what’s up in the booster eric prebys february 27, 2002 and march 6, 2003

18
What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Upload: francis-tucker

Post on 17-Jan-2018

215 views

Category:

Documents


0 download

DESCRIPTION

Some Cold Hard Facts about the Proton Future Running as we are now, the Booster can deliver a little over 1E20 protons per year – this is about a factor of six over typical stacking operations, and gives MiniBooNE about 20% of their baseline. NuMI will come on line in 2005, initially wanting about half of MiniBooNE’s rate, but hoping to increase their capacity – through Main Injector Improvements – until it is equal to MiniBooNE. Whatever the lab’s official policy, there will be great pressure (and good physics arguments) for running MiniBooNE and NuMI at the same time. -> By 2006 or so, the Proton Source will be called upon to deliver 10 times what it is delivering now. At the moment, there is NO PLAN for achieving this, short of a complete replacement! 1.8E20 ten33% 6

TRANSCRIPT

Page 1: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

What’s Up in the Booster

Eric PrebysFebruary 27, 2002 and March 6, 2003

Page 2: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Demand for 8 GeV Protons

8 GeV Proton Demand

0

2

4

6

8

10

12

14

16

18

20

Calendar Quarter

Prot

ons/

Hou

r (1E

16)

MiniBooNEBaseline

NUMI/MINOS

Collider Run I Level

Historical High ~3E12ppp x 13 to Main Ring each 5 sec

Present Operating Level

Fancy MI Loading schemes

Page 3: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Some Cold Hard Facts about the Proton Future

• Running as we are now, the Booster can deliver a little over 1E20 protons per year – this is about a factor of six over typical stacking operations, and gives MiniBooNE about 20% of their baseline.

• NuMI will come on line in 2005, initially wanting about half of MiniBooNE’s rate, but hoping to increase their capacity – through Main Injector Improvements – until it is equal to MiniBooNE.

• Whatever the lab’s official policy, there will be great pressure (and good physics arguments) for running MiniBooNE and NuMI at the same time.

• -> By 2006 or so, the Proton Source will be called upon to deliver 10 times what it is delivering now.

• At the moment, there is NO PLAN for achieving this, short of a complete replacement!

1.8E20

ten 33%

6

Page 4: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Limitations to Total Booster Flux

• Total protons per batch: 4E12 with decent beam loss, 5E12 max.

• Average rep rate of the machine:– Injection bump magnets (7.5Hz)– RF cavities (7.5Hz, maybe 15 w/cooling)– Kickers (15 Hz)– Extraction septa (now 4Hz, 7.5 after Jan. shutdown)

• Beam loss– Above ground:

• Shielding• Occupancy class of Booster towers

– Tunnel losses• Component damage• Activiation of high maintenance items (particularly RF cavities)

Of particular interest to NUMI

Our biggest concern

Page 5: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Proton Timelines

• Everything measured in 15 Hz “clicks”• Minimum Main Injector Ramp = 22 clicks = 1.4 s• MiniBoone batches “sneak in” while the MI is ramping.• Cycle times of interest

– Min. Stack cycle: 1 inj + 22 MI ramp = 23 clicks = 1.5 s– Min. NuMI cycle: 6 inj + 22 MI ramp = 28 clicks = 1.9 s– Full “Slipstack” cycle (total 11 batches):

6 inject+ 2 capture (6 -> 3)+ 2 inject+ 2 capture (2 -> 1)+ 2 inject+ 2 capture (2 -> 1)+ 1 inject+ 22 M.I. Ramp----------------------39 clicks = 2.6 s

Page 6: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Summary of Proton Ecomomics

 

Batches Protons delivered ( x E12 pps)* Total Scenario Cycle (clicks)

prepulse Stack MB NuMI

Rep rate (ave. Hz) Stack MB NuMI E12 /RunII

Stack 23 2 1 2.0 3.3 0. 0. 3.3 1.

Stack/MB 23 2 1 8 7.2 3.3 26.1 0. 29.3 9.0

Stack/NuMI 28 2 1 5 4.3 2.7 0. 13.4 16.1 4.9

Stack/NuMI/MB 28 2 1 10 5 9.6 2.7 28.8 13.4 42.9 13.1

Slipstack/NuMI 39 2 2 9 5.0 3.8 0. 17.3 21.2 6.5

Slipstack/NuMI/MB 39 2 2 13 9 10.0 3.8 25.0 17.3 46.2 14.2

Booster Hardware Issues Radiation Issues

MiniBooNE baseline 5E20 p/year

*assuming 5E12 protons per batch

NUMI “baseline” = 13.4E12 pps x 2E7 s/year 2.7E20 p/year

Right now we’re at roughly 1/3 of the MiniBooNE baseline

Page 7: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Typical Booster Cycle

Various Injected Intensities

Transition

Intensity (E12)

Energy Lost (KJ)

Time (s)

Page 8: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Booster Losses (Normalized to Trip Point)

BRF11: 200 mR/hr @ 1ft

BRF15: 300 mR/hr @ 1ft

Page 9: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Booster Tunnel Radiation Levels

Activation in Booster Tunnel (6 hour cooldown)

0

500

1000

1500

2000

2500

L20

L21_

RF9_ds

S21

L22_

RF12_us

L23_

RF13_us

L23_

RF14_ds

L24_

RF15_ds S24 S1 L3 S3 L5 S6 L8 L9 L1

0S11 S12 L1

3S13

L14_

RF2_us

L15_

RF3_us

L15_

RF4_ds

L16_

RF5_ds

S16

L17_

RF8_us

L18

L19_

RF17_ds S19

Standard Locations (some contact, some 1ft)

mR

/hr 28-Aug-02

17-Dec-02

• On the last access

• The people doing the radiation survey got about 20 mR.

