wspe seminar 1 may 15, 2009 wadot

48
WSDOT Major Road Projects Larry Kyle, P.E. Program Engineering Manager SR 520 Program 1 Ron Paananen, P.E. Deputy Administrator Urban Corridors Office WSPE Annual Meeting & Conference May 15, 2009

Upload: wspe

Post on 18-Nov-2014

1.418 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: WSPE Seminar 1 May 15, 2009 WADOT

WSDOT 

Major Road Projects

Larry Kyle, P.E.Program Engineering Manager

SR 520 Program

1

Ron Paananen, P.E.Deputy AdministratorUrban Corridors Office

WSPE Annual Meeting & ConferenceMay 15, 2009

Page 2: WSPE Seminar 1 May 15, 2009 WADOT

2

Presentation Agenda

• SR 520 – focus project

• Other projects updates:

• Alaskan Way Viaduct

• I‐405 Segments

• I‐90 Snoqualmie Pass

• Columbia River Crossing

• I – 395, North Spokane Corridor

• Lake Washington Congestion Management

Page 3: WSPE Seminar 1 May 15, 2009 WADOT

3

2009 Legislative Actions - WSDOT

• Tunneling Alaskan Way Viaduct

• Tolling SR 520

Page 4: WSPE Seminar 1 May 15, 2009 WADOT

SR 520 Bridge Replacement and HOV Program

4

Page 5: WSPE Seminar 1 May 15, 2009 WADOT

SR 520 Program Description 

5

Page 6: WSPE Seminar 1 May 15, 2009 WADOT

6

SR 520 Delivery Options

Page 7: WSPE Seminar 1 May 15, 2009 WADOT

77

Alternative A

Page 8: WSPE Seminar 1 May 15, 2009 WADOT

88

Alternative L

Page 9: WSPE Seminar 1 May 15, 2009 WADOT

9

SR 520 Fly‐through Visuals

Option K & Eastside Project 

Page 10: WSPE Seminar 1 May 15, 2009 WADOT

SR 520 Program Schedule

10

Page 11: WSPE Seminar 1 May 15, 2009 WADOT

SR 520 Pontoon Construction Project

11

Page 12: WSPE Seminar 1 May 15, 2009 WADOT

Why is the Pontoon Project needed now?

• Constructing and storing pontoons are key elements in catastrophic failure planning. 

• If the floating bridge failed, available detour routes would be overwhelmed with rerouted traffic.

• Recovering the bridge after a catastrophic failure will require new pontoons. We estimate it would take approximately three years to construct enough pontoons to restore the SR 520 bridge.

Existing SR 520 pontoon

12

Page 13: WSPE Seminar 1 May 15, 2009 WADOT

• Support accelerated schedule, reduce risk, and minimize costs

• Field test for pontoons, i.e., form systems, concrete mixes, full‐scale mockups of pontoon sections

• Advertise in Summer 2009‐‐Posted on WSDOT Contract Ad and Award Web site

• Located in Grays Harbor

Advanced Construction Methods and Engineering

Page 14: WSPE Seminar 1 May 15, 2009 WADOT

Use existing facility at Concrete Technology Corporation

• Expedite pontoon construction to stay on schedule

• Does not have capacity to build all the pontoons

• Construction of pontoons to begin in 2010 

Page 15: WSPE Seminar 1 May 15, 2009 WADOT

Two Sites in Grays Harbor

15

Page 16: WSPE Seminar 1 May 15, 2009 WADOT

• Prepare site– Excavate a basin, drive piles,

pour concrete slab.– Stabilize sides of basin with

concrete walls; seal off from open water with a gate.

– Construct support facilities.• Construct pontoons

– Assemble forms around steel frame.

– Pour concrete into forms to create pontoon.

• Launch pontoons– Fill basin with water.– Open gate and use tugboat to

tow pontoon to moorage location.

– Drain basin and repeat process for other pontoons.

How are pontoons built?

