04/10/2013 new injection system - concept
DESCRIPTION
LIU-SPS 50 ns Pb ion injection system review. 04/10/2013 New injection system - concept - PowerPoint PPT PresentationTRANSCRIPT
04/10/2013
New injection system - concept
B.Goddard, O.Aberle, B.Balhan, J.Borburgh, E.Carlier, K.Cornelis, L.Ducimetière, L.K.Jensen, T.Kramer,
D.Manglunki, A.Mereghetti, V.Mertens, D.Nisbet, B.Salvant, L.Sermeus, J.Uythoven, F.Velotti
LIU-SPS 50 ns Pb ion injection system review
Motivation
• Strong request from LIU-ION to study improving injection rise time, to 50 ns– For Pb ions only– Keeping existing injection energy for ions (rigidity of 60 Tm)– Not impacting negatively on injection for p+ or other ions– Flat top to allow injection of 4 bunches at 50 ns spacing (i.e. ~160
ns)– “Acceptable” emittance growth (can assume damper) – so 2-98%
rise-time to respect in B field
SPS injection
MKPAC MKP TBSJ
MSI
• LHC p+ injection (26 GeV/c) uses all kickers, at 52.0 kV (225 ns)• CNGS p+ injection (14 GeV/c) uses MKPA/C, at 49.2 kV (< 1000 ns)• Pb82+ ion injection (17 GeV/c per charge)
– used MKPA/C, at 52 kV for Q26 (200 ns)– uses all kickers at ~40 kV for Q20 (225 ns)
• TBSJ is injection dump (use MDSH119 to improve centering)
Present ion injection
• Present “ion” kickers type MKP-S– Were designed to reach 115 ns (with PFLs, never installed…)
• Measured at <150 ns (2-98%) with present PFNs– Need also to use “LHC p+” MKP-L kickers for Q20
• Imposes 225 ns rise-time• Look at split tunes, or back to Q26 for ions, to reach 150 ns
with present layout
• Addition of PFLs to the present MKP-S magnets is possible (already foreseen in BA layout)– Will give 125 ns for sure, maybe 100 ns– No additional tunnel equipment– Kick strength then only sufficient for ≤13 GeV/c depending on
optics
MKP usage for ions(from discussion with Django)
• 2011– Q26 optics, use first three tanks only (MKP-S)– Pushed voltage to 52 kV and tweaked trajectories and orbits to
make a 17 GeV/c be injected in a system which was designed for 13 GeV/c
– Rise time used was 200 ns• The MKP-S measured rise time 2 % - 98 % is 148 ns. See later slide from
2000.
• 2012– Q20 optics – less help from quad in front of MKP– Used the fourth tank (MKP-L) as well, which was not modified 13
years ago– Rise time used, as for LHC protons: 225 ns, due to the slower
MKP-L
Concepts studied
• Rebuild entire injection kicker system• Add thin pulsed septum and rebuild entire
injection kicker system• Add separate new ion kicker and new thin
pulsed septum, for ion injection only• Add PFLs to existing kickers, with new thin
pulsed septum• Do nothing to existing kickers, either with or
without new thin pulsed septum
Option (i)
• Rebuild existing magnets completely– Higher impedance (16.6 -> 25 Ohm)– Much shorter magnets (0.6-0.7 -> 0.28 m)– Many more individual magnets (12 -> 48)– Much longer magnetic length needed (8 -> 12 m)– No aperture for dumping p+ beam– Extremely expensive even if possible
• Discarded: does not look feasible– Many integration issues– Many technical issues– No aperture for dumped beam– Huge cost and investment even if solutions could be found
Option (ii)
• Add thin in-vacuum septum and rebuild existing MKP, with rearrangement of layout– Only need to rebuild a subset of the MKP– Same issues with very short 28 cm magnets– More issues with magnet aperture (vertical gap not enough)– No solution found to dump p+ beam cleanly
• Discarded: does not look feasible– Some integration issues– Some technical issues– Aperture limits in vertical plane– No way to dump p+ beam– Large cost and investment
Option iii: the minimalist
• Don’t change anything and we can probably go down to 150 ns rise time (2 – 98 %)– If we want to have more margin / less tweaked orbits and
trajectories one can install the MSI-V, but might not be strictly necessary
• In this case the installation of an ion injection dump might be nice to keep it ‘clean’
• Without MSI-V Q20 clearly makes things more difficult – try split tunes?
– More work on the MKP-S front cells in the PFN might make it possible to go down to 125 ns rise time
– Would be available for tests after LS1
Option iv: the intermediate
• To go below 125 ns kicker rise time, aiming for 100 ns kicker rise time (2 – 98 %): install a PFL in parallel to the present PFNs on the MKP-S system. – No kicker magnets to be installed in the tunnel– This reduces the maximum voltage on the PFL to 40 kV and the
installation of the MSI-V becomes obligatory– With MSI-V no problems with Q20 optics– The switching between PFN and PFL requires development and
lab tests– Injection dump for ions would be nice, to control losses
Option v: the full monty
• Install the new MKP-I magnets & MSI-V– If all works well this would allow for a rise time of 75 ns (2 – 98
%). But not easy and a lot of work– Adds impedance to the machine – beam dynamics, and risk of
kicker heating– Not sure that impedance shielding is possible with this rise time– New kickers and cables needed in highly radioactive zone
downstream of TIDVG– Ion injection dump again needed, to stay clean
Option v
Layout in SPS
MKP-I
MSI-V
Option v
17 GeV/c/u Pb82+ ionswithout injection bump
Option v
14 GeV p+ (as done today)
Option v
• Could conceivably have a dump block in a new location just upstream QD.121
• Could misalign MBB.12070/90 by -10 mm in H
~1.4 m available
Option v
Dumping of injected ion beam(continue to use TBSJ for p+ as at present)
Dump blockQD.12110 chamberMBB.12070/90 chamber,with 10 mm offset
30 mm
Considerations
• Performance reach is one important aspect• Others are
– Required effort level (resources, cost) vs. benefit– Radiation doses for installation, operation and
maintenance– Technical risk– Compatibility with injection of p+ beams (aperture)– Compatibility with HL-LHC beams (impedance)
TIDVG
LSS1 is a very active area…
MSI-V MKP-I TBS-I
Summary of performance/costs
Option iii) - optimised present Option iv) - intermediate Option v) - full Monty
Description Trims of existing PFNs/timings, +MSI-V? New MSI-V, PFLs on MKP, new dump New MSI-V, new MKI-P, new dump
batch spacing (ns) 150 (125?) 100 75
New MSI-V no/yes yes yes
New MKP-I no no yes
Cost (kCHF) 100/1300 5500 9000
Manpower (MY) 1.0/3.3 13.1 19.4
CommentAvailable before LS2 w/o MSI-V125 ns needs studies
Attainable rise time to demonstrate. Can already work on existing MKP-S Feasibility of shielding?
Radiation impact None/medium medium high
Impedance impact None/low low potentially high
Compatible with Q20 No/yes with MSI-V (Q26 or split tunes)? yes yes
fin