Federal Aviation Administration Wide Area Augmentation System (WAAS) – Program Overview By: Greg Thompson FAA Manager, WAAS Program Date: February 4, 2020

Upload: others

Post on 02-Jun-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministrationWide Area

Augmentation System (WAAS) –Program Overview

By: Greg Thompson

FAA Manager, WAAS Program

Date: February 4, 2020

Page 2: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 2

WAAS Program OverviewFebruary 4, 2020

Overview• Coverage and Performance• Schedule/Milestones• Current GEO System• Phase 4A/4B Transition• Dual Frequency Operations• Procedures and Avionics• Future Development• Websites

Page 3: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 3

WAAS Program OverviewFebruary 4, 2020

Coverage and Performance

Page 4: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 4

WAAS Program OverviewFebruary 4, 2020

Current WAAS LPV/LPV-200 Performance

Throughout the Continental US WAAS LPV and LPV-200 remains above 99%

Page 5: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 5

WAAS Program OverviewFebruary 4, 2020

Current WAAS RNP 0.3/0.1 Performance

RNP coverage goes to the lowest possible levels throughout all phases of flight within the Continental US and Hawaii

Page 6: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 6

WAAS Program OverviewFebruary 4, 2020

Performance Monitoring• Daily review of performance at 38 WAAS reference stations and

up to 10 NSTB stations– Precision approach

• Daily results documented at http://www.nstb.tc.faa.gov/pasummary/– Non-Precision approach

• Daily results documented at http://www.nstb.tc.faa.gov/npa_sps_summary/– GPS Standard Positioning Service (SPS)

• Daily results documented at http://www.nstb.tc.faa.gov/sps_summaryDB3/

• Daily review of LPV and LPV-200 performance at airports with RNAV instrument approach procedures (IAP)

• Airport predictions– Publish WAAS availability prediction for airports with LPV IAP

• Prediction tool available at http://www.nstb.tc.faa.gov/AirportSchedules/

Page 7: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 7

WAAS Program OverviewFebruary 4, 2020

WAAS Performance Jan 1– Mar 31 2019

Localizer Performance (LP) service is available when the calculated Horizontal Protection Level (HPL) is less than 40 meters. LocalizerPerformance with Vertical Guidance (LPV) service is available when the calculated HPL is less than 40 meters and the Vertical Protection Level (VPL) is less than 50 meters. Localizer Performance with Vertical Guidance to 200 foot decision height (LPV200) service is available when the calculated HPL is less than 40 meters and the VPL is less than 35 meters

Page 8: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 8

WAAS Program OverviewFebruary 4, 2020

WAAS Schedule

Page 9: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Legend

Milestone

ABP/Execution Plan Milestone

GEO Leased Service Ended

GEO Leased Service Started

Satellite Development

WAAS Schedule (2015-2022)G

EOs

FY15 FY17 FY18 FY19 FY20 FY21 FY22

Segment 4A

GEO 5 (SM9)

GEO 6 (S15)

GEO 7 (G30)

AMR

CRW

CRE

11/15

11/16

7/17

Base

FY16

DFO

Dual Frequency Operations Release 1- Processor U/GRelease 2 - GEO 5 IntegrationRelease 3 - Multicast UpgradeRelease 4 - Safety Comp U/GRelease 5 - GEO 6 IntegrationRelease 6 - O&M Fixes and TSS Fixes to BaselineRelease 7 - GEO 7 Integration

4/17

3/18

8/18

2/19

Phase 4A/4B Transition

7/19

4/21

9/21

JRC Strategy Decision

JRC FID DecisionCutover

Cutover

Cutover

Cutover

Cutover

Cutover

System Integration Complete

Base

Base

Phase 4B

Page 10: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 10

WAAS Program OverviewFebruary 4, 2020

GEO System

Page 11: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 11

WAAS Program OverviewFebruary 4, 2020

WAAS GEOs

• Anik F1R (CRE)– On contract thru July 2020 with options thru July 2022

• Eutelsat 117 WB [ex SatMex 9] (GEO 5)– Completed WAAS integration on March 27, 2018

