wspe seminar 1 may 15, 2009 wadot
DESCRIPTION
TRANSCRIPT
WSDOT
Major Road Projects
Larry Kyle, P.E.Program Engineering Manager
SR 520 Program
1
Ron Paananen, P.E.Deputy AdministratorUrban Corridors Office
WSPE Annual Meeting & ConferenceMay 15, 2009
2
Presentation Agenda
• SR 520 – focus project
• Other projects updates:
• Alaskan Way Viaduct
• I‐405 Segments
• I‐90 Snoqualmie Pass
• Columbia River Crossing
• I – 395, North Spokane Corridor
• Lake Washington Congestion Management
3
2009 Legislative Actions - WSDOT
• Tunneling Alaskan Way Viaduct
• Tolling SR 520
SR 520 Bridge Replacement and HOV Program
4
SR 520 Program Description
5
6
SR 520 Delivery Options
77
Alternative A
88
Alternative L
9
SR 520 Fly‐through Visuals
Option K & Eastside Project
SR 520 Program Schedule
10
SR 520 Pontoon Construction Project
11
Why is the Pontoon Project needed now?
• Constructing and storing pontoons are key elements in catastrophic failure planning.
• If the floating bridge failed, available detour routes would be overwhelmed with rerouted traffic.
• Recovering the bridge after a catastrophic failure will require new pontoons. We estimate it would take approximately three years to construct enough pontoons to restore the SR 520 bridge.
Existing SR 520 pontoon
12
• Support accelerated schedule, reduce risk, and minimize costs
• Field test for pontoons, i.e., form systems, concrete mixes, full‐scale mockups of pontoon sections
• Advertise in Summer 2009‐‐Posted on WSDOT Contract Ad and Award Web site
• Located in Grays Harbor
Advanced Construction Methods and Engineering
Use existing facility at Concrete Technology Corporation
• Expedite pontoon construction to stay on schedule
• Does not have capacity to build all the pontoons
• Construction of pontoons to begin in 2010
Two Sites in Grays Harbor
15
• Prepare site– Excavate a basin, drive piles,
pour concrete slab.– Stabilize sides of basin with
concrete walls; seal off from open water with a gate.
– Construct support facilities.• Construct pontoons
– Assemble forms around steel frame.
– Pour concrete into forms to create pontoon.
• Launch pontoons– Fill basin with water.– Open gate and use tugboat to
tow pontoon to moorage location.
– Drain basin and repeat process for other pontoons.
How are pontoons built?
Typical Site‐casting Basin
17
Pontoon Construction Project schedule
18
For more information visit the project website at:www.wsdot.wa.gov/projects/SR520Bridge
19
20
Bored Tunnel Hybrid Alternative
21
22
Alaska Way Viaduct Fly‐through Visuals
23
Program Timeline2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Replace the viaduct between S. Holgate and S. King streets
Relocate electrical lines between S. Massachusetts Street and Railroad Way S.
Implement Moving Forward transit enhancements and other improvements
Mercer Street construction from I-5 to Dexter Avenue
Bored tunnel construction
Alaskan Way and waterfront promenade construction
S. Spokane Street Viaduct Project construction
*Seawall construction will take two years, but will be done seasonally based on environmental and other factors
Mercer West from Dexter to Elliott avenues
Transit service enhancements
Transit capital
Seawall construction*24
I-405
25
Regional ConsensusEIS Record of Decision, 2002
Roadways2 new lanes in each directionLocal arterial improvements
Transit & Transportation ChoicesBus Rapid Transit systemPotential managed lanes system9 new transit centers added50% transit service increase
HOV direct access ramps and flyer stops5000 new Park & Ride spaces1700 new vanpools
Environmental Enhancements
I‐405 Master Plan:
26
I‐405 Funded Projects2008 Budget (08 Leg Fin) Dollars in Millions
SR 520 to SR 527NB 195th St. to SR 527 .....................................................38.74Kirkland Nickel Stage 2 ....................................................104.56NE 124th St. to SR 522 ....................................................173.92NE 132nd St. Bridge ..........................................................27.75
NE 132nd St. Interchange Ramps .............................................................48.50
Kirkland Nickel Stage 1 ..............................................................................81.64
NE 8th St. to SR 520 Braided Ramps ......................................................255.30
NE 10th St. Bridge Crossing ......................................................................63.82
112th Ave. SE to SE 8th St.Bellevue Nickel Project ......................................................179.60112th Ave. SE to I‐90 ...........................................................19.96
