Who we are Will group is a full service tower and wireless communication
site development and construction company located in Cairo, Egypt. It is an extension of Will Company, which was established in 2005.
Will group members started their telecommunication
career since 1996 and gained an extensive experience
through the work in companies with great reputation
such as Lucent Technologies in the Golden Pyramids
project, Alan Deck for Antennas Support in Vodafone
Egypt project, “GSM”.
Will group now offer a complete menu of services
tailored to our clients. As a turnkey solutions provider,
we act as a single source of responsibility for large
well known companies
Our Mission
Will Group looks forward to be the best telecom
contractor in Egypt, Middle East & North Africa
since we are going to provide:
Best quality
Reasonable cost
Shortest time
The top priority for Will Group is our client. That's
why we take the time to assess your particular
communication needs. We strive to be as flexible
and innovative as possible while working within
your financial budgets.
Our thorough evaluation prior to starting a project
assures that the work that is going to be performed
is going to be exceptional.
We stand behind our projects and our clients to
complete a quality and successful project. It is our
goal to earn your respect and develop a lasting
relationship.
Our Activities
• Search & Negotiation for Site Acquisition. • Civil Works related to Urban & Remote Telecom Sites.
• Design, Structural Calculation & Technical Files. • Coordination & Construction Supervision.
• Shelter Installation & Technical Room Construction. • Pylons and Masts Mounting.
• Connection to Electrical Network. • Installation & Commissioning of Radio Equipment.
• Installation & Commissioning of Generators, Rectifier & Batteries.
• Installation of Telecom Equipment.
• Erecting Towers of all Types & Heights. • Grounding & Lightning Protection.
• Mounting Of Radio Antenna and Microwave Links. • Steel fabrication (grillages, steel fences, brackets, trays,
trays support, shelter stairs, ladders, gates & masts).
Our Services
GSM Trunkey Projects
- Site acquisition services
- Line of sight services
- Construction works
- Equipment installation
Fixed Wireless Telephone lines
Turnkey Projects
- Site acquisition services
- Line of sight services
- Construction works
- Equipment installation
GSM Special Projects
- Co- site
- 3G RRH
- Modernization of site
- TX Enhancement
- Radio Enhancement
- RRH with Modernization
Our Services Process
Site Acquisition Survey Quality Control
SF2 Quality Control
Potential Option Choice Negotiation Stage Site Survey Stage Office Work Stage
Receive nominal request form “SF1”
Surveyor visit the site to -Locate the nominal &
search area -Take photos for the
potential
Acquisition Manager discuss the considerable potential
options which meets with the nominal
requirements
One option or
more
Survey report summery Explaining the site Circumstances & Nature to be submitted to the client
Negotiator contact the owner of the nominated options & make each an offer according to ceiling limit
Owner accept
the offer
One option or more
Acq. .manager with both of the legal division & permit choose the best
leasable & permitable option
One option or more
summaries explaining the site (s) circumstances to be
submitted to the client
Negotiator arrange an appointment between owner & surveyor
Surveyor works on producing the survey report
All options to be submitted to the
clients
Surveyor makes the survey for the nominated options as per the client specifications
Surveyor submit the sketch of the site location plan to the
drawing division
Acquisition manager review the survey
report
Survey report Approv
ed
Leasing Quality Control
Receive site evaluation
Leasing Quality Control
Negotiate with all options
Ownership documents
For all options
Legal division to check
Owner ship documents
Documents Status Define & Complete
Missing documents
Lawyer visits the sites to Discuss the lease with owners
Changes to be corporate Into Contract
Meeting with client
To discuss changes
Changes agreed By client
Complete the Lease Package & submit it to
The client
Permits Quality Control
Permits Drawings Quality Control
Cad division receives The package from
Surveyor
Cad division produces :
-Site Location Map -Plan View -Elevation View -Elec. & Lighting protection
Green Field & Rooftop Sites
Issue Permit Package by Permits department
Issue Permits Drawings To client
Construction process takes place
Construction Quality Control for Green Field& Roof Top sites
Construction Drawings Quality Control For Green Field & Roof Top sites
CAD Division receives the Package from Surveyor
CAD Division produces -Approved permit drawings -Arch. drawings -Civil drawings -Structure drawings -
Drawings checked by Surveyor / Cad Supervisor & Acquisition Manager
Drawings Are OK
Issue construction Drawings to client
Will Group For Communications Services
2
Table of Contents
- Introduction
- Our Company
- Employee Organization Chart
- Our Mission
- Our Activities
- Site Acquisition
- Site Construction
- Equipment installation
- Commissioning
- Site Maintenance
- Our Construction Sites
- Construction Photos Samples
Will Group For Communications Services
3
Introduction
• Will Group is established to be the best Telecom contractor in Egypt
and then in the region.
