wind energy china
TRANSCRIPT
-
7/27/2019 Wind Energy China
1/11
1540-7977/11/$26.002011 IEEE6 IEEEpower & energy magazine november/december 2011
Wind Energyin China
C
CHINA IS A LAND WITH ABUNDANT WIND RESOURCES.
According to the latest official release of the national wind energy resource
assessment results, 50-m-high wind energy resource potential amounts
to about 2,580 GW, of which 2,380 GW is onshore and 200 GW is off-shore in the 525-m range of water depth. The areas suitable for developing
large-scale wind power include Northeast, Northwest, and North China, as
well as coastal areas in the provinces of Jiangsu and Shandong, where wind
power potential accounts for about 80% of the wind energy resource poten-
tial of the whole country, as shown in Figure 1. (This article does not contain
the data and information of the Hong Kong Special Administrative Region,
Macao Special Administrative Region, and Taiwan region; maps are for illus-
trative purposes only.)
Construction and Utilizationof Wind Power ProjectsChinas wind power has been experiencing rapid development since 2005. During 2005
2010, the cumulative installed capacity of wind power in China increased 35 times, adding
18.93 GW in 2010 (see Figure 2). By the end of 2010, Chinas cumulative installed capacity had
reached 44.73 GW, surpassing that of the United States and ranking first in the world.
Large and medium-sized projects with capacities of more than 10 MW have dominated wind power
plant construction in China. Especially since 2008, the government has begun to plan and construct a number of
1-GW wind power bases, and even some up to 10 GW. By the end of 2010, the number of wind power plants larger than
100 MW had reached 127, representing 64% of the existing installed capacity.
To date, China has the largest cumulative installed, grid-connected, offshore wind power capacity outside Europe. The
commission of the three 3-MW offshore wind turbines at the Shanghai Donghai Daqiao offshore wind power plant in Sep-
tember 2009 marked the start of Chinas megawatt-scale offshore wind power utilization. Meanwhile, the National Develop-
ment and Reform Commission (NDRC), Chinas top planner, launched the first round of concession projects for offshore
wind power plants in May 2010, with a total capacity of 1,000 MW. By the end of 2010, the total cumulative installed capac-
ity of offshore wind power in China had reached 142.5 MW.
In 2010, Chinas wind power generation was about 50.1 TWh, which accounted for 1.28% of net electricity consumption.
The wind power generation within the northeast power grid reached 17 TWh, or 6.0% of net electricity consumption; the
wind power generation within the eastern region of the Inner Mongolia power grid reached 5.9 TWh, or 21.1% of the net
electricity consumption. In 2010, the average full load hours of wind turbines amounted to 2,082.
Related Policies and Regulatory FrameworkThe Renewable Energy Law of the Peoples Republic of China (PRC) was adopted at the 14th session of the Standing
Committee of the Tenth National Peoples Congress on 28 February 2005 and took effect on 1 January 2006. The law
Digital Objec t Identifier 10.1109/MPE .2011.942350Date of publi cation : 21 October 2011
-
7/27/2019 Wind Energy China
2/11
november/december 2011 IEEEpower & energy magazine 37
Status and Prospects
By Liping Jiang, Yongning Chi, Haiyan Qin,Zheyi Pei, Qionghui Li, Mingliang Liu, Jianhua Bai,Weisheng Wang, Shuanglei Feng, Weizheng Kong,
and Qiankun Wang
DIGITAL VISION
established the basic legal system for
Chinas renewable energy (RE) devel-
opment and formed a general policy
and regulatory framework for promoting
renewable energy development and utili-
zation. On the basis of the law, the National
Energy Administration (NEA), Ministry
of Finance (MoF), State Electricity Regula-
tory Commission (SERC), and the other relatedgovernment authorities successively issued a series of
specified policies and regulations on RE generation, cov-
ering the definitions and related regulatory measures with
respect to priority scheduling and priority purchasing as well
as cost sharing among electricity consumers nationwide.
Through efforts spanning several years, a series of poli-
cies and a regulatory framework to promote RE develop-
ment have been put in place in China. In order to keep up
with the rapid development of RE, the Amendment of the
Renewable Energy Law was adopted at the 12th session
of the Standing Committee of the 11th National Peoples
Congress on 26 December 2009. The amendment empha-
sized the responsibilities and obligations of central and
local governments regarding the surveying of resources
and development planning and provided detailed sup-
port for the integration of RE generators. The amend-
ment established a dedicated RE development fund, whose
sources include both financing from the central government
budget and revenue from a legally authorized levy on electric-
ity consumers nationwide (the RE electricity surcharge). To
date, some of the methods supporting the Renewable Energy Law
are still under development or revision.