• SES-15 (GEO 6)– Completed WAAS integration on June 15, 2019

Page 12: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 12

WAAS Program OverviewFebruary 4, 2020

GEO Sustainment (GEO 7)• GEO 7 Satellite Acquisition

– Task Order awarded to Leidos on March 8, 2018 • GEO is Intelsat at 125 West

– Integrated Baseline Review (IBR) completed September 2018– Preliminary Design Review (PDR) completed December 2018– Critical Design Review (CDR) completed April 2019– GEO Launch projected for June 13, 2020– GSP IOT projected to be complete October 2020– Phase 1 Testing (Milestone 1A) projected to be complete

February 2021– WAAS Integration, Test and Cutover projected by September

2021

Page 13: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 13

WAAS Program OverviewFebruary 4, 2020

WAAS GEO Coverage

Current and Future GEO Coverage

Page 14: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 14

WAAS Program OverviewFebruary 4, 2020

WAAS Phase 4A/4B Transition

Page 15: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 15

WAAS Program OverviewFebruary 4, 2020

WAAS Phase 4A – 4B Transition• FY20/21

– Two year continuation of the WAAS program prior to Phase 4B FID– Two releases to focused on continued sustainment of the operational

WAAS (Releases 6 and 7)• Release 6 will improve WAAS performance enhancements by correcting anomalies

to the O&M, Test Support Software (TSS) and network critical message logging capabilities

• Release 7 will integrate GEO 7 into WAAS and upgrade with new Signal Generator including the retrofitting of new

• SIGGENs at the GEO 5 and GEO 6 legacy GUS sites. GEO 7 projected to be operational by September 2021

– Continued definition of DFO Phase 4B requirements and alignment with GPS modernization schedule

– Demonstration of alternatives to transition the communications network from Time Division Multiplexing (TDM) to Internet Protocol (IP)

– Additional work will include:• Completion of L5 Dual Frequency (DF) signal analysis and support Minimal Operational

Performance Standards (MOPS) development to facilitate requirements definition• Resolution of WAAS Operations & Maintenance software reliability and maintainability

issues• Integration of GEO 7 • Replacement of obsolete Signal Generator (SIGGEN) • Generation of WAAS Phase 4B FID Artifacts

Page 16: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 16

WAAS Program OverviewFebruary 4, 2020

WAAS Dual Frequency Operations (DFO)

Page 17: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 17

WAAS Program OverviewFebruary 4, 2020

WAAS Phase 4B

GEO Acquisition & Integration

• GEO 7 Integration• GEO 8 Acquisition &

Integration

H-ARAIM

Evaluation & testing of Horizontal Advanced Receiver

Autonomous Integrity Monitoring Capabilities

Dual Frequency Operations

Hardware• C&V Hardware• Obsolete Processor Upgrade• SIGGEN• GUS Receivers

TDM-IP Transition

Design, testing, and implementation of TDM-IP

transition

Design, testing, and implementation of DFO

Software• L5 Message Generation• Correction & Verification • AIX to Linux• L2 to L5

Page 18: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 18

WAAS Program OverviewFebruary 4, 2020

Phase 4B Release timeframe2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

R1

R2

R3: IP Solution – Design / Development / Cutover

R4: DF LOC Design / Development

R9: DF FOC

R6: GEO 8

R8: GEO 9

R7: L2P(Y) Transition

L5 Test Signal (Non-continuous)

L5 (Non Aviation)

DF FOC

R5: System HW Refresh

DF IOC L5 (Aviation Use)

R4: DF IOC Development / Cutover

DF LOC

R3: Security Design / Implementation

WAAS Phase 4 DFO, began in 2014 to leverage improvements the Department of Defense (DoD) will make as part of its GPS modernization program, specifically the introduction of the second civil frequency (L5). Current US Air Force GPS plans predictdeclaration of GPS L5 Initial Operational Capability (IOC) in FY2022 and Full Operational Capability (FOC) in late FY 2028. FAA plans are for a 24-month transition leading to a WAAS DFO FOC in FY2030.

