wk 'dwh qg
TRANSCRIPT
भारत सरकार
क ीयिव ुत ािधकरण दि ण े ीय िव तु सिमित
29, रेसकोस ास रोड
बगलूर- 560 009
Government of India Central Electricity Authority
Southern Regional Power Committee 29, Race Course Cross Road
Bengaluru-560 009
Email:[email protected] Web site: www.srpc.kar.nic.in Fax: 080-22259343 सं/No. SRPC/SE(O)/180th OCC/2021-22/ दनांक/ Date 22nd July 2021
सवेा म / To
सलं सचूी के अनसुार As per the list enclosed
वषय: द े वस क चालन सम वय उप स म तक 180 वी बठैक के कायवृ त के सबंधं म।े Subject: Minutes of the 180thmeeting of Operation Coordination Sub- Committee-reg.
महोदय/महोदया/ Sir/ Madam,
दनांक 09 जुलाई 2021 को वी डयो कां सगं के मा यम से हुई द ण े ीय व युत स म त क चालन सम वय स म त क 180 वी बैठक क कायवृ द े वस के वेबसाईट (www.srpc.kar.nic.in) म उपल धहै।
Enclosed, please find the minutes of the 180thMeeting of the Operation Coordination
Sub-Committee of SRPC held on 09th July 2021through Video Conferencing. The
sameis available at SRPC website (www.srpc.kar.nic.in).
The 181st Meeting of the Operation Coordination Sub-Committee of SRPC is scheduled
on 10th August 2021(Tuesday) through Video Conferencing.
भवद य /Yours faithfully,
(के पी मध ु/ K P Madhu)
अधी कअिभयंता/Superintending Engineer
े षती सचूी/Mailing List ( Operation Coordination Sub-Committeeof SRPC)
1. Chief Engineer (GO),APTRANSCO,Vijayawada 2. Chief Engineer (Generation), APGENCO, Vijayawada 3. Director (O),APSPDCL, Tirupati 4. Chief Engineer (E), SLDC, KPTCL, Bengaluru 5. ChiefEngineer (ED), KPCL, Bengaluru 6. Chief Engineer (TSO), KSEBL, Kalamaserry 7. Chief Engineer (Opn.), TANTRANSCO, Chennai 8. Chief Engineer (Mech), TANGEDCO, Chennai 9. Chief Engineer (GO),TSTRANSCO, Hyderabad 10. Chief Engineer (Generation), TSGENCO, Hyderabad
11. Chief General Manager (Opn-II), TSNPDCL, Warangal. (cgmop2@tsnpdcl. In) 12. Superintending Engineer - I, Electricity Department, Puducherry 13. General Manager (OS), SRHQ, NTPC,Secunderabad 14. General Manager, RSTPS, Jyothinagar, Ramagundam 15. General Manager, STPP Stg - II, NTPC, Talcher 16. Chief General Manager, Simhadri STPS, Simhadri 17. General Manager(O&M), NTECL, Vallur, Chennai 18. Chief General Manager, Neyveli TPS-II, Neyveli 19. General Manager, NNTPS, Neyveli 20. General Manager, TPS-I Expansion, Neyveli 21. General Manager, TPS-II Expansion, Neyveli 22. Chief General Manager (Ele), NLC Tamil Nadu Power Limited(NTPL), Tuticorin 23. Operation Superintendent, MAPS, Kalpakkam 24. STE (E&I), Kaiga G.S. Stage - I, Kaiga 25. STE (E&I), Kaiga G.S. Stage - II, Kaiga 26. Operation Superintendent, KKNPP, Kudankulam 27. General Manager (O&M), SRTS–I, PGCIL, Secunderabad. 28. General Manager (O&M), SRTS- II, PGCIL, Bengaluru. 29. AGM, JSWEL Vijayanagar Plant, Torangallu, Bellary 30. V.P.,Udupi Power Corporation Limited, (UPCL), Bengaluru 31. Electrical Advisor, Coastal Energen Pvt Ltd, (CEPL), Tuticorin 32. Head (O),SEIL Phase-I, Hyderabad 33. Head (O),SEIL Phase-II, Hyderabad 34. IL& FS Tamil Nadu Power Company Limited, Cuddalore 35. Sr.Vice President (O&M),HNPCL,Hyderabad 36. Director, GM Division, CEA, New Delhi. 37. Director, NPC Division, CEA, New Delhi 38. Executive Director, SRLDC, Bengaluru
***
Minutes of the 180thmeeting of OCC (09.07.2021) Page 1 of 54
Southern Regional Power Committee (SRPC)
Minutes of the 180 th Meeting of
Operational Coordination Sub-Committee
(held on 09.07.2021 through VC)
1. Introduction
1.1. The 180th Meeting of Operation Coordination Sub-Committee (OCC) was held on
09thJuly 2021through Video Conferencing (VC). The list of participants is at
Annexure-1.1.
1.2. Shri A Balan, Member Secretary, SRPC& Chairperson of Operation
Coordination Sub-Committee (OCC) extended warm welcome to the members and
participants to the 180th Meeting of OCC. The following was brought to the notice of
the forum:
(i) The demand is in upward path after lifting of lockdown in the States due to the
second wave of COVID-19 pandemic and also huge variation (increase)
compared to last year pandemic situation. All India power demand crossed
200 GW on 07.07.2021 for the first time.
(ii) On frequency side, Grid operated at above 50.05. Hz. for a period of 18.81 %
and 50Hz and above for a period of 59.7 % which is a matter of concern. It was
observed that the frequency of operation above 50 Hz, was very high on many
days, like on 30.06.2021 the Grid operated at a frequency above 50 Hz for
87.64 % of time.
(iii) The issue of heavy UD/OD by SR constituents needed to be addressed urgently
to assure secure Grid Operation. SRLDC may appraise during the course of
meeting the forum regarding the challenge/difficulties met by SRLDC as the
Regional Grid Operator and the reasons which lead to such instances.
(iv) Chairperson, SRPC vide letter dated 28th June 2021 has taken up the issues in
respect of KKNPP (Restoration of Bus Reactor & 400 kV KKNPP-
Thirunelveli line-I, operating of units at partial loading, ensuring availability of
both the units during peak months of SR) with CMD, NPCIL.
(v) CEA, Thermal Project Renovation &Modernization Division vide letter dated
22.06.2021 (Annexure-1.2.v) has advised all generating plants/utilities
(Central/State/Private) that each generating plant/utility may take necessary
action for operation of all the generating units under their administrative
control at 55% load and identify at least 50% of the capacity for further
Minutes of the 180thmeeting of OCC (09.07.2021) Page 2 of 54
lowering the minimum load operation and initiate discussion with OEM to
operate 200-600 MW size unit at 40-45% load and 660-800 MW at 45-50%
load and ramping test (2-3%) on urgent basis and take necessary action for
implementation of measures as identified in the test.
(vi) MoP vide Notification dated 28.06.2021 had Amended Electricity (Right of
Consumers) Rules 2020 and this will be called as Electricity (Right of
Consumers) Amendment Rules 2021.
(vii) MoP has extended timelines for submission of comments on Discussion Paper
on Market Based Economic Despatch (MBED) by 15 days i.e. till 15.07.2021.
(viii) MoP vide letter dated 05th July 2021 has issued clarification on the clause
2(VIII) of the Guidelines on enabling the Discoms to either continue or exit
from the PPA after completion of the term of the PPA i.e beyond 25 years or a
period specified in the PPA and allow flexibility to the Generators to sell
power in any mode after State/Discom exit from PPA.
(ix) CERC has extended the last date until 15th July 2021 for submission of
comments/objections/ suggestions on the Draft Central Electricity Regulatory
Commission (Ancillary Services) Regulations, 2021.
(x) Joint Secretary (OM, R & R), Ministry of Power convened a Meeting on
02.07.2021 to review the implementation of the scheme for Flexibility in
Generation and Scheduling of Thermal Power Stations to reduce emissions.
CERC, SRPC, NLDC, SRLDC and NTPC had participated in the meeting.
(xi) Fourth Meeting of the Task Force on Bengaluru Islanding scheme was held on
06.07.2021.
(xii) CTUIL vide e-mail dated 07.07.2021 has informed that M/s SIEMENS is
proposing 5 days training program on PSSE Software for CEA, CTU, WRPC,
SRPC, POSOCO, Western Region STUs and Southern Region STUs from 2nd
to 6th August 2021 from 11 AM to 1:30 PM. Kindly forward the nominations /
additional topics, if any to be covered in the training program.
Then Superintending Engineer (O), SRPC took up the agenda.
2. Confirmation of the Minutes of 179th Meeting of OCC
The 179th Meeting of OCC was held on 09.06.2021 through VC and the Minutes
were issued on 23.06.2021.
The Minutes of the 179th meeting of OCC were confirmed.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 3 of 54
3 Agenda Items
3.1 Monthly Review of Maintenance schedules of ISGS
3.1.1 Review of Maintenance schedule of ISGS / CGS
The list of maintenance schedules of ISGS and MPPs proposed to avail during the
period of current month and next month period (July / August, 2021) and
postponed from these periods were reviewed in the meeting and mailed to OCC
Google Group.
Deliberation:
(i) KKNPP informed that the Unit-1 would be revived in the 3rd week of August,
2021. Accordingly, KKNPP Unit-1 (1000 MW) outage for refueling would be
for 65 days from 22.06.2021 to 25.08.2021.
(ii) NTPC informed that the revival of RSTPS Unit-3 (200 MW), which was
taken out on 16.01.2021 getting delayed due to COVID-19 restrictions and
expected by the 1st week of August 2021. Accordingly, outage of RSTPS Unit-
3 would be for 204 days from 16.01.2021 to 07.08.2021 (Turbine R&M, ESP
R&M, DVR & Boiler OHs)
(iii) NTPL informed that Unit- 2 (500 MW) outage for Boiler License renewal
during from 17.07.2021 to 23.07.2021 not required as the renewal activities
were carried out during the OSD.
SRPC requested NTPL to furnish the boiler license renewal dates and NTPL
agreed to furnish the same.
(iv) IL & FS (ITPCL) informed that they advanced their AOH programme for
Unit- 2 (600MW) to avail from 20.07.2021 to 09.08.2021 (21 days). [Original
schedule was to avail during August, 2021 for a period of 30 days].
SRPC requested to IL&FS to furnish the revised schedule of Unit-1 (600MW),
which was originally planned to avail during June, 2021 and postponed due to
COVID-19 pandemic restrictions. IL&FS agreed to furnish the revised
schedule shortly.
(v) SEIL P1 informed that outage of Unit-1 (660MW) to carry out AOH would be
availed from 01.11.2021 to 15.11.2021 (15 days).
3.1.2 Maintenance schedule of Unit-1 (500 MW) of Simhadri STPS Stage-I
(i) The original maintenance plan for 2021-22 scheduled by NTPC in respect of
Unit-1of Simahadri STPS Stage-I was to avail for a period of 35 days from
01.06.2021 to 05.07.2021.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 4 of 54
(ii) In the 179th OCC meeting, NTPC had informed that the Unit was under RSD
then and the outage for Boiler License Renewal could be availed after the Unit
revival and the revised schedule of outage of 35 days would be informed
shortly.
(iii) In the meeting, NTPC informed that the Unit outage would be availed during
September 2021 and the revised schedule would be furnished shortly.
(iv) It was noted that the Simhadri STPS-I Unit outage was linked with the outage
of Simhadri - Kalpaka Lines, requested by APTRANSCO to be availed during
September, 2021 along with Unit outage.
(v) OCC advised NTPC to furnish exact dates of maintenance schedules in
respect of 500 MW Unit-1 of Simhadri STPS Stage-I at the earliest as the
Unit outage was linked with the outage of Simhadri - Kalpaka Lines
requested by APTRANSCO. NTPC agreed to furnish the outage schedule.
3.1.3 Maintenance schedule of Unit- 3 (500 MW) Talcher STPS
(i) The original maintenance plan for 2021-22 scheduled by NTPC in respect of
Talcher STPS Unit-3 was to avail for a period of 30 days from 08.07.2021 to
06.08.2021.
(ii) NTPC vide mail dated 06.07.2021 had informed that the mobilization of work
force and other resources were getting delayed due to the ongoing lockdown
and travel restrictions imposed in many States because of prevailing COVID-
19 pandemic situation. Therefore, the overhauling programme was rescheduled
and the shutdown was deferred.
(iii) In the meeting, NTPC informed that the Unit outage was postponed for a
period of 10 days and the revised outage programme of Talcher STPS Unit-3
would be from 18.07.2021 – 16.08.2021 (30 days).
3.1.4 Shifting the maintenance schedules of Kudgi STPS Unit 1&3 (800MW each)
In the 179thmeeting of OCC, TSTRANSCO had requested NTPC to complete the
outage of Unit 1&3 of Kudgi STPS by July 2021 or to avail during
November/December 2021. OCC Forum had requested NTPC to revise their
schedules for availing the same during July 2021 and to furnish revised schedules.
Deliberation:
(i) NTPC informed that they would avail the maintenance and boiler license
renewal outage as per their original schedules.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 5 of 54
(ii) TSTRANSCO requested to postpone this unit outage to October /November,
2021, as their demand would be very high during the period of
August/September 2021 due to LIS and agricultural loads.
(iii) KPTCL informed that in Karnataka wind generation would be high during
August and availing the Kudgi STPS Units maintenance works during August
would be better. Moreover, the demand of Karnataka would pick up during
October, 2021.
(iv) Other beneficiaries opined that unit outage as per the original schedules during
August, 2021 would be convenient for them.
(v) ED, SRLDC suggested TSTRANSCO may arrange power through STOA to
meet the demand as the market price would be reasonable during the period
August /September.