-
7/27/2019 Wind Energy China
3/11
8 IEEEpower & energy magazine november/december 2011
Project Approval and ManagementAuthorized by the PRC State Council, NDRC is the price
administration of the country and consequently respon-
sible fordeciding on and approving RE-generated electric-
ity pricing. NEA has the responsibility for formulating and
issuing annual plans, as well as for medium- and long-term
wind power development planning and for approving newly
built wind power projects and power grid projects. SERC
is responsible for supervising the operations of wind power
plants and the power grid.
According to the Regulation on Management of RE Gen-
eration introduced by NDRC in 2006, wind power projects
with capacities of 50 MW and above should be approved by
NDRC, and those with capacities below 50 MW should be
approved by the local provincial authority reporting to NDRC.
Feed-In TariffsFeed-in tariff policy for RE power generation in China has
experienced several different periods. Before 2003, the
feed-in tariff was determined case by case along with each
individual wind power project, based on the power purchase
agreement signed between the wind power plant operator
and the grid enterprise, approved by the local government,
and reported to the National Price Bureau. During 2003
2007, a concession bidding pricing mechanism was intro-
duced. This was meant to be the main pricing mechanism
for wind power, along with a feed-in tariff equivalent to the
benchmarked local desulfurized coal-fired power feed-in
tariff plusa subsidy of no more than CNY 0.25 per kWh.
On 1 August 2009, NDRC issued the Notice on Price Pol-
icy Improvement for Onshore Wind Power, which instituted
a fixed-benchmark pricing system for onshore wind power
in place of the concession bidding pricing mechanism. This
new mechanism created four categories of feed-in tariff,based on the regional wind resource and difference
5071,2
67
1,2
88
2,5
55
3,3
11
5,8
66
6,1
54 12,0
20
13,8
03
18,9
28
44,7
33
50,000
40,000
30,000
20,000
10,000
0
MW
2005 2006 2007 2008 2009 2010
25,8
05
AddedInstalled CapacityAccumulativeInstalled Capacity
figure 2. Wind power capacity of China, 20052010.
100
100
100
100
200100
100
150
50
150
150150
150
150
200
200
150100
150 150
150
150
150
150
150
150
150
150100
100
100
100
200
50
50
50
50
150
100
100 100
200
200
200
200
200
200200
200
50
50
100
100
200 W/m2 or Above (High)
150200 W/m2
100150 W/m2
50100 W/m2
50 W/m2 or Below (Low)
Area ofNorthwest
China
Area
of
North
Chi
na
Area of
NortheastChina
Coastal Areas
figure 1. Schematic diagram of wind power resources in China.
-
7/27/2019 Wind Energy China
4/11
november/december 2011 IEEEpower & energy magazine 39
in geographical conditions. The
four benchmark feed-in tariffs
were set up correspondingly as
CNY0.51/kWh, CNY0.54/kWh,
CNY0.58/kWh, and CNY0.61/kWh
(see Table 1 and Figure 3). They
reflect the concept that the betterthe average wind conditions are, the
lower the tariff level should be.
Mechanism ofRE Electricity SurchargeAccording to the cost-sharing prin-
ciples determined by the Renew-
able Energy Law, the excess of the
renewable energy power generation
project feed-in tariff over the local
desulfur ized coalpower bench-
mark price and the excess of theoverall cost of the independent RE-
based power system project over the
Category I: 0.51 CNY/kWh
Category II: 0.54 CNY/kWh
Category III: 0.58 CNY/kWh
Category IV: 0.61 CNY/kWh
figure 3. Benchmark feed-in tariff zones for onshore wind power.
table 1. Benchmark feed-in tariffs for onshore wind power.