Page 19: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 19

WAAS Program OverviewFebruary 4, 2020

DFO Expected Deliverables• DFO development work

– Re-baseline Dual Frequency (DF) Prototype– Develop DF capability from Single Frequency (SF) Code base– Separate Correction and Verification (C&Vs) for SF and DF services– Develop a shadow environment DF approach– Integrate Covariance User Differential Range Error (UDRE) algorithm– Modify G-III to track higher GPS PRNs– Hardware updates to meet new FAA-E-2892e DF requirement standards

• The WAAS System requires continual modification and updates to meet the safety standards set forth by the FAA. In support of the new DF capability the program office will make updates to the Wide Area Master Stations (WMS) C&V subsystem, Operations and Maintenance (O&M) and the GUS Processor (GPT)

• Further critical DFO work will be identified during the next two years and integrated into the new WAAS DFO Prime Contract projected to be awarded by 2022

Page 20: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 20

WAAS Program OverviewFebruary 4, 2020

WAAS Procedures and Avionics

Page 21: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 21

WAAS Program OverviewFebruary 4, 2020

WAAS LPV/LP Instrument Approaches

• Most of the airports throughout the National Airspace System contain WAAS Procedures

• As of January 2020 there are currently 1,546 ILS procedures while WAAS has 4,764 LPV/LP procedures published

Page 22: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 22

WAAS Program OverviewFebruary 4, 2020

WAAS Avionics Equipage Status • Over 131,000 WAAS equipped aircraft

in the NAS– WAAS receivers provided by companies

such as: • Garmin, Universal, Rockwell Collins, Honeywell,

Avidyne, Innovative Solutions & Support (IS&S), Thales and Genesys Aerosystem (Chelton)

• Since 2006, aircraft equipage rates have increased each year

• All classes of aircraft are served in all phases of flight

• Enabling technology for NextGenprograms– Automatic Dependent Surveillance

Broadcast (ADS-B) – Performance Based Navigation (PBN)

Page 23: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 23

WAAS Program OverviewFebruary 4, 2020

Future Development

Page 24: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 24

WAAS Program OverviewFebruary 4, 2020

WAAS Phase 4B Investigations• Dual-Frequency Multi-constellation Capability (DFMC)

– International Focus is on taking advantage of other GPS like constellations

• International Civil Aviation Organization (ICAO) Navigation Systems Panel (NSP) has developed work plan that supports development of future standards for use of other Global Navigation Satellite Systems (GNSS)

– ICAO completed drafted SARPS Nov 2018– SARPS currently out for review and validation to be approved by October 2020

• SBAS Interoperability Working Group (IWG) has proposed preliminary DFMC requirements and a SBAS interface control standard

• ICAO NSP, RTCA and EUROCAE are developing draft standards– Aircraft equipage is expected no earlier than 2026– EU is expected to offer interim services for a wide range of users

• FAA supporting DFMC SBAS standards development– SARPS and MOPS development and validation

http://www.gps.gov/policy/cooperation/#europe

Page 25: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 25

WAAS Program OverviewFebruary 4, 2020

WAAS Phase 4B Investigations (cont.)• Advanced RAIM (ARAIM)

– Avionics-centric approach to dual-frequency multi-constellation– WG-C is developing a new work plan to develop standards and

supporting validation information• User Algorithm Documentation, Draft SARPs and CONOPS – Completed in 2018• Safety Documentation – Completed Sep 2018

– FAA focus on development of initial requirements for horizontal navigation (H-ARAIM)

• Developing airborne prototypes for flight testing• Document ground offline monitoring and begin prototyping if needed• Preliminary H-ARAIM safety case (include V-ARAIM as time allows)• Preliminary ICAO/RTCA requirements• Propose and validate new GPS/Galileo commitments• Gain approval for SARPS changes in 2020• Add material to DFMC MOPS to incorporate ARAIM function

http://www.gps.gov/policy/cooperation/#europe

Page 26: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 26

WAAS Program OverviewFebruary 4, 2020

Aviation Long-term Timeline

Page 27: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 27

WAAS Program OverviewFebruary 4, 2020

WAAS Phase 4B Investigations (cont.)