(vi) After deliberation, OCC approved the following maintenance schedule of
Kudgi STPS as per the original schedules:
a) Unit-1 (800 MW) : COH from 01.08.2021 to 29.09.2021(60 days)
b) Unit-3 (800 MW) : Boiler License Renewal from 29.07.2021 to
04.08.2021 (7 days)
3.1.5 Maintenance schedule of NLC TS II Expansion Unit-1 (250 MW)
(i) The original maintenance plan (AOH) for 2021-22 scheduled by NLC TS II
Expansion in respect of Unit-1 for April, 2021 had been revised in the 179th
OCC meeting to avail for a period of 45 days from 15.07.2021 to 28.08.2021.
(ii) In the meeting, NLC TS II Exp. informed that the Unit-1 outage was postponed
for a period of one week (7 days) to avail from 22.07.2021 for 45 days. The
maintenance works involve Boiler, IP Turbine & Generator Overhaul and the
postponement of this work was due to COVID-19 situation. The revised
schedule furnished vide letter dated 12.07.2021 is as follows:
☛ Unit-1 (250 MW) NLC TS II Expansion: from 25.07.2021 to 07.09.2021
(45days).
3.1.6 NNTPS Units (2 x 500 MW) Outage programme
(i) NNTPS had scheduled tentatively the PG Test Preparation in the 179th OCC
meeting for Unit-1 to carry out during 11th – 20th July 2021.
(ii) In the meeting, NNTPS informed that the Unit-1 outage was postponed for a
period of one week (7 days) to carry out PG Test Preparation.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 6 of 54
(iii) The revised PG Test Preparatory outage programme informed by NNTPS are
as follows :
☛ Unit- 1 (500 MW ) : from 16.07.2021 to 24.07.2021 (09 days)
☛ Unit- 2 (500 MW) : from 16.08.2021 to 25.08.2021 (10 days)
3.1.7 All the maintenance schedules of ISGS/MPP Generating Units, pertaining to the
period of July / August, 2021were discussed in the meeting and the approved list of
maintenance schedules is at Annexure- 3.1.7. The same was mailed to OCC Google
Group on 11.07.2021.
3.1.8 All the beneficiaries were requested to note the schedules and all the Generators
were requested not to revise their AMP frequently unless otherwise, if required,
depending on the then Grid condition.
3.2 Processing of monthly outage proposals of Transmission Lines and Elements in
the Outage Coordination Meeting
The outages proposed for the month of August, 2021 in respect of Transmission
Lines and Elements by other regions, State Transmission Utilities, PGCIL and other
transmission Entities were processed and discussed in the Outage Coordination
Meeting held on 07.07.2021 through VC. Some of the outage proposals for which
the consent was not reached for approving the outage proposals were brought
forward to the OCC Forum for deliberations. Some outages, stated as urgent, by the
Requesters, were also proposed in the meeting and the following transmission lines
were deliberated in the meeting.
3.2.1 Outage proposal of 400/230 kV Neyveli TS II ICT-1
(i) NLC had informed in the Outage Co-ordination meeting held on 07.06.2021
that they had proposed to carry out oil filtration work as the dissolved
Hydrogen content was very high and hence oil had to be filtered.H2
concentration level was very high in 400/230 kV ICT-1 at TS2/NLCIL.
(ii) 179th OCC had approved 400/230 kV Neyveli TS II ICT-1 for availing during
18, 19, 20thJune, 2021subject to the availability of MAPS Unit-2, as suggested
by TANTRANSCO.
(iii) NLC had informed that L.C on ICT-1 approved from 18.06.2021 to
20.06.22021 in 179th OCC could not be availed, as the MAPS & TAQA Units
were under shutdown. NLC had proposed vide “PNOCC Outage Portal” (RQ
No:28081) for the shutdown of ICT 1 from 09.07.2021 / 09.00 hrs to
12.07.2021/18.00 hrs for carrying out oil filtration works.
(iv) TANTRANSCO vide their mail dated 02.07.2021 had concurred the ICT
outage to avail from 09.07.2021 to 11.07.2021.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 7 of 54
(v) Accordingly, the shutdown of 400/230 kV Neyveli TS II ICT-1 to avail from
has been approved from 09.07.2021 to 11.07.2021.
OCC noted the above.
3.2.2 Shutdown of 400 kV NNTPP – Puducherry Ckt- 1
(i) NNTPS had requested in the 180thOutage Coordination meeting to avail the
outage of 400 kV NNTPS – Puduchery Ckt-1 from 24th (0700Hrs ) to 25th
(1700 Hrs) August 2021to carry out annual maintenance works.
(ii) There was no representation from PED, Puducherry and hence the shutdown
proposal was referred to 180th OCC meeting for discussion.
Deliberation:
(i) PED informed that the outage could be concurred with the condition that NLC
TS II - Karaikal - Bahour line would be available during the outage period.
(ii) SRLDC suggested that the shutdown could be concurred for the proposed
period based on the real time condition. In case of constraints, if any, the
proposal could be postponed.
(iii) OCC approved the outage of 400 kV NNTPP – Puducherry Ckt-1 to
carry out annual maintenance works during 24th&25th August 2021
subject to availability of NLC TS II - Karaikal - Bahour line and SRLDC
may postpone the outage based on real time condition.
3.2.3 Outage of KGS ICT 1, 2 & 220 kV Bus 1, 2 proposed by NPCIL
(i) In the meeting, NPCIL proposed the outage (for PM checks,DS-30B job, CT
replacement etc.) of KGS ICT 1, 2 & 220 kV Bus 1, 2, as follows :
☛ KGS ICT 1 : 14-17 July, 2021
☛ KGS ICT 2 : 18-22 July, 2021
☛ KGS 220 kV Bus 2 : 14-15 July, 2021
☛ KGS 220 kV Bus 1 : 16-17 July, 2021
(ii) NPCIL had not proposed the outage of KGS ICT 1, 2 & 220 kV Bus 1, 2 in the
179th OCC Outage Co-ordination meeting.
Deliberation:
(i) OCC advised KGS to plan and propose the outage of Transmission Lines /
Elements well in advance and to propose these outages in the PWC Ouatge
Portal.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 8 of 54
(ii) After deliberation. OCC approved the following maintenance schedules subject
to proposing these outages in the PWC Outage Portal and regulation of hydro
generation at Kadra & Kodasalli, by KPTCL/KPCL if required, during the
shutdown.
Element Outage Duration Condition
(i) KGS ICT 1 14-17 July, 2021 Subject to availability of ICT 2 in
service
(ii) KGS ICT 2 18-22 July, 2021 Subject to availability of ICT 1 in
service
(iii) KGS 220 kV Bus 2 14-15 July, 2021 Subject to availability of Bus 1 in
service (No N-1 for Bus 1)
(iv) KGS 220 kV Bus 1 16-17 July, 2021 Subject to availability of Bus 2 in
service (No N-1 for Bus 2)
(iii) KPTCL/KPCL agreed in the meeting that they would regulate their hydro
generation at Kadra & Kodasalli, if required, during the above shutdown.
3.2.4 Trial run of 800 kV Raigarh-Pugalur HVDC Bi-Pole2 during 05.07.2021 –
15.07.2021
(i) GM (RTAMC), PGCIL SR-II had requested vide mail dated 26.06.2021 &
01.07.2021 that they had proposed to carry out trial run for the800 kV Raigarh -
Pugalur HVDC Bi-Pole - 2(Pole 3&4) and requested for approval (Annexure-
3.2.4).
(ii) SRLDC had informed the following vide mail dated 01.07.2021 :
(a) The trail run operation was a part of the contractual agreement between the
OEM and PGCIL. Hence separate trail run operation will be taken up in
consultation with NLDC for the COD.
(b) The minimum and maximum power order in the Bipole-2 would be
300MW and 3000MW respectively with Bipole-1 in service. However,
NLDC will decide the real time power order in consultation with the
SRLDC in all the four Poles of 800 kV Raigarh – Pugalur, honouring the
following N-1 limits :
☛ 400 kV Pugalur-Pugalur_HVDC D/C [N-1 limit of each CKT is
around 1243MW (Sensitivity of 69%)].
☛ 400kV Pugalur_HVDC-Arasur D/C [N-1 limit of each CKT is around
1300MW (Sensitivity 0f 62%)].
Minutes of the 180thmeeting of OCC (09.07.2021) Page 9 of 54
☛ All the limits were given by considering the thermal limit of AC lines
as 2100MW.
☛ In case of operation of 320kV VSC Pugulur-Trichur HVDC, Pole-
1&2 will be used with the N-1 compliance of the 400/220kV Cochin
ICTs (N-1 limit of each ICT is 219MW), 400/220kV Palakkad
ICTs(N-1 limit of each ICT is 205MW), 400/220kV Madakkathara
ICTs (N-1 limit of each ICT is 240MW)
(iii) The trail run test of 800kV Raigarh - Pugalur Pole 3 & 4 from 5thto 15th July,
2021, was approved subject to the following:
(a) Further coordination by SRLDC is to be made with NLDC and
precautionary measures to be done suggested by NLDC / SRLDC, if any.
(b) Advance intimation by SRLDC (D-3) to the State SLDCs in connection
with the Power Order details and precautionary measures to be taken by
SLDCs, if any.
OCC noted the above.
3.2.5 Outage of APTRANSCO’s 400 kV Kalpaka – Simhadri Stg I Ckt-2, 3& 4
(i) APTRANSCO had proposed the outage of their 400 kV Kalpaka – Simhadri Stg
I Ckt 2, 3 & 4 to avail during August, 2021 one after another. In the 180th
Outage Coordination meeting held on 07.07.2021, these outages had been
approved subject to the outage of 500 MW NTPC Simhadri Unit 1 and
regulation of generation at Stage 1 by APTRANSCO, as suggested by SRLDC.
Deliberation:
(i) NTPC informed that they had postponed Simhadri STPS Unit-1 maintenance
outage from June / July 2021to September, 2021.
(ii) NTPC not confirmed the dates of revised schedule. NTPC was requested to
furnish their exact dates of maintenance schedules at the earliest as the Unit
outage was linked with the outage of Simhadri - Kalpaka Lines, requested by
APTRANSCO to avail during August, 2021.
(iii) APTRANSCO agreed to avail their lines outage along with Simhadri Unit 1
outage during September, 2021 to avoid regulation of generation at Stage-1.
Accordingly, the following outage of lines, proposed by APTRANSCO were
postponed to September, 2021.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 10 of 54
SL Line / Element Name Reason for outage
Proposed
From Date /
Time
Proposed To
Date / Time
1 400kV-Kalpakka-
Simhadri_Stg1-3
Forperiodical Line
Maintenance works
Thu, 12-
Aug-2021,
09:00
Postponed to
Sep, 2021
Thu, 12-Aug-
2021, 19:00
Postponed to
Sep, 2021
2 400kV-Kalpakka-
Simhadri_Stg1-2
For periodical Line
Maintenance works,
general maintenance
of yard equipment,
periodical bay
equipment and relay
testing.
Sat, 21-Aug-
2021, 09:00
Postponed to
Sep, 2021
Sat, 21-Aug-
2021, 19:00
Postponed to
Sep, 2021
3 400kV-Kalpakka-
Simhadri_Stg1-4
For periodical Line
Maintenance works
Tue, 31-
Aug-2021,
09:00
Postponed to
Sep, 2021
Tue, 31-Aug-
2021, 19:00
Postponed to
Sep, 2021
Conclusion:
(i) NTPC to furnish their exact dates of maintenance schedules in respect of
Simhadri STPS Stage- I Unit-1 (500MW) at the earliest as the Unit outage was
linked with the outage of Simhadri - Kalpaka Lines, requested by
APTRANSCO.
(ii) APTRANSCO’s 400 kV Kalpaka – Simhadri Stg I Ckt 2, 3 & 4 were postponed
to September, 2021, subject to the outage of 500 MW NTPC Simhadri Unit 1
and regulation of generation at Simhadri Stage-1 by APTRANSCO, as
suggested by SRLDC.
(iii) SRLDC may further shift the 400 kV Kalpaka – Simhadri Stg I Ckt 2, 3 & 4, if
required, as per the system requirement and in line with the outage of 500 MW
NTPC Simhadri Unit 1 or may regulate the generation at Stage I of Simhadri, if
the Unit outage is not taken during September, 2021.
3.2.6 Major outages of inter-regional transmission lines and elements, discussed in
the 180th OCC Outage Coordination Meeting
The following Major outages of inter-regional transmission lines and elements were
approved / discussed in the 180th OCC Outage Coordination Meeting:
Minutes of the 180thmeeting of OCC (09.07.2021) Page 11 of 54
(i) 400 kV Bolangir - Meramundali -1: The shutdown of 400 kV Bolangir -
Meramundali -1 was approved to avail during 10-11th July, 2021 subject to non-
availing of any other previously approved shutdowns in ER-SR corridor during
this outage period and all the outages approved during this period stands
cancelled.
(ii) 765 kV Sholapur – Raichur -1:This outage proposed in the 180th OCC
Outage Co-ordination Meeting to avail on Mon, 2-Aug-2021, 07:00-18:00 Hr,
to carry out AMP works for the line side equipment, involving TTC Reduction
up to 550 MW in the WR-SR corridor was postponed to September, 2021, as
desired by PGCIL SR I. The Line Reactor which was proposed to avail along
with Line was also deferred to September, 2021. PGCIL was requested to
submit their revised proposal in the next Outage Co-ordination Meeting.
(iii) 765 kV Wardha – Nizamabad -1 & 2:
a) This outage was approved in the 180th OCC Outage Co-ordination Meeting
to avail on Sat, 07-Aug-2021, 08:00 - 17:00 Hrin respect of ckt 1 and on
Sun, 08-Aug-2021, 08:00 - 17:00 Hrfor the diamond crossing works of
400kV Wardha - Auranagabad D/C line over 765kV Wardha-Nizamabad
D/C line. During this outage A/R would be kept in non-auto mode for
765kV Wardha – Nizamabad respective circuits for the safety of working
team. There will be a TTC Reduction up to 600 MW in the WR - SR
Corridor during the shutdown period.The outage of these lines would be
availed along with Line Reactors for the AMP works of Reactors.