ResourceZone
Benchmark Feed-InTariff (CNY/kWh) Administrative Areas Included
Category I 0.51 Inner Mongolia Autonomous Region exceptChifeng, Tongliao, Xinganmeng, Hulunbeier;
Xinjiang Uygur Autonomous Region:Urumqi, Yili, Karamay, Shihezi
Category II 0.54 Hebei Province: Zhangjiakou, Chengde;Inner Mongolia Autonomous Region:Chifeng, Tongliao, Xinganmeng, HulunbeierGansu Province: Zhangye, Jiayuguan, Jiuquan
Category III 0.58 Jilin Province: Baicheng, Songyuan;Heilongjiang Province:
Jixi, Shuangyashan, Qitaihe, Suihua, Yichun,Daxinganling region;Gansu Province exceptZhangye, Jiayuguan, Jiuquan;Xinjiang Uygur Autonomous Region exceptUrumqi, Yili, Changji, Karamay, Shihezi;Ningxia Hui Autonomous Region
Category IV 0.61 Other parts of China not mentioned above
-
7/27/2019 Wind Energy China
5/11
0 IEEEpower & energy magazine november/december 2011
local provincial average retail tariff, as well as a calculated
cost for RE power integration, should be subsidized by an RE
electricity surcharge. This surcharge is currently imposed on
electricity customers nationwide and applies to about 85% of
the total electricity consumption. NDRC and SERCjointly
release a report on the RE Electricity Surcharge Levy and
Subsidy Arrangement to the public periodically every year,
since 2006.The RE electricity surcharge was raised from CNY 0.1
cent/kWh in 2006 to CNY 0.4 cent/kWh in 2009. The total
RE electricity surcharge in 2009 was about CNY12 billion,
but this amount covered only about 70% of the needed subsi-
dies for RE generation. It appears that the RE electricity sur-
charge deficit will be enlarged with the rapid development of
RE in the coming years.
Concession Bidding of Wind Power ProjectsIn order to promote development of wind power and determine
the real costs of wind power generation, the Chinese govern-
ment decided to implement a concession bidding mechanism
for some large-scale wind power projects in 2003. From 2003
to 2007, five concession biddings of onshore wind power were
conducted, which covered 15 projects and 2.6 GW. In 2010,
the concession bidding process for four offshore wind power
projects located in the coastal area of Jiangsu, totaling 1 GW,
was completed. Table 2 summarizes these developments.
Technical Standards for Wind Power GridConnection, Operation, and ManagementA lack of technical standards and the absence of regula-
tions for wind power integration were recognized as two of
the main issues encumbering Chinas wind power develop-ment, especially with the rapid growth of wind power within
the past ten years. In December 2010, NEA finally issued
a regulation, Tentative Management Procedures for Grid-
Connection Testing of Wind Turbines, requiring that, from
1 January 2011, wind turbines within newly approved wind
power plants must pass grid-connection testing and comply
with the relevant technical requirements before they can
be permitted to connect to the grid and begin operation. In
March 2011, NEA issued the Management Procedures on
Wind Power Forecasting and Coordinated Operation with
the Power System (a draft guide) to identify the explicit
responsibilities of different stakeholders and specify system
requirements and supervision. Certain other, related techni-
cal standards and regulations are still under discussion.
Development of WindTurbine Industry and Technology
Status of the Wind Turbine IndustryThanks to the great support of policy incentives and huge
market demand during the past ten years, the wind turbine
manufacturing industry has developed rapidly in China,
with a full industry supply chain being formed. By the end
of 2010, 88% of the domestic market was occupied by Chi-
nese wind turbine manufacturers, compared with 30% in
2005. Wind turbines, blades, gearboxes, and other com-
ponents have been exported to countries in North Amer-
ica, Africa, Europe, and Southeast Asia. DEC, Goldwind,
Sinovel, and United Power were listed among the top ten
global turbine suppliers in 2010, and three more Chinese
domestic manufacturers were included in the top 15 (see
Figure 4).
In terms of the cumulative installed capacity in China,
there were 16 wind turbine manufacturers with a market
share of more than 1% at the end of 2010. Among them,five foreign manufacturers shared 17.5% of the market, with
table 2. Concession bidding of wind power projects in China.
Type Bidding Time Projects Capacity (MW) Bidding Prices Range (CNY/kWh)
Onshore September 2003 2 200 0.43650.5013
Onshore September 2004 3 300 0.38200.5190
Onshore August 2005 3 450 0.46160.6000
Onshore August 2006 3 700 0.40560.5006Onshore November 2007 4 950 0.46800.5510
Offshore September 2010 4 1,000 0.62350.7370
14%
12%
10%
8%
6%
4%
2%
0%
Vestas
Sinovel
GE
GoldWind
Enercon
Gamesa
DEC
Sulon
Siemens
UnitedPower
MingYang
ShanghaiElectric
Nordex
XEMC
Repower
figure 4. The top 15 global wind turbine manufactur-
ers and their shares of the global market (source: ChineseWind Energy Association).
-
7/27/2019 Wind Energy China
6/11
november/december 2011 IEEEpower & energy magazine 41
7,285 MW of capacity, and 11 Chinese domestic manufactur-
ers shared 75.7% of the market, with 33,962 MW of capacity.
