1 general status of commissioning piotr krzysztof skowroński ctf3 collaboration technical meeting...

70
1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Upload: rodney-knight

Post on 17-Jan-2018

217 views

Category:

Documents


0 download

DESCRIPTION

CTF3 base line programme 3 CTF3 – R&D Issues - where fully loaded acceleration recombination x 2 phase-coding bunch length control recombination x 4 bunch compression PETS two-beam acceleration structures 12 GHz structures 30 GHz Deceleration stability

TRANSCRIPT

Page 1: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

1

General Status ofCommissioning

Piotr Krzysztof Skowroński

CTF3 Collaboration Technical Meeting27 January 2009

Page 2: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Commissioning

Proving that machine is technically operational

and the beam is as we want it to be

Outline Status year ago Operations and machine setup Activities in 2008 Current status on optics control

2

Page 3: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

CTF3 base line programme

3

CTF3 – R&D Issues - where

fully loadedacceleration

recombination x 2

phase-coding

bunch lengthcontrol

recombinationx 4

bunchcompression

PETS

two-beamacceleration

structures12 GHz

structures 30 GHz

Decelerationstability

Page 4: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

DLTL1

CRM

CR

TL2CLEX

4

CLIC Test Facility 3

4

TL1 & CRM commissioned fall 2006

Linac: commissioned with beam 2003 - 2004

Delay Loop: commissioned with beam 2005-2006

CR commissioning since 2007TL2 and TBTS commissioning started August 2008

Page 5: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting5

Main Points of 2006

Delay Loop Commissioned 7A after DL 1400 ns pulse length

TL1 and CR injectionCommissioned 3.2A in TL1, 3A in CRM RF injection to CR

0 500 1000 1500 2000 2500

6

4

2

0

t [ns]

I [A

]

1

2

3

Page 6: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

66

Main Points of 2007TL1 and CR

Transfer Line 1 relatively quickly commissioned No major problems with establishing injection to CRLong and painful CR commissioning being finished only now Fast Vertical Instability caused by the deflectors Bad cabling of quadrupoles Wrongly calibrated BPMs Unstable gun Inaccurate model of the ring

current

Vpos

Hpos

Page 7: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

CTF3 Collaboration Meeting7

Main Points of 2007CR results

Besides all the problems We have managed to recombine the train factor 4

OK, almost 4, but the principle was shown to be valid Perform the optics studies

which enabled gradualdebugging and validation of the machine model

Page 8: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Operations

The machine is operated in two modes PETS beam for 30GHz structures tests

From Friday to Monday morningSetup is done by CTF3 teamNight and weekend supervision from CCC by PS operators

Commissioning beamFrom Monday to ThursdayTwo overlapping shifts (voluntary),

From 8AM to 4PM From 2PM to 8PM

8

Page 9: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Machine Setup on one slide

Machine setup is based on quad scans Beam is set-up to the screen on girder 10

Phases of acc-structures up to girder 10 are adjusted to get full loading

Twiss parameters are measured and whole linac is rematched

Phase adjustment for the rest of the structuresEnergy profile is measured at girder 10 and elsewhere is calculated

Another quad scan is made at CTS TL1 and is matched to the CR closed solution at this given

energyIf something changes at given point, we must redo the setup from there

DLTL1

CRM

CRTL2

CLEX

Page 10: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting10

Beam recombination in CR is made with time variable bump

(a)

(b)

CR Injection

2nd deflector

RF deflector fieldlo

injection line

septum

localinner orbits

1st deflector

Page 11: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Long circulating CR beam

Many measurements require long circulating beam in CR Tune Closed orbit correction Closed orbit length measurement

The beam is injected to the ring using RF deflector The klystron timing is adjusted so the RF pulse ends

when the last bunch of the train leaves the deflector Since those are travelling wave cavities with short filling

time the RF is gone before the first beam of the train comes back to the deflector

This way beam makes several hundreds turns before it irradiates too much energy thru synchrotron radiation to be fitted in the acceptance

Page 12: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting12

30 GHz30GHz onlyDL & CR

RUN 1

Today

2008 Schedule

DL, CR, TL2 TBTS

CALIFES

PETS in TBTS

RUN 2

RUN 3Installation:

tail clipper

Installation:TL2, CALIFES, TBTS, new deflectors

Linac only

Linac, Ring area, (CLEX)

Page 13: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting13

2008 program – Run 1

Find and repair the problem with the gunLinac Establish stable & documented working point Stability studies diagnostic consolidation

Delay Loop Beam optics measurements Re-establish recombination

Finish the commissioning of CR Perform set of optics measurements Validate the machine model Tune and b function dependence of vertical

instabilityTest new devices and techniques EuroTeV BPMs Bunch length measurement with RF pickup Transient compensation Dispersion Free Steering and other automatic

algorithms

Page 14: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Unstable gun

Already since the first run of 2007 we observe large beam jitter that originates from the gun instability The current is slightly different from shot to shot Since we operate in the fully loaded mode

phases are adjusted so all the RF energy is transferred to the beam

bunches with different current are accelerated differently It leads to position jitter in the dispersive regions

What makes the setup and measurements very hard!

27 Jan 2009CTF3 Collaboration Meeting14

StableUnstable

Page 15: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Unstable gun (cont.)