Approved outages are as follows :
765 kV Wardha – Nizamabad - 1 :Sat, 07-Aug-2021, 08:00-17:00 Hr
along with L/R of Ckt 1 @ Nizamabad
765 kV Wardha – Nizamabad - 2 :Sun, 08-Aug-2021, 08:00-17:00 Hr
along with L/R of Ckt 2 1 @ Nizamabad
b) Outage of this same line of Ckt 1, proposed in the 180th OCC Outage Co-
ordination Meeting to avail on Sun, 22-Aug-2021, 08:00-18:00 Hr again
for the rectification of OPGW loss between Tower No 64 to 66 for capacity
expansion of Mumbai - Chennai NLD backbone link, was deleted and
combined with the outage approved to avail on 07.08.2021.
The list of outages of Transmission Lines and Elements, approved in the
Outage Coordination Meeting, was uploaded in PWC Web portal as well as
on SRPC Website and mailed to OCC Google Group on 11.07.2021.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 12 of 54
3.3 Monthly Review of LGBR for the next five months (Availability &Requirement)
The Availability & Requirement in respect of the State System are reviewed every
month for the next five months. Constituents are requested to submit this data by 3rd
of the month. Constituents were also requested to furnish the detailed Availability &
Requirement for the period from July 2021 to November 2021.
Deliberation:
(i) It was noted that all the states had furnished the five months ahead LGB(July
2021 to November 2021). The abstract/analysis of the information furnished
by states is at Annexure-3.3
(ii) It was observed hat all the states except Telangana (demand shortage during
August to October 2021 and energy shortage in August and October 2021) are
in comfortable power position, as projected by states.
(iii) TSTRANSCO informed that due to this expected shortage they are requesting
all generators to avoid outages during August to October 2021. Telangana is
expecting peak loads during this period.
(iv) SE(O), SRPC said that during the months of December/ January market price
may be very high and opined that TSTRANSCO may plan for purchase of
power from the market during August to October 2021. Since other States are
expecting comfortable LGB during this period and market price also would be
comparatively less.
3.3.1 Quarterly Review of LGBR (July, 2021 – March, 2022)
(i) The data for the Review LGBR (185 LGBR) for the period July,2021 – March,
2022 needed to be submitted to SRPC by States / Generators by 09.07.2021,
so that the report can be brought out by the middle of July, 2021. The format
for furnishing the data was issued on 02.07.2021 (Annexure - 3.3.1)
(ii) Annual Peak LGBR 2021-22, Off Peak LGBR 2021-22 reports are available on
SRPC website.
(iii) In the meeting, KPTCL, KSEBL, NTPC, NLC TS II Expansion, NTECL,
MAPS, KGS, KKNPP &IPPs were requested to expedite submission of
LGBR / Generation data to SRPC.
3.3.2 Outage Deviation Reports for 2020-21 & 2021-22 Q1
(i) Data for the Outage Deviation Report for the year 2020-21 & 2021-22 (April
– June, 2021) were sought from the pending Constituents / Transmission
Utilities / Gencos / Generators to furnish in the prescribed format mailed to
the OCC Google Group on 06.07.2021& 09.07.2021 respectively.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 13 of 54
(ii) The States / Generators / Transmission Utilities were requested to furnish the
data by 10.07.2021 & 14.07.2021 respectively for the Outage deviation
Reports for 2020-21 & 2021-22 Q1 (April – June). It was requested to furnish
monthly deviation data along with OCC data every month, without fail.
(iii) In the meeting, PGCIL SR-I, KPTCL, KPCL, KSEBL, NLC TS II
Expansion, NTECL, MAPS, KGS, KKNPP & MPPs were requested to
submit their LGBR / Generation data to SRPC urgently.
3.3.3 Data for SRPC Annual Report 2020-21
(i) The data for the preparation of Annual Report of SRPC for the year 2020-21
was requested to furnish by 23-07-2021 to SRPC. The format for furnishing
the Annual Report data had been mailed to OCC Google Group also.
(Annexure- 3.3.3).
(ii) In the meeting, SRPC requested all the Constituents / Transmission Utilities /
Gencos / Generators to submit the data in the format urgently.
3.4 Upgrading existing RTUs / Gateways reporting to Ethernet on IEC 104 protocol
(i) SRLDC had requested the Constituents in the 174th OCC Meeting to
technically approve the up-gradation of 101 Protocol RTUs to 104 Protocol
RTUs at the DCPC located Control Centers. The issue was being followed
up in monthly OCC/COM SR Meetings.
(ii) In the COM SR Meeting held in February 2021 PGCIL had suggested that
the state utilities may carry out migration wherever possible and states
agreed to explore the possibility. PGCIL had requested to arrange
recommendation by SRPC for migration of 101 protocol to 104 protocol
wherever possible so that states can take up the migration.
(iii) All the States were requested to submit the details of RTUs communicating
on 101 Protocol, along with the plan for migrating to 104 Protocol to SRPC,
so that the issue would be taken up to TCC / SRPC through OCC meeting as
agreed in the COM SR – Outage March, 2021 meeting to implement the
migration of 101 RTUs with the present condition to 104 RTUs wherever
possible.
(iv) SRPC vide communication dated 19.03.2021 had requested all the states to
furnish the details of RTUs which are communicating 101 protocol along
with the plan for migrating to 104 protocol to put up to TCC/SRPC through
OCC. It was also requested to furnish the suggestions/comments on the
Minutes of the 180thmeeting of OCC (09.07.2021) Page 14 of 54
technical/configuration issues to midrate to 104 protocols and additional
preventive measures to prevent the cyber-attacks.
(v) KPTCL had informed that KPTCL had informed that all the RTUs in
KPTCL communication system are reporting on 104 protocol.
(vi) The information had been received from APTRANSCO, KSEBL,
TSTRANSCO & Puducherry (Annexure-3.4.vi).
(vii) The information from TANTRANSCO was awaited.
(viii) In the meeting of COM SR- Outage July 2021 held on 24.06.2021 the
following were suggested:
a) SRLDC opined that a Registry of IP addresses being used for IEC-104 &
VC needed to be maintained by SRLDC. All the Entities may submit the
details to SRLDC for compiling the said Registry. SRLDC informed that
the said Registry would be useful for planning the IP addressing scheme
for next SCADA up-gradation. SRLDC informed that they would
communicate to the Entities, their official and secured mail ID to which
the Communication Entities will share the IP address details for
maintaining the "IP Registry" by SRLDC, so that the information could be
collected by the said stipulated time as decided in the meeting.
b) Further, as suggested by PGCIL in the previous meeting that each Entity
may nominate a member for the “Core Committee”, which would be a
part of coordinating the “IP Registry”, to be maintained by SRLDC.
Deliberation:
(i) SE (O), SRPC said that in the COM SR meetings PGCIL had requested to
arrange recommendation by SRPC for migration of 101 protocol to 104
protocol wherever possible so that states can take up the migration. The
recommendation of OCC would be put up to TCC/SRPC for consideration.
(ii) The status of RTUs as informed by the states is as follows:
Minutes of the 180thmeeting of OCC (09.07.2021) Page 15 of 54
(iii) SE(O) requested the states to update on the latest status and the following
were noted:
APTRANSCO informed that the works are under progress. As and when
improvement is there, the same would be informed. SE(O) SRPC requested
AP to update the status monthly to SRPC.
CE (TSO), KSEBL informed that OPGW works are getting delayed, at
present works are under progress. For RTU tender is under prequalification
stage. Six months will be taken to achieve the target.
TANTRANSCO informed that the status would be furnished shortly.
(iv) SE(O), SRPC stated that in the COM SR July Meeting SRLDC had opined
that a Registry of IP addresses being used for IEC-104 & VC needed to be
maintained by SRLDC. All the Entities may submit the details to SRLDC for
compiling the said Registry. MS SRPC had expressed concern regarding this
in view of security point of view. He requested ED SRLDC to express his
view on this proposal.
(v) MS SRPC further added that concern was mostly w.r.t cyber security.
Transparency in respect of IP addresses etc. are not advisable in the current
scenario. States may take a stand on this.
(vi) ED SRLDC observed that Government of India is watching all NIC mails and
this information as proposed may be communicated in very confidential way
only.
(vii) APTRANSCO informed that they would share the information confidentially
to SRLDC.
(viii) KPTCL informed that whatever transaction required between SRLDC and
SLDC would be communicated for the integration, communication and data
transfer facilitating smooth operation of the Grid.
(ix) Endorsing the views of KPTCL, KSEBL informed that information on need
basis would be submitted to SRLDC.
(x) TANTRRANSCO informed that they would discuss with higher
management and come back with their views.
(xi) SE (O), SRPC recalled that PGCIL in the previous meeting had suggested
that each Entity may nominate a member for the “Core Committee”, which
would be a part of coordinating the “IP Registry”, to be maintained by
SRLDC.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 16 of 54
(xii) ED, SRLDC emphasized that cyber security also has taken a role as critical
requirement as normal grid operation. At present in all utilities there is only
minimum number of officials who are involved in IT and SCADA related
activities who takes care of cyber security aspects also. Even a small issue
can be addressed and resolved with mutual coordination of different parties.
In view of this if such a core committee (with identified officials) is formed,
the process of addressing and resolving of issues like IP conflict problems
etc. would be a little easier and faster.
(xiii) SE, KPTCL SCADA opined that at present CISO (GO) and an alternate
member had already been identified. The same nodal officers may be
assumed as the member of core committee as suggested by PGCIL. All IP
conflict issues will be resolved through this core committee.
Conclusion:
(i) All states (except KPTCL and Puducherry - all are reporting to 104
protocol) will furnish the status update on up-gradation of 101 Protocol
RTUs to 104 Protocol RTUs at the DCPC located Control Centers.
(ii) OCC recommended for migration of 101 protocol to 104 protocol wherever
possible. This issue will be put up to TCC/ SRPC.
(iii) With respect to SRLDC proposal to keep a Registry of IP addresses, all the
utilities may furnish the IP address as per their discretion from the
organization mail ID to SRLDC mail ID(one to one). SRLDC to keep the
information with outmost confidential.
(xiv) The Nodal Officers who were identified as CISO(GO) and alternate
CISO(GO) would also act as Core Committee Members for coordinating
the “IP Registry”, to be maintained by SRLDC. All the day to day
practical issues/IP conflicts would be solved through this Core committee
members.
3.5 Non availability of proper SCADA data
(i) In the meeting of COM SR – Outage May, 2021 (25.04.2021) SRLDC had
requested all the Communication Nodal Officers to ensure that they conduct
System studies regularly so that maintenance of real time data could be
ensured including penetration of RE data and also would be helpful to identify
the congestion issues up to 220 kV level. All the Nodal officers informed that
they have separate study group under their Planning Division and were
carrying out the study.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 17 of 54
(ii) In the meeting of COM SR – Outage July 2021 (24.06.2021) SRLDC had
presented the progress in respect of proper SCADA availability with respect to the
previous meeting and sensitized the importance of “State Estimator” with the
increased penetration of RE Generation in SR so as to improve the
rectification of one time SCADA related issues and in respect of the issues
which need continuous activities for rectification. Emphasized the
requirement of converging State Estimator in real time up to 220 kV level
telemetry and the importance of checking for the telemetry error / bad quality
data every week and to run the “State Estimator” periodically. Further,
requested to nominate a dedicated person for coordinating with SRLDC /
SLDC SCADA Engineers.
(iii) The following had been noted in the meeting of COM SR – Outage July
2021:
a) All the utilities may arrange a dedicated officer to address the non-
availability & bad quality SCADA data and for addressing the “State
Estimator” related issues to SRLDC.
b) All the utilities will ensure the convergence of SCADA data by
rectifying the telemetry issues like errors and bad quality data and will
take necessary steps to run the “State Estimator” periodically to ensure
SCADA availability without error.
c) All the Entities will carry out the rectification works step by step in a
phased manner as pointed out by SRLDC and to resolve the issues
within the time limit informed by them in the meeting.
Deliberation:
(i) SE(O), SRPC informed that in the meeting of COM SR – Outage July
2021 held on 24.06.2021,SRLDC had emphasized the requirement of
converging State Estimator in real time up to 220 kV level telemetry and
the importance of checking for the telemetry error / bad quality data
every week and to run the “State Estimator” periodically and had further
requested to nominate a dedicated person for coordinating with SRLDC /
SLDC SCADA Engineers. He requested states to express their views.
(ii) APTRANSCO informed the nodal officer for communication issues
would be the officer who will take care of the State Estimator/SCADA
also.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 18 of 54
(iii) SE, SCADA, KPTCL informed that a single officer would take care of
the issues related to SCADA data, State estimator etc. and to ensure that
requirements are met. He informed that every 5 minutes state estimator
is running and converging also.
(iv) CE (TSO), KSEBL opined that this is a requirement not only of SRLDC
but also of SLDC and informed that a dedicated officer (from SCADA
team) would be identified and details would be shared shortly.
(v) TANTRANSCO informed that a dedicated officer would be identified
from SCADA for this purpose.
(vi) SRLDC informed that the identified officer is responsible for running the
state estimator and should see that it is converged. Maintaining the
model, running the state estimator with telemetry checking, correction
etc. will be the responsibility of the nodal officer. Weekly model
updating/synchronization would be carried out upto 220 kV level. It is
observed that states are coming forward for rectification of the issues
whenever drawal figures are affected. With the increase in RE
penetration the significance of correct modeling at least upto 220 kV
level assumes an important role. Studies would be meaningful only if
correct data is available.
Conclusion:
(i) All the states may identify an officer exclusively for attending the issues
with State Estimator/SCADA, responsible for running and maintain the
model and ensure that cases are converged.
(ii) The requirement of a dedicated officer to address the non-availability &
bad quality SCADA data and for addressing the “State Estimator” related
issues to SRLDC is a need of the hour and states may take up with higher
management for the approval of the same.
(iii) The details of the identified officer needed to be communicated to
SRLDC.