• Will Group provides solutions to satisfy the wireless networks on the
global bases.
• Will Group is capable of executing turn key projects with
• High quality,
• Reasonable cost
• In the shortest time.
• Will Group has the most experienced & well trained staff.
Will Group For Communications Services
4
Our Company
Will Group for Communications is a company duly incorporated under
the laws of Egypt with organization number 35801 and having its principal
office at 103 Misr/Helwan Agricultural road , Maadi, Helwan, Egypt.
Will Group for Communications is an extent ion of Will Company which
was established in Nov. 2005
Will Group for Communications provides solutions to satisfy the wireless
networks on the global bases.
Will Group for Communications had experience with several companies
such as;-
- Lucent Technologies in the Golden Pyramids project, “Egypt
wireless telephone System” from 1998 to 2000 as a company staff.
- Alan Deck for Antennas Support in Vodafone Egypt project, “GSM”
from 2000 to 2005 as a company staff.
- Ericsson Egypt Limited in Etisalat Egypt project, “GSM” from 2005
to 2007 as a company (civil work turnkey).
- Ericsson Egypt Limited in Vodafone Egypt project, “GSM” from 2006
up till now as a company (civil work turnkey).
- Nokia Siemens Networks in Vodafone Egypt project, “GSM” from
2007 up till now as accompany (civil work turnkey).
- Vodafone Egypt in Vodafone Power project from 2007 up till now.
Will Group For Communications Services
6
Our Mission
• We look forward to be the best telecom contractor in Egypt since
we are going to provide:
1. Best quality
2. Reasonable cost
3. shortest time
• The top priority for Will is our client. That's why we take the time to
assess your particular communication needs.
• We strive to be as flexible and innovative as possible while working
within your financial budgets
• Our thorough evaluation prior to starting a project assures that the
work that is going to be performed is going to be exceptional.
• We stand behind our projects and our clients to complete a quality
and successful project. It is our goal to earn your respect and develop
a lasting relationship.
Will Group For Communications Services
7
Our Activities Will Group scope of work include:-
• Search & Negotiation for Site Acquisition.
• Civil Works related to Urban & Remote Telecom Sites.
• Design, Structural Calculation & Technical Files.
• Coordination & Construction Supervision.
• Shelter Installation & Technical Room Construction.
• Pylons and Masts Mounting.
• Connection to Electrical Network.
• Installation & Commissioning of Radio Equipment.
• Installation & Commissioning of Generators, Rectifier & Batteries.
• Installation of Telecom Equipment.
• Erecting Towers of all Types & Heights.
• Grounding & Lightning Protection.
• Mounting Of Radio Antenna and Microwave Links.
Will Group For Communications Services
8
Site Acquisition Implementation of best practice in site acquisition ensures the entire
Process from site selection to completion of legal agreements.
- Will Group has the staff capable of completing the Site acquisition
process as quickly as possible.
- Will Group will take your RF Design and do site survey and negotiations as
well as doing the governmental approvals and final engineering design
& RF Design. The site acquisition team will also do the Construction
Drawings.
- Will Group knows that second to location, speedy installation is your main
concern. We believe that strong relationships with planning
departments and the wider community will be a good support for the
work of our acquisition surveyors. Next pages will show a simple chart
of the site acquisition quality control.