• Two technicians received 30 mR doing a minor HV cable repair.

• We’re at (or past??) the absolute limit on our overall activation

Page 10: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Hardware Improvements to Booster

• Shielding and reclassification of Booster towers: complete 2001• New extraction septum (MP02) power supply: complete 11/02• New extraction septum: magnet complete. To be installed 1/03• Collimation system: complete, but cannot be used until…• Collimation system shielding: 75 tons of steel to be stacked 1/03• Time line improvements (very important for MiniBooNE

operation): more or less complete.• More cables for extraction septum (will allow 15 Hz

operation): ??• New injection bump magnets and PS: ??• New RF cavities: ??

Page 11: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Near Term Plan

• All near term hardware improvements will be complete by summer 2003. At the point the Booster will physically be able to run a 7.5 Hz.

• Proceed with tuning improvements (C. Ankenbrandt coor.):– Orbit correctors: complete, working out operational issues– Precision lattice measurement: Transition studies (gamma-t jump??): – Damping improvements: Pellico + ??– Dogleg compensation??– 37MHz laser prechopping.– Ramping stopband correction.– Injection bump lengthening.– Injection tune manipulation.– Etc.

Page 12: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Dogleg Problem

• Because of edge effects, the vertical dogleg magnets which steer beam around the extraction septa distort the injection lattice badly.

• Considering several solutions:– Two large aperture lattice magnets (best idea, lots of

money)– Stretch out or redesign doglegs. Can minimize but not

eliminate the problem.– Correction quads. No magic solution found.

• Took advantage of the recent TeV failure to move the dump septum and turn off its dogleg. Doing studies now.

Page 13: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Effect of Doglegs on Booster Dispersion

Page 14: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

RF Project

• RF cavities form the primary aperture restiction in the Booster (2 ¼” vs 3 ¼” beam pipe).

• Slight modified design will have 5” beam pipe.• Powered prototype built and tested. Two vacuum

prototypes will be fabricated with fabrication done largely by MiniBooNE and NuMI universities.

• These will be installed in the summer shutdown.• Full project ~$5.5M, maybe less with university help.• New solid state power supplies also ~$5.5M, but

largely a separate (and separately justifiable!) project.

Page 15: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Upgrade Cost EstimateTUNERNew ferrite cores 28 $500 $14,000New copper disks 28 $300 $8,400End caps 2 $300 $600Center hub casting 1 $5,000 $5,000Center conductor cones 2 $1,500 $3,000Internal bus package 1 $5,000 $5,000External bus package 1 $5,000 $5,000Stem 1 $1,500 $1,500Machine Shop per Tuner 1 $5,000 $5,000Misc. 1 $5,000 $5,000Total per tuner cost $52,500

CAVITYNew ceramic windows 2 $10,000 $20,000New blocking capacitor 1 $13,750 $13,750New B+ choke 1 $2,500 $2,500New beam tube 1 $1,500 $1,500New mu tube 1 $1,000 $1,000New end plate assemblies 2 $1,000 $2,000New outer shell 1 $15,000 $15,000New inner conductor 1 $10,000 $10,000New gap electrodes 4 $500 $2,000New tuner 3 $52,500 $157,500Machine Shop per Cavity 1 $23,810 $23,810Misc 1 $10,000 $10,000

Total per cavity cost $259,060

Total for 21 cavities 21 $5,440,249.92Labor Cost Estimate is shown below

LABOR (in man-years) Estimate for Cavity & Tuner OnlyMechanical Engineer 1 $100,000 $100,000RF Engineer 1.5 $100,000 $150,000Drafting 1 $100,000 $100,000Technician 3 $100,000 $300,000

Total labor cost $650,000

Series Tube Modulator 20 90,000 1,800,000.00

6 Kwatt Solid State Wideband driver 20 100,000 2,000,000.00

200 Kwatt Power Amplifier 20 80,000 1,600,000.00 -

Installation 18 5,000 90,000.00

Total Excluding FNAL Labor 10,930,249.92

Summary:

• ~$260K per cavity, of which $160K goes for the three tuners.

• A roughly equal amount for the power supply chain.

• About 20 cavities.

-> $11M total

Page 16: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Vague Longer Term Plans

• Dogleg improvements?– Separate downstream doglegs– beta-bump correctors– Large aperture lattice magnet.

• Injection bump improvements?– New magnets?– Move existing magnets further apart and redisign injection

girder (requires new injection “Lambertson”).– Improved power supply (being designed but on the back

burner).

Page 17: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Big Projects Which Have Nothing to Do with Intensity

• New Linac Lambertson (done, will be installed in summer).

• New EDWA magnets in MI-8 line (ditto).• New vacuum system (Eats up ~1 engineer). Finished

by summer?• LLRF upgrade. Slowly but surely.• New MP01, ML01 + PS. Replace VBC1 with ML02.

(magnets not built, no installation plan).

Page 18: What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Conclusions

• We are at or near the present limit of the Booster output.

• This is a factor of up to six away from what is needed.• Current plans might realistically increase things by a

factor of two or three, tops.• Getting further will be hard!!!• The Proton Source CANNOT achieve its goals

parasitically.• The pressure from the collider program is not going to

go away, so we have to come up with a plan to live together.