Of these 16, Sinovel, Gold Wind, DEC, Vestas, and United
Power are the top five in order of market share.
Status of Wind Power Technology
The unit size of wind turbines has been increasing in recentyears. Before 2005, wind turbines with unit capacities of
250 kW, 600 kW, and 850 kW dominated the Chinese mar-
ket. Imported MW-level wind turbines were introduced
into the Chinese market during the first and second con-
cession bidding. About 51% of the annual newly installed
market was held by MW-level wind turbines in 2007, with
an average rated capacity of 1,048.9 kW, which increased
to 1,466.8 kW in 2010 when the MW-level wind turbine
became a mainstream product. Figure 5 shows the growth
of wind turbine unit capacity from 2000 to 2010. More
recently, multi-MW wind turbine production and applica-
tion in China has made considerable progress. The 3-MWwind turbine has been put into batch production and
installed successfully; furthermore, a prototype 5-MW
wind turbine has been produced.
The application of both gearbox drive and direct-drive
technology is popular. As in the global market, the dou-
bly fed induction generator (DFIG) with multistage gear-
box drive train has become a mainstream technology, with
mature development and full utilization in China. During
the past five yearsfrom 2006 to 2010high-speed gear-
box drive technology took a 70% market share in China;
meanwhile, direct-drive technology has also been develop-
ing steadily, with its market share growing from 0.1% in
2006 to 21.5% in 2010.
Offshore wind technology has also made great prog-
ress in China. The 3-MW wind turbine manufactured by
Sinovel and installed in the Shanghai Donghai Bridge off-
shore wind project in March 2009 was a milestone demon-
strating Chinas success in MW-scale offshore wind turbine
research and manufacture.
Grid Code andGrid-Connection ProceduresThe first Chinese grid code presenting technical require-
ments and specifying procedures for wind power integra-
tionGB/Z 19963-2005, Technical Rule for Connecting
Wind Power Plant with Power Grid, drafted by the China
Electric Power Research Institute (CEPRI) and managed
by the China Electricity Council (CEC)was issued on 12
December 2005 by the General Administration of Quality
Supervision, Inspection, and Quarantine (AQSIQ) and the
Standardization Administration of China (SAC).
At the beginning of the grid code formulation procedure,
the technical requirements for grid-connected plants were
moderate in some aspects, given the lower wind penetration
actually achieved and the technological limitations of thevarious wind turbine manufacturers.
With the rapid growth of Chinese installed capacity
which has approximately doubled annually during the pastfive yearsthe impact of wind power became a prominent
issue in power system operation and security in some areas.
In order to ensure the stable and reliable operation of wind
power plants, certain new technical requirements were
added to the revised grid code, which was drafted mainly by
CEPRI, China LongYuan Power Group Corporation, and the
Electric Power Research Institute of Southern Power Grid,
in collaboration with China Power Engineering Consulting
(Group) Corporation.
Grid Code Requirementsfor Wind Power PlantsFigure 6 shows the terminology and definitions used in
the grid code for wind power plants, points of connection
(POCs), active power, and reactive power, as well as for the
transmission lines of wind power plants.
The following requirements were included in the revised
grid code:
Active power control: A wind power plant should have
the ability to control active power according to orders
issued by the dispatching center of the power system.
In order to fulfill this control function, a wind power
plant active power control system must be installed.
Reactive power capacity and voltage control: For a
single wind power plant directly connected to the pub-
lic network, the capacitive reactive power compensa-
tion should cover not only the reactive power loss of
the wind power plant collector system and the step-up
transformers but also half of the reactive power loss of
the transmission line in the case of heavy loading. In
the case of light loading, the inductive reactive power
compensation should cover half of the capacitive charg-
ing reactive power of the transmission line. For large
wind power clusters, the capacitive reactive power de-
vices should compensate all the reactive power loss ofthe transmission line in the case of heavy loading; in the
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
695
.2
618
.3
608.4
75
0.4
7
90.2
852
921.7
1,0
48.9
1,2
13.5
1,3
62.7
1,4
66.8
kW
figure 5. Average rated capacity of newly installed windturbines in China, 20002010.
-
7/27/2019 Wind Energy China
7/11
2 IEEEpower & energy magazine november/december 2011
case of light loading, the inductive reactive power de-vices should compensate all the charging capacitive re-
active power of the transmission line. The wind power
plant should regulate the voltage of the POC so that it
remains within 97107% of nominal voltage when the
system voltage is within the normal operating range.