Will Group For Communications Services
9
Will Group has been finished all the acquisition works for wireless
telephones (Lucent Technologies).
Name of Exchange Sites
1. Shubra 23
2. Maarg 31
3. Marrioteyah 29
4. El Ahram 20
5. Heliopolis 9
6. Mokkatam 9
7. Nozha 13
8. Maadi net El Salam 12
9. Kalaa 22
10. Maadi 1 17
11. Maadi 2 4
12. Tora 4
13. Opera 10
14. Helwan 15
15. Abbassia 4
Our Services Process
Site Acquisition Survey Quality Control
SF2 Quality Control
Potential Option Choice Negotiation Stage Site Survey Stage Office Work Stage
Receive nominal request form “SF1”
Surveyor visit the site to -Locate the nominal &
search area -Take photos for the
potential
Acquisition Manager discuss the considerable potential
options which meets with the nominal
requirements
One option or
more
Survey report summery Explaining the site Circumstances & Nature to be submitted to the client
Negotiator contact the owner of the nominated options & make each an offer according to ceiling limit
Owner accept
the offer
One option or more
Acq. .manager with both of the legal division & permit choose the best
leasable & permitable option
One option or more
summaries explaining the site (s) circumstances to be
submitted to the client
Negotiator arrange an appointment between owner & surveyor
Surveyor works on producing the survey report
All options to be submitted to the
clients
Surveyor makes the survey for the nominated options as per the client specifications
Surveyor submit the sketch of the site location plan to the
drawing division
Acquisition manager review the survey
report
Survey report Approv
ed
Leasing Quality Control
Receive site evaluation
Leasing Quality Control
Negotiate with all options
Ownership documents
For all options
Legal division to check
Owner ship documents
Documents Status Define & Complete
Missing documents
Lawyer visits the sites to Discuss the lease with owners
Changes to be corporate Into Contract
Meeting with client
To discuss changes
Changes agreed By client
Complete the Lease Package & submit it to
The client
Permits Quality Control
Permits Drawings Quality Control
Cad division receives The package from
Surveyor
Cad division produces :
-Site Location Map -Plan View -Elevation View -Elec. & Lighting protection
Green Field & Rooftop Sites
Issue Permit Package by Permits department
Issue Permits Drawings To client
Construction process takes place
Construction Quality Control for Green Field& Roof Top sites
Construction Drawings Quality Control For Green Field & Roof Top sites
CAD Division receives the Package from Surveyor
CAD Division produces -Approved permit drawings -Arch. drawings -Civil drawings -Structure drawings -
Drawings checked by Surveyor / Cad Supervisor & Acquisition Manager
Drawings Are OK
Issue construction Drawings to client
Will Group For Communications Services
14
Survey “SF2” Quality Control
The Surveyor shall visit the site and locate the nominal and the search area radius according to SF1 by using GPS and binoculars. The Surveyor will make a sketch and take photographs of the potential usable options. The Acquisition Manager shall meet with the Surveyor and discuss the potential options taking the following conditions in consideration:-
a- General conditions (for Rooftop and Greenfield):-
1- The potential options should be in the search area.
2- The potential options fulfill the conditions and requirements of the different authorities and Ministers such as Environmental Ministry, Irrigation Ministry, Agriculture Ministry, Defense Ministry, Civil Aviation authorities, Housing Ministry, New Urban Authority and Health Ministry.
b- Rooftop special conditions:-
1- The buildings skeletons of potential options should not bearing walls.
2- The Roof should be reinforced concrete and in a good condition. 3- The options should be accessible. 4- The options should have suitable entrance and available access
to the roof. 5- The option should have available power source.
c- Greenfield special conditions:- 1- The options should be accessible. 2- The access roads leading to the site should be suitable to
construction equipments and vehicles (Trans-mixers, Loaders, trucks, Concrete pump, Cranes...etc).