• Time-Division Multiplexing to Internet Protocol (TDM-to-IP)– TDM-to-IP project is an agency-wide initiative for transitioning of existing

Time Division Multiplexing (TDM) based point-to-point communication circuits into a NAS Operational Internet Protocol (OPIP) or Private Ethernet Virtual Local Area Network (VLAN)(PEV)

– WAAS Program Office is in coordination with the FAA Communications, Information & Network Programs (CINP) group and FAA Authorizing Official Designated Representative (AODR) on requirements

– Completed the TDM-IP Transition Study to select the best System Architecture for WAAS, and Demonstration tests have begun

– OPIP demo tests began August 2019– PEV demo tests scheduled to begin March 2020

Page 28: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 28

WAAS Program OverviewFebruary 4, 2020

Websites

Page 29: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 29

WAAS Program OverviewFebruary 4, 2020

Informational Sites

• For further detailed information please visit:– https://www.gps.gov/– Instrument Flight Procedures (IFP) Inventory Summary:

https://www.faa.gov/air_traffic/flight_info/aeronav/procedures/ifp_inventory_summary/

– William J. Hughes Technical Center WAAS Test Team: http://www.nstb.tc.faa.gov/

– FAA TV: The WAAS Experience : https://www.faa.gov/tv/?mediaId=730– Satellite Navigation WAAS Website:

https://www.faa.gov/about/office_org/headquarters_offices/ato/service_units/techops/navservices/gnss/waas/

Page 30: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 30

WAAS Program OverviewFebruary 4, 2020

Summary

• Maintaining a three GEO constellation

• Currently within Phase 4A-4B Transition Period– DFO follow on Contract

– Update of SIGGENs

– WAAS performance enhancements

– TDM-IP Demo Testing

– Integration of GEO 7

• Ongoing Future work with DFMC and ARAIM

Page 31: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 31

WAAS Program OverviewFebruary 4, 2020

BACKUP

Page 32: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 32

WAAS Program OverviewFebruary 4, 2020

Infrastructure and Requirements

Page 33: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 33

WAAS Program OverviewFebruary 4, 2020

WAAS System Architecture

Page 34: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 34

WAAS Program OverviewFebruary 4, 2020

WAAS System Architecture Wide-Area Reference Station (WRS)

• Collects Data from GPS and GEO Satellites

• Screens Data for ‘Outliers’

• Forwards Data to WMS’s

• Triple Redundant

Page 35: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 35

WAAS Program OverviewFebruary 4, 2020

WAAS System Architecture Wide-Area Master Station (WMS)

• Receives Data from WRS’s

• Calculates Satellite and IonosphericCorrections

• Defines IonosphericGrid Points (IGP’s)

• Ensures Satellite and IGP Integrity

• Generates WAAS Messages

• Sends Data to GUS’s

Page 36: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 36

WAAS Program OverviewFebruary 4, 2020

WAAS System Architecture GEO Uplink Subsystem (GUS)

• Receives WAAS Messages from WMS’s

• Schedules WAAS Messages

• Transfers Scheduled Messages to the RF Uplink Subsystem

• RFU Transmits WAAS Messages to GEO

• Verifies Integrity of Transmitted Messages

Page 37: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 37

WAAS Program OverviewFebruary 4, 2020

WAAS System Architecture Operations and Maintenance Subsystem (O&M)

• Provides Equipment Status for all WAAS Facilities• Monitors WAAS Performance• Allows Control of Equipment States/Modes• Provides Fault Isolation for All WAAS Facilities

Page 38: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 38

WAAS Program OverviewFebruary 4, 2020

WAAS Terrestrial Comm Network (TCN)

C&V

WEI

TCN

OEI

NOCC O& M

Network 1

Network 2

ZLA ZTL

ZAU ZDC

Local Site

WRS

Remote Sites

WRS / GUST

Remote Sites

WRS/ GUST

TCN

CN

CN

External Interface

Remote Sites

CNWRS TCN

Local Site

WRS

Local Site

WRS

Local Site

WRS

TCN

TCN

TCN

ZSE

CN

C&V

WMS

CN

WMS

WMS

Remote Sites

WRS/GUST Remote Sites

WRS/GUST

TCN

TCN

TCN TCN

C&V

WEI

TCN

OEI

POCC O &M

WMS

WMS

WRS

Local Site

Remote Sites

CNWRS TCN

TJXWMS

Page 39: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 39

WAAS Program OverviewFebruary 4, 2020

WAAS Requirements

Page 40: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 40

WAAS Program OverviewFebruary 4, 2020

WAAS GPS Requirements• Spectrum Requirement

– The WAAS must receive and process the GPS Signal In Space (SIS) at the L1, L2P(Y) and L5 frequencies through a one-way interface, generated in accordance with the GPS SPS PS, Interface Specification (IS)-GPS-200, IS-GPS-705 and GPS WAAS PS. In the event of conflict between the GPS documents and the GPS WAAS Performance Standard, the GPS WAAS Performance Standard will take precedence

