wind energy china

Upload: andres-vanegas-guillen

Post on 14-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Wind Energy China

    1/11

    1540-7977/11/$26.002011 IEEE6 IEEEpower & energy magazine november/december 2011

    Wind Energyin China

    C

    CHINA IS A LAND WITH ABUNDANT WIND RESOURCES.

    According to the latest official release of the national wind energy resource

    assessment results, 50-m-high wind energy resource potential amounts

    to about 2,580 GW, of which 2,380 GW is onshore and 200 GW is off-shore in the 525-m range of water depth. The areas suitable for developing

    large-scale wind power include Northeast, Northwest, and North China, as

    well as coastal areas in the provinces of Jiangsu and Shandong, where wind

    power potential accounts for about 80% of the wind energy resource poten-

    tial of the whole country, as shown in Figure 1. (This article does not contain

    the data and information of the Hong Kong Special Administrative Region,

    Macao Special Administrative Region, and Taiwan region; maps are for illus-

    trative purposes only.)

    Construction and Utilizationof Wind Power ProjectsChinas wind power has been experiencing rapid development since 2005. During 2005

    2010, the cumulative installed capacity of wind power in China increased 35 times, adding

    18.93 GW in 2010 (see Figure 2). By the end of 2010, Chinas cumulative installed capacity had

    reached 44.73 GW, surpassing that of the United States and ranking first in the world.

    Large and medium-sized projects with capacities of more than 10 MW have dominated wind power

    plant construction in China. Especially since 2008, the government has begun to plan and construct a number of

    1-GW wind power bases, and even some up to 10 GW. By the end of 2010, the number of wind power plants larger than

    100 MW had reached 127, representing 64% of the existing installed capacity.

    To date, China has the largest cumulative installed, grid-connected, offshore wind power capacity outside Europe. The

    commission of the three 3-MW offshore wind turbines at the Shanghai Donghai Daqiao offshore wind power plant in Sep-

    tember 2009 marked the start of Chinas megawatt-scale offshore wind power utilization. Meanwhile, the National Develop-

    ment and Reform Commission (NDRC), Chinas top planner, launched the first round of concession projects for offshore

    wind power plants in May 2010, with a total capacity of 1,000 MW. By the end of 2010, the total cumulative installed capac-

    ity of offshore wind power in China had reached 142.5 MW.

    In 2010, Chinas wind power generation was about 50.1 TWh, which accounted for 1.28% of net electricity consumption.

    The wind power generation within the northeast power grid reached 17 TWh, or 6.0% of net electricity consumption; the

    wind power generation within the eastern region of the Inner Mongolia power grid reached 5.9 TWh, or 21.1% of the net

    electricity consumption. In 2010, the average full load hours of wind turbines amounted to 2,082.

    Related Policies and Regulatory FrameworkThe Renewable Energy Law of the Peoples Republic of China (PRC) was adopted at the 14th session of the Standing

    Committee of the Tenth National Peoples Congress on 28 February 2005 and took effect on 1 January 2006. The law

    Digital Objec t Identifier 10.1109/MPE .2011.942350Date of publi cation : 21 October 2011

  • 7/27/2019 Wind Energy China

    2/11

    november/december 2011 IEEEpower & energy magazine 37

    Status and Prospects

    By Liping Jiang, Yongning Chi, Haiyan Qin,Zheyi Pei, Qionghui Li, Mingliang Liu, Jianhua Bai,Weisheng Wang, Shuanglei Feng, Weizheng Kong,

    and Qiankun Wang

    DIGITAL VISION

    established the basic legal system for

    Chinas renewable energy (RE) devel-

    opment and formed a general policy

    and regulatory framework for promoting

    renewable energy development and utili-

    zation. On the basis of the law, the National

    Energy Administration (NEA), Ministry

    of Finance (MoF), State Electricity Regula-

    tory Commission (SERC), and the other relatedgovernment authorities successively issued a series of

    specified policies and regulations on RE generation, cov-

    ering the definitions and related regulatory measures with

    respect to priority scheduling and priority purchasing as well

    as cost sharing among electricity consumers nationwide.

    Through efforts spanning several years, a series of poli-

    cies and a regulatory framework to promote RE develop-

    ment have been put in place in China. In order to keep up

    with the rapid development of RE, the Amendment of the

    Renewable Energy Law was adopted at the 12th session

    of the Standing Committee of the 11th National Peoples

    Congress on 26 December 2009. The amendment empha-

    sized the responsibilities and obligations of central and

    local governments regarding the surveying of resources

    and development planning and provided detailed sup-

    port for the integration of RE generators. The amend-

    ment established a dedicated RE development fund, whose

    sources include both financing from the central government

    budget and revenue from a legally authorized levy on electric-

    ity consumers nationwide (the RE electricity surcharge). To

    date, some of the methods supporting the Renewable Energy Law

    are still under development or revision.