The Acquisition Manager shall instruct the team Negotiator to contact the owner of all nominated options that fulfill the above conditions. If the potential options don't fulfill the above conditions, the Acquisition Manager shall instruct the Surveyor to make SF2 Summary explaining the nature and circumstances of the site and submit it to the client to either revise the nominal or to increase the search area.
Will Group For Communications Services
15
Leasing Quality Control Procedure
1- During the process of the SF2 and the negotiation for the options,
Will Group negotiator obtains a preliminary agreement (Heads of
Terms (H.O.T.s.)), signed by the owner/landlord, for each option.
This agreement to state the lease amount, the annual increase, any
advance payment due and what ownership documents are likely to
be submitted by the time of signing the lease contract.
2- Will Group negotiator to leave a copy of the standard lease contract
for the owner/landlord to study, leaving the owner/landlord sufficient
time to review it and make any comments. The negotiator will take
away a copy of the ownership documents.
3- The negotiator then refers back to the legal department of Will
Group, submitting the copy of the ownership documents (or
originals) and a copy of the SF2 of each option.
4- The legal department studies each option separately, and defines the
ownership documents required. If what the negotiator has submitted
is sufficient, a site visit is conducted to the first candidate assigned
by the client. If any legal document is missing, the legal department
informs the negotiator of what is required.
5- The negotiator refers back to the owner/landlord asking for the
missing documents. If they are not available, the process of issuing it
through the different legal authorities is initiated.
6- The negotiator arranges for a site visit with the lawyer, in order to
meet the owner/landlord face to face, to discuss any comments on
the lease contract and any modifications that may be required.
7- The legal department incorporates all the changes required by the
owner/landlord into the lease contract to get the clients approval.
8- A complete legal package is prepared for submission to the client,
which contains:
a- A signed Head of Terms with the owner/landlord.
b- A complete set of the ownership documents, checked by the Legal
Department.
c- A modified lease contract to satisfy the requirement of the
owner/landlord and the client.
Will Group For Communications Services
16
Permitting Analysis
a) General Permit Information :-
1. The process of permitting starts at the same time as the negotiation. The options, nominated for each site, should satisfy the requirements and the rules set by the Egyptian Environmental Affairs Agency. The Protocol, which was issued (2005) by EAA and the Ministry of Communication, should be followed strictly.
2. From our past experience, the options selected should be away from any Military Areas, and Military Airports, or Civil Aviation Airports. Also, any options near schools, hospitals and any health or education institutes have proven to be extremely difficult to complete the permitting process.
3. The requirements for the permit application package include : a. A delegation letter from the client, mentioning the address and
the name of the owner/landlord, to apply for the permit in their name for the specific site.
b. Lease contract, signed by each party, the landlord/owner and the operator.
c. Supervision Certificate issued by a consultant, signed and approve by the Engineering Syndicate, stating that the construction will be performed under the supervision of the consultant.
d. For Roof Top sites, a Safety Certificate for the building/structure.
e. For Greenfield sites, some municipalities ask for a Safety Certificate for the tower itself.
f. Form "A" of the "Environmental Form", completed and stamped by the operator, stating the equipment to be used, the height of the sub tower, and the antennas, and the height of the towers in the green field sites.
g. Simple drawing showing the layout of the site and the site location map. In the case of green field sites, only a general arrangement for the site is required.
4. It is almost impossible to state all the permit agencies in the country, but to simplify it; there is an agency in each village, town, city and governorate. The permit can be obtained from any, depending on the regulations in each governorate. In big cities like Cairo, Alex and Tanta, the permit is obtained from the Municipality of the district which the address of the site falls within.
