15 87

    Batter's EyeBatter's Eye 41 17-Sep-15 10-Nov-15 77

    A2440 Structural Steel Batter Eye 5 17-Sep-15 24-Sep-15 15

    A4040 CMU Batter Eye 10 24-Sep-15 07-Oct-15 23

    A4020 Fencing & Windscreen Batter Eye 5 07-Oct-15 14-Oct-15 94

    A4030 Railings Batter Eye 5 04-Nov-15 10-Nov-15 77

    Outfield Bar & RestroomsOutfield Bar & Restrooms 72 25-Aug-15 25-Nov-15 76

    A2560 CMU walls - OF Bar 5 25-Aug-15 01-Sep-15 76

    A4060 Roof structure - OF Bar 5 01-Sep-15 07-Sep-15 76

    A4050 UG MEP - OF Bar 4 07-Sep-15 11-Sep-15 76

    A4080 SOG - OF Bar 5 11-Sep-15 17-Sep-15 76

    A4090 INT Framing - OF Bar 3 17-Sep-15 22-Sep-15 76

    A4150 EXT Doors & hardware - OF Bar 3 22-Sep-15 25-Sep-15 76

    A4070 Exterior finish - OF Bar 15 25-Sep-15 15-Oct-15 89

    A4100 MEP R / I walls & overhead - OF Bar10 25-Sep-15 08-Oct-15 76

    A4110 INT wall finishes - OF Bar 5 08-Oct-15 15-Oct-15 76

    A4170 Flooring - OF Bar 5 15-Oct-15 21-Oct-15 76

    A4120 MEP trim out - OF Bar 5 21-Oct-15 28-Oct-15 76

    A4140 Millwork & Casework - OF Bar 5 21-Oct-15 28-Oct-15 76

    A4130 Toilet partitions & accessories - OF Bar3 28-Oct-15 30-Oct-15 76

    A4160 Painting - OF Bar 4 30-Oct-15 05-Nov-15 76

    A4180 Bar FF & E - OF Bar 15 05-Nov-15 25-Nov-15 76

    OF Bar TerraceOF Bar Terrace 40 14-Oct-15 03-Dec-15 68

    A4320 Backfill & Grading OF BAR Terrace 3 14-Oct-15 19-Oct-15 24

    A4190 FTG terrace walls OF BAR Terrace 5 19-Oct-15 26-Oct-15 24

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    Install Score Board

    02-Nov-15, LF Terrace

    Backfill & Grading LF Terrace

    FTG LF Terrace

    UG MEP / Drainage LF Terrace

    F / P LF Terrace

    Aisle SOG LF Terrace

    F / P Steps LF Terrace

    Railings LF Terrace

    10-Nov-15, LF Berm

    Backfill & Grading LF Berm

    FTG Wallls LF Berm

    F / P Walls LF Berm

    UG MEP / Drainage LF Berm

    Railings LF Berm

    Topsoil, irrigation, sod LF berm

    10-Nov-15, Batter's Eye

    Structural Steel Batter Eye

    CMU Batter Eye

    Fencing & Windscreen Batter Eye

    Railings Batter Eye

    25-Nov-15, Outfield Bar & Restrooms

    CMU walls - OF Bar

    Roof structure - OF Bar

    UG MEP - OF Bar

    SOG - OF Bar

    INT Framing - OF Bar

    EXT Doors & hardware - OF Bar

    Exterior finish - OF Bar

    MEP R / I walls & overhead - OF Bar

    INT wall finishes - OF Bar

    Flooring - OF Bar

    MEP trim out - OF Bar

    Millwork & Casework - OF Bar

    Toilet partitions & accessories - OF Bar

    Painting - OF Bar

    Bar FF & E - OF Bar

    03-Dec-15, OF Bar Terrace

    Backfill & Grading OF BAR Terrace

    FTG terrace walls OF BAR Terrace

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 10 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    A4200 F / P terrace walls OF BAR Terrace 7 27-Oct-15 04-Nov-15 23