Page 17: WSPE Seminar 1 May 15, 2009 WADOT

Typical Site‐casting Basin

17

Page 18: WSPE Seminar 1 May 15, 2009 WADOT

Pontoon Construction Project schedule

18

Page 19: WSPE Seminar 1 May 15, 2009 WADOT

For more information visit the project website at:www.wsdot.wa.gov/projects/SR520Bridge

19

Page 20: WSPE Seminar 1 May 15, 2009 WADOT

20

Page 21: WSPE Seminar 1 May 15, 2009 WADOT

Bored Tunnel Hybrid Alternative

21

Page 22: WSPE Seminar 1 May 15, 2009 WADOT

22

Alaska Way Viaduct Fly‐through Visuals

Page 23: WSPE Seminar 1 May 15, 2009 WADOT

23

Page 24: WSPE Seminar 1 May 15, 2009 WADOT

Program Timeline2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

Replace the viaduct between S. Holgate and S. King streets

Relocate electrical lines between S. Massachusetts Street and Railroad Way S.

Implement Moving Forward transit enhancements and other improvements

Mercer Street construction from I-5 to Dexter Avenue

Bored tunnel construction

Alaskan Way and waterfront promenade construction

S. Spokane Street Viaduct Project construction

*Seawall construction will take two years, but will be done seasonally based on environmental and other factors

Mercer West from Dexter to Elliott avenues

Transit service enhancements

Transit capital

Seawall construction*24

Page 25: WSPE Seminar 1 May 15, 2009 WADOT

I-405

25

Page 26: WSPE Seminar 1 May 15, 2009 WADOT

Regional ConsensusEIS Record of Decision, 2002

Roadways2 new lanes in each directionLocal arterial improvements

Transit & Transportation ChoicesBus Rapid Transit systemPotential managed lanes system9 new transit centers added50% transit service increase 

HOV direct access ramps and flyer stops5000 new Park & Ride spaces1700 new vanpools

Environmental Enhancements

I‐405 Master Plan:

26

Page 27: WSPE Seminar 1 May 15, 2009 WADOT

I‐405 Funded Projects2008 Budget (08 Leg Fin) Dollars in Millions

SR 520 to SR 527NB 195th St. to SR 527 .....................................................38.74Kirkland Nickel Stage 2 ....................................................104.56NE 124th St. to SR 522 ....................................................173.92NE 132nd St. Bridge ..........................................................27.75

NE 132nd St. Interchange Ramps .............................................................48.50

Kirkland Nickel Stage 1 ..............................................................................81.64

NE 8th St. to SR 520 Braided Ramps ......................................................255.30

NE 10th St. Bridge Crossing ......................................................................63.82

112th Ave. SE to SE 8th St.Bellevue Nickel Project ......................................................179.60112th Ave. SE to I‐90 ...........................................................19.96

NE 44th St. to 112th Ave. SE......................................................................150 

Springbrook Creek Wetland Mitigation......................................................16.39 

I‐5 to SR 169 Stage 1 WideningRenton Nickel Project .........................................................126.41I‐5 to SR 181 ........................................................................19.78SR 167 SB: I‐405 to SE 180th St. ........................................17.38

I‐5 to SR 169 Stage 2 Widening and SR 515 InterchangeRenton Nickel Stage 2 ..........................................................55.46SR 515 Interchange .............................................................113.36NB SR 167 to SR 169 ..............................................................6.77

Thunder Hills Creek Emergency Culvert Replacement.....................................................................................................8.49

I‐405 Corridor Total State Investment ..............................$1507.83

27

Page 28: WSPE Seminar 1 May 15, 2009 WADOT

Bellevue Braided RampsNE 8th to SR 520 Improvement Project 

• Builds new structures to separate NB traffic exiting to SR 520 from traffic entering  I‐405 at NE 8th Street in Bellevue