  • 7/27/2019 Wind Energy China

    3/11

    8 IEEEpower & energy magazine november/december 2011

    Project Approval and ManagementAuthorized by the PRC State Council, NDRC is the price

    administration of the country and consequently respon-

    sible fordeciding on and approving RE-generated electric-

    ity pricing. NEA has the responsibility for formulating and

    issuing annual plans, as well as for medium- and long-term

    wind power development planning and for approving newly

    built wind power projects and power grid projects. SERC

    is responsible for supervising the operations of wind power

    plants and the power grid.

    According to the Regulation on Management of RE Gen-

    eration introduced by NDRC in 2006, wind power projects

    with capacities of 50 MW and above should be approved by

    NDRC, and those with capacities below 50 MW should be

    approved by the local provincial authority reporting to NDRC.

    Feed-In TariffsFeed-in tariff policy for RE power generation in China has

    experienced several different periods. Before 2003, the

    feed-in tariff was determined case by case along with each

    individual wind power project, based on the power purchase

    agreement signed between the wind power plant operator

    and the grid enterprise, approved by the local government,

    and reported to the National Price Bureau. During 2003

    2007, a concession bidding pricing mechanism was intro-

    duced. This was meant to be the main pricing mechanism

    for wind power, along with a feed-in tariff equivalent to the

    benchmarked local desulfurized coal-fired power feed-in

    tariff plusa subsidy of no more than CNY 0.25 per kWh.

    On 1 August 2009, NDRC issued the Notice on Price Pol-

    icy Improvement for Onshore Wind Power, which instituted

    a fixed-benchmark pricing system for onshore wind power

    in place of the concession bidding pricing mechanism. This

    new mechanism created four categories of feed-in tariff,based on the regional wind resource and difference

    5071,2

    67

    1,2

    88

    2,5

    55

    3,3

    11

    5,8

    66

    6,1

    54 12,0

    20

    13,8

    03

    18,9

    28

    44,7

    33

    50,000

    40,000

    30,000

    20,000

    10,000

    0

    MW

    2005 2006 2007 2008 2009 2010

    25,8

    05

    AddedInstalled CapacityAccumulativeInstalled Capacity

    figure 2. Wind power capacity of China, 20052010.

    100

    100

    100

    100

    200100

    100

    150

    50

    150

    150150

    150

    150

    200

    200

    150100

    150 150

    150

    150

    150

    150

    150

    150

    150

    150100

    100

    100

    100

    200

    50

    50

    50

    50

    150

    100

    100 100

    200

    200

    200

    200

    200

    200200

    200

    50

    50

    100

    100

    200 W/m2 or Above (High)

    150200 W/m2

    100150 W/m2

    50100 W/m2

    50 W/m2 or Below (Low)

    Area ofNorthwest

    China

    Area

    of

    North

    Chi

    na

    Area of

    NortheastChina

    Coastal Areas

    figure 1. Schematic diagram of wind power resources in China.

  • 7/27/2019 Wind Energy China

    4/11

    november/december 2011 IEEEpower & energy magazine 39

    in geographical conditions. The

    four benchmark feed-in tariffs

    were set up correspondingly as

    CNY0.51/kWh, CNY0.54/kWh,

    CNY0.58/kWh, and CNY0.61/kWh

    (see Table 1 and Figure 3). They

    reflect the concept that the betterthe average wind conditions are, the

    lower the tariff level should be.

    Mechanism ofRE Electricity SurchargeAccording to the cost-sharing prin-

    ciples determined by the Renew-

    able Energy Law, the excess of the

    renewable energy power generation

    project feed-in tariff over the local

    desulfur ized coalpower bench-

    mark price and the excess of theoverall cost of the independent RE-

    based power system project over the

    Category I: 0.51 CNY/kWh

    Category II: 0.54 CNY/kWh

    Category III: 0.58 CNY/kWh

    Category IV: 0.61 CNY/kWh

    figure 3. Benchmark feed-in tariff zones for onshore wind power.

    table 1. Benchmark feed-in tariffs for onshore wind power.

