wg belgian grid - elia.be · b. de eigenaar van de elektriciteitsproductie-installatie een...
TRANSCRIPT
WG Belgian Grid
6 June 2019 – Users’ Group Plenary Meeting
Publication Federal Grid Code – 22 April 2019
- High level overview submitted version VS. published version
- Techniqual requirements
Capacity reservation in the context of a future CRM – proposition to
adaptation of the Federal Grid Code
Drop-off procedure
- Vision of the membres
Activities Belgian Grid
3
Federal level
Current status:
• CWaPE decision:
Une unité est considérée comme existante “si le propriétaire de cette unité a conclu un contrat définitif et contraignant pour l’achat du
composant principal de production au plus tard deux mois après la date de publication sur le site internet de la CWaPE de la décision
d’approbation des exigences d’application générale visées à l’article 7 du Code de réseau RfG [ou DCC]. »
• VREG decision:
“Een elektriciteitsproductie-eenheid wordt als bestaand in de zin van artikel 4.2 van de netcode RfG beschouwd, als ten laatste 2 maanden
na de datum van publicatie op de website van de VREG van de beslissing van de goedkeuring van de algemene toepassingseisen zoals
bedoeld in artikel 7 van de netcode RfG:
a. aangesloten is op het elektriciteitsdistributienet, het plaatselijk vervoernet van elektriciteit of een gesloten distributienet, of
b. de eigenaar van de elektriciteitsproductie-installatie een definitief en bindend contract heeft gesloten voor de aankoop van
het belangrijkste onderdeel van de productieinstallatie, en dit ten laatste 3 maanden na de datum van publicatie op de website
van de VREG van de hogervermelde beslissing, gemeld heeft aan de bevoegde netbeheerder (of beheerder van het gesloten
distributienet) en aan de transmissienetbeheerder.”
• BRUGEL decision:
« Les installations de production d’électricité ainsi que les installations de consommation visées respectivement par le règlement (UE)
2016/631 et le règlement (UE) 2016/1833 seront considérées comme « nouvelles » au sens des codes établis par ces règlements qu’après
deux mois suivant la publication de l’approbation de BRUGEL des propositions d’exigences d’application générale soumises par les
gestionnaires de réseau compétents selon les mêmes codes de réseau. »
Regional level
Art. 35 §7-8 of FGC:
• The contract for buying the main component must be signed before 27/4/2019 for a unit to be considered as existing
• Then, Elia is notified within 3 months and a request for recognition is introduced at the CREG within 6 months
New/existing
Capacity reservation process
-
Evolutions coming from new
FTR (EIF 29/4/19)
1) Impact of new FTR (capacity reservation process)a. How was the capacity reservation process organized so far (< 28/4/2019)
EOS process – 40 working days
Intro. request 10 WD
Request complete
Y/N No
Missing info
Yes
Not reasonable (security, reliability or grid efficiency)
EOS sent30 WD
Intro. request
EDS process – 70 working days
Tech. agreement
Art. 99 FTR – reference to art. 4 electricity law
Capacity allocation
Connection contract process
30 WD
Submit project
connection contract10 WD
Request complete
Y/NNo Missing info
Yes
Analyze technical info ELIA / requester40 WD
60 WD
If no technical solution, connection process ends and capacity reservation is cancelled (art. 106)
30 WD Conclusion connection
contract
Additional delay
Capacity reservation
Art. 98
Art. 105 § 1
Art. 105 § 2
1
1 Timing can be extended (common agreement) if complexity of connection request requires it (art. 105 § 3)
2
2
Submit production permit
3
3 If no connection contract within declared timings, connection procedure ends (art. 110) No more capacity reservation
6
1) Impact of new FTR (capacity reservation process)B. What are the most significant changes brought by new FTR (EIF as from 28/4/2019)
EOS process – 40 working days
Intro. request 10 WD
Request complete
Y/N No
Missing info
Yes
Not reasonable (security, reliability or grid efficiency)
EOS sent30 WD
Intro. request
EDS process – 70 working days
Tech. agreement
Art. 99 FTR – reference to art. 4 electricity law
Capacity allocation
Connection contract process
30 WD
Submit project
connection contract10 WD
Request complete
Y/NNo Missing info
Yes
Analyze technical info ELIA / requester40 WD
60 WD
30 WD Conclusion connection
contract
Additional delay
Capacity reservation*
Submit production permit
60 WD
From moment EDS is sent
120 WD
Capacity reservation*
Valid as long as technical agreement remains valid
new
1st extension by default
Illimited number of requests for extension (ELIA’s approval needed)
new
* If connection request concerns consumption, capacity reserved from moment request is complete.