• Builds a new on‐ramp at NE 10th Street to SR 520

• Scheduled ad date Jan 2010

UPCOMING

28

Page 29: WSPE Seminar 1 May 15, 2009 WADOT

Braided Ramps Configuration

Page 30: WSPE Seminar 1 May 15, 2009 WADOT

Renton Stage 1 – WideningI‐5 to SR 169

• One new north and southbound general purpose lane from I‐5 to SR 167 

• One new southbound auxiliary lane on SR 167 

• Lengthen southbound HOV lane on SR 167

• Scheduled completion 2010

CONSTRUCTION

$91.5 M

Page 31: WSPE Seminar 1 May 15, 2009 WADOT

Renton Stage 2 & SR 515 Interchange

• One new north and southbound lane from SR 167 to SR 169

• Creating new half‐diamond interchange at SR 515

• Bids to be opened 2/4/09

UPCOMING

Page 32: WSPE Seminar 1 May 15, 2009 WADOT

I-90 Snoqualmie Pass EastProject Update

32

Page 33: WSPE Seminar 1 May 15, 2009 WADOT

$595 million$595 million

Spring 2009Spring 2009

33

Page 34: WSPE Seminar 1 May 15, 2009 WADOT

I-90 along Keechelus Lake 34

Page 35: WSPE Seminar 1 May 15, 2009 WADOT

Rockfall on I-90

Wildlife / vehicle collision

Sharp CurvesCongestion on a holiday weekend

Deteriorated Pavement

Avalanche over east Snowshed

35

Page 36: WSPE Seminar 1 May 15, 2009 WADOT

• Draft Environmental Impact Statement issued in 2005

• Preferred Alternative identified June 2006

• Final Environmental Impact Statement issued August 2008

• FHWA signed Record of Decision in October 2008

• Construction begins June 2009

36

Page 37: WSPE Seminar 1 May 15, 2009 WADOT

• Add a lane in each direction

• Rebuild three new bridges and one culvert

• Address unstable rock slopes

• Extend chain up / off areas

Construction begins: 2010

• Add a lane in each direction

• Replace all existing concrete pavement

• Replace existing 500 ft. snowshed with a 1,100 ft.structure

• Rebuild two bridges and one culvert

• Address unstable rock slopes

• Extend chain up / off areas

Construction begins: 2011

• Build long-term detour bridge at Gold Creek

• Replace lake storage impacts in Keechelus Lake

Construction begins: 2009

Page 38: WSPE Seminar 1 May 15, 2009 WADOT
Page 39: WSPE Seminar 1 May 15, 2009 WADOT

Columbia River Crossing

39

Page 40: WSPE Seminar 1 May 15, 2009 WADOT

I‐5 Columbia River Crossing

A bridge, transit, and highway project aimed at improving travel efficiency and safety on Interstate 5

Vancouver WA Portland OR

5-mile project area in red

Columbia River

40

Page 41: WSPE Seminar 1 May 15, 2009 WADOT

• CongestionTravel demand exceeds capacity

• Freight Mobility through the area is impaired

• Public transit Service is limited by congestion

• SafetyCrash rates are too high

• Bicyclists and pedestrians Facilities and connections are inadequate

• Earthquake safetyBridges don’t meet current seismic standards

Project Purpose and Need

Draft EIS document

41

Page 42: WSPE Seminar 1 May 15, 2009 WADOT

Project Elements

• Replacement bridge for Interstate 5 across the Columbia River

• Light rail extension from Expo Center in north Portland to Clark College in Vancouver

• Improvements to seven closely‐spaced highway interchanges

• Wider path for bicyclists and pedestrians

• Electronic tolling

42

Page 43: WSPE Seminar 1 May 15, 2009 WADOT

Schedule

43

Page 44: WSPE Seminar 1 May 15, 2009 WADOT
Page 45: WSPE Seminar 1 May 15, 2009 WADOT

NSC Nickel Project OverviewNSC Nickel Project Overview

Construct 8 contracts:Construct 8 contracts:• Drivable link between Francis

and Wandermere.• Estimated total cost was ~$190

million. Cost Range in projects is $10 million to $45 million

• Open to traffic 2009, 2011

Page 46: WSPE Seminar 1 May 15, 2009 WADOT

NSC ConstructionNSC Construction

Page 47: WSPE Seminar 1 May 15, 2009 WADOT

Lake Washington Congestion Management

47

Page 48: WSPE Seminar 1 May 15, 2009 WADOT

48

Lake Washington Urban Partnership

Designed to reduce congestion through

the “Four T’s”:

· Transit · Technology

· Telecommuting · Tolling

Awarded $154.5 million to assist

WSDOT, Puget Sound Regional

Council and King County in applying

these innovative approaches to reduce

congestion in the 520 corridor in

Western Washington.

Funded by:

LAKE WASHINGTON URBAN PARTNERSHIP

Artist’s rendering of what electronic tolling might look like on the existing SR 520 Bridge