    ResourceZone

    Benchmark Feed-InTariff (CNY/kWh) Administrative Areas Included

    Category I 0.51 Inner Mongolia Autonomous Region exceptChifeng, Tongliao, Xinganmeng, Hulunbeier;

    Xinjiang Uygur Autonomous Region:Urumqi, Yili, Karamay, Shihezi

    Category II 0.54 Hebei Province: Zhangjiakou, Chengde;Inner Mongolia Autonomous Region:Chifeng, Tongliao, Xinganmeng, HulunbeierGansu Province: Zhangye, Jiayuguan, Jiuquan

    Category III 0.58 Jilin Province: Baicheng, Songyuan;Heilongjiang Province:

    Jixi, Shuangyashan, Qitaihe, Suihua, Yichun,Daxinganling region;Gansu Province exceptZhangye, Jiayuguan, Jiuquan;Xinjiang Uygur Autonomous Region exceptUrumqi, Yili, Changji, Karamay, Shihezi;Ningxia Hui Autonomous Region

    Category IV 0.61 Other parts of China not mentioned above

  • 7/27/2019 Wind Energy China

    5/11

    0 IEEEpower & energy magazine november/december 2011

    local provincial average retail tariff, as well as a calculated

    cost for RE power integration, should be subsidized by an RE

    electricity surcharge. This surcharge is currently imposed on

    electricity customers nationwide and applies to about 85% of

    the total electricity consumption. NDRC and SERCjointly

    release a report on the RE Electricity Surcharge Levy and

    Subsidy Arrangement to the public periodically every year,

    since 2006.The RE electricity surcharge was raised from CNY 0.1

    cent/kWh in 2006 to CNY 0.4 cent/kWh in 2009. The total

    RE electricity surcharge in 2009 was about CNY12 billion,

    but this amount covered only about 70% of the needed subsi-

    dies for RE generation. It appears that the RE electricity sur-

    charge deficit will be enlarged with the rapid development of

    RE in the coming years.

    Concession Bidding of Wind Power ProjectsIn order to promote development of wind power and determine

    the real costs of wind power generation, the Chinese govern-

    ment decided to implement a concession bidding mechanism

    for some large-scale wind power projects in 2003. From 2003

    to 2007, five concession biddings of onshore wind power were

    conducted, which covered 15 projects and 2.6 GW. In 2010,

    the concession bidding process for four offshore wind power

    projects located in the coastal area of Jiangsu, totaling 1 GW,

    was completed. Table 2 summarizes these developments.

    Technical Standards for Wind Power GridConnection, Operation, and ManagementA lack of technical standards and the absence of regula-

    tions for wind power integration were recognized as two of

    the main issues encumbering Chinas wind power develop-ment, especially with the rapid growth of wind power within

    the past ten years. In December 2010, NEA finally issued

    a regulation, Tentative Management Procedures for Grid-

    Connection Testing of Wind Turbines, requiring that, from

    1 January 2011, wind turbines within newly approved wind

    power plants must pass grid-connection testing and comply

    with the relevant technical requirements before they can

    be permitted to connect to the grid and begin operation. In

    March 2011, NEA issued the Management Procedures on

    Wind Power Forecasting and Coordinated Operation with

    the Power System (a draft guide) to identify the explicit

    responsibilities of different stakeholders and specify system

    requirements and supervision. Certain other, related techni-

    cal standards and regulations are still under discussion.

    Development of WindTurbine Industry and Technology

    Status of the Wind Turbine IndustryThanks to the great support of policy incentives and huge

    market demand during the past ten years, the wind turbine

    manufacturing industry has developed rapidly in China,

    with a full industry supply chain being formed. By the end

    of 2010, 88% of the domestic market was occupied by Chi-

    nese wind turbine manufacturers, compared with 30% in

    2005. Wind turbines, blades, gearboxes, and other com-

    ponents have been exported to countries in North Amer-

    ica, Africa, Europe, and Southeast Asia. DEC, Goldwind,

    Sinovel, and United Power were listed among the top ten

    global turbine suppliers in 2010, and three more Chinese

    domestic manufacturers were included in the top 15 (see

    Figure 4).

    In terms of the cumulative installed capacity in China,

    there were 16 wind turbine manufacturers with a market

    share of more than 1% at the end of 2010. Among them,five foreign manufacturers shared 17.5% of the market, with

    table 2. Concession bidding of wind power projects in China.

    Type Bidding Time Projects Capacity (MW) Bidding Prices Range (CNY/kWh)

    Onshore September 2003 2 200 0.43650.5013

    Onshore September 2004 3 300 0.38200.5190

    Onshore August 2005 3 450 0.46160.6000

    Onshore August 2006 3 700 0.40560.5006Onshore November 2007 4 950 0.46800.5510

    Offshore September 2010 4 1,000 0.62350.7370

    14%

    12%

    10%

    8%

    6%

    4%

    2%

    0%

    Vestas

    Sinovel

    GE

    GoldWind

    Enercon

    Gamesa

    DEC

    Sulon

    Siemens

    UnitedPower

    MingYang

    ShanghaiElectric

    Nordex

    XEMC

    Repower

    figure 4. The top 15 global wind turbine manufactur-

    ers and their shares of the global market (source: ChineseWind Energy Association).

  • 7/27/2019 Wind Energy China

    6/11

    november/december 2011 IEEEpower & energy magazine 41

    7,285 MW of capacity, and 11 Chinese domestic manufactur-

    ers shared 75.7% of the market, with 33,962 MW of capacity.