Will Group For Communications Services
17
5. The agencies which we have obtained permits from include, but are not limited to : a. Local Municipality (In big cities, each district has its
Municipality) b. Local Council of towns c. Local Council of Villages d. Environment Office e. The Governor's Office
6. The possible permits that may be required : a. Environmental Permit, for each site without exceptions, takes
from seven to ten days. Sometimes, it has to be issued from the Governor's office itself.
b. Civil Aviation permit, depends on the municipality, takes one month.
c. Internal Affairs permit, not required by every municipality, takes one week.
d. Fire and Civil Defense permit, not necessarily required, takes one week.
e. Health Authority permit, not necessarily required, takes two weeks.
f. Agriculture permit, required for each Greenfield site, takes ten days.
g. Military permits, required for towers in desert areas or on roads, takes one month, but it does not delay issuing the build permit.
h. Archaeological permit for any areas suspected to have buried monuments, takes two months.
i. In the New Urban Authorities areas, an approval for the land or roof top must be obtained prior to the submittal of the option. This approval takes two months.
j. Build permit normally withheld until any other permits have been obtained. The build permit is the end result and takes two weeks.
k. Power permit takes one week for Roof Tops and is normally issued after building the site.
Will Group For Communications Services
18
b) Specific Information for Roof Top Permits:
1. It is important to get the Environment Form "A" approved by the Environmental Affairs Agency - it is the main document for getting the final permit.
2. Some Governorates withhold issuing the final permit (or the power permit) unless the Environment Affairs Agency conduct a second site visit and issue a second report stating that the site has been built according to their Specification (The Protocol).
3. Some Governorates issue the power permit coincidentally with the build permit. In these cases, it is preferable to install the power meter during or before the construction to speed up the total process.
4. Some Local Councils insist on having the Governor's approval
before they issue the build permit. 5. In some cases, donations to the Local Councils are an essential
factor in obtaining the permit. 6. In other cases, the local municipality insists on using local
consultants, to issue the supervision certificate or the safety certificate.
7. In all cases, money is the key factor to speed up the process of obtaining the permits.
c) Specific Information for Greenfield Permits:
1. Exactly the same as the Roof Top permits with the exception of
the power permit. Most of the time, the power permit is granted
after finishing the construction. To avoid delaying these sites for
revenue purposes, power is normally delivered by means of
temporary generators and the sites put 'On-Air'. If the site is close
to a power supply, we apply for the power, and the Electrical
Authority in the area is responsible of connecting the power after
paying the determined fees.
2. Agriculture permits are essential for the Greenfield sites in Delta.
3. Military Permits are essential in the Sinai and along Desert Roads.
4. If the site is in any of the New Urban Authority areas, as 6th of
October City or New Dumyiat, the process is completely different.
Once we have the approval of the New Urban Authority, the
permit can be obtained in one week based on that approval.
5. If the site is in an area belong to the Tourism Ministry, the process
is different again, as they sell the land and do not rent. After
Will Group For Communications Services
19
paying the agreed price, the permit can be obtained within two
weeks.
d) Health legislation and requirements:
1. The option nominated has to be away from hospitals, schools,
universities and any education institutes.
2. Roof Top sites should be chosen according to the Protocol issued
by Egypt Telecommunication and the Environmental Affairs
Agency (2005).
Will Group For Communications Services
20
Site Construction Will construction team provides all required civil work for telecom & IT networks such as
• Excavation for tower foundation • Tower foundation
• Tower erection
• Shelter installation • Tower grillage (for roof top sites)
• Poles & brackets for antennas, MW dishes, Bridges
Equipment Installation Will has experienced & well trained technician teams to achieve the RF, Rigging & power works in a very short time. Will provides all the required tests for equipments & cables
Site Maintenance Maintenance of communication towers is increasingly important and we provide a complete inspection of your structure which includes alignment and tensioning of guy wires, foundations, guy anchors and supports, lighting protection and paint conditions. The gathered data is stored on a database enabling us to keep our clients informed of needed maintenance
Will Group For Communications Services
21
and repairs. We give your structure the extended life and performance you demand. Our Constructed sites Will Group constructed all type of GSM sites, such as
- Roof Top Macro Site Indoor “Shelter” 6m poles structure. Indoor “Shelter” 9m poles structure. Indoor “Shelter” 9m stub tower structure. Indoor “Shelter” 12m stub tower structure. Indoor “Shelter” 15m stub tower structure. Indoor “Shelter” 21m stub tower structure. RRD.