3.6 SRLDC agenda Items
A. SRLDC has proposed the following new items for discussion:
a) Prolonged outage of grid elements
b) Significant OD/UD of states in the month of May 2021
Minutes of the 180thmeeting of OCC (09.07.2021) Page 19 of 54
c) Revival of Kadamparai HEP Units: by 30th June 2021 for pump mode
operation.
d) Overloading of ICTs
e) Radial operation of 230 kV Villianur & Bahoor loads which was agreed by
Puducherry in 179th OCC meeting of SRPC.
f) Status of PSS/E Base case Submission
g) Frequent tripping of lines
h) Non-furnishing of Details for Grid Events by Constituents
i) Procedure for PSS/E Base case preparation Methodology
B. SRLDC has proposed the following follow up items:
a) List of Substations with Single Bus Operation
b) Follow up of special meeting held with RE developers on 25.02.2021
i. SCADA related Issues
ii. Operation
iii. Measurement of Harmonics, Flicker and DC Injection
iv. Uploading of data to SRLDC REMC reporting website
v. Registration of generating plants
c) SCADA Data availability issues
i. Non-reporting of real time SCADA data MTPS Stg-3 (Tamil Nadu)
ii. Non-reporting of real time SCADA data from N P Kunta
iii. Non-reporting of real time SCADA data from 400 kV SEPL station
iv. Partial reporting of real time SCADA data from 230kV Kalpakam
(MAPS) Station.
d) Real time data discrepancy issues
C. Status review of the following:
a) Commissioning of Bus reactors &STATCOMS as approved in various
meetings & Standing Committee.
b) Review of operational performance of Condenser mode of operation of
N’Sagar & Srisailam LB.
c) Status review of AUFR, df/dt& Automatic disconnection of Radial feeders
under ADMS.
d) Review of forecast vs Actual demand of SR constituents
e) Status review of ATC / TTC calculation by SLDCs and LGBR submission
Minutes of the 180thmeeting of OCC (09.07.2021) Page 20 of 54
f) Condenser mode of operation in other Hydro stations:
The details of the above items furnished by SRLDC are at Annexure-3.6.
A a) Prolonged outage of grid elements
S.
No Element Owner Reason for outage
Out From
(Date)
Last
Expected
date
1
400KV-
SRISAILAM_LEFT_BANK
-SATTENPALLY-1
TSTRANSC
O
COMPLETE
OUTAGE OF
SRISAILAM
STATION
20-08-2020 31-08-2021
(i) In the Meeting TSTRANSCO informed that cable joint had to be replaced and
order had been given (LS Cables, Chorea). It will take 6 months to receive the
same and complete the works.
A b) Significant OD/UD of states in the month of June 2021
% TimeOD> Min DSM Limit at Low Freq(<49.90 Hz) & % time UD>Min DSM Limit at High freq. (>50.05 Hz)
S. No. Date AP(%/MW) TS(%/MW) KA(%/MW) TN (%/MW) 1 02-06-2021 4.31(UD)/ -1143 4.03(UD)/ -337 2 03-06-2021 12.29(OD)/ 1173 4.51(OD)/ 664 3 04-06-2021 10.28(UD)/ -1057 9.17(UD)/ -539 8.33(UD)/ -578 4 06-06-2021 4.44(UD)/ -1341 4.93(UD)/ -732 5 10-06-2021 9.1(UD)/ -395 6 12-06-2021 5.9(UD)/ -499 4.24(UD)/ -261 7 15-06-2021 4.03(UD)/ -446 4.72(UD)/ -833 8 16-06-2021 4.58(UD)/ -764 9 17-06-2021 5.07(UD)/ -1472 10 20-06-2021 7.5(UD)/ -1352 11 21-06-2021 6.25(OD)/ 557 15(OD)/ 1088 10.83(OD)/ 1367 12 22-06-2021 7.36(OD)/ 1188 4.93(OD)/ 698 13 24-06-2021 6.18(UD)/ -865 14 25-06-2021 4.1(UD)/ -586 4.38(UD)/ -1082 15 28-06-2021 9.93(OD)/ 881 5.83(UD)/ -570 11.39(OD)/ 1669
Deliberation:
(i) SRLDC projected the % Time OD> Min DSM Limit at Low Freq (<49.90
Hz) & % time UD>Min DSM Limit at High freq. (>50.05 Hz) during the
month of June 2021. The quantum of OD/UD was also projected.
AP UD(4 incidences) had touched 1143 MW on 02.06.2021 and OD(3
incidences) 1173 MW on 03.06.2021.
TS UD(6 incidences) touched 570 MW on 15.06.2021. OD incidences
crossing deviation limit were not observed.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 21 of 54
KPTCL UD(4 incidences) touched 1472 MW on 17.06.2021. OD (2
incidences) touched 1188 MW on 22.06.2021.
TN UD(5 incidences) touched 865 MW on 24.06.2021. OD(3 incidences)
touched 1367 MW on 21.06.2021
(ii) ED, SRLDC observed that states are updating on the reason for these UD/OD.
But the corrective actions carried out to avoid such incidences in future
needed to be explored and framed. He emphasized that all the states needed to
ensure that ADMS are enabled.
(iii) MS, SRPC stated that the general view is that there is no power shortage. But
the operation of ADMS may give a different observation.
(iv) APTRANSCO informed that all the incidences presented were noted down
and had taken up with system operators and had requested them to carry out
corrective actions to avoid such incidences in future. He informed that some
constraints are faced by AP in arranging RTM power and DAM power due to
quantum variation and price variation. High RE integration/sudden RE
variation also lead to OD/UD in several occasions. In some occasions
APSLDC had opted for even load restrictions to mitigate the OD quantum. He
ensured that all thermal and hydro stations are brought back on bar.
Krishnapatanam units are having coal shortage issues. RTPP, one unit got
technical issues. Despite of all these constraints he ensured that huge OD/UD
will be controlled.
(v) TANTRANSCO informed that June-July months are wind months and
normally on daily basis 80-90 MU wind power injection is expected. But due
to abrupt climate changes the difference between forecast and actual become
more. At present day solar injection is around 2800 MW and during peak
hours it become zero, and to compensate this TN is depending on day ahead
market. At the same time, to compensate sudden wind variation only available
mechanism is real time market, but constraints are observed in getting RTM
power due to non-availability of power even at higher price which leads to
OD from Grid. He observed that high RE penetration (MUST RUN Status)
without proper balancing mechanism is leading to heavy OD/UD and opined
that this issue needed more deliberations and studies.
(vi) ED, SRLDC suggested that NTECL Vallur, CEPL etc. may be kept on bar
giving Technical minimum schedule rather than taking out under RSD, which
may help in such situations of heavy OD. Online reserves should be
maintained always.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 22 of 54
(vii) TANTRANSCO expressed concern regarding the MOD which is strictly to be
followed which is the constraints for keeping the generators on bar by
scheduling to technical minimum level.
(viii) KPTCL informed that on 17.06.2021, KPTCL UD is around 1400 MW. In
spite of all thermal units keeping under Technical Minimum UD followed on
18.06.2021 also. Day peak needed to be met with solar and evening peak
needed to be met through internal generation and ISGS which is a difficult
task to Grid Operator. Complexities are added when the huge errors are there
in RE forecasts. Even RE generations are curtailed except Pavagada, they
refused to curtail quoting that they are under purview of SRLDC scheduling.
Upto 17th rains were received as per IMD forecast, but after 17th daily 20 MU
increase in demand was observed due to stoppage of rain which was not as
per prediction. Even though thermal generators are advised to come back on
bar, constraints were there due to the time period required to come on bar
from RSD. Releasing of the pandemic lock down made demand forecast more
difficult. Heavy RE integration (MUST RUN Status)/huge variation in RE
injection without proper balancing mechanism puts system operator in
ambiguity w.r.t system operation. Endorsing the views of TANTRANSCO,
KPTCL also desired for a separate study in this regard.
(ix) TSTRANSCO informed that on 02/04.06.2021, there were unpredicted rains
all over the state which caused to demand crash leading to UD. There was
sudden change in solar on some of the days leading to UD. On one rainy day,
they failed in regularizing the loads in time which lead to UD. He ensured that
care would be taken to avoid such incidences in future.
(x) MS SRPC observed that on 21.06.2021 most of the states are under drawing
and desired to know whether it was at same time. SRLDC clarified that the
incidences were at different timings and expressed that simultaneous OD/UD
may even lead to grid incidences.
Conclusion:
All the States to take immediate corrective action to avoid heavy OD/UD at any
point of time.
A c) Revival of Kadamparai Units:
(i) SLDC TANTRANSCO had informed that Kadamparai HEP Units will be
revived by 30th June 2021 for pump mode operation.TN SLDC may deliberate
on revival of Kadamparai Units.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 23 of 54
(ii) In the Meeting, SE TNSLDC informed that the works are in advanced stage.
Some of the water conducting system had been charged. Units will be bringing
on bar one by one from 15.07.2021.
A d) Overloading of ICT
a. N-1 violation of Kaiga ICTs observed when the cumulative generation at 220kV
Kadra and Kodasalli HEP is around 250 MW. Need for SPS may be discussed to
trip generation at Kadra or Kodasalli for contingency of 400/220kV ICT’s.
b. N-1 violation of 400/220kV Mysore ICT’s
Deliberation:
(i) CGM, SRLDC stated that Kodasalli-Nagjheri line is kept open. Kadra &
Kodasalli generation needed to be evacuated through Kaiga 400/220 kV ICTs
where Kaiga generation is also being added.If Kodasalli-Nagjheri line is
closed, the power from Kadra, Kodasalli and Kaiga will flow to Naghjeri area
where the network is already weak. This issue had been deliberated in various
forums and SRLDC had given feedback to Standing Committee. It was
advised that the network from Kodasalli, Nagjheri, Ambewadi to Narendra
needed to be strengthened to HTLS conductors.
(ii) KPTCL confirmed that Kodasalli-Naghjeri line was kept open on power
regulation to avoid overloading of Nagjeri lines and for smooth evacuation of
Naghjeri power.
(iii) On a query by MS SRPC, SRLDC clarified that these ICTs were meant for
evacuation of Kaiga Stage I units (220 kV levels). If one of the ICTs trips,
other ICT overloads and trips, along with Kadra and Kodasalli generations
Kaiga Stage I generation also will lose. He opined that if KPTCL, KPCL &
KGS agree an SPS may be formed such that whenever there is an N-1 issue at
ICTs, the lines towards Kadra and Kodasalli may be tripped at Kaiga end. In
such cases Hydro generation only will be lost which can be selectively
charged on to Nagjheri bus.
(iv) KPTCL informed that at high hydro level situation Kaiga needed to be
operated otherwise back water will be pushed towards Kaiga. This issue
needed to be addressed. SPS as suggested may also be thought of.
(v) CGM, SRLDC opined that if all the parties concerned agree, a SPS may be
devised with a logic that “ if one of the ICTs at Kaiga(400/220 kV) trips and
the other ICT flow crosses 480 MVA, Kaiga - Kodasalli & Kaiga – Kadra
Minutes of the 180thmeeting of OCC (09.07.2021) Page 24 of 54
lines may be tripped”. KGS and KPCL may be advised on the same for
implementation.
(vi) KPCL informed that during June-August, if Kadra generators are not running
continuously, water needed to be allowed to flow through gates, and water
will flow towards Kaiga GS Complex.
(vii) CGM, SRLDC clarified that even with SPS, Kadra generation is not being
affected.
(viii) KGS informed that in principal he is willing to the proposal and opined that
this SPS will safeguard Kaiga Units which are connected at 220 kV level. The
proposal and logic/level of ICT loading for tripping of Kaiga – Kadra and
kaiga – Kodasalli lines for SPS operation will be informed to Technical Team
of KGS and a communication will be given on the same to SRPC/SRLDC
shortly.
Conclusion:
(a) KPTCL& KPCL agreed the proposal of SRLDC for SPS at Kaiga - “ if one
of the ICTs at Kaiga(400/220 kV) trips and the other ICT flow crosses 480
MVA, Kaiga - Kodasalli & Kaiga – Kadra lines may be tripped at Kaiga end”.
(b) KGS given in principle concurrence and official communication would be
sent after discussion with the technical team of Kaiga GS.
(c) Accordingly, SRLDC would take up the implementation of the SPS.
Ae) Radial operation of 230kV Villianur & Bahoor loads
(i) 400kV Pondicherry-SVChatram is being kept in hand tripped condition on
power regulation. Puducherry SLDC may share updates regarding the radial
operation of 230kV Villianur & Bahoor loads which was agreed in 179thOCC
meeting of SRPC.
(ii) In the Meeting, Puducherry informed that on requirement basis the
radialisation of loads may be carried out. He informed that a written
communication concurring for this radial operation will be sent shortly.
TANTRANSCO also agreed for the proposal.
(iii) Neyveli-Villianur & Neyveli-Bahoor lines would be opened at Neyveli end.
Whenever there is a tripping at Ramanathaparam- Villianur, Villianur may go
dark and to avoid this NLCIL should be ready to revive these lines at Neyveli
end at any point of time. NLCIL agreed for the same.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 25 of 54
(iv) It was concluded that as and when official communication from Puducherry is
received for concurrence of radialization of the Neyveli-Villianur & Neyveli-
Bahoor lines, SRLDC will take up the implementation with intimation to
Puducherry, NLCIL & TANTRANSCO.
Af) Status of PSS/E Basecase Submission
(i) The constituents are requested to submit the PSS/E Base case of 4 different
scenarios Peak: - 1800 Hrs. Off-Peak: 0300 Hrs. Morning Peak: 0900 Hrs.
Solar Peak: - 1300 Hrs. for the upcoming 4th month by 20th of every month to
enable RLDC to determine the Margin for STOA and declare TTC by 26th of
every month. The status of PSS/E case submitted by constituents is given below.
TTC calculation by each control area is mandatory as per the “Detailed
Procedure for relieving Congestion in real time Operation, 2013” approved by
CERC.Constituents are requested to furnish the PSS/E cases timely before
OCCM and Declare the Control area Drawl Capability in their website
S.