    Of these 16, Sinovel, Gold Wind, DEC, Vestas, and United

    Power are the top five in order of market share.

    Status of Wind Power Technology

    The unit size of wind turbines has been increasing in recentyears. Before 2005, wind turbines with unit capacities of

    250 kW, 600 kW, and 850 kW dominated the Chinese mar-

    ket. Imported MW-level wind turbines were introduced

    into the Chinese market during the first and second con-

    cession bidding. About 51% of the annual newly installed

    market was held by MW-level wind turbines in 2007, with

    an average rated capacity of 1,048.9 kW, which increased

    to 1,466.8 kW in 2010 when the MW-level wind turbine

    became a mainstream product. Figure 5 shows the growth

    of wind turbine unit capacity from 2000 to 2010. More

    recently, multi-MW wind turbine production and applica-

    tion in China has made considerable progress. The 3-MWwind turbine has been put into batch production and

    installed successfully; furthermore, a prototype 5-MW

    wind turbine has been produced.

    The application of both gearbox drive and direct-drive

    technology is popular. As in the global market, the dou-

    bly fed induction generator (DFIG) with multistage gear-

    box drive train has become a mainstream technology, with

    mature development and full utilization in China. During

    the past five yearsfrom 2006 to 2010high-speed gear-

    box drive technology took a 70% market share in China;

    meanwhile, direct-drive technology has also been develop-

    ing steadily, with its market share growing from 0.1% in

    2006 to 21.5% in 2010.

    Offshore wind technology has also made great prog-

    ress in China. The 3-MW wind turbine manufactured by

    Sinovel and installed in the Shanghai Donghai Bridge off-

    shore wind project in March 2009 was a milestone demon-

    strating Chinas success in MW-scale offshore wind turbine

    research and manufacture.

    Grid Code andGrid-Connection ProceduresThe first Chinese grid code presenting technical require-

    ments and specifying procedures for wind power integra-

    tionGB/Z 19963-2005, Technical Rule for Connecting

    Wind Power Plant with Power Grid, drafted by the China

    Electric Power Research Institute (CEPRI) and managed

    by the China Electricity Council (CEC)was issued on 12

    December 2005 by the General Administration of Quality

    Supervision, Inspection, and Quarantine (AQSIQ) and the

    Standardization Administration of China (SAC).

    At the beginning of the grid code formulation procedure,

    the technical requirements for grid-connected plants were

    moderate in some aspects, given the lower wind penetration

    actually achieved and the technological limitations of thevarious wind turbine manufacturers.

    With the rapid growth of Chinese installed capacity

    which has approximately doubled annually during the pastfive yearsthe impact of wind power became a prominent

    issue in power system operation and security in some areas.

    In order to ensure the stable and reliable operation of wind

    power plants, certain new technical requirements were

    added to the revised grid code, which was drafted mainly by

    CEPRI, China LongYuan Power Group Corporation, and the

    Electric Power Research Institute of Southern Power Grid,

    in collaboration with China Power Engineering Consulting

    (Group) Corporation.

    Grid Code Requirementsfor Wind Power PlantsFigure 6 shows the terminology and definitions used in

    the grid code for wind power plants, points of connection

    (POCs), active power, and reactive power, as well as for the

    transmission lines of wind power plants.

    The following requirements were included in the revised

    grid code:

    Active power control: A wind power plant should have

    the ability to control active power according to orders

    issued by the dispatching center of the power system.

    In order to fulfill this control function, a wind power

    plant active power control system must be installed.

    Reactive power capacity and voltage control: For a

    single wind power plant directly connected to the pub-

    lic network, the capacitive reactive power compensa-

    tion should cover not only the reactive power loss of

    the wind power plant collector system and the step-up

    transformers but also half of the reactive power loss of

    the transmission line in the case of heavy loading. In

    the case of light loading, the inductive reactive power

    compensation should cover half of the capacitive charg-

    ing reactive power of the transmission line. For large

    wind power clusters, the capacitive reactive power de-

    vices should compensate all the reactive power loss ofthe transmission line in the case of heavy loading; in the

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    2009

    2010

    695

    .2

    618

    .3

    608.4

    75

    0.4

    7

    90.2

    852

    921.7

    1,0

    48.9

    1,2

    13.5

    1,3

    62.7

    1,4

    66.8

    kW

    figure 5. Average rated capacity of newly installed windturbines in China, 20002010.

  • 7/27/2019 Wind Energy China

    7/11

    2 IEEEpower & energy magazine november/december 2011

    case of light loading, the inductive reactive power de-vices should compensate all the charging capacitive re-

    active power of the transmission line. The wind power

    plant should regulate the voltage of the POC so that it

    remains within 97107% of nominal voltage when the

    system voltage is within the normal operating range.

