Southwestern Public Service Co. (SPS)

Transmission Customer Meeting May 9, 2019

Page 2: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

DISCUSSION TOPICS FOR TODAY

• Xcel Energy & SPS System Overviews

• Completed 2018 Projects

• 2019 and Future Projects

• SPP Model Building Discussion

• DISIS Overview

• NERC Standards Efficiency Review

• Questions and Adjourn 2

Page 3: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

SYSTEM MAPS

Xcel Energy SPS

Northern States Power Co. Minnesota

(NSPM)

Northern States Power

Co. Wisconsin (NSPW)

Public Service Co. of

Colorado (PSCo)

Southwestern Public Service

Co. (SPS)

3

Page 4: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

2018-2019

TRANSMISSION SYSTEM ADDITIONS

Page 5: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Atoka to Eagle Creek 115kV

(New)

5

115kV

19 miles

ISD: 12/2018

NTC: Yes

Page 6: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Cochran Co to Whiteface 69kV

(Rebuild)

6

69kV

25 miles

ISD: 12/2018

NTC: Yes

Page 7: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Custer Mountain to Ochoa 115kV

Custer Mountain to Whitten 115kV

(Rebuild)

7

115kV

15 miles

ISD: 5/2018

NTC: Yes

Page 8: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

NE Hereford to La Plata 115kV

(New)

8

115kV

7 miles

ISD: 4/2018

NTC: Yes

CCN: Yes

Page 9: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Hobbs to Kiowa to North Loving to China Draw 345kV

(New)

Kiowa to Roadrunner 345kV

(Conversion)

9

345kV

88 miles

ISD: 3/2018

NTC: Yes

CCN: Yes

Page 10: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Roosevelt County Substation

(230kV Conversion)

10

230kV

ISD: 6/2018

Page 11: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Portales Loop 115kV

(New)

11

115kV

22 miles

ISD: 7/2018

NTC: Yes

Page 12: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Roswell Loop 115kV

(New)

12

115kV

15 miles

ISD: 1/2018

NTC: Yes

Page 13: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Sierra Distribution Substation

(New)

13

115/69kV

ISD: 12/2018

NTC: Yes

Page 14: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Canyon West to Deaf Smith 115kV

(Rebuild)

14

115kV

27miles

ISD: 11/2018

NTC: Yes

Page 15: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Carpenter 345kV Substation

(New)

15

345kV

ISD: 6/2018

NTC: Yes

Page 16: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

CANCELLED NTC PROJECTS

16

Upgrade Potash Junction 230/115 kV Transformer

oReceived withdraw support from SPP staff

Second 230/115 kV Transformer at Plant

oReceived withdraw support from SPP staff

Pecos 230/115 kV Transformer Upgrade

oIn progress with SPP

Bailey – New Amherst – Lamb 115 kV project

oWithdrawn with SPP BOD approval

Page 17: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

ACTIVE PROJECTS

*Project schedule and scope could be subject to changes.

Page 18: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Artesia Country Club 115kV Substation

(Conversion)

18

115kV

ISD: 12/2019

NTC: Yes

Page 19: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Eddy County Substation

(230kV Conversion)

19

230kV

ISD: 4/2019

NTC: Yes

Page 20: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Ink Basin Substation

(New)

20

230/115kV

ISD: 6/2018

NTC: Yes

Page 21: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Mustang to Shell CO2 115kV

(New)

21

115kV

9 miles

ISD: 5/2019

NTC: Yes

CCN: Yes

Page 22: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

North Loving to Loving South 115kV

(Conversion)

22

115kV

3.5 miles ISD: 12/2019

NTC: Yes

Page 23: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Potash Junction to Livingston Ridge 115kV

(Rebuild)

23

115kV

14 miles

ISD: 3/2019

NTC: Yes

Page 24: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Tuco to Yoakum to Hobbs 345kV

(New)

24

345kV

160 miles

ISD: 6/2020

NTC: Yes

CCN: Yes

Page 25: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

FUTURE PROJECTS

*Project schedule and scope could be subject to changes.

Page 26: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Amarillo Distribution Additions

(New)

26

4 New

Dist.Substations

ISD’s: 2020/21

Page 27: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Mustang to Seminole 115kV

(New)

27

115kV

20 miles

ISD: 6/2020

NTC: Yes

CCN: Yes

Page 28: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Tierra Blanca Substation

(New)

28

115kV

.5 mile

ISD: 10/2021

Page 29: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Tolk Substation

(230kV Conversion)

29

230kV

ISD: 12/2022

Page 30: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Tuco to Indiana 115kV

(Rebuild)

30

115kV 20 miles ISD: 10/2022

Page 31: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Terry Co to Denver City 115kV

(Rebuild)

31

115kV

37 miles

ISD: 11/2022

Page 32: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Cunningham to Monument Tap 115kV

Byrd Tap to Cooper Ranch to Oil Center to lea Road 115kV

(Rebuild)

32

115kV

20 miles

ISD: 4/2021

NTC: Yes

Page 33: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Eddy to Kiowa 345kV

(New)

33

345kV

34 miles

ISD: 11/2020 NTC: Yes

CCN: In Progress

Page 34: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

China Draw to Phantom to Roadrunner 345kV

(New)

34

345kV

40 miles

ISD: 11/2021

NTC: Yes

CCN: Late 2019

Page 35: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

South Loving to Malaga Bend to Phantom 115kV

(New)

35

115kV

21 miles

ISD: 11/2020

Page 36: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

McDowell Creek Substation 230/115kV

(New)

36

230/115kV

ISD: 4/2022

NTC: Yes

Page 37: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

Power for the Plains Website

37

http://www.powerfortheplains.com/

• Project descriptions

• Routing maps, when available

• General project information

Page 38: Xcel Energy - Southwestern Public Service Co. (SPS ......Xcel Energy SPS Northern States Power Co. Minnesota (NSPM) Northern States Power Co. Wisconsin (NSPW) Public Service Co. of

QUESTIONS?