– The GPS L1 and L5 bands used by WAAS are Aeronautical Radio Navigation Service (ARNS) protected. GPS L2, also in use by the WAAS ground system, is Radio Navigation Satellite Service (RNSS) protected

• WAAS must be consistent with national and international standards for these bands (e.g. Radio Frequency (RF) standards delineated by the International Telecommunication Union (ITU) and Annexes to the International Civil Aviation Organization (ICAO) Convention that establish international Standards and Recommended Practices (SARPs) for aeronautics

Page 41: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 41

WAAS Program OverviewFebruary 4, 2020

WAAS GPS Requirements

• Functional Requirement– A nominal GPS constellation of 24 operational

satellites with an availability of 0.95– At least 21 healthy satellites in the 24 nominal

plan/slot positions with an availability of 0.98– The GPS constellation must be compliant with the

GPS Standard Positioning Service (SPS) Performance Standard (PS)

Page 42: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 42

WAAS Program OverviewFebruary 4, 2020

WAAS User Requirements

• TSO-C145 “Airborne Navigation Sensors Using the GPS Augmented by the WAAS”

• TSO-C146 “Stand-Alone Airborne Navigation Equipment using the GPS Augmented by the WAAS”

Page 43: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 43

WAAS Program OverviewFebruary 4, 2020

WAAS User Requirements• TSO-C145/146c

– Minimum Performance Standards (MPS) qualification and documentation requirements for functional equipment Class Gamma or Delta in RTCA, Inc. document RTCA/DO-229D, Minimum Operational Performance Standards for Global Positioning System/Wide Area Augmentation System Airborne Equipment

– Qualifications• Functional Qualification

– Demonstrate the required performance under the test conditions in RTCA/DO-229D

• Environmental Qualification– Test the equipment according to RTCA/DO-229D,Section 2.4, and RTCA/DO-

160E, Environmental Conditions and Test Procedures for Airborne Equipment• Software Qualification

– Develop the software according to RTCA/DO-178B, Software Considerations in Airborne Systems and Equipment Certification

• Electronic Hardware Qualification– Develop the component to the guidance in FAA Advisory Circular (AC) 20-152,

RTCA, Inc. Document RTCA/DO-254, Design Assurance Guidance for Airborne Electronic Hardware

Page 44: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 44

WAAS Program OverviewFebruary 4, 2020

Benefits

Page 45: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 45

WAAS Program OverviewFebruary 4, 2020

WAAS vs ILS

• Provides service similar to ILS Category I– Vertical guidance– Glidepath more stable than that of ILS– Minimums as low as 200 feet

• which is lower than all Required Navigation Performance (RNP) Authorization Required (AR) approaches and all conventional (e.g. VOR, NDB) non-precision approaches

– Currently outnumber ILS approaches with a factor of greater then two to one

Page 46: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 46

WAAS Program OverviewFebruary 4, 2020

WAAS in All Areas of Flight

• WAAS provides benefits over standard GPS for all phases of flight to include Flight Planning, Terminal and Enroute Operations– Allows use of LNAV/VNAV minima without temperature

restrictions– Provides vertically-guided approach procedures capability at

airports that do not have groundbased navigational aides – Is not affected by snow reflections that can impact ILS

operations– Allows RNAV (GPS) approaches to be used for alternate

airport flight planning

Page 47: Wide Area Federal Aviation Administration …...– TDM-to-IP project is an agency-wide initiative for transitioning of existing Time Division Multiplexing (TDM) based point-to-point

Federal AviationAdministration 47

WAAS Program OverviewFebruary 4, 2020

WAAS in All Areas of Flight (cont.)

• Increases number of alternate airport options which improves flight planning flexibility

• Satisfies equipment requirements for ‘T’ and ‘Q’ routes (meets SFAR 97 in Alaska)

• Eliminates RAIM check requirement per AC 90-100A• Provides two additional ranging sources (from WAAS GEOs)• Enables extension of terminal mode operations for both

departure and• arrival to beyond 30 nautical miles from the airport reference

point• Increased accuracy and availability• Eliminates ILS critical areas• Enables ADS-B