    Low-voltage ride-through (LVRT): The requirements

    of wind power plant low-voltage ride-through are

    shown in Figure 7.

    If the voltage at the POC of the wind power plant is higher

    than the voltage profile, drops to 20% of the nominal volt-

    age with the duration for 625 ms and recovers to 90% of the

    nominal voltage within two seconds, which arose from the

    grid fault and is shown in Figure 7, all wind turbines within

    the wind power plant shall remain connected to the system

    without tripping.

    The active power output of the connected wind turbines

    must be continuously restored to the original value after

    fault clearance and with a gradient of at least 10% of the

    rated power per second.

    Wind power plants located in 1-GW and larger wind

    power clusters should be designed to support reactive power

    dynamically during a balanced

    system fault. The dynamic reac-

    tive current injected into the power

    system from a wind power plant

    should be equal to 1.5 (0.9

    UT) IN, where 0.2 #UT# 0.9

    and whereIN is the rated current inper unit of wind power plant and

    UT is the voltage in per unit at the

    POC of the wind power plant.

    Grid-Connection Testing Contents of testing: Figure 8

    shows the main areas of wind

    power plant and wind turbine

    testing; these include wind

    turbine type testing, wind

    turbine grid-connection

    testing, and wind power plant grid-connection test-ing. Grid-connection testing of wind power plants

    should comply with State Grid Corporation of China

    (SGCC) Enterprise Standard Q/GDW 392-2009,

    Technical Rule for Connecting Wind Power Plants

    with the Power Grid, which presents requirements for

    wind power plants regarding power quality, active and

    reactive power control capability, LVRT, and so on.

    LVRT testing: International experience has shown

    that wind power plant LVRT capability relies greatly

    on the LVRT capability of individual wind turbines.

    CEPRI has made substantial progress in the LVRT

    testing of wind turbines, developing (in cooperation

    with FGH Germany) the first mobile wind turbine

    LVRT test facility in China.

    Grid-Connection Procedures,Including LVRT VerificationAccording to Q/GDW 392-2009, the entire wind power plant

    should have LVRT capability and other controllability. In

    many countries, modeling and simulation are used for the

    verification of wind power plant LVRT capability. Based on

    the LVRT testing results, modeling of the wind turbine can be

    carried out and verified. Based on the verified wind turbine

    model, the modeling of the whole wind power plant can then

    be established, and the LVRT capability of the wind power

    plant can be verified through power system simulation.

    Main Issues of Wind Power Integration

    Flexibility of Power System OperationsFrom the power system perspective, the big barrier in China

    to accommodation of large-scale wind power integration is

    poor system operational flexibility, since the major form of

    generation in China is the coal-fired power plant and the flex-

    ibility of hydropower in China is limited (this is due to the highproportion of run-of-river power plants whose responsibilities

    Voltage Dip Caused by Grid Fault

    Wind TurbineMust Not

    Trip

    1.21.1

    10.90.80.70.60.50.40.30.20.1

    01 0 0.625

    Time (s)

    Voltageat

    PointofConnection(p

    u.)

    1 2 3 4

    Wind Turbine May Trip

    figure 7. Wind power plants: LVRT capabilityrequirement.

    Transmission Line ofWind Power Plant

    Active Power

    WindTurbine

    Collection System

    Step-UpTransformer

    Reactive Power

    Wind PowerPlant

    High-Voltage Bus(Point of Connection)

    P Q

    . . .

    . . . . . . . . . .

    figure 6. Wind power terminology and definitions in the grid code.

  • 7/27/2019 Wind Energy China

    8/11

    november/december 2011 IEEEpower & energy magazine 43

    include flood control, agricultural

    irrigation, shipping, and so on).

    By the end of 2010, total cumula-

    tive installed generation capacity

    in China was 966 GW, of which

    the installed capacity of coal-fired

    plants accounted for 66.9% butnatural gasfired and oil-fired gen-

    eration accounted for only 3.6%.

    Hydropower (including pumped

    storage at 15.3 GW or 1.5%)

    accounted for 22.4% (see Figure 9).

    The situation in north, north-

    eastern, and northwestern China,

    where the abundant wind resources

    are located, has been even worse

    during the winter. Winter is a sea-

    son of heavy heat demand, and

    the power generation output ofthe coal-fired combined heat and

    power (CHP) plants is determined

    by heating demand. Therefore, the

    systems ability to accommodate

    large-scale wind power is dra-

    matically reduced in winter. Take

    northeastern China as an exam-

    ple: it becomes more difficult to

    accommodate a high wind penetration because of the lower

    regulation capability of coal-fired plants in winter and spring,

    when the wind blows strongest.