    A4210 UG MEP / Drainage OF BAR Terrace5 04-Nov-15 11-Nov-15 66

    A4250 Final Backfill & grading OF BAR Terrace5 11-Nov-15 18-Nov-15 66

    A4240 F / P Steps OF BAR Terrace 5 18-Nov-15 24-Nov-15 66

    A4220 Railings OF BAR Terrace 3 24-Nov-15 27-Nov-15 66

    A4230 Topsoil, irrigation, sod OF BAR Terrace5 27-Nov-15 03-Dec-15 68

    RF BermRF Berm 42 14-Oct-15 07-Dec-15 66

    A4260 Backfill & Grading RF Berm 3 14-Oct-15 19-Oct-15 95

    A4290 UG MEP / Drainage RF Berm 3 19-Oct-15 22-Oct-15 95

    A4280 F / P apron next to OF wall RF Berm2 04-Nov-15 06-Nov-15 84

    A4300 Railings RF Berm 2 27-Nov-15 01-Dec-15 66

    A4310 Topsoil, irrigation, sod RF berm 5 01-Dec-15 07-Dec-15 66

    RF PorchRF Porch 40 14-Oct-15 03-Dec-15 68

    A3700 Backfill & Grading RF Porch 3 14-Oct-15 19-Oct-15 29

    A4330 FTG walls RF Porch 3 26-Oct-15 28-Oct-15 24

    A4340 F / P walls RF Porch 5 28-Oct-15 04-Nov-15 24

    A4270 UG MEP / Drainage RF Porch 5 04-Nov-15 11-Nov-15 81

    A4350 P / P SOG RF Porch 3 11-Nov-15 13-Nov-15 81

    A4360 Railings RF Porch 3 01-Dec-15 03-Dec-15 68

    Field Maintenance AreaField Maintenance Area 157 03-Jul-15 20-Jan-16 31

    A4370 Loading Dock Concrete Steps & Rail5 03-Jul-15 10-Jul-15 178

    A4380 UG MEP / Drainage field access ramp15 24-Nov-15 14-Dec-15 31

    A2300 P / P SOG Field access ramp 10 14-Dec-15 25-Dec-15 31

    A2570 Fencing & Gates 15 25-Dec-15 13-Jan-16 31

    A3690 Concrete material bins 5 25-Dec-15 31-Dec-15 43

    A4390 Pipe bollards 3 31-Dec-15 05-Jan-16 43

    A2250 Loading Dock Equip 5 13-Jan-16 20-Jan-16 31

    Playing FieldPlaying Field 61 04-Dec-15 19-Feb-16 7

    A2030 Field subsurface 15 04-Dec-15 23-Dec-15 7

    A3070 Bowl collector field piping 10 17-Dec-15 30-Dec-15 7

    A2270 Install Foul Poles 5 23-Dec-15 30-Dec-15 23

    A2430 Field drainage piping 10 23-Dec-15 05-Jan-16 7

    A2800 Field irrigation 12 30-Dec-15 14-Jan-16 7

    A3060 Field AV equipment / wiring / devices15 12-Jan-16 01-Feb-16 23

    A2290 Backstop Netting 5 14-Jan-16 20-Jan-16 31

    A2830 Field rootzone 5 14-Jan-16 20-Jan-16 7

    A2480 Padding walls & rails 10 20-Jan-16 02-Feb-16 7

    A3080 Field clay surfaces 4 02-Feb-16 08-Feb-16 7

    A2040 Sod Playing Field 5 08-Feb-16 15-Feb-16 7

    A2280 Dugout equipment installation 5 15-Feb-16 19-Feb-16 7

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    F / P terrace walls OF BAR Terrace

    UG MEP / Drainage OF BAR Terrace

    Final Backfill & grading OF BAR Terrace

    F / P Steps OF BAR Terrace

    Railings OF BAR Terrace

    Topsoil, irrigation, sod OF BAR Terrace

    07-Dec-15, RF Berm

    Backfill & Grading RF Berm

    UG MEP / Drainage RF Berm

    F / P apron next to OF wall RF Berm

    Railings RF Berm

    Topsoil, irrigation, sod RF berm

    03-Dec-15, RF Porch

    Backfill & Grading RF Porch

    FTG walls RF Porch

    F / P walls RF Porch

    UG MEP / Drainage RF Porch

    P / P SOG RF Porch

    Railings RF Porch

    20-Jan-16, Field Maintenance Area

    Loading Dock Concrete Steps & Rail

    UG MEP / Drainage field access ramp

    P / P SOG Field access ramp

    Fencing & Gates

    Concrete material bins

    Pipe bollards

    Loading Dock Equip

    19-Feb-16, Playing Field

    Field subsurface

    Bowl collector field piping

    Install Foul Poles

    Field drainage piping

    Field irrigation

    Field AV equipment / wiring / devices

    Backstop Netting

    Field rootzone

    Padding walls & rails

    Field clay surfaces

    Sod Playing Field

    Dugout equipment installation

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 11 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Activity ID Activity Name Original