NE 44th St. to 112th Ave. SE......................................................................150
Springbrook Creek Wetland Mitigation......................................................16.39
I‐5 to SR 169 Stage 1 WideningRenton Nickel Project .........................................................126.41I‐5 to SR 181 ........................................................................19.78SR 167 SB: I‐405 to SE 180th St. ........................................17.38
I‐5 to SR 169 Stage 2 Widening and SR 515 InterchangeRenton Nickel Stage 2 ..........................................................55.46SR 515 Interchange .............................................................113.36NB SR 167 to SR 169 ..............................................................6.77
Thunder Hills Creek Emergency Culvert Replacement.....................................................................................................8.49
I‐405 Corridor Total State Investment ..............................$1507.83
27
Bellevue Braided RampsNE 8th to SR 520 Improvement Project
• Builds new structures to separate NB traffic exiting to SR 520 from traffic entering I‐405 at NE 8th Street in Bellevue
• Builds a new on‐ramp at NE 10th Street to SR 520
• Scheduled ad date Jan 2010
UPCOMING
28
Braided Ramps Configuration
Renton Stage 1 – WideningI‐5 to SR 169
• One new north and southbound general purpose lane from I‐5 to SR 167
• One new southbound auxiliary lane on SR 167
• Lengthen southbound HOV lane on SR 167
• Scheduled completion 2010
CONSTRUCTION
$91.5 M
Renton Stage 2 & SR 515 Interchange
• One new north and southbound lane from SR 167 to SR 169
• Creating new half‐diamond interchange at SR 515
• Bids to be opened 2/4/09
UPCOMING
I-90 Snoqualmie Pass EastProject Update
32
$595 million$595 million
Spring 2009Spring 2009
33
I-90 along Keechelus Lake 34
Rockfall on I-90
Wildlife / vehicle collision
Sharp CurvesCongestion on a holiday weekend
Deteriorated Pavement
Avalanche over east Snowshed
35
• Draft Environmental Impact Statement issued in 2005
• Preferred Alternative identified June 2006
• Final Environmental Impact Statement issued August 2008
• FHWA signed Record of Decision in October 2008
• Construction begins June 2009
36
• Add a lane in each direction
• Rebuild three new bridges and one culvert
• Address unstable rock slopes
• Extend chain up / off areas
Construction begins: 2010
• Add a lane in each direction
• Replace all existing concrete pavement
• Replace existing 500 ft. snowshed with a 1,100 ft.structure
• Rebuild two bridges and one culvert
• Address unstable rock slopes
• Extend chain up / off areas
Construction begins: 2011
• Build long-term detour bridge at Gold Creek
• Replace lake storage impacts in Keechelus Lake
Construction begins: 2009
Columbia River Crossing
39
I‐5 Columbia River Crossing
A bridge, transit, and highway project aimed at improving travel efficiency and safety on Interstate 5
Vancouver WA Portland OR
5-mile project area in red
Columbia River
40
• CongestionTravel demand exceeds capacity
• Freight Mobility through the area is impaired
• Public transit Service is limited by congestion
• SafetyCrash rates are too high
• Bicyclists and pedestrians Facilities and connections are inadequate
• Earthquake safetyBridges don’t meet current seismic standards
Project Purpose and Need
Draft EIS document
41
Project Elements
• Replacement bridge for Interstate 5 across the Columbia River
• Light rail extension from Expo Center in north Portland to Clark College in Vancouver
• Improvements to seven closely‐spaced highway interchanges
• Wider path for bicyclists and pedestrians
• Electronic tolling
42
Schedule
43
NSC Nickel Project OverviewNSC Nickel Project Overview
Construct 8 contracts:Construct 8 contracts:• Drivable link between Francis
and Wandermere.• Estimated total cost was ~$190
million. Cost Range in projects is $10 million to $45 million
• Open to traffic 2009, 2011
NSC ConstructionNSC Construction
Lake Washington Congestion Management
47
48
Lake Washington Urban Partnership
Designed to reduce congestion through
the “Four T’s”:
· Transit · Technology
· Telecommuting · Tolling
Awarded $154.5 million to assist
WSDOT, Puget Sound Regional
Council and King County in applying
these innovative approaches to reduce
congestion in the 520 corridor in
Western Washington.
Funded by:
LAKE WASHINGTON URBAN PARTNERSHIP
Artist’s rendering of what electronic tolling might look like on the existing SR 520 Bridge