- Green Filed Macro Site
Indoor “Shelter” 24m tower structure. Indoor “Shelter” 30m tower structure. Indoor & outdoor 36m tower structure. Indoor & outdoor 45m tower structure. Indoor & outdoor 55m tower structure. Indoor & outdoor 60m tower structure. GRD. Indoor 35m tower tube.
- Microcell site
Outdoor site. Indoor site.
- Co site, 3G site & Enhancement
- Other Operator Sharing Sites
Will Group For Communications Services
22
Our list is below;-
No. Site Location Site Type Structure Type
1 Basattine _ Cairo RT stand alone 15m Stub Tower
2 Helwan _ Cairo RT stand alone 15m Stub Tower
3 Mansorya _ Giza RT stand alone 15m Stub Tower
4 Mansouria Mehwar _ Giza GFstand alone 36m Monopole
5 Misr El Qadeema _ Cairo GFstand alone 36m Monopole
6 Shubra _ Cairo Microcell Out Door
7 Heliopolies _ Cairo Microcell In Door
8 Sayeda Zeinab _ Cairo Microcell Out Door
9 Attaba _ Cairo Microcell Out Door
10 15 May _ Helwan GFstand alone 36m Tower
11 Helwan RT stand alone 6m & 9m Poles
12 Helwan GFstand alone 36m Monopole
13 Gezirat El Arab Mohandseen
_ Giza RT stand alone 12m Stub Tower
14 Shubra _ Cairo RT stand alone 15m Stub Tower
15 3th Gatharing _ New Cairo RT stand alone 21m Stub Tower
16 Materia _ Cairo RT stand alone 12m Stub Tower
17 Materia _ Cairo RT stand alone 12m Stub Tower
18 Hurgadah _ Red Sea RT stand alone 15m Stub Tower
19 Suhag GFstand alone 45m Tower
20 Suhag GFstand alone 55m Tower
21 Suhag GFstand alone 45m Tower
22 Suhag RT stand alone 12m Stub Tower
23 Suhag GFstand alone 45m Tower
24 Suhag GFstand alone 45m Tower
25 Suhag GFstand alone 45m Tower
26 Suhag RT stand alone 12m Stub Tower
Will Group For Communications Services
23
27 Suhag GFstand alone 45m Tower
28 Suhag RT stand alone 12m Stub Tower
29 Qena RT stand alone 12m Stub Tower
30 Suhag RT stand alone 12m Stub Tower
31 Suhag GFstand alone 45m Tower
32 Qena GFstand alone 55m Tower
33 Qena GFstand alone 45m Tower
34 Cairo Alex. Road GFstand alone 24m Tower
35 Sharm - Dahab GF Sharing sites
36 Sharm - Dahab GF Sharing sites
37 Sharm - Dahab GF Sharing
sites
38 Sharm - Dahab GF Sharing
sites
39 Damanhour _ Beheira GFstand alone 45m Tower
40 Sharqiya GFstand alone 45m Tower
41 Suhag GFstand alone 45m Tower
42 Monofia GFstand alone
45m Tower
43 Beheira GFstand alone 45m Tower
44 Beheira GFstand alone 45m Tower
45 Beheira GFstand alone 45m Tower
46 Beheira GFstand alone 45m Tower
47 Beheira RT stand alone 15m Stub Tower
48 Beheira GFstand alone 45m Tower
49 Beheira GFstand alone 45m Tower
50 Suhag GFstand alone 45m Tower
51 Qena GFstand alone 45m Tower
52 Qena RT stand alone 15m Stub Tower
53 Qena GFstand alone 45m Tower
54 Maadi _ Cairo Repeater
Will Group For Communications Services
24
55 Helioplis _ Cairo Repeater
56 Sharm - Dahab Repeater Sharing
57 Abasyia PTT TX
enhancement
58 Abou Rawash PTT TX
enhancement
59 Asuit PTT TX enhancement
60 Bab El Luk PTT Trays
61 Garden City RT Cosite
62 Bolaaq _ Giza GF Cosite
63 Boulaq _ Giza RT Cosite
64 Zahraa _ Cairo RT Cosite
65 Hadayk Helwan RT Cosite
66 Damanhor kafr el Dawar GF Cosite
67 Cairo Belbis Road RT Cosite
68 Banha RT Cosite
69 Banha RT Cosite
70 El Hamul _ Kafr El Sheikh GF Cosite
71 Sidi Barany _ Matrouh GF Cosite
72 Shubra _ Cairo GF Cosite