Low-voltage ride-through (LVRT): The requirements
of wind power plant low-voltage ride-through are
shown in Figure 7.
If the voltage at the POC of the wind power plant is higher
than the voltage profile, drops to 20% of the nominal volt-
age with the duration for 625 ms and recovers to 90% of the
nominal voltage within two seconds, which arose from the
grid fault and is shown in Figure 7, all wind turbines within
the wind power plant shall remain connected to the system
without tripping.
The active power output of the connected wind turbines
must be continuously restored to the original value after
fault clearance and with a gradient of at least 10% of the
rated power per second.
Wind power plants located in 1-GW and larger wind
power clusters should be designed to support reactive power
dynamically during a balanced
system fault. The dynamic reac-
tive current injected into the power
system from a wind power plant
should be equal to 1.5 (0.9
UT) IN, where 0.2 #UT# 0.9
and whereIN is the rated current inper unit of wind power plant and
UT is the voltage in per unit at the
POC of the wind power plant.
Grid-Connection Testing Contents of testing: Figure 8
shows the main areas of wind
power plant and wind turbine
testing; these include wind
turbine type testing, wind
turbine grid-connection
testing, and wind power plant grid-connection test-ing. Grid-connection testing of wind power plants
should comply with State Grid Corporation of China
(SGCC) Enterprise Standard Q/GDW 392-2009,
Technical Rule for Connecting Wind Power Plants
with the Power Grid, which presents requirements for
wind power plants regarding power quality, active and
reactive power control capability, LVRT, and so on.
LVRT testing: International experience has shown
that wind power plant LVRT capability relies greatly
on the LVRT capability of individual wind turbines.
CEPRI has made substantial progress in the LVRT
testing of wind turbines, developing (in cooperation
with FGH Germany) the first mobile wind turbine
LVRT test facility in China.
Grid-Connection Procedures,Including LVRT VerificationAccording to Q/GDW 392-2009, the entire wind power plant
should have LVRT capability and other controllability. In
many countries, modeling and simulation are used for the
verification of wind power plant LVRT capability. Based on
the LVRT testing results, modeling of the wind turbine can be
carried out and verified. Based on the verified wind turbine
model, the modeling of the whole wind power plant can then
be established, and the LVRT capability of the wind power
plant can be verified through power system simulation.
Main Issues of Wind Power Integration
Flexibility of Power System OperationsFrom the power system perspective, the big barrier in China
to accommodation of large-scale wind power integration is
poor system operational flexibility, since the major form of
generation in China is the coal-fired power plant and the flex-
ibility of hydropower in China is limited (this is due to the highproportion of run-of-river power plants whose responsibilities
Voltage Dip Caused by Grid Fault
Wind TurbineMust Not
Trip
1.21.1
10.90.80.70.60.50.40.30.20.1
01 0 0.625
Time (s)
Voltageat
PointofConnection(p
u.)
1 2 3 4
Wind Turbine May Trip
figure 7. Wind power plants: LVRT capabilityrequirement.
Transmission Line ofWind Power Plant
Active Power
WindTurbine
Collection System
Step-UpTransformer
Reactive Power
Wind PowerPlant
High-Voltage Bus(Point of Connection)
P Q
. . .
. . . . . . . . . .
figure 6. Wind power terminology and definitions in the grid code.
-
7/27/2019 Wind Energy China
8/11
november/december 2011 IEEEpower & energy magazine 43
include flood control, agricultural
irrigation, shipping, and so on).
By the end of 2010, total cumula-
tive installed generation capacity
in China was 966 GW, of which
the installed capacity of coal-fired
plants accounted for 66.9% butnatural gasfired and oil-fired gen-
eration accounted for only 3.6%.
Hydropower (including pumped
storage at 15.3 GW or 1.5%)
accounted for 22.4% (see Figure 9).
The situation in north, north-
eastern, and northwestern China,
where the abundant wind resources
are located, has been even worse
during the winter. Winter is a sea-
son of heavy heat demand, and
the power generation output ofthe coal-fired combined heat and
power (CHP) plants is determined
by heating demand. Therefore, the
systems ability to accommodate
large-scale wind power is dra-
matically reduced in winter. Take
northeastern China as an exam-
ple: it becomes more difficult to
accommodate a high wind penetration because of the lower
regulation capability of coal-fired plants in winter and spring,
when the wind blows strongest.