No. State
ATC/TTC
Computation
furnished to
SRLDC
PSS/E
Case
Submitted
Four (4)
Scenarios
Submitted
State
1 Andhra
Pradesh Yes Yes Yes
Andhra
Pradesh
2 Telangana No Yes Yes Telangana
3 Karnataka No Yes No Karnataka
4 Tamil
Nadu No Yes Yes Tamil Nadu
5 Kerala Not Applicable Yes Yes Kerala
6 Puducherry No No No Puducherry
(ii) Presently, S1-S2 TTC is limited by 400/230kV ICT constraints (Allundur,
Thiruvallam &Checknoorani), hence it’s time to move State wise TTC.Also, to
enhance TTC States, constituents are requested to do transformer augmentation.
(iii) In the meeting. SRLDC informed that APSLDC had submitted the details
which was checked by SRLDC and requested AP to upload the same on their
website.
(iv) All other states are requested to calculate the ATC/TTC and submit to SRLDC
which will be vetted by SRLDC and states can upload on their website. Along
Minutes of the 180thmeeting of OCC (09.07.2021) Page 26 of 54
with PSSE base case submission this calculation also may be submitted. He
observed that states may come to know on the constraints on the ICT loadings
w.r.t each control area through this exercise which may be passed on to planners
also for planning accordingly.
(v) CGM, SRLDC added that this exercise of computing ATC/TTC may help in
analyzing the constraints at different levels of drawals. This information may be
passed on to STUs/planners and they can help in achieving the system with
future anticipated drawl levels/load growth.
A g) Frequent tripping of lines
(i) Details of frequent tripping of lines during June 2021 are given below (Tripping
of lines on OV protection are not included):
S. No. Name of the Element No. of Trippings
1 220kV ASUPAKA - LOWER_SILERU-1 4
2 220 kV AMBEWADI - PONDA 1 4
(ii) All constituents are requested to take appropriate remedial actions in order to
avoid frequent tripping of lines.
(iii) In the Meeting, SRLDC requested AP, TS and KPTCL to ensure that such
trippings are avoided.
(iv) KPTCL informed that in the four (4) trippings as mentioned, three are
attributable to Goa. Trippings were on distance protection. After identifying
and rectifying the issues, to close the lines, delay is observed in receiving the
code.
(v) SRLDC suggested that KPTCL may communicate as and when the fault is
rectified and SRLDC will immediately take up with NLDC to issue the code,
being an inter-regional line; NLDC code is required for charging this line.
(vi) KPTCL informed that the delay is usually from WRLDC side.
(vii) SRLDC requested KPTCL to give a mail regarding the issues faced by KPTCL
in this regard so that SRLDC will take up with WRLDC and NLDC in this
regard which was agreed by KPTCL.
A h) Non-Furnishing of Details for Grid Events by Constituents:
(i) As per the provisions of Regulation 5.2 (r) of CERC (Indian Electricity Grid
Code) Regulations 2010 and Regulation of 5 (9) of CERC (Indian Electricity
Grid Code) (First Amendment) Regulations, 2012 all the Regional Entities of
Minutes of the 180thmeeting of OCC (09.07.2021) Page 27 of 54
Southern Region shall furnish the tripping details including DR & SEL output
to SRLDC with in 24hrs of the event for analysis and identify the real time
measures required in future to ensure secured grid operation.
(ii) In the Meeting, SRLDC requested all constituents to furnish data timely in
SRLDC Tripping portal. It was noted that delay / non-furnishing of information
delays analysis of the event and further obstructs the information dissemination
by SRLDC to all concerned.
A i) Procedure for PSS/E Base case preparation Methodology
(i) The Timelines may be followed as below:
S.No. Description Responsibility Timeline
1
Preparation of All India and
Regional Load Forecast on 03
month ahead basis
NLDC To be Shared by
1st Week
2
Preparation of State-Wise
Forecast
on 03 month ahead basis
SRLDC
To be shared by
10th of Every
month
3
Preparation of State base cases
based on the methodology
suggested and submission
CONSTITUENT
To Be shared by
20th of Every
Month
4 Stitching of state cases and
preparation of SR cases SRLDC
To be done by
26th of Every
month
(ii) The States are requested to submit the TTC and Declare TTC in their website
along-with PSS/E cases submission.
(iii) In the meeting, SRLDC presented the modified Procedure for PSS/E Base case
preparation Methodology.
(iv) All the states opined that they will give their opinion on the modified procedure
after discussion with their system study team.
(v) It was decided that the modified procedure will be communicated to all the
states by SRLDC and the views/concurrence on implementation of the
modified procedure will be communicated by the states within 10 days by
all the states.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 28 of 54
B a) List of Substations with Single Bus Operation:
(i) States were asked to submit the list of substations with Single bus operation and
submit the action plan for making them double bus through bus coupler in 178th
OCC meeting.
(ii) In the meeting, it was noted that the information had been received only from
AP & KPTCL. Other states were requested to furnish the information within a
week.
B b) Follow up of special meeting held with RE developers on 25.02.2021.
The updates furnished by SRLDC in the Meeting are as follows:
Description of the
Issue. Pending as on Previous OCC (179th
OCC) Completed as compared to
previous OCC Pending as on date
SCADA as per RE
frame work/ FTC and
Actual Position viz
points not provided
ACME P1, ACME P3,
ACMEP6,FRV-1,FRV-
2,AZURE,NPKPS-1,NTPC
8 NIL 0 ACME P1, ACME P3,
ACMEP6,FRV-1,FRV-
2,AZURE,NPKPS-1,NTPC
8
SCADA points
provided but data not
coming /consistent
(i) SRLDC informed that there was no improvement w.r.t SCADA validation.There was a one to one meeting with SRLDC
SCADA, KSPDCL SCADA team and Pavagada implementing agency, GE. The following time schedule was framed on
the issues.
1. Availability of PPC by 9th July 2021.
2. Pending SLDs to SRLDC by 9th July 2021. 3.Nodal persons by 15th July 2021.
4. Sharing IEC address list to KSPDCL an end to end testing by 19th July 2021
5. Db configuration at KSPDCL end and SRLDC end to be completed by 31st July
6. P-t-p testing and compliance of all telemetry requirements to be completed by 31st Aug.
(ii) SRLDC had taken up with NTPC w.r.t the pending issues and NTPC had replied mentioning with time lines for
addressing the pending issues.
Nodal officer
confirmation for
SCADA validation &
taking up real time
SCADA issues
Pavagada:Fortum,KREDLNpkunta:,
FRV,FRV2,NTPC
Tuticorin:-Mytrah
8 Acme
Rewari,Kurukshetra,KRE
DL
3 Pavagada:Acme
Rewari,Kurukshetra,
FortumNpkunta:,FR
V,FRV2,NTPC
Tuticorin:-Mytrah
5
(iii) SRLDC expressed concern in the dealy made even to identify a Nodal Officer and opined that this issue needed to be
taken up seriously. SE(O), SRPC suggested SRLDC to take up with the respective SPDs officially. OCC deliberations
only may not help in this regard.
Providing VOIP Pavagada: - All
Npkunta: Acme Bhiwadi, Hisar,
Karnal, FRV, FRV2, NTPC,SB
Energy, Tata, Azure
Tuticorin: Pending-Girel,
Mytrah
32 Nil 0 Pavagada: - All
Npkunta: Acme
Bhiwadi, Hisar, Karnal,
FRV, FRV2, NTPC,SB
Energy, Tata, Azure
Tuticorin: Pending-
Girel, Mytrah
32
VoIP issues are again to be discussed specifically since much improvement is not observed and requested SRPC to convene a
Meeting.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 29 of 54
Voltage control mode
of operation within the
capability limits.
Pavagada: Pending-Adyah
Block 1, 10, 13,2,3,6,
RenewTn2, Acme Rewari,
Kurukshetra, Fortum, Fortum
Solar, KREDL, SB Energy,
Yarrow, Avada Solar, Solarise
–P-22, Parampujya, TATA
Renewable
Npkunta: Acme Bhiwadi, Hisar,
Karnal, FRV, FRV2, NTPC,SB
Energy,
Tutuicorin: Girel, Mytrah
NIl 0 Same as Previous OCC 0
No progress
LVRT/HVRT Pavagada:Pending-Fortum,KREDL
Npkunta: Pending -
AcmeBhiwadi,Hisar,Karnal,FRV,F
RV2,NTPC
Tutuicorin:Mytrah
11 Acme
Rewari,Kurukshetra,Mytr
ah,KREDL, NTPC
4 Pavagada:Pending-
AcmeRewari,Kurukshetra,
Fortum
Npkunta: Pending -
AcmeBhiwadi,Hisar,Karnal
,FRV,FRV2,
6
Confirmation of LVRT/HVRT, and on which regulatory clause implementation was carried out etc were sought and the same
information in pending from 6 SPDs. Developers are requested to furnish the tripping report on regular basis. Even if there is
no tripping, no tripping report needed to be furnished.
Measurement of
Harmonics, Flicker and
DC Injection
All are pending except Ayana 33 Nil 0 Same as Previous OCC 33
Multiple developers are injecting at same Pooling Station. Measurement at common pooling point is becoming difficult.
Measurement at 33 kV level at developer wise may be thoghut of. Developers are ready for this. After internal discussion,
SRLDC will further update on the proposal.
Uploading of weather
parameters on monthly
basis in specified
format
All are pending 34 ANP_SBEnegy,ANP_spr
ingagnitra 2 AllexceptANP_SBEnegy,A
NP_springagnitra 32
Registration with CEA Pavagada-AvvadaSolarise,KREDL
NPKunta–,FRV,FRV2,
NTPC pendingTirunelveli-Mytrah
6 Nil 0 Pavagada-
AvvadaSolarise,KREDLN
PKunta–
,FRV,FRV2,NTPC
pendingTirunelveli-Mytrah
6
KREDEL officials had met SRLDC on 08.07.2021 and had ensured that all pending issues with Kredel will be addressed
within three days.
Geo tagging
Information for each
wind turbine with
NIWE
Mytrah, GIREL, Orange 3 Orange is taking up
with project vendor
and they have
submitted data to
NIWE. GIREL have
submitted data to
NIWE
Note: Currently
NIWE is facing
Issues with their
portal once it is
corrected, both
GIREL and Orange
will be done.
0 Mytrah, GIREL,
Orange
3
(i) SRLDC informed that there was an audit carried by CEA during March 2021.
Monthly status updates are furnished to CEA.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 30 of 54
(ii) AP forecasting is being stopped due to nonpayment issues and SRLDC also is not
receiving any RE forecast w.r.t RE. APSLDC may kindly address the issue. For
the time being, APSLDC may share the day ahead forecasting to SRLDC.
(iii) APSLDC informed that a separate Bank Account will be opened to make the
REMC payment. Mostly within one-two days account will be opened and
payment will be done.
B.c) SCADA Data availability issues
(i) Non-reporting of real time SCADA data MTPS Stg-3(Tamil Nadu)
1) Reported SAS issue at Mettur.
2) Following up since 168th OCCM.
3) Data of Mettur Stg-3 is yet to be restored.
4) Non-compliance of IEGC clause 4.6.2 pertaining to data availability
In the Meeting, MTPS informed that SCADA issues will be solved during next
week. Delivery of DCU is expected this week.
(ii) Non-reporting of real time SCADA data from NPKunta
i. SCADA data from Galiveedu PS-1 & NPKunta PS-1 not reporting to
SRLDC Backup Control Centre since Jan 2021.
1. POWERGRID has informed of IP-conflict issues with respect to data
reporting to Back up SRLDC from Galiveedu PS-1 & NPKunta PS-1.
SRLDC has assigned new IP addresses for data reporting to Backup
SRLDC.
2. Implementation of the same is pending by APSPCL & POWERGRID.
ii. Developer-wise data of NTPC (connected to NP Kunta PS-1) is not
reporting to Main & Backup SRLDC SCADA.
Yet to be attended by NTPC
(iii) Non-reporting of real time SCADA data from 400KV SEPL station
a. Data not reporting to SRLDC on either channel
b. 400KV SEPL (Main Channel): not getting loop. Link not healthy;
(Secondary Channel): loop ok but data not reporting though this healthy
link.
c. 178th OCC discussion: PGCIL, SR-I informed that link has been rectified
and the same would be checked by SRLDC. The other link is to be taken
Minutes of the 180thmeeting of OCC (09.07.2021) Page 31 of 54
up by SEPL. SRLDC requested PGCIL to communicate the same in a
return mail.
d. Follow up letter sent to SEPL on 1st June 2021.
SEPL informed OEM not able to depute Engineer owing COVID-
19restrictions
(iv) Partial reporting of real time SCADA data from 230kV Kalpakam (MAPS)
Station
a. Lines- except 230kV Kalpakam-Echur lines, all other 230kV lines are
not reporting.
b. GT HV and LV side MVAR data of both units are not reporting.
c. GT HV and LV side MVAR data of both units are not reporting.
d. Follow up letter sent to MAPS on 1st June 2021.
e. Faulty telemetry yet to be rectified.
MAPS informed that they are in touch with PGCIL, SR II. Due to COVID-
19works are delayed. Within one works issues will be solved.
SR II informed that the status update will be furnished shortly.
B.d) SCADA data discrepancy issues:
Data discrepancy issues are compiled and being shared on monthly basis to
all SR states, ISGS and POWERGRID for rectification.
Discrepancy list updated and shared on 3rd June.
Letter sent to POWERGRID SR1 & SR2 for site wise contact details for
checking of faulty telemetry. Contact details received for SR1 stations and
details awaited from SR2.
Except Telangana, all other SR States has reverted back on the discrepancy
points.
All utilities are required to initiate action on rectification of the identified
points.
In the Meeting, SRLDC informed that data discrepancy issues are being taken up
on alternate days. 220 kV network is also being monitored. Monthly
discrepancies are being informed to the concerned entity and being addressed.