* If connection request concerns production (type B – C or D, HVDC,…), capacity reserved from moment EDS is sent
Capacity reservation
process (new FTR)
-
Concrete examples
1st EDS requested Capacity reserved (120-180 WD)
1st EDS sent
2 EDS received by ELIA. Both EDS influence each other (same area; significant volumes).
2nd EDS requested Extension timing
Needs to consider reserved capacity of EDS 1 (from moment capacity is reserved) as input in grid’s model
Art.160 § 4 – extension of initial period as grid configuration evolves and need to be considered in 2nd EDS technical analysis.
70 WD
70 WD
25 WD (example)
25 WD (example)
Scenario 1 – both projects can receive capacity
2nd EDS sent
Capacity reserved (120-180 WD)
Scenario 2 – both projects cannot be realized together
Extension timing Capacity reserved (120-180 WD)
1st example
Connection possible
No connection contract – no more capacity reserved
No technical agreement can be found – need to wait for the end of capacity reservation period of EDS 1 (120 – 180 WD)
Connection possible
These examples only concerns production units (B – C – D); hydro; HVDC…Connection process for consumption does not change (capacity reserved from moment request is complete)
70 WD Capacity reserved (120-180 WD)
EDS 1 sent
70 WD Extension timing – art 160 § 4
70 WD Capacity reserved (120-180 WD)
Connection not possible (FCFS –waiting for EDS 2)
EDS 2 requested – 1000 MW
EDS 1 requested – 500 MW
70 WD
EDS 3 requested450 MW
EDS 2 (1000 MW) cannot be combined with EDS1
Extension timing – waiting end of reserved capacities
500 MW (EDS1) as input to analysis of on-going EDS
Connection possible
Connection possible ( If EDS 2 : 1000 MW)
2nd example
3 EDS received by ELIA. EDS influence each other (similar localization and significant volumes) Available capacity in this area : 1000 MW
In accordance to the “first come first served” principle and to minimize impact of EDS on each other (significant delay), ELIA will communicate to requester # 2 information on the remaining available capacity (taking reserved capacity into consideration). Example here: 500 MW
EDS 2 modified – 500 MW
Connection possible (500 MW)
Capacity reserved (120-180 WD)
Extension timing – waiting end of reserved capacity 1 and 2 (> 1 year)
These examples only concerns production units (B – C – D); hydro; HVDC…Connection process for consumption does not change (capacity reserved from moment request is complete)
or
“First come first serve” principle still valid.
Due to change of capacity reservation process in new FTR (capacity reserved from the moment EDS is sent + timing of 120 – 180 WD) and independent of the
CRM mechanism:
- Additional operational process to put in place (ELIA) to monitor the 120 – 180 WD period ; communicate on on-going EDS;…
- Risk of additional delay for connection requester if he is not the first one to introduce an EDS (up to a year) during which no EDS will be sent
Additional conclusion linked to the CRM mechanism
ELIA expects to receive several EDS in parallel in the coming months. Any connection request introduced from now on will be treated according to the principles
presented here (new FTR applicable) even though an EOS was introduced before 28/4/2019
Conclusions based on the 2 examples shown
Negative impact on liquidity and may increase costs as a consequence
ELIA’s proposal minimizes impact of several EDS introduced in parallel on project’s developers while respecting the “FCFS” principle
DROP-OFF PROCEDURE
FEDERAAL TECHNISCH REGLEMENT
27/04/2019
VERGADERING WERKGROEP BELGIAN GRID
22/05/2019
BILATERALE MEETINGS MET BELANGHEBBENDEN
EERSTE DRAFT VERSIE DROP-OFF PROCEDURE
SEPTEMBER VERGADERING WERKGROEP BELGIAN GRID
FINALE VERSIE DROP-OFF PROCEDURE
Eind 2019 / begin 2020
ANDERE AANPASSINGEN AAN HET TOEGANGSCONTRACT
PUBLIEKE CONSULTATIE
27/04/2019
Thank you for your attention
6 June 2019 – Users’ Group Plenary Meeting