The relatively low capacity of the tie lines in the regional
power grids results in interregional power transmission
congestion and a shortfall of mutual power-balancing sup-
port capability, thus reducing the capability of the whole
power system to accommodate wind power. Table 3 shows
the load, wind power capacity, and tie-line capacity of north-
eastern and northwestern China, where there is high wind
penetration but low load. In some
areas of northeastern China (e.g.,
the eastern region of Inner Mon-
golia Autonomous Region, Jilin
Province, and Liaoning Province)
and northwestern China (e.g.,
Gansu province and Xinjiang
Uygur Autonomous Region), wind
power integration is confronting
significant challenges due to the
poor flexibility of the system, low
load, and limited tie-line capacity.
Transmission forLarge-Scale Wind PowerA higher-voltage transmission sys-
tem with larger power capabilityis being developed for improved
wind power integration and accommodation. As in Europe,
where it has been necessary to develop dedicated power corri-
dors and grid-connection projects to integrate large-scale off-
shore wind power plants, it is necessary for large-scale wind
power plants located in remote regions of northeastern and
northwestern China to connect to high-voltage transmission
lines in order to send energy out to load centers. For exam-
ple, the Ganhekou wind power project in Gansu Province
consists of several 200-MW wind power plants. Several
330-kV dedicated wind power substations, each of which
Wind Turbine Type Testing
Power Performance
Noise
Load
Power QualityPower Quality
LVRTLVRT
Active Power/ReactivePower Controllability
Active Power/Reactive
Power Controllability
Frequency/VoltageCompliance
AntiinterferenceCapability
Frequency/VoltageCompliance
Antiinterference
Capability
Wind TurbineGrid Connection Testing
Wind Power PlantGrid Connection Testing
figure 8. Contents of grid-connection testing of wind power plants and windturbines.
Other0.3
0.0%
Wind29.63.1%
Nuclear10.81.1%
Hydro216.122.4%
Thermal Power709.773%
Coal-Fired646.666.9%
Gas andOil-Fired
35.23.6%
Other ThermalPower27.92.9%
figure 9. Existing Chinese grid-connected generation capacity, in GW (source: CEC).
-
7/27/2019 Wind Energy China
9/11
4 IEEEpower & energy magazine november/december 2011
collects the output of two or three wind power plants, are
connected to the main 750-kV system to deliver the large
quantity of wind power produced by wind farms located at
Ganhekou to the northwestern power grid.
According to SGCC statistics, by the end of 2010,
23,200 km of transmission line for wind power grid con-
nection had been built, of which 58.1% (13,450 km) is
rated at 220 kV and above. Figure 10 shows the propor-tion of these transmission lines rated at each of several
voltage levels.
Based on the evaluation of wind resource and site condi-
tions, NEA has put forward an ambitious plan and launched
the construction of eight 10-GW-level wind power bases (see
Figure 11). According to this plan, SGCC has carried out a
comprehensive integration study for each wind power base,
including an assessment of system accommodation capabil-
ity and wind power trading markets, as well as the power
delivery plan. The study concluded that:
Wind power in Shandong and Jiangsu provinces
should be accommodated within the local prov-
inces.
Wind power in Hebei Province should be sent out to
the northern, eastern, and central China power grids
in addition to the Beijing, Tianjin, and Tangshan
power grids.
Wind power in the other five bases should be sent
out to the northern, eastern, and central China grids
through interprovincial or interregional tie lines.
The eight large-scale wind power bases being estab-
lished will account for more than 70 GW of the 100 GW
of wind capacity called for by 2015 in the national wind
power development plan. Of this 70 GW, 42 GW will be
delivered through interprovincial or interregional tie lines.
Furthermore, when wind power installed capacity in China
reaches 160 GW, these eight bases will provide more than
75% of total wind capacity, and the wind power deliveredacross provinces or regions will reach 70 GW. With such
large-scale development planned for the future, additional
grid expansion and reinforcement are needed.
Role of Wind Power ForecastingAccurate wind power forecasting is the foundation for
increasing the precision of power dispatching and enhancing
the ability of the power system to accommodate wind power.
It is also helpful in order to decrease the needed reserve
capacity, improve the economy of the power system as a
whole, and thus reduce the cost of wind power development.
Government has provided significant policy, regulatory, and
financial support to facilitate innovation to increase the preci-
sion of wind power forecasting and promote better forecasting
technologies. The Ministry of Science and Technology led two
national science and technology support programs, Develop-
ment and Demonstration of Wind Power Forecasting Systems
and Research on Key Technologies for a Wind/PV/Storage/
Transmission Joint Demonstration Project. The NEA con-
ducted a study on the policy aspects of coordination and man-
agement of wind power forecasting and the power system. The
National Meteorological Administration developed a numeri-
cal weather-forecasting model with 1-km horizontal resolution
for the Jiuquan wind power base in Gansu Province. SGCC set
up the Operations Center for Numerical Weather Forecasting at
CEPRI for wind power forecasting, based on massively paral-
lel computing and using more than 4,000 cores. The center is
expected to eventually incorporate 10,000 cores.