Except Telanagana all other utilities are communicating to SRLDC regarding the
status.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 32 of 54
4. Follow up issues
4.1 Overloading ICTs in Tamil Nadu control area violating of N-1security
a) 400/230 kV 2X250 MVA ICTs at Neyveli Stage-II:
The following are the actionable points as per 179th OCC Meeting:
(i) TANTRANSCO agreed for the SPS as suggested in the Special Meeting held
on 28.05.2021(In case the flow become uncontrollable and flow on ICT
crosses 230 MVA,400 kV line to Kalivathappattu would be opened
considering the availability of other evacuation lines. As far as the N-
1condition(one ICT tripping),TANTRANSCO may come up with a
plan for taking out some loads (only under N-1 condition and
theotherICTloadingcrosses250MVA)like tripping of Neyveli-Bahoor,
Neyveli-Villianur, Neyveli-Kadalangudi lines etc. so that flow on the
other ICT would be maintained and avoid ICT tripping.)
(ii) TANTRANSCO to study the study the proposal agreed by Puducherry
(radialysation of Villianur&Bahoor loads). SRLDC reliability team will study
on the A/R issues. Puducherry to carry out the patrolling of the lines and may
ensure the healthiness of the lines.
(iii) SRLDC, TANTRANSCO and Puducherry jointly discuss and study the
proposal and would implement the approved scheme at a convenient date with
the approval of SRPC.
(iv) NLC TS-II may explore the possibilities of shifting of NLC TS-II
Unit-IV connectivity (or any other unit connected to 400 kV) to 230
kV side as decisively requested by TANTRANSCO.
(v) TANTRANSCO to expedite/accelerate the action for commissioning
of 400kV S/Ss at Cuddalore, Ariyalur and Manalmedu and associated
downstream networks.
Deliberation:
(i) NLCIL again reiterated the apprehension regarding the implementation
of the proposal of shifting one of the NLCIL Stage II Unit which is
connected to 400 kV level to 230 kV level.
(ii) On a query to NLCIL SRLDC clarified that the 400kV NLCTS2 -
NNTPP S/C line loading was as high as 700 MW during peak wind
season and less generation in Chennai area. Further to reduce high short
circuit current problem at Neyvelli generation complex, one ckt. of
Minutes of the 180thmeeting of OCC (09.07.2021) Page 33 of 54
Neyvelli TS-II – Salem 400kV D/c line and Neyvelli TSII – NNTPS
400kV S/c line (bypassing Neyvelli TS-II) to form NNTPS – Salem
400kV S/C line was approved in the 42nd SCM held on 27.04.2018 and
the same was carried out on 01.03.2021. Restoring the same is not
possible at this juncture. SRLDC desired to know whether NLCIL ICT
can be enhanced.
(iii) TANTRANSCO opined that the suggestion to NLCIL to connect one of
the Generator to 220 kV side needed to be considered favorably by
NLCIL.
(iv) After deliberation, it was agreed that the proposal of shifting of NLC
TS-II Unit-IV connectivity (or any other unit connected to 400 kV) to
230 kV side would be put up to TCC/SRPC.
b) 400/230 kV 2X315 MVA+ 1X500 MVA ICTs at Trichy SS&400/230 kV
2X315 MVA ICTs at Tiruvalam SS:
The following are the actionable points:
1) TANTRANSCO to expedite the action for commissioning for
Pudukkottai S/S (LILO point of 400 kV Pugalur-Karaikkudi line) to
alleviate loading issue at Trichy. In the 179th OCC Meeting
TANTRANSCO had informed that Pudukkottai S/S would be
commissioned by September 2021.
2) TANTRANSCO to expedite the action for procuring and commissioning
of third 500 MVA ICT at Thiruvalam to mitigate the loading of existing
Thiruvalam ICTs.
In the Meeting, TANTRANSCO noted that the status remains the same.
4.2 Non-reporting of real time SCADA data MTPS Stg-3&Non availability of OPGW on
NTECL - North Chennai lines (since October 2019):
1) TANTRANSCO had informed that RTU issue is observed and tendering
process for new RTU is over. LOI is issued. Supply and erection is pending
and new RTU is expected to be commissioned by June 2021.
2) In the 179th OCC Meeting (09.06.2021), TANTRANSCO had informed that
PO issued for new RTU. Delivery is delayed due to COVID-19 restrictions.
3) In the COM SR- outage July 2021 Meeting held on 24.06.2021 the
following had been noted:
Minutes of the 180thmeeting of OCC (09.07.2021) Page 34 of 54
a) TANTRANSCO had informed that DTPC was under installation and the
materials for DTPC had been allotted to NTECL, Vallur and NCTPS.
Drawal& installation was to be taken up shortly.
b) The OFC works were under progress under the Reliable Communication
Scheme.
c) TANTRANSCO had assured that the interim arrangement by linking the
NTECL Vallur – Alamathy OPGW Link with Alamathy – NCTPS Link
@ Alamthy to make the NTECL – NCTPS link through, would be
completed by July, 2021.
d) TANTRANSCO had assured that NTECL – NCTPS permanent OPGW
link works would be awarded after the end of code of conduct period and
the works would be completed by August, 2021.
In the Meeting, TANTRANSCO informed that OPGW on NTECL – NCTPS
line would be completed by August 2021 as informed earlier.
4.3 Reserve Shut Down (RSD) – Implementation of new Procedure
i. Implementation of new RSD procedure on trial basis for two months was
agreed in the special meeting held on 03.09.2020. All the utilities had
conveyed concurrence for implementation of new RSD procedure on trial
basis for two months.
ii. In the 178th OCC Meeting, SRLDC had informed that implementation of RSD
had already been taken up with NLDC/PWC for implementation and changes
in WBES has been agreed upon by PWC. It was agreed by SRLDC that action
for the implementation would be expedited in coordination with PWC as
requested by the Forum, especially felt by TSTRANSCO.
iii. Subsequently, TSTRANSCO vide letter dated 27.05.2021had requested
SRPC/SRLDC to take immediate action to implement the RDS procedure
(trial run for two months) at the earliest or modify the Entitlement ON bar &
OFF bar quantity to reduce part load compensation liability of TSDICOMs
who is actually not a part in part load operation.
iv. In the 179th OCC Meeting, the following had been noted:
a) In principle all the states had agreed for the procedure for implementation
off bar.
b) SRLDC would revert back within one week after detailed study on the
issues in implementing the off bar in consultation with commercial
division of SRPC. Accordingly States would be informed and if needed
Minutes of the 180thmeeting of OCC (09.07.2021) Page 35 of 54
special meeting may also be convened with states to appraise the outcome
of the studies and to decide on further course of action.
c) MS SRPC had opined that the decision may be taken at the earliest since
SRPC members/higher management have already given consent for trial
run of new RSD procedure.
d) TS SLDC had requested SRLDC to avoid further delay and SRLDC had
agreed to expedite.
Deliberation:
(i) SE(O), SRPC requested SRLDC to apprise the forum on the status of
the implementation process of NEW RSD procedure.
(ii) ED, SRLDC stated that the process of implementation of revised
procedure required significantly more efforts/time than what was
anticipated. This includes two parts, one is for taking out for RSD and
the other for reviving from RSD. SRLDC team had faced many
hurdles/challenges during the development of the logic/software and
despite of all the team had succeeded in completing around 80 % of the
work. The efforts, results, hurdles faced, what will be the final schedule
etc. will be represented by SRLDC team. The dates from which mock
trial can be started and also actual trial run etc may be deliberated.
(iii) SRLDC presented the status of implementation. It was noted that a web
based application was developed by SRLDC internal IT team. SRLDC
demonstrated base case for new RSD procedure.
(iv) SE(O), SRPC opined that as per developed application SRLDC may
implement the procedure. SRLDC may conclude on the plan for the
implementation time lines.
(v) SRLDC informed that by 14.07.2021 all the works w.r.t the
implementation including testing would be over. From 15.07.2021
mock trial (without commercial implication) may be started(till
18.07.2021) to experience the impact by States. In consultation with
SRPC, trial run for 2 months may be started from 19.07.2021. The data
would be jointly validated jointly by SRLDC and SRPC before
officially submitting to SRPC for commercial accounting.
(vi) SE(O), SRPC suggested that a workshop may be convened to make the
associated officials more aware of the procedure which was agreed by
Minutes of the 180thmeeting of OCC (09.07.2021) Page 36 of 54
the forum. He said that two months trial operation may be commenced
form 1st day of the month.
(vii) SE, TSSLDC expressed sincere gratitude to ED, SRLDC and his team
for the gigantic effort put to bring the NEW RSD procedure to
implementation stage. He thanked MS SRPC and his team for
facilitating the same.
(viii) All the constituents agreed that the implementation of new RSD
procedure on trial basis with commercial implication may be
commenced from 01.08.2021.
Conclusion:
(i) A workshop to be arranged (tentatively on 13.07.2021) in which SRLDC
will demonstrate the NEW RSD procedure.
(ii) The dates for mock trial (without commercial implications) and actual
trial run for two months would be decided in the said workshop.
4.4 Status update of Primary Frequency Response testing at ISGS & IPPs
i. The following had been noted in the 179th Meeting of OCC:
(i) NNTPS had informed that they have placed work order on 07.05.2021.
(ii) NTPC had informed that Simhadri STPS Unit-3 PFT is planned in third
week of June 2021. NTPC was requested to furnish the schedule
requirement as and when the date is confirmed.
(iii) W.r.t SEIL, SRLDC informed that due to COVID-19 restrictions testing
was on hold and once issues are contained, status would be updated.
(iv) SEIL(P1) informed that they were in touch with Solvino and they
informed after the pandemic is in control, they will give the date.
(v) SEIL(P2) informed that Work Order had been placed.
(vi) SRLDC observed that all the generators had been placed Order and
testing needed to be scheduled.
Deliberation:
(i) NTPC, Simhadri informed that since only one unit was running with
technical minimum (other units under RSD) during June 2021, the testing
were not carried out. All the units are on bar at present, Siemens also has
come up with readiness. It is tentatively planned to carry out the testing
for all the units from 21.07.2021(12 days may be required), one by one.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 37 of 54
The schedule of testing will be intimated shortly. He requested all
beneficiaries to support to facilitate the testing.
(ii) NTPL informed that 500 MW each Unit-1 and Unit-2 achieved COD on
18.06.2015 and 29.08.2015 respectively. However, Natural Draught
Cooling Tower (NDCT) Performance Guarantee tests were not conducted
so far by the package contractor M/s GECPL. GECPL had invoked
arbitration and same is pending before Arbitral Tribunal. Now GECPL
has come forward to conduct PG test. It is mandatory to NTPL to provide
schedule for the testing. Request was given to ED SRLDC/SRLDC/All
SLDCs to give full schedule on 08.07.2021 and 09.07.2021. But except
TANTRANSCO & KSEBL nobody gave full schedule. He requested the
states to give full schedule on 12th or 13th whichever is convenient.
Testing is required on Cooling Towers, and during the period of testing
wind velocity should not exceed 5 m/sec (plant is located at costal area).
Evening wind velocity is more. So, he requested all states to give full
schedule at least for 4 hours during day time.
(iii) SRLDC opined that testing may be carried out from 12:00 hours to 16:00
hours of 11.07.2021, if agreeable by all the beneficiary states.
(iv) All the beneficiaries of NTPL agreed for the test from 12:00 hours to
16:00 hours on 11.07.2021.
4.5 Shifting of PMUs
i. In the 36th meeting of SRPC held on 12.07.2019, it was agreed that some PMUs
installed as part of URTDSM project in SR may be optimized by shifting them
to critical substations, lift irrigation substations and substations with FACTS
devises etc. Accordingly SRLDC had suggested for shifting of PMUs at
Vemagiri to KTS VII (PST) &Vemagiri to Ramadagu (LI).
ii. In the 177th OCC Meeting, it was noted that three Nos of PMUs connected to
400 kV Vemagiri-Gowthami-1, Gowthami-2, Konasema-2, GVK-1 and GVK-2
feeders are dismantled by M/s.GE T&D India Ltd and the 3 No’s removed
PMUs were handed over to M/s.GE T&D India Ltd.
iii. In the 179th Meeting, TSTRANSCO had informed that Ramagudu and Veltoor
PMUs are integrated and data is reporting. At KTPS VII PMU is to be integrated
which is delayed due to COVID-19 restrictions.
iv. In the Meeting, TSTRANSCO informed that works had been startedon
05.07.2021.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 38 of 54
4.6 Daily Load Forecasting by SLDCs
(i) SLDCs are requested to furnish the load forecast error (forecast Vs actual
demand) for the month of June 2021to SRLDC along with reasons for
substantial deviations.
(ii) States were requested to break the state load into area wise like district
wise/Substation wise while carrying out the forecasting incorporating
weather conditions etc.
(iii) In the meeting, SRLDC presented the load forecast error (forecast Vs actual
demand) for the month of June 2021.On an average the error was observed
to be below 8 % (Annexure -4.6).
4.7 Renewable forecasting
(i) All states had been requested to furnish the implemented forecast, day ahead
forecast & actuals also (before 5th of every month). It was noted that this data
was being sought by higher forums and other entities.
(ii) SRLDC had submitted the RE forecasting for June 2021 (Annexure-4.7)
4.8 Furnishing of EHV Transmission Elements Details in the prescribed format
i. In the 178th OCC Meeting, SRLDC had requested all the constituents to
provide consolidated statement of the transmission elements
charged/commissioned in the previous month for updation of SRLDC
Database, PSS/E base case which is used for TTC/ATC computations, PoC
base case and Real-Time Security Desk. As opined by MS SRPC SRLDC
was suggested to furnish the modified formats for furnishing the
information.
ii. Accordingly SRLDC had furnished the FORMATS which had been
forwarded to all concerned.
iii. It is noted that no states are furnishing the information as per FORMAT.
AP & TS are separately furnishing the information of new elements, but
FORMAT to be modified as per SRLDC FORMAT. Other states are
furnishing the progress, but newly commissioning elements are not
reported separately.
All the entities may furnish the details on monthly basis (by 8th of every
month or along with OCC data).