    Duration

    Start Finish Total Float

    Main Entrance PlazaMain Entrance Plaza 95 16-Oct-15 16-Feb-16 11

    A4400 FTGs Main plaza 5 16-Oct-15 23-Oct-15 11

    A4410 UG MEP / Drainage Main plaza 7 23-Oct-15 02-Nov-15 11

    A4420 F / P Walls Main plaza 10 02-Nov-15 13-Nov-15 11

    A4480 Backfill & grading Main plaza 4 13-Nov-15 19-Nov-15 11

    A1790 CMU Main plaza 12 19-Nov-15 07-Dec-15 10

    A2330 Brick veneer & steps Main plaza 25 01-Dec-15 01-Jan-16 11

    A2340 Curb & Gutter, Sidewalks, Aprons Main plaza10 08-Dec-15 21-Dec-15 16

    A4450 Railings Main plaza 20 21-Dec-15 14-Jan-16 16

    A4430 P / P SOG Main plaza 15 01-Jan-16 20-Jan-16 11

    A4440 MEP fixtures & trimout Main plaza 7 20-Jan-16 29-Jan-16 14

    A4470 Fencing & Gates 10 20-Jan-16 02-Feb-16 11

    A4460 Landscape Plantings Main plaza 10 02-Feb-16 16-Feb-16 11

    Close OutClose Out 29 22-Jan-16 01-Mar-16 0

    A4790 Fire Inspection 1 22-Jan-16 25-Jan-16 28

    A4800 Contractor's Punch List 10 01-Feb-16 12-Feb-16 0

    A4820 Systems Training 3 01-Feb-16 04-Feb-16 20

    A4810 Architect / Owner's Punch List 12 12-Feb-16 29-Feb-16 0

    A4780 Owner Final Inspection 1 29-Feb-16 01-Mar-16 0

    0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0

    N D J F M A M J J A S O N D J F M A M J J A S O

    16-Feb-16, Main Entrance Plaza

    FTGs Main plaza

    UG MEP / Drainage Main plaza

    F / P Walls Main plaza

    Backfill & grading Main plaza

    CMU Main plaza

    Brick veneer & steps Main plaza

    Curb & Gutter, Sidewalks, Aprons Main plaza

    Railings Main plaza

    P / P SOG Main plaza

    MEP fixtures & trimout Main plaza

    Fencing & Gates

    Landscape Plantings Main plaza

    01-Mar-16, Close Out

    Fire Inspection

    Contractor's Punch List

    Systems Training

    Architect / Owner's Punch List

    Owner Final Inspection

    Spirit Communications Park

    22-Apr-15 15:29

    Actual Work

    Remaining Work

    Critical Rem...

    Milestone

    Page 12 of 12 Baseline DD 07 April 2015

    © Oracle Corporation

  • Appendix B

  • Page 1

    NON-COLLUSION AFFIDAVIT – ATTACHMENT D

    State of __________________________________) County of _________________________________) ________________________________ being first duly sworn, deposes and says that:

    (1) He is __________________________ of __________________________, the Respondent that has submitted the attached Proposal:

    (2) He is fully informed respecting the preparation and contents of the attached Proposal and of all pertinent circumstances respecting such Proposal: (3) Such Proposal is genuine and is not a collusive or sham Proposal: (4) Neither the said Respondent nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affidavit, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Respondent, firm or person to submit a collusive or sham in connection with the Contract for which the attached Proposal has been submitted or to retain from proposing in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Respondent, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage against the City of Columbia, S.C. or any person interested in the proposed Contract; and (Signed)___________________________________

    ___________________________________ (Title)

    Subscribed and sworn to before me this __________day of ______________, 20_____ ___________________________________________________

    (Notary Public) My commission expires _________________