So far, wind power forecasting service providers have
mastered the technology of short-term forecasting methods,
including physical, statistical, and hybrid methods, as well
as ultra-short-term forecasting methods based on real-time
observed wind and power data. In November 2008, the first
wind power forecasting system was put into operation at
the Jilin electric dispatching center. By the end of 2010, thewind power forecasting system covered more than 20 GW
110 kV and Below,9,703 km
750 kV, 1,694 km
500 kV, 2,786 km
330 kV, 475 km
220 kV, 8,494 km
,
50
220 k
figure 10. Wind power grid connection transmission linesinstalled through 2010, by voltage type.
table 3. Tie-line capacity in northeastern and northwestern China power grids in 2010.
RegionMax Load(MW)
Wind PowerInstalledCapacity (MW)
Capacity/Maximum Load Tie Lines
MaxTransmissionCapacity (MW)
Northeast 46,835 9,208 19.7% To north:Gaoling (back-to-back HVdc)
3,000
Northwest 50,503 4,272 8.5% To center:Lingbao (back-to-back HVdc)Debao (HVdc)
1,1103,000
-
7/27/2019 Wind Energy China
10/11
november/december 2011 IEEEpower & energy magazine 45
of wind capacity, or 60% of total
installed capacity. The use of
wind power forecasting provides
a strong support for increasing
the ability of the power system to
accommodate wind power.
Power System Dispatchand Control ProceduresChinas power dispatch system
follows an integrated dispatch-
ing and hierarchy management
mechanism, which means that
lower-level dispatching centers
are subordinate to higher-level
ones, while each level has its own
responsibilities. Wind power dis-
patching follows the same mecha-
nism, as shown in Table 4. Thereare five levels for dispatching cen-
ters in China, including a national
center (the National Electric Power
Dispatching and Communication
Center, or NEPDCC), six regional
centers, 31 provincial centers, 374 municipal-level centers,
and 2,057 county-level centers.
On the other hand, wind power and other renewables are
given first priority in dispatching under normal conditions of
system security and reliability, according to the Renewable
Energy Law and its related regulations. The main strategies
available to the dispatching centers are to adjust the annual,
monthly, daily, and even real-time dispatching schedules to
facilitate the flexibility of conventional power generators and
maximize tie-line transmission capacity among the regions.
Meanwhile, authorities such as NEA and SERC have
emphasized supporting regulations for building wind power
plant control and monitoring systems. Grid operators conse-
quently established the means to access wind power operation
information in parallel with the regular system information.
Essential operating information is sent to the system dispatch-
ing center so that the dispatcher is aware of real-time opera-
tional status. To date, all grid-connected wind power plants
have been included in the real-time monitoring system of the
local, provincial, regional, and national dispatching centers.
Moreover, NEPDCC is able to access real-time wind power
operation information from the regional and provincial grids.
It is clear that the integrated dispatching mechanism in
China plays an important role in terms of accommodating
table 4. Levels and responsibilities of dispatching centers in China.
Dispatching Center Dispatching ScopeResponsibilityfor Wind Power
National(NEPDCC) Ultra-high-voltage power grid;tie lines across regions;electric generators transmitting electricity across regions(large thermal or hydropower plants)
Dispatching the wind powerand transmitting electricityacross regions
Regional 500/330-kV power grid;all the tie lines across provinces;pumped-storage power station;some regulation and emergency power plants directly connected to500/330-kV power grid
Dispatching the wind powerand transmitting electricityacross provinces in theregion
Provincial 500/330-kV terminal substations and power plants, except for the onescontrolled by upper-level dispatching centers in the province;220-kV power grid
Dispatching the wind powerwithin the province
Municipal level 220-kV and smaller substations and local power plants, except for theones controlled by upper-level dispatching centers
Dispatching the wind powerat the city level
County level 110-kV and smaller substations and local power plants, except for theones controlled by upper-level dispatching centers Not dispatching the windpower
Hami
Northwest
Tibet
South
North,
Center,East of
China
Jiangsu
Shandong
Inner Mongolia EastInner Mongolia West
Jilin
Northeast
Hebei
Jiuquan
figure 11. Schematic diagram of eight wind power bases and their associatedpower flows.
