Southwestern Public Service Co. (SPS)
Transmission Customer Meeting May 9, 2019
DISCUSSION TOPICS FOR TODAY
• Xcel Energy & SPS System Overviews
• Completed 2018 Projects
• 2019 and Future Projects
• SPP Model Building Discussion
• DISIS Overview
• NERC Standards Efficiency Review
• Questions and Adjourn 2
SYSTEM MAPS
Xcel Energy SPS
Northern States Power Co. Minnesota
(NSPM)
Northern States Power
Co. Wisconsin (NSPW)
Public Service Co. of
Colorado (PSCo)
Southwestern Public Service
Co. (SPS)
3
2018-2019
TRANSMISSION SYSTEM ADDITIONS
Atoka to Eagle Creek 115kV
(New)
5
115kV
19 miles
ISD: 12/2018
NTC: Yes
Cochran Co to Whiteface 69kV
(Rebuild)
6
69kV
25 miles
ISD: 12/2018
NTC: Yes
Custer Mountain to Ochoa 115kV
Custer Mountain to Whitten 115kV
(Rebuild)
7
115kV
15 miles
ISD: 5/2018
NTC: Yes
NE Hereford to La Plata 115kV
(New)
8
115kV
7 miles
ISD: 4/2018
NTC: Yes
CCN: Yes
Hobbs to Kiowa to North Loving to China Draw 345kV
(New)
Kiowa to Roadrunner 345kV
(Conversion)
9
345kV
88 miles
ISD: 3/2018
NTC: Yes
CCN: Yes
Roosevelt County Substation
(230kV Conversion)
10
230kV
ISD: 6/2018
Portales Loop 115kV
(New)
11
115kV
22 miles
ISD: 7/2018
NTC: Yes
Roswell Loop 115kV
(New)
12
115kV
15 miles
ISD: 1/2018
NTC: Yes
Sierra Distribution Substation
(New)
13
115/69kV
ISD: 12/2018
NTC: Yes
Canyon West to Deaf Smith 115kV
(Rebuild)
14
115kV
27miles
ISD: 11/2018
NTC: Yes
Carpenter 345kV Substation
(New)
15
345kV
ISD: 6/2018
NTC: Yes
CANCELLED NTC PROJECTS
16
Upgrade Potash Junction 230/115 kV Transformer
oReceived withdraw support from SPP staff
Second 230/115 kV Transformer at Plant
oReceived withdraw support from SPP staff
Pecos 230/115 kV Transformer Upgrade
oIn progress with SPP
Bailey – New Amherst – Lamb 115 kV project
oWithdrawn with SPP BOD approval
ACTIVE PROJECTS
*Project schedule and scope could be subject to changes.
Artesia Country Club 115kV Substation
(Conversion)
18
115kV
ISD: 12/2019
NTC: Yes
Eddy County Substation
(230kV Conversion)
19
230kV
ISD: 4/2019
NTC: Yes
Ink Basin Substation
(New)
20
230/115kV
ISD: 6/2018
NTC: Yes
Mustang to Shell CO2 115kV
(New)
21
115kV
9 miles
ISD: 5/2019
NTC: Yes
CCN: Yes
North Loving to Loving South 115kV
(Conversion)
22
115kV
3.5 miles ISD: 12/2019
NTC: Yes
Potash Junction to Livingston Ridge 115kV
(Rebuild)
23
115kV
14 miles
ISD: 3/2019
NTC: Yes
Tuco to Yoakum to Hobbs 345kV
(New)
24
345kV
160 miles
ISD: 6/2020
NTC: Yes
CCN: Yes
FUTURE PROJECTS
*Project schedule and scope could be subject to changes.
Amarillo Distribution Additions
(New)
26
4 New
Dist.Substations
ISD’s: 2020/21
Mustang to Seminole 115kV
(New)
27
115kV
20 miles
ISD: 6/2020
NTC: Yes
CCN: Yes
Tierra Blanca Substation
(New)
28
115kV
.5 mile
ISD: 10/2021
Tolk Substation
(230kV Conversion)
29
230kV
ISD: 12/2022
Tuco to Indiana 115kV
(Rebuild)
30
115kV 20 miles ISD: 10/2022
Terry Co to Denver City 115kV
(Rebuild)
31
115kV
37 miles
ISD: 11/2022
Cunningham to Monument Tap 115kV
Byrd Tap to Cooper Ranch to Oil Center to lea Road 115kV
(Rebuild)
32
115kV
20 miles
ISD: 4/2021
NTC: Yes
Eddy to Kiowa 345kV
(New)
33
345kV
34 miles
ISD: 11/2020 NTC: Yes
CCN: In Progress
China Draw to Phantom to Roadrunner 345kV
(New)
34
345kV
40 miles
ISD: 11/2021
NTC: Yes
CCN: Late 2019
South Loving to Malaga Bend to Phantom 115kV
(New)
35
115kV
21 miles
ISD: 11/2020
McDowell Creek Substation 230/115kV
(New)
36
230/115kV
ISD: 4/2022
NTC: Yes
Power for the Plains Website
37
http://www.powerfortheplains.com/
• Project descriptions
• Routing maps, when available
• General project information
QUESTIONS?