73 Adfina PTT RT Cosite
74 Monouf Shohada RT Cosite
75 El Mahal GF Cosite
76 Shirbin _ Mansoura GF Cosite
77 Koum Hamada _ Beheira GF Cosite
78 Rasheed _ Beheira GFstand alone 45m Tower
79 Rasheed _ Beheira RT stand alone 15m Stub Tower
80 Helwan RT Cosite
81 El Omrania _ Giza RT Cosite
82 Wadi Hof _ Helwan RT Cosite
83 Hadayk Helwan RT Cosite
Will Group For Communications Services
25
84 Helwan RT Cosite
85 Nasr City 3 PTT RT Cosite
86 El Haram _ Giza RT Cosite
87 El Talbeiya - Giza RT Cosite
88 El Waylee _ Cairo RT Cosite
89 El-Ma'sara _ Helwan RT Cosite
90 Nobar _ Cairo RT Cosite
91 Helwan RT Cosite
92 Helwan GF Cosite
93 Bab El Sha'riaa _ Cairo RT Cosite
94 Shorouk City RT Cosite
95 Shorouk City RT Cosite
96 Gezirat El Arab Mohandseen
_ Giza RT Cosite
97 Obur PTT RT Cosite
98 Mitaria _ Cairo RT Cosite
99 Mahala El Kobra GF Cosite
100 Zagazig GF Cosite
101 Zagazig GF Cosite
102 Mansoura GF Cosite
103 Qaha _ Banha GF Cosite
104 El Zagaig GF Cosite
105 Giza PTT TX enhancement
106 Helwan PTT shelter
107 Imbaba PTT TX enhancement
108 Helwan GFstand alone 45m Tower
109 Embaba _ Giza RT stand alone 15m Stub Tower
110 El Mansoraya _ Giza RT stand alone 15m Stub Tower
111 Baragel _ Giza RT stand alone 15m Stub Tower
112 El Warak _ Giza RT stand alone 15m Stub Tower
113 Bolaaq _ Cairo RT stand alone 6m Poles
Will Group For Communications Services
26
114 3rd Gathareing _ New Cairo GF stand alone 35m Palm
115 Maydoub PTT TX enhancement
116 Menia PTT Shelter
117 Nozha PTT Shelter
118 Ras El Bar PTT Shelter
119 Asiuat GF stand alone 45m Tower
120 Suhag GFstand alone 45m Tower
121 Suhag GFstand alone 45m Tower
122 Suhag GFstand alone 45m Tower
123 Suhag GFstand alone 45m Tower
124 Qena GFstand alone 45m Tower
125 Qena GFstand alone 45m Tower
Will Group for Communications
Will Constructed Sites Samples
Green Field Tower Site
Roof Top Stub Tower Site
Green Filed Palm Tree Site
Green Field GRD Site
Will Group for Communications
Will Constructed Sites Samples
Green Field Tower Site
Roof Top Stub Tower Site
Green Filed Palm Tree Site
Green Field GRD Site
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
1) GF Site (45m Tower + Shelter)
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
2) Excavation photo
�
3) Soil Replacement & Compaction photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
4) Plain Concrete photo
5) Reinforce Concrete photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
6) Reinforce Concrete photo
7) Reinforce Concrete photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
8) Reinforce Concrete photo
9) Reinforce Concrete photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
10) Bituminus Insolation photo
11) Backfilling photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
12) Backfilling photo
13) Shelter & Generator Slab photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
14) Shelter & Generator Slab photo
15) Tower erection photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ���
16) Tower Erection photo
17) Tower Erection photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
18) Tower Erection photo
19) Shelter Assembly photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
20) Shelter Assembly photo.