-
7/27/2019 Wind Energy China
11/11
6 IEEEpower & energy magazine november/december 2011
large-scale wind power development along with rapid
growth and electrical balancing in the wider area network.
Outlook for ChinasWind Power DevelopmentWind power will continue its rapid development in the coming
decades, due to Chinas commitment to energy efficiency and
carbon dioxide emission reduction. During the 2010 United
Nations Climate Change Conference held in Copenhagen, the
Chinese government promised to devote major resources to
developing renewable and nuclear energy to ensure that by2020, consumption of nonfossil fuel power will account for
15% of the countrys total primary energy consumption and
the intensity of carbon dioxide emissions per unit of GDP will
be reduced by 4045% as compared with the emission level
of 2005. The Chinese government accordingly has decided
to dedicate a supplementary investment of CNY500 billion
to developing RE and nuclear power over the next ten years.
It appears that RE may assume even greater significance than
previously thought as a consequence of the nuclear disaster at
the Fukushima Daiichi power plant in Japan.
Preliminary analysis indicates that the contribution rate
of wind power to the 15% goal is about 10%, which means
wind power capacity must reach at least 150 GW by 2020.
This in turn means that in the years 20102020, the growth
rate of wind power installed capacity will be kept at least at
14%, or 12 GW of annually added capacity. According to
Chinas 12th five-year plan, the generation of nonfossil fuel
power will account for 11.4% of the countrys total primary
energy consumption by 2015, instead of 8.2% as in 2005.
By 2015, there will be about 100 GW of wind power, which
could displace the equivalent of 430 million tons of coal and
reduce CO2 emissions by 1.2 billiontons annually, contribut-
ing 5% to achieving the emission reduction goal.
We believe that the experience and success of China in
large-scale wind power development will be a valuable con-
tribution to the development of global wind power utiliza-
tion. With the gradual construction of large-scale wind power
bases and the continued technical progress of domestic wind
turbine technology, Chinas manufacturing enterprises will
maintain the growth of quantity as well as quality. Apart from
supplying the domestic market, these companies will pro-
vide excellent equipment and service to the global market.
At the same time, the experience of solving the large number
of technology and management challenges faced by China,
including the lack of system flexibility, long-distance trans-mission, and large-scale wind power development, will estab-
lish a good base of operating knowledge that can provide use-
ful insights for other countries and regions in the world.
For Further ReadingAmendment of Renewable Energy Law of Peoples Republic
of China, State Council, Dec. 26, 2009.
CREIA, GWEC. (2010, Oct.). Greenpeace. China Wind
Power Outlook 2010 [Online]. Available: http://www.gwec.
net/fileadmin/documents/test2/wind%20report0919.pdf
D. Sheng, H. Dai, M. Chen, and Y. Chi, Discussion of
wind farm integration in China, in Proc. Transmission andDistribution Conf. Exhibition: Asia and Pacific, 2005, p. 1.
Chinese Wind Energy Association. (2011). Statistics of
Installed Wind Power Capacity in China 2010 [Online].
Available: http://www.cwea.org.cn/download/display_info.
asp?cid=2&sid=&id=39
IEA. (2011). Integration of RenewablesStatus and
Challenges in China [Online]. Available: http://www.iea.
org/papers/2011/Integration_of_Renewables.pdf
Y. Zhang, Z. Duan, and X. Liu, Comparison of grid
code requirements with wind turbine in China and Europe,
in Proc. 2010 Asia-Pacific Power and Energy Engineering
Conference (APPEEC), pp. 14.
BiographiesLiping Jiang is with the State Grid Energy Research Insti-
tute, China.
Yongning Chi is with the China Electric Power Research
Institute, China.
Haiyan Qin is with the Chinese Wind Energy Associa-
tion, China.
Zheyi Pei is with the National Electric Power Dispatch-
ing and Communication Center, China.
Qionghui Li is with the State Grid Energy Research In-
stitute, China.
Mingliang Liu is with the Chinese Wind Energy Asso-
ciation, China.
Jianhua Bai is with the State Grid Energy Research In-
stitute, China.
Weisheng Wang is with the China Electric Power Re-
search Institute, China.
Shuanglei Feng is with the China Electric Power Re-
search Institute, China.
Weizheng Kong is with the State Grid Energy Research
Institute, China.
Qiankun Wang is with the State Grid Energy ResearchInstitute, China. p&e
Wind power will continue its rapid developmentin the coming decades, due to Chinas commitment toenergy efficiency and carbon dioxide emission reduction.