Southwestern Public Service Co. (SPS)
Transmission Customer Meeting November 16, 2017
![Page 2: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/2.jpg)
DISCUSSION TOPICS FOR TODAY • Xcel Energy & SPS System Overviews • Completed 2016 & 2017 Projects • 2018 and Beyond Projects • SPP’s Integrated Transmission Planning – A
Summary
• Transmission Line Ratings • New Modeling Standards • Dynamic Load Modeling • Questions and Adjourn
2
![Page 3: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/3.jpg)
SYSTEM MAPS
Xcel Energy SPS
Northern States Power Co. Minnesota
(NSPM)
Northern States Power
Co. Wisconsin (NSPW)
Public Service Co. of
Colorado (PSCo)
Southwestern Public Service
Co. (SPS)
3
![Page 4: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/4.jpg)
Area Construction Overview
4
![Page 5: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/5.jpg)
2016-2017 TRANSMISSION SYSTEM ADDITIONS
![Page 6: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/6.jpg)
BOWERS - HOWARD (W-67/Y-62)
6 40 miles, mixed 115/69 kV, completed Jan 2016
![Page 7: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/7.jpg)
OCHILTREE - LIPSCOMB (W-50)
7 20 miles, 115 kV, completed April 2016
![Page 8: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/8.jpg)
WHEELER – COBURN CREEK (W-78)
8 13 miles, 115 kV, completed June 2016
![Page 9: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/9.jpg)
CURRY - BAILEY (W-69)
9 38 miles 115 kV, completed Oct 2016
![Page 10: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/10.jpg)
CARDINAL – SAGE BRUSH (W89)
10 19 miles, 115 kV, completed Dec 2016
![Page 11: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/11.jpg)
PCA-QUAHADA (W76)
11 13 miles, 115 kV, completed Feb 2017
![Page 12: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/12.jpg)
WOOD DRAW – CHINA DRAW (W84)
12 14 miles, 115 kV, completed Jun 2017
![Page 13: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/13.jpg)
CUSTER – PONDEROSA (W81)
13 11 miles, 115 kV, completed Jun 2017
![Page 14: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/14.jpg)
CARLISLE - WOLFFORTH (K-99)
14 13 miles, 230 kV, completed Dec 2017
![Page 15: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/15.jpg)
2016/2017 PROJECT COMPLETION UPDATE
15
Grassland Intg. 230/115 kV Upgrade – ISD Feb 2016 Puckett West Breaker Additions– ISD March 2016 Happy Intg. 115/69 kV Autos Upgrade – ISD April 2016 Deaf Smith Intg. –230/115 kV Transformer Upgrades – ISD May 2016 Potash Junction 230/115 KV Auto Upgrade– ISD April 2016 Roadrunner 115 kV Static Var Controller (SVC) Addition – ISD April 2016 China Draw 115 kV Static Var Controller (SVC) Addition – ISD June 2016 Hitchland 345 kV Line Reactor Relocations – ISD April 2016 Andrews Co. Substation – Add 2 230/115 kV 168 MVA Autos – ISD May 2016 Andrews Co. Sub. – NEF Substation 115 kV line – ISD May 2016 Randall Co – Canyon West Sub 115 kV Reconductor – ISD May 2016 Atoka Sub and Eddy-Seven Rivers 115 kV Line - ISD Sept 2016 Cardinal Substation Project – ISD Oct 2016 Curry County 115 kV Bus Rebuild – ISD Dec 2016 Hobbs Gen – Higg 115 kV Line Tap and tap to Bensing Substation – ISD May 2017 Custer Mountain 115 kV Substation – ISD May 2017 Ponderosa Substation – ISD June 2017
![Page 16: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/16.jpg)
ACTIVE and FUTURE PROJECTS
![Page 17: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/17.jpg)
ROSWELL 115 kV LOOP
17 24 miles, 115 kV, estimated ISD Jan 2018
![Page 18: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/18.jpg)
NE HEREFORD – LA PLATA 115 kV Project
18 8 miles, 115 kV, estimated ISD Jan 2018
![Page 19: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/19.jpg)
PORTALES 115 kV LOOP
19 14 miles, 115kV, Estimated ISD Feb 2018
![Page 20: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/20.jpg)
HOBBS – CHINA DRAW 345 kV PROJECT
20 90 miles, 345 kV, estimated ISD June 2018
![Page 21: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/21.jpg)
CARPENTER – SUNFLOWER HARBINGER 345 kV PROJECT
21
J07
J07
30 mi
Colorado
Texas
Oklahoma
Kansas
345 kV substation, interconnect with Sunflower, estimated ISD June 2018
![Page 22: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/22.jpg)
COCHRAN – WHITEFACE 69 kV (115 kV)
22 4.5 miles, 115 kV const, oper 69 kV, estimated ISD 1st qtr 2019
![Page 23: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/23.jpg)
MUSTANG - SHELL CO2 SUBSTATION
23 9 miles115 kV, estimated ISD Nov 2019
![Page 24: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/24.jpg)
TUCO-YOAKUM-HOBBS 345 kV PROJECT
24 168 miles, 345 kV, estimated ISD Jun 2020
![Page 25: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/25.jpg)
MUSTANG - SEMINOLE 115 kV LINE PROJECT
25
S
S S
S S
S
S
S S S
S
S
S
S
S
S
MUSTANG INTG
S S S S
S
S
S
S
SEMINOLE INTG
S
New
115kV Line (17m
i.) K69
230kV Line 115kV Line 69kV Line
New Line Non Xcel Energy Line
T56
Y99 W
11 Y9 8
T89
W11
W1
3
W1
6
W14
K56
K55
V80 T5
7 Y95
Y99
W33
Mi 0
1 2 3 4 5
K69
17 Miles 115 kV Est ISD 6/2021
![Page 26: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/26.jpg)
BAILEY – NEW AMHERST- LAMB 115 kV PROJECT
26 48 miles, 115 kV, estimated ISD Mar 2022
![Page 27: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/27.jpg)
SE New Mexico Projects Map
27
![Page 28: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/28.jpg)
Power for the Plains Website
28
http://www.powerfortheplains.com/ • Project descriptions • Routing maps, when available • General project information
![Page 29: Southwestern Public Service Co. (SPS ... - Xcel Energy](https://reader033.vdocument.in/reader033/viewer/2022042804/626876edd2d7d150b264f5b3/html5/thumbnails/29.jpg)
QUESTIONS?