    The relatively low capacity of the tie lines in the regional

    power grids results in interregional power transmission

    congestion and a shortfall of mutual power-balancing sup-

    port capability, thus reducing the capability of the whole

    power system to accommodate wind power. Table 3 shows

    the load, wind power capacity, and tie-line capacity of north-

    eastern and northwestern China, where there is high wind

    penetration but low load. In some

    areas of northeastern China (e.g.,

    the eastern region of Inner Mon-

    golia Autonomous Region, Jilin

    Province, and Liaoning Province)

    and northwestern China (e.g.,

    Gansu province and Xinjiang

    Uygur Autonomous Region), wind

    power integration is confronting

    significant challenges due to the

    poor flexibility of the system, low

    load, and limited tie-line capacity.

    Transmission forLarge-Scale Wind PowerA higher-voltage transmission sys-

    tem with larger power capabilityis being developed for improved

    wind power integration and accommodation. As in Europe,

    where it has been necessary to develop dedicated power corri-

    dors and grid-connection projects to integrate large-scale off-

    shore wind power plants, it is necessary for large-scale wind

    power plants located in remote regions of northeastern and

    northwestern China to connect to high-voltage transmission

    lines in order to send energy out to load centers. For exam-

    ple, the Ganhekou wind power project in Gansu Province

    consists of several 200-MW wind power plants. Several

    330-kV dedicated wind power substations, each of which

    Wind Turbine Type Testing

    Power Performance

    Noise

    Load

    Power QualityPower Quality

    LVRTLVRT

    Active Power/ReactivePower Controllability

    Active Power/Reactive

    Power Controllability

    Frequency/VoltageCompliance

    AntiinterferenceCapability

    Frequency/VoltageCompliance

    Antiinterference

    Capability

    Wind TurbineGrid Connection Testing

    Wind Power PlantGrid Connection Testing

    figure 8. Contents of grid-connection testing of wind power plants and windturbines.

    Other0.3

    0.0%

    Wind29.63.1%

    Nuclear10.81.1%

    Hydro216.122.4%

    Thermal Power709.773%

    Coal-Fired646.666.9%

    Gas andOil-Fired

    35.23.6%

    Other ThermalPower27.92.9%

    figure 9. Existing Chinese grid-connected generation capacity, in GW (source: CEC).

  • 7/27/2019 Wind Energy China

    9/11

    4 IEEEpower & energy magazine november/december 2011

    collects the output of two or three wind power plants, are

    connected to the main 750-kV system to deliver the large

    quantity of wind power produced by wind farms located at

    Ganhekou to the northwestern power grid.

    According to SGCC statistics, by the end of 2010,

    23,200 km of transmission line for wind power grid con-

    nection had been built, of which 58.1% (13,450 km) is

    rated at 220 kV and above. Figure 10 shows the propor-tion of these transmission lines rated at each of several

    voltage levels.

    Based on the evaluation of wind resource and site condi-

    tions, NEA has put forward an ambitious plan and launched

    the construction of eight 10-GW-level wind power bases (see

    Figure 11). According to this plan, SGCC has carried out a

    comprehensive integration study for each wind power base,

    including an assessment of system accommodation capabil-

    ity and wind power trading markets, as well as the power

    delivery plan. The study concluded that:

    Wind power in Shandong and Jiangsu provinces

    should be accommodated within the local prov-

    inces.

    Wind power in Hebei Province should be sent out to

    the northern, eastern, and central China power grids

    in addition to the Beijing, Tianjin, and Tangshan

    power grids.

    Wind power in the other five bases should be sent

    out to the northern, eastern, and central China grids

    through interprovincial or interregional tie lines.

    The eight large-scale wind power bases being estab-

    lished will account for more than 70 GW of the 100 GW

    of wind capacity called for by 2015 in the national wind

    power development plan. Of this 70 GW, 42 GW will be

    delivered through interprovincial or interregional tie lines.

    Furthermore, when wind power installed capacity in China

    reaches 160 GW, these eight bases will provide more than

    75% of total wind capacity, and the wind power deliveredacross provinces or regions will reach 70 GW. With such

    large-scale development planned for the future, additional

    grid expansion and reinforcement are needed.

    Role of Wind Power ForecastingAccurate wind power forecasting is the foundation for

    increasing the precision of power dispatching and enhancing

    the ability of the power system to accommodate wind power.

    It is also helpful in order to decrease the needed reserve

    capacity, improve the economy of the power system as a

    whole, and thus reduce the cost of wind power development.

    Government has provided significant policy, regulatory, and

    financial support to facilitate innovation to increase the preci-

    sion of wind power forecasting and promote better forecasting

    technologies. The Ministry of Science and Technology led two

    national science and technology support programs, Develop-

    ment and Demonstration of Wind Power Forecasting Systems

    and Research on Key Technologies for a Wind/PV/Storage/

    Transmission Joint Demonstration Project. The NEA con-

    ducted a study on the policy aspects of coordination and man-

    agement of wind power forecasting and the power system. The

    National Meteorological Administration developed a numeri-

    cal weather-forecasting model with 1-km horizontal resolution

    for the Jiuquan wind power base in Gansu Province. SGCC set

    up the Operations Center for Numerical Weather Forecasting at

    CEPRI for wind power forecasting, based on massively paral-

    lel computing and using more than 4,000 cores. The center is

    expected to eventually incorporate 10,000 cores.

    So far, wind power forecasting service providers have

    mastered the technology of short-term forecasting methods,

    including physical, statistical, and hybrid methods, as well

    as ultra-short-term forecasting methods based on real-time

    observed wind and power data. In November 2008, the first

    wind power forecasting system was put into operation at

    the Jilin electric dispatching center. By the end of 2010, thewind power forecasting system covered more than 20 GW

    110 kV and Below,9,703 km

    750 kV, 1,694 km

    500 kV, 2,786 km

    330 kV, 475 km

    220 kV, 8,494 km

    ,

    50

    220 k

    figure 10. Wind power grid connection transmission linesinstalled through 2010, by voltage type.

    table 3. Tie-line capacity in northeastern and northwestern China power grids in 2010.

    RegionMax Load(MW)

    Wind PowerInstalledCapacity (MW)

    Capacity/Maximum Load Tie Lines

    MaxTransmissionCapacity (MW)

    Northeast 46,835 9,208 19.7% To north:Gaoling (back-to-back HVdc)

    3,000

    Northwest 50,503 4,272 8.5% To center:Lingbao (back-to-back HVdc)Debao (HVdc)

    1,1103,000

  • 7/27/2019 Wind Energy China

    10/11

    november/december 2011 IEEEpower & energy magazine 45

    of wind capacity, or 60% of total

    installed capacity. The use of

    wind power forecasting provides

    a strong support for increasing

    the ability of the power system to

    accommodate wind power.

    Power System Dispatchand Control ProceduresChinas power dispatch system

    follows an integrated dispatch-

    ing and hierarchy management

    mechanism, which means that

    lower-level dispatching centers

    are subordinate to higher-level

    ones, while each level has its own

    responsibilities. Wind power dis-

    patching follows the same mecha-

    nism, as shown in Table 4. Thereare five levels for dispatching cen-

    ters in China, including a national

    center (the National Electric Power

    Dispatching and Communication

    Center, or NEPDCC), six regional

    centers, 31 provincial centers, 374 municipal-level centers,

    and 2,057 county-level centers.

    On the other hand, wind power and other renewables are

    given first priority in dispatching under normal conditions of

    system security and reliability, according to the Renewable

    Energy Law and its related regulations. The main strategies

    available to the dispatching centers are to adjust the annual,

    monthly, daily, and even real-time dispatching schedules to

    facilitate the flexibility of conventional power generators and

    maximize tie-line transmission capacity among the regions.

    Meanwhile, authorities such as NEA and SERC have

    emphasized supporting regulations for building wind power

    plant control and monitoring systems. Grid operators conse-

    quently established the means to access wind power operation

    information in parallel with the regular system information.

    Essential operating information is sent to the system dispatch-

    ing center so that the dispatcher is aware of real-time opera-

    tional status. To date, all grid-connected wind power plants

    have been included in the real-time monitoring system of the

    local, provincial, regional, and national dispatching centers.

    Moreover, NEPDCC is able to access real-time wind power

    operation information from the regional and provincial grids.

    It is clear that the integrated dispatching mechanism in

    China plays an important role in terms of accommodating

    table 4. Levels and responsibilities of dispatching centers in China.

    Dispatching Center Dispatching ScopeResponsibilityfor Wind Power

    National(NEPDCC) Ultra-high-voltage power grid;tie lines across regions;electric generators transmitting electricity across regions(large thermal or hydropower plants)

    Dispatching the wind powerand transmitting electricityacross regions

    Regional 500/330-kV power grid;all the tie lines across provinces;pumped-storage power station;some regulation and emergency power plants directly connected to500/330-kV power grid

    Dispatching the wind powerand transmitting electricityacross provinces in theregion

    Provincial 500/330-kV terminal substations and power plants, except for the onescontrolled by upper-level dispatching centers in the province;220-kV power grid

    Dispatching the wind powerwithin the province

    Municipal level 220-kV and smaller substations and local power plants, except for theones controlled by upper-level dispatching centers

    Dispatching the wind powerat the city level

    County level 110-kV and smaller substations and local power plants, except for theones controlled by upper-level dispatching centers Not dispatching the windpower

    Hami

    Northwest

    Tibet

    South

    North,

    Center,East of

    China

    Jiangsu

    Shandong

    Inner Mongolia EastInner Mongolia West

    Jilin

    Northeast

    Hebei

    Jiuquan

    figure 11. Schematic diagram of eight wind power bases and their associatedpower flows.