4.9 Communication & Cyber Security Audit
i. As per the requirement of clause 10 of Central Electricity Regulatory
Commission (Communication System for inter-State transmission of
Minutes of the 180thmeeting of OCC (09.07.2021) Page 39 of 54
electricity) Regulations, 2017, RPC Secretariat shall issue necessary
instructions to all stakeholders to comply with the audit requirements within
the time stipulated by the RPC Secretariat and an Annual Report on the
audit carried out by respective RPCs shall be submitted to the Commission
within one month of closing of the financial year.
ii. In the 178th OCC Meeting, it was noted that Cyber security audit was not
carried out by many of the entities. NLCIL had earlier committed that they
would take action to carry out the Cyber security Audit in line with NTPL.
NLCIL informed that the action taken would be intimated by mail.
All the entities to carry out the Cyber Security Audit/VA/VAPT at an
interval as mandated by Regulations in future.
4.10 Ensuring Proper Functioning of under Frequency Relays (AUFR)
&df/dtRelays
i. In the 178th OCC meeting, the states had agreed the list of identified S/S for
inspection/functionality test for the year 2021-22
ii. SRPC vide letter dated 25.05.2021hadcommunicated the list of substations
to states along with FORMATS for furnishing the report.
iii. Utilities may carry out the inspection and submit the report in the
prescribed format before 31.01.2022.KPTCL had submitted the report.
4.11 PSS Tuning
i. SRPC is following a specific plan for the PSS tuning exercise, and is
regularly pursued with generating Stations. Seven Meetings (till 31st March
2021) were conducted with generators to analyze the PSS test reports.
Recommendations were communicated to each generator after the Meetings.
ii. The 8th Meeting of PSS Tuning was held on 20.04.2021 and analysis of
around 36 units was carried out. The action taken in respect of the
recommendations in the 8thmeeting of PSS tuning may be updated.
iii. 9th PSS Tuning Meeting is scheduled for 20th July 2021. The reports
submitted by the following 16 units would be analyzed/discussed.
Entity Station Unit
KPCL
BTPS 1,2 &3
Nagjheri HEP 3
Sharavathy HEP 1,2,4,5,8
KAR IPP UPCIL 1&2
TANGEDCO MTPS Stage- III 1
TSGENCO Kothagudem TPS 12
SCCL Singareni TPS 1 &2
NPCIL KGS 3
Minutes of the 180thmeeting of OCC (09.07.2021) Page 40 of 54
In the Meeting, SE(O) SRPC requested all the concerned entities to carry out
the PSS tuning as recommended in the 8th PSS Meeting. The action taken report
as per the 8th PSS Meeting also may be furnished. He requested all the generators
to participate in the scheduled 9th PSS Meeting on 20th July 2021 to enable the
discussion/analysis fruitful.
4.12 Reactive Power Capability of Invertors, Its utilization and way forward for
pilot project
i. SRLDC had furnished a note on Reactive Power Capability of Invertors, its
utilization and way forward for pilot project.
ii. SRPC had noted that all such pilot schemes in India are being implemented
in consultation with NLDC and suggested that since the issue is not regional
specific, NLDC may come up with a National perspective and requested
SRLDC to arrange for views of NLDC on the notes for facilitating
deliberation in SRPC forums.
iii. SRLDC vide letter dated 29.06.2021 had requested NLDC for consent and
modus operandi on the Notes on Reactive Power Capability of Invertors, its
utilization and way forward for pilot project submitted by SRLDC for
facilitating deliberation in SRPC forums.
iv. NLDC vide letter dated 06.07.2020(Annexure-4.12) had furnished their
comments for further discussion at SRPC level.
v. SRLDC vide E-mail dated 08.07.2021 had requested SRPC to take up this
issue in the 180th OCC meeting and take view/consent on trial operation.
Deliberation:
(i) ED, SRLDC apprised the forum that a testing was carried out on MVAR
absorption of solar inverters during night hours at Pavagada and based on
the findings the note was prepared and the same had brought to OCC forum.
The suggestion was appreciated by all and even the initiative from SR is
spreading throughout the country. He observed that to control the over
voltage, on daily basis around 40 lines are being opened. Many lines are kept
open on sustained basis. Keeping the Solar inverters in MVAR absorption
mode at night hours would help in addressing these issues up to an extent.
NLDC had accorded for the proposal quoting the previous experiences and
had noted the below:
Minutes of the 180thmeeting of OCC (09.07.2021) Page 41 of 54
The operation of solar inverters in night mode for controlling high
voltage appears a good initiative and would help the system reliability.
Similar usage of synchronous condenser mode of operation of hydro
plants is being done in Northern Region since long at Tehri and Pong
hydro generating plants. The arrangement for commercial settlement is
based on an agreement at Regional Power Committee level. In this
agreement, the active power which is consumed by the generating station
for operation in synchronous condenser mode goes to the regional losses
and plants do not have to incur deviation charges for the same.
(ii) APTRANSCO suggested that a workshop may be arranged separately in
which the proposal may be presented and both operation and commercial
officials may participate.
(iii) KPTCL informed that this issue had already been deliberated in their state
Grid Committee Review Meeting held on 08.07.2021 and solar inverters
would be approached for operating at night mode.
(iv) Chief Engineer (TSO), KSEBL informed that they would revert back with
their views after studying the Note.
(v) TSTRANSCO intimated that after receiving the note, the same would be
studied and submit their observations.
(vi) TANTRANSCO informed that since commercial implications are
envisaged, the proposal needs to be studied further and views may be
submitted accordingly.
Conclusion:
i. SRPC to circulate the communications from NLDC along with the SRLDC
Note on the Reactive Power Capability of Invertors, Its utilization and way
forward for pilot project to all the concerned to enable the beneficiaries to
study the implications.
ii. A special meeting would be convened shortly in which SRLDC would
present the proposal and the way forward on the implementation (both
operational & commercial).
The communications from NLDC along with the SRLDC Note were circulated
to the constituents on 09.07.2021.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 42 of 54
5. Frequency related Issues
5.1 High Frequency
(i) SRLDC presented the under drawal of states when frequency was above 50.05
Hz.
(ii) The Regional Grid had operated above IEGC range ie 50.05 Hz for 18.91 % of
the time. It was also noted that the frequency on some of the days was higher
for considerable duration of times.
(iii) Maximum frequency had touched 50.26 Hz at 18:05 hours of 04.06.2021
(Graph at Annexure-5.1.A).No under drawals observed during this time. Also
the duration of time Grid operated above IEGC limit is observed to be high
which is to be looked into seriously.
(iv) The under drawal of states when frequency was above 50.05 Hz (Annexure-
5.1.B). The maximum under drawal touched by States during June 2021 was
also presented.
(v) Constituents were advised to avoid under drawal at high frequencies. SRPC
requested all the constituents that action needs be taken to adhere to the
schedule since it has commercial/operational impacts even for under drawal.
5.2 Pump mode operation
It was noted that during June 2021, there was no pump mode consumption at
Srisailam and at Kadamaprai. N’sagar pump mode consumption was around 32.60
MU.
5.3 Low Frequency
It was noted that the frequency of grid operation was at times lower than IEGC
range. Grid had operated below IEGC range ie 49.90 Hz for 6.20 % of time
during the month.
(i) SRLDC informed that minimum frequency touched 49.64 Hz at 19:49 hrs
on 03.06.2021.Drawal of Southern Regional states at that instance were
also projected which were in limits.(Graph atAnnexure-5.3.A).No over
drawal was observed during this time.
(ii) Over drawal by SR constituents at frequency less than 49.90 Hz
(Annexure-5.3.B) was presented by SRLDC. The maximum over drawal
touched by States also was presented.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 43 of 54
6. Voltage Related Issues
6.1 Low Voltage
Details of capacitors installed during June 2021 in the prescribed format to be
submitted by all the states.
6.2 High Voltage issues
6.2.1 MVAR Interchange
In the 169th OCC Meeting it was suggested that MVAR testing may be taken up
after the COVID -19 pandemic issues settle down.
In the Meeting, SRLDC informed that testing had not been taken up due to
prevailing COVID-19 pandemicconditions.
6.3 RE Generators for Reactive Compensation & High Voltage
All the states were again requested to kindly examine and ensure voltage based
MVAR interchange for RE generators.
6.4 Status review of Bus/Line Reactors, Line Reactors and STATCOM
Status of implementation of Bus / Line Reactors approved in the Standing
Committee/SRPC pending for commissioning by the SR constituents is at
Annexure- 6.4.
All the Constituents/Entities are requested to update the status.
Reactors added during 2020-21 may be furnished separately by all entities.
6.5 Reactor status
a) Hoody reactor: Inspection by Electrical Inspectorate pending.
Commissioning would be decided after inspection.
b) KKNPP reactor: Contract yet to be awarded. Discussions are going on with
contractor. By September 2021 end the status would become to know.
c) KGS reactor: Tendering is over. The date for submission of tender is
extended up to 08.08.2021. PGCIL also was requested to participate in the
tender.
7. Network Protection/Security issues
7.1 U/F &df/dt Relays Schemes
Concerned to update the status on regular basis.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 44 of 54
7.2 Implementation of SRPC recommended quantum
(i) It was noted that all States had implemented AUFR and df/dt schemes fully.
(ii) SRLDC presented the load relief realized as a percentage of AUFR quantum
declared in the identified feeders during the month of June 2021 as follows:
(Detailed Presentation is at Annexure-7.2.A)
AP: 94 %, TS: 82 %, KAR: 63%, KER: 88%, TN: 76%, Pudu: 87% &SR:
93 %.
(iii) SRLDC expressed concern regarding the less response w.r.t KAR and
requested to analyze the same.
S.NO State SCADA
mapped %
Status
1 AP 98 All the stages vetting completed.
2 TS 88 TSTRANSCO*
*Informed that additional RTUs at 132 kV level are required to achieve
100 %. Project is taken under PSDF funding. Tenders are floated.
3 KAR 100
4 KER 100
5 TN 88 Some of the RTUs are faulty. After
rectification the percentage will increase.
6 Pudu 92
7 SR 94
8. RGMO/FGMO
(i) As per 5th Amendment to IEGC, gas stations above 50 MW Installed Capacity
were also to come under RGMO/FGMO Operation w.e.f. 1st October 2017.
(ii) Inadequate response was needed to be taken up by SLDCs with respective
SERC’s in line with Hon’ble CERC Orders in respect of Petition No.
84/MP/2015 and 302/MP/2013.The non-performance of the generators under
SRLDC control would be taken up by SRLDC with the respective generators.
(iii) SRLDC vide letter dated 25.06.2021 (Annexure-8.iii) had furnished the
RGMO/FGMO analysis for the incidents during 2020-2021 to CERC.
(iv) SRLDC vide communication dated had furnished (Annexure-8.iv)the Southern
Region Frequency Response characteristics for the event of 1500MW generation
loss in Northern Region happened due to multiple trippings at 400/220kV
Akal(Rajasthan) & 400kV Jaisalmer-2(Rajasthan) on 11thJune, 2021 at 16:02 Hrs.
FRC has been calculated state wise and generating station wise.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 45 of 54
Sl.No. State/Region FRC(%)
1 Andhra Pradesh 5
2 Telangana -22
3 Karnataka 39
4 Tamil Nadu -1
5 Kerala -55
6 Puducherry 171
7 Southern Region 33
(v) Constituents are requested to submit the same for their control area.
(vi) SRLDC vide E-mail dated 17.06.2021 had informed that at 16:03 HrsHrs on 11th
June 2021, 220 kV Akal-Bhu -1&2 tripped due to snapping of B-phase jumper
which resulted into 1200MW wind generation loss and 300MW solar generation
loss in Northern region. Frequency dropped from 50.09 Hz to 49.92 Hz.
(vii) RGMO analysis based on SRLDC SCADA data was attached in the google
spreadsheet and all generators were requested to enter data pertaining to the
event in the above spreadsheet.
(viii) In the Meeting, SRLDC informed that for 11.06.2021 incident, analysis are yet
to be received from many generators. He requested all the generators to update
the Google Spread Sheet shared at the earliest. In case response is not updated it
will be taken from SRLDC SCADA and analysis will be presented in 181st OCC
meeting.
9. Automatic Demand Side Management Scheme (Petition No. 250/MP/2012) &
GSES (Petition No. 265/MP/2012)
(a) It was noted that all states had implemented revised ADMS logic. (Alarm at
49.90 Hz and below for 10 minutes, Trip at 49.85 Hz, Min DSM limit for 15
Minutes).
(b) ADMS feeders may also be mapped, for enhanced visualization and analysis of
ADMS operation. All states were requested to identify additional feeders which
could be tripped through SCADA rotationally with load relief of (OD-Max dev
limit). Any loads tripped under ADMS should be brought back only under the
directions of SLDC keeping in view the frequency, overdrawal etc.
(c) It was noted that the States could support the ADMS relief (feeder tripping)
through SoE. Incidence can be validated accordingly.
(d) SRLDC vide E-mail dated 06.06.2021 had submitted the ADMS instances during
the month of June 2021(Annexure-9.d)
Minutes of the 180thmeeting of OCC (09.07.2021) Page 46 of 54
(e) TN had submitted the details regarding the ADMS incidences in June 2021
(Annexure-9.e)
Deliberation:
(i) SRLDC expressed concern that no states are giving updates on the status of
ADMS incidences. SRLDC suggested that ADMS feeders may be mapped to
SCADA.
(ii) ED, SRLDC desired to know from the states regarding the mapping.
(iii) KPTCL informed that feeders identified are more and individual mapping is
difficult and opined that as group mapping may be done on area basis.
(iv) KSEBL informed that ADMS scheme is covered under Innovative Project
funded through PSDF. Within two to three weeks scheme will be taken over
and commissioned. A separate server will be available for ADMS and
information can be fetched from this server. All the information like initiation
of ADMS tripping signal, list of feeders tripped, quantum of relief etc would
be available in the server. The system will assure the required quantum of
relief also. If at first tripping required quantum of relief was not realized,
system will initiate another sequence of tripping. ADMS feeders are not
mapped to SCADA.
(v) ED, SRLDC suggested that KSEBL may share these details to other states.