21) Shelter Assembly photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
22) Shelter Assembly photo
23) Shelter installation of the internal fittings
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
24) Electric Distribution Panel
25) Installation of Switch Hand with Weather Proof Socket photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
26) Installation of Feeder Cable photo
27) Installation of Feeder Cable photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
28) Installation of Antennas photo
29) Photo for site access road
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
30) Security Fence Plain Concrete photo
31) Security Fence Semel photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
32) Security Fence Columns photo
33) Security Fence Columns photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
34) Brick Wall Security Fence photo
35) Brick Wall Security Fence photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
36) Finishing of the Brick Wall Security Fence photo
37) Cable Tray photo
Will Group for Communications
Green Field Site Construction Photos
���������� �� ����
38) Site Galvanized Gate photo
39) Site Leveling photo
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
1) RT Site (18m Tower + Shelter)
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
2) RT Site (18m Tower + Shelter)
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
3) RT Site (18m Tower + Shelter)
�
4) RT Site (6m Poles + Shelter)
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
5) Grillage Fixation
6) Grillage Fixation
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
7) Stub Tower Erection
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
8) Stub Tower Erection
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
9) Stub Tower Erection
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
10) Stub Tower Erection
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ���
11) Antennas Installation
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
12) Antennas Installation
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
13) Antennas Installation
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
14) RT Shelter
15) RT Shelter Grillage
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
16) Outdoor A/C Photo
17) Indoor A/C Photo
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
18) Shelter Distribution Board
19) Feeder Entry Glands
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
20) Cable tray
21) Cable tray
Will Group for Communications
Roof Top Site Construction Photos
���������� �� ����
22) Earth System Main Bas Bar.
23) Power and Earth main roots
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 1
1) Palm Tree Site (36m)
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 2
2) Palm Tree Site (36m)
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 3
3) Excavation photo
4) Soil Replacement & Compaction photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 4
5) Plain Concrete photo
6) Reinforce Concrete photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 5
7) Reinforce Concrete photo
8) Reinforce Concrete photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 6
9) Reinforce Concrete photo
10) Reinforce Concrete photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 7
11) Bituminus Insolation photo
12) Shelter & Generator Slab photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 8
13) Shelter & Generator Slab photo
14) Palm Tree erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 9
15) Palm Tree Erection photo
16) Tower Erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 10
17) Palm Tree Erection photo
18) Palm Tree Erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 11
19) Palm Tree Erection photo
20) Palm Tree Erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 12
21) Palm Tree Erection photo
22) Palm Tree Erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 13
23) Palm Tree Erection photo
24) Palm Tree Erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 14
25) Palm Tree Erection photo
26) Palm Tree Erection photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 15
27) Palm Tree Erection photo.
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 16
28) Shelter Assembly photo
29) Shelter Assembly photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 17
30) Shelter installation of the internal fittings
31) Electric Distribution Panel
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 18
32) Installation of Switch Hand with Weather Proof Socket photo
33) Security Fence Plain Concrete photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 19
34) Security Fence Semel photo
35) Security Fence Columns photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 20
36) Cable Tray photo
Will Group for Communications
Palm Tree Site Construction Photos
Will Group Page 21
37) Site Galvanized Gate photo
38) Site Leveling photo
������������������ ������ ���
���������� �� ���
�
��������� ����� ����
�
�
�
�
�
�
�
�
�
�
�
� �
�
�
������������������ ������ ���
���������� �� ���
�
��������� ����� ����
�
�
�
�
�
�
�
�
�
�
� �
� �
�
�
�
�
�
�
�
������������������ ������ ���
���������� �� ���
�
��������� ����� ����
�
�
�
�
�
�
�
�
�
�
� �
�
�
�
�
�
�
�
�
������������������ ������ ���
���������� �� ���
�
��������� ����� ����
�
�
�
�
�
�
�
�
�
�
� �
�
�
