winter 2013-2014 energy needs assessment

29
Winter 2013-2014 Energy Needs Assessment MC/RC MEETING APRIL 17, 2013 Presented by: Wayne Coste, Project Manager/Economic Planning Steve Weaver, Manager/Operational Performance, Training and Integration

Upload: vlora

Post on 04-Feb-2016

19 views

Category:

Documents


0 download

DESCRIPTION

Winter 2013-2014 Energy Needs Assessment. mc/rc meetingapril 17, 2013. Presented by: Wayne Coste, Project Manager/Economic Planning Steve Weaver, Manager/Operational Performance, Training and Integration. OVERVIEW: Objective and methodologies. Objective. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Winter 2013-2014  Energy Needs Assessment

Winter 2013-2014 Energy Needs Assessment

MC/RC MEETING APRIL 17, 2013

Presented by:Wayne Coste, Project Manager/Economic PlanningSteve Weaver, Manager/Operational Performance, Training and Integration

Page 2: Winter 2013-2014  Energy Needs Assessment

OVERVIEW: OBJECTIVE AND METHODOLOGIES

Page 3: Winter 2013-2014  Energy Needs Assessment

Objective

• The objective of this exercise is to calculate the incremental energy needs of the system to serve higher loads during colder weather conditions or more prolonged cold weather conditions than we experienced this past winter

• Any incremental procurement to meet these needs will be for the purpose of protecting reliability if those conditions materialize, and not for the purposes of increasing supplemental commitments– That is, the ISO does not expect to change the frequency or quantity

of supplemental commitments for a given set of weather conditions compared with past practice

– The ISO is also planning to better reflect reserve needs in the market reserve requirements and resulting prices

3

Page 4: Winter 2013-2014  Energy Needs Assessment

Methodologies• ISO-NE used two methodologies to calculate needs for the upcoming

winter• Both utilize temperatures from Winter 2003-04, which had the coldest

weather in the last 10 years• Both assume that the colder weather drives increased electric load and

reduced gas availability (per the ICF study)• Methodology 1: 2012-13 generation fleet dispatched against 2003/2004

demand with gas availability reductions based on temperature• Methodology 2: Incremental energy needed to meet system demand

calculated based on hourly gas unit output limited by colder temperatures in 2003/2004 compared to 2012/2013– Additional scenario assumes lower natural gas imports from the north, which represents

a more extreme set of circumstances • Both approaches result in additional energy required to serve load during

a severe winter– For illustrative purposes only, MWh are converted into barrels of oil

4

Page 5: Winter 2013-2014  Energy Needs Assessment

ASSUMPTIONS

Page 6: Winter 2013-2014  Energy Needs Assessment

Assumption: Colder Weather Reduces Gas Availability

6

Page 7: Winter 2013-2014  Energy Needs Assessment

Assumption: Colder Weather Leads to Higher System Demand

• Colder weather correlates to higher system demand

• January 2004 was considerably colder than recent years– Actual peak load very close to 90/10 forecast

• 2012-2013 was comparatively mild– Actual peak load less than the 50/50 forecast

7

Page 8: Winter 2013-2014  Energy Needs Assessment

Other Assumptions

• The energy available from the generation fleet during the winter of 2012-2013 will serve as the baseline – The generation fleet, in aggregate, will have the same level of fuel in

December 2013 as it had in December 2012– Oil and LNG storage were at very low levels or at times exhausted during the

2012-2013 winter period

• For conversion of MWh to barrels of oil it is assumed that, in aggregate, the generation to meet the additional demand for next winter has the following characteristics:– Heat rate of 10,000 Btu/kWh– Fuel heat content of 137,000 BTU/gallon

• The procured quantity must meet the incremental needs identified• i.e., it must offset reductions of natural gas availability due to colder

weather and higher system demand due to colder weather

8

Page 9: Winter 2013-2014  Energy Needs Assessment

METHODOLOGY 1:RESULTS OF DISPATCHING CURRENT GENERATION PROFILE AGAINST 2003/2004 LOAD CURVES

9

Page 10: Winter 2013-2014  Energy Needs Assessment

Approach

10

• ISO-NE performed the simulation for selected years – Historical loads for each winter season and the current resource fleet

were dispatched in the order shown– For the gas-only units:

• Temperature vs. gas unavailable curve was used• Driven by hour 18:00 temperatures

– Dual fueled gas/distillate oil units were assumed to be using gas unless the temperature dropped to 30 degrees • If this happened, they generated using distillate

– Last, if more energy was needed, residual oil was used

Page 11: Winter 2013-2014  Energy Needs Assessment

0

5,000

10,000

15,000

20,000

25,000

Dec Jan Feb

Actual Generation by Fuel Type With 2012/2013 Weather

Nuclear Coal Renewables Net Imports NG Dual on NG Dual on Oil Oil Hydro/PS

0

500

1,000

1,500

2,000

Cum

ulati

ve G

Wh

Dec Jan Feb

Actual Cumulative Distilate and Residual Fuel With 2012/2013 Weather

Dual on Oil Residual

11

Actual is approximately 0.9 Million BBL of oil

Page 12: Winter 2013-2014  Energy Needs Assessment

0

500

1,000

1,500

2,000

Cum

ulati

ve G

Wh

Dec Jan Feb

Est. Cumulative Distilate and Residual Fuel With 2003/2004 Weather

Dual on Oil Residual

3.2 Million BBL of oil actual (but simplification shows mostly distillate)USINGCALIBRATEDMODEL

0

5,000

10,000

15,000

20,000

25,000

Dec Jan Feb

Est. Generation by Fuel Type With 2003/2004 Weather

Nuclear Coal Renewables Net Imports NG Dual on NG Dual on Oil Oil Hydro/PS

12

Page 13: Winter 2013-2014  Energy Needs Assessment

0

500

1,000

1,500

2,000

Cum

ulati

ve G

Wh

Dec Jan Feb

Est. Cumulative Distilate and Residual Fuel With 2004/2005 Weather

Dual on Oil Residual

2.5 Million BBL of oil (but simplification shows mostly distillate)USINGCALIBRATEDMODEL

0

5,000

10,000

15,000

20,000

25,000

Dec Jan Feb

Est. Generation by Fuel Type With 2004/2005 Weather

Nuclear Coal Renewables Net Imports NG Dual on NG Dual on Oil Oil Hydro/PS

13

Page 14: Winter 2013-2014  Energy Needs Assessment

0.00

1.00

2.00

3.00

4.00

5.00

Tota

l Oil

(Mill

ion

BBL)

Dec Jan Feb

Est. Total Oil Inventory Drawdown Percentiles(Neglecting Start-up and Min Run-Time)

Winter 2003/04

Winter 2012/13

Ending with 1.0 Million BBL in Inventory

Hypothetical Total Oil Inventory Drawdown

14

Notes: - Inventory means fuel in the tanks or in the delivery “pipeline”- Assumed an ending inventory of 1.0 million BBL of oil

Page 15: Winter 2013-2014  Energy Needs Assessment

Conclusions

• In this exercise, it was determined that a total of 3.2 million barrels of oil will be needed to meet the 2003/2004 demand (the rest of the generation profile being equal to the 2012/2013 winter)

• To recognize minimum usable tank capacity, a 1 million barrel inventory is assumed for the end of the season

• The total is 4.2 million barrels

15

Page 16: Winter 2013-2014  Energy Needs Assessment

METHODOLOGY 2:RESULTS OF REDUCING AVAILABLE NATURAL GAS

16

Page 17: Winter 2013-2014  Energy Needs Assessment

Determination of Incremental MWh Needed in Each of Two Scenarios

• Two scenarios studied for next winter:– Scenario 1: Reductions of natural gas availability due to increased gas

LDC demand as a result of colder weather– Scenario 2: Scenario 1 conditions plus further generator reductions

due to lower gas imports from the north– This is an extreme scenario

• For each scenario, ISO determined the amount of additional MWh required using the actual hourly temperatures from the 2003/2004 winter

17

Page 18: Winter 2013-2014  Energy Needs Assessment

Scenario 1: Gas Assumptions for Design Day

• Tennessee at Full Capacity

• Iroquois at Full Capacity

• Algonquin at Full Capacity

• PNGTS - 200,000 Dth/d

• Sable Island - 150,000 Dth/d

• Distrigas - 50% (includes fulfillment of existing obligations only and some injections into the pipeline)