He requested all the states (AP, TS and TN) to take an immediate initiative in
this regard so that at least by this month end area-wise monitoring is possible.
(vi) APTRANSCO informed that the analysis had made for the incidences during
the month of May 2021. With respect to incidences during June 2021,
analysis will be carried out and observations would be furnished shortly.
(vii) KPTCL informed that w.r.t KPTCL around 3000 feeders are identified for
ADMS tripping. DISCOM-wise relief may be obtained. If in need feeder wise
mapping also may be carried out.
Conclusion:
(i) AP, TS and TN would explore the possibility of mapping the ADMS feeders
to SCADA and the status may be updated to SRLDC/SRPC within a month.
In case feeder wise mapping is not possible, area wise/DISCOM wise
grouping may be done and monitored.
(ii) TSTRANSCO to furnish the list of feeders identified for ADMS scheme at
the earliest.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 47 of 54
(iii) States are requested to extend the status points to SRLDC whenever ADMS
are acted.
10. Grouping of loads (IEGC clause 5.4.2 (e))
Regulations in respect of Grouping of loads to be complied by all the concerned
utilities.
11. LVRT Implementation / Status review of Pending points as discussed in 4th
RE/LVRT meeting
Quarterly reports of the SR constituents jointly validated by SRLDC/SRPC
Secretariat are being communicated to Hon’ble CERC in this regard to monitor the
installation and performance of LVRT installed on existing WTGs as per the
directives of Hon’ble CERC.
(i) SRPC had again requested the SLDCs to furnish the LVRT status (33 kV &
above) for the WTGs being commissioned w.e.f. 06.08.2019.
(ii) SRPC vide letter dated 26.03.2021had requested TANTRANSCO to arrange
the data in the prescribed format at the earliest.
In the Meeting, it was noted that TANTRANSCO had furnished the information
in the prescribed format.
12. Automatic Generation Control (AGC) Central Sector implementation
(a) As per CERC Order dated 28.08.2019 all ISG stations whose Tariff is
determined or adopted by CERC should be AGC-enabled before 28th February
2020.
(b) In the9th Meeting of NPC, RPCs were requested to furnish the status update of
the implementation status on monthly basis.
(c) Status update as on 30.06.2021 is as below:
Entity Generator Status
NTPC Simhadri STPS Stage- II (2 x
500 MW)
AGC implemented (18.11.2018)
Ramagundam STPS Stage-
II (4x500 MW)
Commissioned on 31.03.2021.
Simhadri STPS Stage- I (2 x
500)
Both the units had been tested. Units are
ready to put under AGC.
Ramagundam STPS Stage-I
(3x200 MW)
AGC implementation works would be
taken after the maintenance/ renovation
works.
Talcher STPS ( 4 x 500)
NTECL Vallur TPS (3 x 500 MW) NLDC had carried out testing. AGC would
be put in service after getting clearance
Minutes of the 180thmeeting of OCC (09.07.2021) Page 48 of 54
from NLDC
NLCIL TPS II (7 x 210 MW) Works under progress (M/s ABB)
TPS I Expn ( 2
x 210 MW) The works would be taken up after
implementation of AGC at TPS-II TPS II Expn ( 2 x 250 MW)
NNTPS (2 x 500 MW)
NTPL NTPL (2 x 500 MW) The work in progress and expected to
complete shortly
NP-
Kunta
Solar in AP
AGC :5 blocks of 50 MW
i.e. 5 x 50 = 250 MW
Placing of order by Delloitte (consultant of
USAID) is in progress.
In the Meeting the following were noted:
(a) NTPC, Simhadri informed that Simgadri STPS Stage-I units are kept in
service from evening 4 to 7 hours as advised by NLDC(since last one
week). The observations will be sent to NLDC from Corporate office.
(b) NLCIL TPS II Stage II: Erection of ABB panelis over. Commissioning
under progress.
(c) NLC TS I Expn.: Panel Erection is over. For commissioning works ABB
will be reaching the site by this month end.
(d) NTPL informed that AGC at NTPL is in operation from 14.06.2021.
Performance is observed to be satisfactory.
The status update on implementation of AGC needed to be furnished regularly.
13. AGC at state Level- Pilot Project identification & Implementation
Status update is as follows:
State Generator Status Andhra
Pradesh
Krishnapatnam (2 x 800 MW) Discussions are going with
APGENCO along with SRLDC.
A meeting though VC was
requested by them to take
guidance and technical support for
implementing the AGC.
In addition to Krishnapatnam planning AGC at VTPS, RyTPP, Upper
Sileru& Lower Sileru. Approached APERC with the proposal. Concurrence
from APERC awaited.
Karnataka Sharavathy Generating Station (1035
MW)
Implementation of AGC Pilot
under USAID GTG Scheme
completed. Available MW for
AGC is 10 % of Live load up to
maximum of 100MW (10% 0f
Minutes of the 180thmeeting of OCC (09.07.2021) Page 49 of 54
1035 MW).
Varahi Under Ground Power House(4 x
115 MW)
Hardware & software deployment
and configuration completed (Nov
2020)Go-live pilot completed (Jan
2021).Available MW for AGC is
20% of live load uptomaximum of
80 MW as per the programme
planned.
Kerala Kuttiady Unit No. 5 (50MW) Operational
State Regulator has been
appoached for putting AGC on
regular basis
Idukki Unit No.1 (130MW) AGC would be implemented once
the Optical Fibre link from SLDC
to Idukki PH is established
Tamil Nadu North Chennai TPS Stage-II ( one unit
i.e. 1 x 600 MW) Software part is completed.
Hardware part (connection
from Control Room to
switchyard is pending. Works
would be completed within
three months.
MTPS - II (1 x 600 MW) Software part completed. Intend
submitted for approvalfor
DPR.Willcompletewithin4-
5months.
Telangana KTPS- VI (500 MW)
Kothagudem E (132 MW) downward)
Placed the PO. Material delivery
expected by 06.05.2021.
The status update on implementation of AGCneeded to be furnished
regularly.
(i) In the 179th meeting of OCC APSLDC had requested SRLDC to arrange a special
meeting through VC in presence of SDSTPS at the earliest to facilitate the
implementation of AGC pilot project with the support of POSOCO.
(ii) SRLDC had conducted a workshop regarding the "Automatic Generation Control
(AGC)" on 06.07.2021.
Delineation:
(a) APSLDC informed that the works at Krishnapatanam would be initiated
shortly.
(b) KPTCL informed that both at Sharavathi & Varahi testing is over. In
coordination with KPCL the units would be put under AGC operation.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 50 of 54
(c) KSEBL & TANTRANSCO informed that the status is the same.
(d) TSTRANSCO informed that supplier had informed that material will reach
the site within 10 days. Accordingly works would be started.
14. Status of Implementation of the revised FGD Installation / ESP Up-gradation
Plan
(i) CEA/MoP is seeking updated information in respect of implementation of
revised FGD installation/ESP Up-gradation Plan and the regular updated may
kindly be furnished.
(ii) TANGEDCO had submitted the update (Annexure-14).
All the concerned to comply with norms, as per CPCB timelines and changes
thereof since the activity is monitored by Hon’ble Supreme Court / Government.
15. PSP- daily Demand and Consumption pattern
CEA had sought daily Demand and Consumption pattern and the reasons for
significant variations w.r.t last year and past few days. The format in this regard has
been communicated to States and SRLDC by mail dated 21.04.2020 by SRPC.
All the states were requested to furnish the information on regular basis.
16. Category-wise Consumption Pattern
CEA vide E-mail dated 17.03.2020 had sought category-wise consumption of
electricity in the States/UTs. RPCs had been requested to discuss/collect the data
in OCC meetings on a regular basis in the prescribed format.
The status of data furnished is as below:
APTRANSCO April 2021
TSTRANSCO May 2021
KPTCL March 2021
KSEBL April 2021
TANTRANSCO April 2021
Puducherry March 2021
All the states were requested to furnish the information on regular basis.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 51 of 54
17. Emergency Restoration System (ERS)
Transmission
Utility
Requirement
as per MoP
Existing Status/Remarks as noted in
179th OCC
APTRANSCO 3 2 APTRANSCO informed that *
* against the suggested quantity of 3 sets of ERS in the state by MoP, 2 sets of
ERS infra structure consisting of 20 Nos towers were procured by AP and
placed at three different locations, 3 nos in Srikakulam, 7 nos in
Visakhapatanam and 10 Nos in Nellore coastal districts to meet the exigencies
in case of natural calamities for restoration in the existing transmission
network. No other ERS System is under procurement.
KPTCL 2 2
KSEBL 1 0 KSEBL had informed that #
# because of ROW issues ERS may not be useful in Kerala which was the
opinion arrived in the pre-bid meeting. A communication from Transmission
wing would be arranged to SRPC in this regard.
TANTRANSCO 2 0 TANTRANSCO informed that $
$ supply of materials expected by February 2022 (delayed due to COVID-19
pandemic)
TSTRANSCO 1 0 TSTRANSCO informed that
tender opened on 08.06.2021
and evaluation is under
progress.
PED Nil Nil
PGCIL 4 4 SR-I & SR- II Two Nos. Each
In the Meeting, SE(O) SRPC requested KSEBL a communication from transmission
wing of KSEBL regarding their views as agreed in the 179th OCC meeting.
CE (TSO), KSEBL informed that he had taken up this issue with transmission wing
and a communication in this rgard would be arranged shortly.
TANTRANSCO informed that the status remains the same.
TSTRANSCO informed that tender had been opened and evaluation is under progress.
All the states were requested to furnish the updates on monthly basis. The same
would be put up to TCC/SRPC forum.
Minutes of the 180thmeeting of OCC (09.07.2021) Page 52 of 54
18. REMC Project under SR SLDCs
The following were noted in the 179th OCC Meeting:
a) TSTRANSCO informed that all the panels TSTRANSCO informed that all the
panels are integrated and evaluation is going on.
b) APTRANSCO had informed that higher level discussions (CMD level) were
going on regarding the NOC issue. Outcome would be intimated accordingly.
Deemed taking over clause also being explored.
In the Meeting the following were noted:
(i) TSTRANSCO informed that some missing/discrepancies are observed
during FAT which is being sorted out which will be over within two weeks.
By third week SAT will be started. Due to COVID-19 restrictions, less
officials are on the job.
(ii) APTRANSCO informed that separate account opening is under process
exclusively for REMC payment. Within two three days payment can be
done.
19. Compliance of CEA Regulations for Grid connectivity of RE Sources
The updated status on RE SCADA availability as noted in the 178thMeetingof OCC
is at Annexure-19
All the states are requested to update the status to SRPC on monthly basis.
20. Black Start Procedure
a) Point to point mock exercise for black start to be carried out by all constituents.
b) Mock drills conducted in June 2021 are to be furnished.
c) Mock drills scheduled for July 2021& January 2021 to June 2021 were to be
furnished.
In the Meeting SRLDC informed that they had shared a Google Sheet to fill the
details regarding the schedule for Mock Drills. Entities may update in the same.
(i) The first half Status: AP- 3 out of 3, TS: 02out of 2, KAR: 4 out of 6, TN: 4
out of 14, KER: 1 out of 6. Total SR out of 30 stations 14 stations only are
conducted the mock drills.
(ii) Mock drill schedule dates for Second half 2021 (Jul21-Dec21):
Received from AP & TS
Yet to receive from KA, TN & KL
Minutes of the 180thmeeting of OCC (09.07.2021) Page 53 of 54
21. Items for Information:
(i) CEA has brought out a document on “Standard Technical Specification of
Power Transformers for Solar Park Pooling Station (available at CEA website).
This document will certainly help in the proper design and standardization of
specification of transformers in Solar generation pooling station leading to
quality and reliability, faster delivery and the uniform practice across the utilities
in the country. This document may be used by all the concerned stake holders to
make the vision of ‘One Nation, One Specification’ a reality.
(ii) MOP vide Order dated 21.06.2021 ( available at MoP website) has amended the
Order on Waiver of inter-state transmission charges on transmission of the
electricity generated from solar and wind sources of energy dated 15.01.2021
regarding waiver of Inter-State Transmission system (ISTS) charges on
transmission of electricity generated from solar and wind sources projects.
(iii) MoP: Testing power system equipment for use in the Supply System and
Network in the country for Cyber Security: MoP vide Order dated
08.06.2021(Annexure-21.iii) has communicated that Central Power Research
Institute (CPRI) is hereby notified as the nodal agency for testing power system
equipment for use in the Supply System and Network in the country for Cyber
Security. The designated laboratories and the products for which cyber security
conformance testing is to be undertaken on payment of applicable test charges
are furnished. The protocols to be followed for testing the products for cyber
security conformance testing, testing criteria and details of type tests are also
furnished.
22. Grid Highlights June 2021
a) Black-start exercise of HVDC Pugalur-Thrissur pole-1 was successfully carried
out on 12th June 2021 (Report by SRLDC at Annexure-22.a).
b) Karnataka BSR Procedure review meeting conducted on 30.06.2021.
c) Wind capacity of 1.5 MW (2x7.5) - STU- was added to TANTRANSCO system
on 05.06.2021(at 33 kV level, LVRT Compliant).
d) Solar capacity of 12 MW (2x6) –CTU-M/s. Vivid Solaire Energy Pvt Ltd. was
added to TANTRANSCO system on 09.06.2021(at 33 kV level, LVRT
Compliant).
e) Solar capacity of 39 MW (3x13) –CTU-M/s. SPRNG Renewable Energy Pvt Ltd
- was added to TANTRANSCO system on 29 .06.2021(at 33 kV level, LVRT
Compliant).
Minutes of the 180thmeeting of OCC (09.07.2021) Page 54 of 54
23. Conclusion:
Member Secretary, SRPC thanked all the officials participated in the deliberation. He
requested all the members to comply with the decisions/recommendations arrived in
the Meeting.
24. 181st Meeting of OCC
The 181stMeeting of OCC is scheduled on 10thAugust 2021 (Tuesday) through
Video Conferencing (VC).
****