welcome to the los angeles street civic building ......deconstruction of building and sequence of...

1

Upload: others

Post on 17-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING -DEMOLITION OF PARKER CENTER PROJECT

INFORMATIONAL MEETINGJuly 26, 2018, 4 to 6pm | Garden Room A at JACCC

Page 2: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Introduction

• Los Angeles Councilmember Jose Huizar, District Office 14• Los Angeles City Bureau of Engineering • Construction Contractor Silverado Constructors, Inc. • Outreach Specialist Katherine Padilla & Associates (KPA)• Community Liaison Kristin Fukushima, Little Tokyo Community Council

• Speakers Today▪ Mahmood Karimzadeh, AIA – Principal Architect, Bureau of Engineering▪ Meghan Aldrich, PE – Construction Manager, Bureau of Engineering

2

Page 3: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

New Civic Building

3

Page 4: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Site Context

4

Page 5: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Site Area

5

Page 6: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Project History

• EIR Process started in 2008• On March 2017, the LA City Council approved the EIR and demolition

of the Parker Center• Parker Center Demolition Project Construction Award Information:

▪ Award Date: June 4, 2018▪ Award Amount: $16,737,549

6

Page 7: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Demolition Site

7

Page 8: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Deconstruction Phases

• Deconstruction of Building and Sequence of Work

Phase 1Administration and Jail Wing

Phase 2Roof to 3rd Floor

Phase 3Remaining Tower

8

Page 9: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Overall Demolition Plan – Agenda Topics

• Haul Route• Hazmat Abatement• Dust Mitigation for Deconstruction• Noise and Vibration• Data Conduits & Cabling – Street Work • Traffic Plan and Impact

9

Page 10: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Haul Route

10

HAUL ROUTE FOR C & D DEBRIS1. North on Judge John Aiso2. East on Temple Ave.3. South on Alameda St.4. East on Olympic Blvd.5. Arrive at 2424 E. Olympic Blvd.

Page 11: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Haul Route

11

HAUL ROUTE FOR CONCRETE SPOILS – INGRESS1. Exit Hwy. 101 at Vignes St

(North)2. Loop to Ramirez St. (South)3. West on Commercial St.4. South on Alameda St.5. Right on Temple St.6. Left on Judge John Aiso into

job siteHAUL ROUTE FOR CONCRETE SPOILS – EGRESS1. Exit job site north on Judge

John Aiso2. Right on Temple St.3. Left on Alameda St.4. Right on Commercial St.5. Left onto Hwy. 101

Page 12: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Hazmat

Air Quality Control

• General Site:▪ Mitigate fugitive dust on site

• HAZMAT:▪ Critical openings ▪ Work areas will be under negative pressure▪ Consultant will be present on a daily basis as HAZMAT work is ongoing▪ 3rd party hygienist verifications and approvals▪ Clearance letters▪ Removal of the negative pressure and sealed enclosure

12

Page 13: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Dust Mitigation for Deconstruction & Site Grading

• Dust Mitigation:▪ Visual dust monitoring will be performed on an ongoing basis and

will be in accordance with SCAQMD Rule 1403 (Fugitive Dust)▪ Water misting of building structure , concrete, spoils, loading

activities and path of travel▪ Tarped and/or covered truck loads ▪ Speed reduction of vehicles through site▪ Sweeping of work areas as needed

13

Page 14: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Noise and Vibration

• Noise and Vibration:

14

Location of Noise and Vibration Monitoring

Limits of Demolition

Page 15: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Street work – Data Conduit Duct Bank & Cabling Installation

15

Page 16: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Data Conduit - Street Work - Phasing

16

Phase 1 - Stage 1: One Lane Closure (Right Lane) North-East bound on Los Angeles St.

16

Page 17: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Data Conduit - Street Work - Phasing

17

Phase 1 - Stage 2: One Lane Closure (Left Lane) North-East bound on Los Angeles St.

17

Page 18: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Data Conduit - Street Work - Phasing

18

Phase 2 - Stage 1: Bike Lane Closure and Right Hand Turn Pocket Closure.

18

Page 19: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Data Conduit - Street Work - Phasing

19

Phase 3 - Stage 1:Middle of the St. closure allowing One Lane of Travel in each Direction on Judge John Aiso St. Mid Block Crossing and Walk Closed.

19

Page 20: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Data Conduit - Street Work - Phasing

20

Phase 4 - Stage 1:One Lane Closure (Right Lane) South-East of Left Turn Hand Turn from Temple St. to South bound Los Angeles Closed.

20

Page 21: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Project Hotline

1-888-840-2610

21

• Demolition related questions and comments• Extensions for English, Japanese, Korean, and Spanish• Will respond back in 48 hours

Page 22: WELCOME TO THE LOS ANGELES STREET CIVIC BUILDING ......Deconstruction of Building and Sequence of Work . Phase 1. Administration and Jail Wing. Phase 2. Roof to 3. rd. Floor. Phase

Questions?

22