• Canaport - 50%

• Deep Panuke – 200,000 Dth/d (latest information indicates DP will be operational by end of Q2, 2013)

18

Page 19: Winter 2013-2014  Energy Needs Assessment

Scenario 1: Assumption for Generator Reductions

• Slope for natural gas reductions under this scenario

19

Page 20: Winter 2013-2014  Energy Needs Assessment

Scenario 1: Energy Required Under this Scenario

20

Total hours over the period (Dec through Feb) 2160 hours

Additional energy required ~1,079,027 MWh

Using assumed generator characteristics ~78,761,097 gal

42 gallons per barrel of oil ~1,875,000 barrels

Page 21: Winter 2013-2014  Energy Needs Assessment

Scenario 2: Gas Assumptions for Design Day

• Tennessee, Iroquois, Algonquin at Full Capacity

• PNGTS - 200,000Dth/d (the average flow for the coldest week of 2012/2013 winter season)

• Sable Island - 150,000 Dth/d (the average value for 2012/2013 winter season)

• Distrigas - 35% (includes fulfillment of obligations only)

• Canaport - 0%

• Deep Panuke - 0 Dth/d

21

Page 22: Winter 2013-2014  Energy Needs Assessment

Scenario 2: Assumption for Generator Reductions After Taking Into Account Natural Gas Reductions From the North • Slope for natural gas reductions under Scenario 2

22

Page 23: Winter 2013-2014  Energy Needs Assessment

Scenario 2: Incremental Energy Required Under this Scenario (in addition to Scenario 1)

23

Total hours over the period (Dec through Feb) 2160 hours

Additional energy required ~417,224 MWh

Using assumed generator characteristics ~30,454,284 gal

42 gallons per barrel ~725,102 barrels

Page 24: Winter 2013-2014  Energy Needs Assessment

Energy Needs Summary

Energy Needs Input Factor

MWh Energy Converted to Barrels of Oil

Scenario 1 (Base Case) 1,079,027 1,875,264

Scenario 2 (Incremental to Base Case)

417,224 725,102

1,496,251 2,600,336

24

Page 25: Winter 2013-2014  Energy Needs Assessment

CONCLUSIONS AND NEXT STEPS

Page 26: Winter 2013-2014  Energy Needs Assessment

Baseline Results from ISO-NE’s Winter 2012/2013 Fuel Survey• The final reported total oil storage capacity in New England is

~278 million gallons or 6.631 million barrels– Survey results over the past few months have shown mild variations in

total oil storage capacity

• Fuel survey in Fall 2012 reported a normal expected inventory level of 2.348 million barrels of oil, which translates to 35.4% of aggregate inventory

• Actual inventories carried from Dec. 2012 – Feb. 2013 averaged 1.594 million barrels of oil, which translates to 24% of aggregate inventory

26

Page 27: Winter 2013-2014  Energy Needs Assessment

Summary of Conclusions• Using methodology 1, it was determined that a total of 4.2

million barrels of oil will be needed to meet the 2003/2004 demand (with a 1 million barrel inventory left at the end of the season)– Less the normal inventory of 2.34 million barrels of oil at the

beginning of winter 2012-13, the reliability gap is 1.86 million barrels of oil

– Less the actual inventory of 1.59 million barrels of oil reported from Dec. 2012 – Feb. 2013, the reliability gap is 2.6 million barrels of oil

• Energy is converted into barrels of oil for illustrative purposes only

27

Page 28: Winter 2013-2014  Energy Needs Assessment

Summary of Conclusions

• Using methodology 2, the reliability gap is 1.079 million MWh in Scenario 1 and 1.496 million MWh in Scenario 2– This translates to 1.875 - 2.600 million barrels of oil

• Energy is converted into barrels of oil for illustrative purposes only

28

Page 29: Winter 2013-2014  Energy Needs Assessment

Open Issues and Next Steps

29

• Confirm MWh reliability gap for Winter 2013-14 from range presented

• Determine if gap can be offset through other quantifiable measures

• Determine procurement mechanism to meet remaining gap

• Determine what resources can meet the remaining gap