  • 7/27/2019 Wind Energy China

    11/11

    6 IEEEpower & energy magazine november/december 2011

    large-scale wind power development along with rapid

    growth and electrical balancing in the wider area network.

    Outlook for ChinasWind Power DevelopmentWind power will continue its rapid development in the coming

    decades, due to Chinas commitment to energy efficiency and

    carbon dioxide emission reduction. During the 2010 United

    Nations Climate Change Conference held in Copenhagen, the

    Chinese government promised to devote major resources to

    developing renewable and nuclear energy to ensure that by2020, consumption of nonfossil fuel power will account for

    15% of the countrys total primary energy consumption and

    the intensity of carbon dioxide emissions per unit of GDP will

    be reduced by 4045% as compared with the emission level

    of 2005. The Chinese government accordingly has decided

    to dedicate a supplementary investment of CNY500 billion

    to developing RE and nuclear power over the next ten years.

    It appears that RE may assume even greater significance than

    previously thought as a consequence of the nuclear disaster at

    the Fukushima Daiichi power plant in Japan.

    Preliminary analysis indicates that the contribution rate

    of wind power to the 15% goal is about 10%, which means

    wind power capacity must reach at least 150 GW by 2020.

    This in turn means that in the years 20102020, the growth

    rate of wind power installed capacity will be kept at least at

    14%, or 12 GW of annually added capacity. According to

    Chinas 12th five-year plan, the generation of nonfossil fuel

    power will account for 11.4% of the countrys total primary

    energy consumption by 2015, instead of 8.2% as in 2005.

    By 2015, there will be about 100 GW of wind power, which

    could displace the equivalent of 430 million tons of coal and

    reduce CO2 emissions by 1.2 billiontons annually, contribut-

    ing 5% to achieving the emission reduction goal.

    We believe that the experience and success of China in

    large-scale wind power development will be a valuable con-

    tribution to the development of global wind power utiliza-

    tion. With the gradual construction of large-scale wind power

    bases and the continued technical progress of domestic wind

    turbine technology, Chinas manufacturing enterprises will

    maintain the growth of quantity as well as quality. Apart from

    supplying the domestic market, these companies will pro-

    vide excellent equipment and service to the global market.

    At the same time, the experience of solving the large number

    of technology and management challenges faced by China,

    including the lack of system flexibility, long-distance trans-mission, and large-scale wind power development, will estab-

    lish a good base of operating knowledge that can provide use-

    ful insights for other countries and regions in the world.

    For Further ReadingAmendment of Renewable Energy Law of Peoples Republic

    of China, State Council, Dec. 26, 2009.

    CREIA, GWEC. (2010, Oct.). Greenpeace. China Wind

    Power Outlook 2010 [Online]. Available: http://www.gwec.

    net/fileadmin/documents/test2/wind%20report0919.pdf

    D. Sheng, H. Dai, M. Chen, and Y. Chi, Discussion of

    wind farm integration in China, in Proc. Transmission andDistribution Conf. Exhibition: Asia and Pacific, 2005, p. 1.

    Chinese Wind Energy Association. (2011). Statistics of

    Installed Wind Power Capacity in China 2010 [Online].

    Available: http://www.cwea.org.cn/download/display_info.

    asp?cid=2&sid=&id=39

    IEA. (2011). Integration of RenewablesStatus and

    Challenges in China [Online]. Available: http://www.iea.

    org/papers/2011/Integration_of_Renewables.pdf

    Y. Zhang, Z. Duan, and X. Liu, Comparison of grid

    code requirements with wind turbine in China and Europe,

    in Proc. 2010 Asia-Pacific Power and Energy Engineering

    Conference (APPEEC), pp. 14.

    BiographiesLiping Jiang is with the State Grid Energy Research Insti-

    tute, China.

    Yongning Chi is with the China Electric Power Research

    Institute, China.

    Haiyan Qin is with the Chinese Wind Energy Associa-

    tion, China.

    Zheyi Pei is with the National Electric Power Dispatch-

    ing and Communication Center, China.

    Qionghui Li is with the State Grid Energy Research In-

    stitute, China.

    Mingliang Liu is with the Chinese Wind Energy Asso-

    ciation, China.

    Jianhua Bai is with the State Grid Energy Research In-

    stitute, China.

    Weisheng Wang is with the China Electric Power Re-

    search Institute, China.

    Shuanglei Feng is with the China Electric Power Re-

    search Institute, China.

    Weizheng Kong is with the State Grid Energy Research

    Institute, China.

    Qiankun Wang is with the State Grid Energy ResearchInstitute, China. p&e

    Wind power will continue its rapid developmentin the coming decades, due to Chinas commitment toenergy efficiency and carbon dioxide emission reduction.