Wetland Overview. By: Yugadi Hullur Aidan O’Brien Graham Stamper Chase Thompson Ashleigh Richardson. People Involved in the W etland Project. Students of Rowan County Middle School Mr. Jay Padula Ms. Jennifer Pecco Mr. Thomas Biebighauser - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Wetland Overview](https://reader030.vdocument.in/reader030/viewer/2022033101/56816309550346895dd3882c/html5/thumbnails/1.jpg)
WETLAND OVERVIEW
By: Yugadi HullurAidan O’Brien
Graham StamperChase Thompson
Ashleigh Richardson
![Page 2: Wetland Overview](https://reader030.vdocument.in/reader030/viewer/2022033101/56816309550346895dd3882c/html5/thumbnails/2.jpg)
People Involved in the Wetland Project
Students of Rowan County Middle School
Mr. Jay Padula Ms. Jennifer Pecco Mr. Thomas Biebighauser These people will be assisting in
the Wetland Project.
![Page 3: Wetland Overview](https://reader030.vdocument.in/reader030/viewer/2022033101/56816309550346895dd3882c/html5/thumbnails/3.jpg)
Where RCMS Wetland Will Be
Wetland locations #1 and 2
Wetland location #3
![Page 4: Wetland Overview](https://reader030.vdocument.in/reader030/viewer/2022033101/56816309550346895dd3882c/html5/thumbnails/4.jpg)
Brief Description of Wetland Project
There will be three wetlands They will be approximately 20 x 30 feet
to 30 x 40 feet in size They will be less than 15 inches deep The slopes around the wetland will be
gradual 5-percent or less
![Page 5: Wetland Overview](https://reader030.vdocument.in/reader030/viewer/2022033101/56816309550346895dd3882c/html5/thumbnails/5.jpg)
Construction Requirements
Rowan County Floodplain coordinator, Mr. Bobby Wells was contacted
No floodplain permits needed Excavation will be completed in one day,
and supervised by Tom Biebighauser