Finding the problem was difficult and tedious The system operates on high voltage (130-150kV) and

hence specialized knowledge and equipment is needed for investigations

On top of that the device is constructed by LAL and the designer is retired

It was finally found that the high voltage power converter produces chainsaw-like signal

however according to the manufacturer the device itself was OK

After inspection in-situ one of resistors was found crackedconnecting capacitor bank to the ground

at low voltage the resistance was 0, but when 150kV applied than it was conducting thru arcing

And later another resistor found crackedbetween capacitor bank and the high voltage deck

Since than (end of September 2008) the gun behaves OKHowever, we are not certain that it was the core of the problem and it is going to come back at some point27 Jan 2009CTF3 Collaboration Meeting15

Page 16: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Difficult Run 1

Due to the gun problems, but also many other technical problems like Instable water temperatures for the pulse compression

cavities Controls

TimingVME crates overloaded and hanging up permanently

Vacuum leaks Klystrons often down

the first run was not extremely productiveAnyway me managed to Perform optics measurements and study Linac and TL1

Response MatrixDispersion

Consolidate beam diagnostics in those sections

Page 17: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Bunch length measurements

27 Jan 2009CTF3 Collaboration Meeting17

We have two methods to measure the bunch length Standard way with RF deflector and MTV screen Novel non-destructive RF pickup

For further details see Anna Dabrowski talk at 3PM

Page 18: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Steering Algorithms

We have successfully, but not without problems applied following steering techniques dispersion free one-to-one all-to-all

27 Jan 2009CTF3 Collaboration Meeting18

Comparison between results ofDispersion Free Steering and All-to-All

Linac Orbit after all-to-all correction

Page 19: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

EuroTeV BPMs

We have tested the new high precision BPMsWe have already tried during previous year however, we could not get full transmission thru 2nd and 3rd BPM Turned out to be a hardware problem

We have installed standard BPM after the tested tripletMeasurements successfully repeated this year

27 Jan 2009CTF3 Collaboration Meeting19

-0.004-0.002 0 0.002 0.00405

10152025Histogram

[mm]

Stdev1PBPM _1.5A= 0.6µm

Page 20: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting20

2008 program – Installations 1

Technical break in June and July for Complete TL2 installation Install new deflectors Complete CLEX installations

When the dump after CR was removed to make place for TL2 personnel was not allowed to enter CLEX when the beam was in DL or CR (and vice versa)

DLTL1

CRM

CR

TL2CLEX

Page 21: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting21

2008 initial program for Run 2

Run 2 Commission the new RF deflectors Re-setup beam recombination in CR Full recombination with DL and CR (factor 8) Commissioning of

TL2TBTS (no PETS)First trial for CALIFES

Water leak on a bi-metal joint Coherent Diffraction Radiation measurements

DLTL1

CRM

CR

TL2CLEX

Page 22: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

TL2 and TBTS Commissioning

Strip-line kicker works wellBPMs based on the new LAPP electronics in principle work, but

30ns time jitter Big problems with OASIS viewer

The traces are digitized in-situ and analog signals are not available and we have to use this application to get them

Swapped vertical with horizontal for one type of pickups, OK for the other

Front-end task often crashing Constant improvement in making

them stably operational See F.Tecker talk at 14.40 for more

No MTV suitable for quad scansThe beam setup was very, very, very difficult

27 Jan 2009CTF3 Collaboration Meeting22

Current

Horizontal

Vertical

Page 23: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

TL2 and TBTS Commissioning

After long fight we have managed to transport the beam till the end of TBTS, however, with 50% current loss We had some problem with the optics, which was not

diagnosed yetEither incoming CR beam was terribly mismatched Rather doubtful since the beam was able to circulate for

tens of turns in CRThere was some optics error in TL2 itself, but it was difficult to diagnose not having Full transmission Operational beam monitors

27 Jan 2009CTF3 Collaboration Meeting23

Page 24: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

TL2 and TBTS Commissioning

We have attempted to do some optics measurements, but they were not very successful mainly due to Losses along the line

One has to get somehow full transmission and only then try optics measurements

Problems with BPMs

Page 25: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

New deflectors in Combiner Ring The Instability Gone

27 Jan 2009CTF3 Collaboration Meeting25

Old deflectors, undamped

New deflectors, dampeddamping loads

BPM signals shoving vertical instability

current

BPM signals, no instability

horizontal

vertical

Page 26: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

New deflectors in Combiner Ring The Instability Gone

Stable beam circulating for milisecondsRecombination factor 4Since than all the measurements were much easier to do and much more precise Tune measurements Orbit corrections

Still the model did not describe the ring optics precisely enough

27 Jan 2009CTF3 Collaboration Meeting26

Page 27: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Bunch length from Coherent Diffraction Radiation

Prototype device installed in CRM lineInitially very noisy signalsImproved device is much better

Measured radiation in function of target position consistent with the expectationsGood start for this yearSee Pavel Karataev talk today at 5PM

Page 28: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

DLTL1

CRM

CR

TL2CLEX

27 Jan 2009CTF3 Collaboration Meeting28

Installations in October Tail clipper CALIFES installations PETS in TBTS

Initial program for Run 3 Commissioning of

CALIFESTBTS (with PETS)PHIN

2008 Program

Page 29: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

RF power from PETS in TBTS

Power produced by PETS (Ibeam=2A)without and with recirculation

Page 30: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Recombined beam to PETS

8A through PETSAlmost 30MW obtained

Page 31: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

PHIN Commissionning

First measurements in Nov Nominal 1.3 ms pulse with

666 ps bunch separation Measured nominal energy

with good energy spread 5.3 MeV with 0.5 % σ energy spread

Emittance ‘to good to be true’ Laser control and diagnostic

insufficient Strange asymmetric beam

See Wednesday afternoon presentations

Page 32: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

CALIFES Commissioning

Started on Dec 1The beam with laser pulse train of 100 ns length (150 bunches) 0.073 nC per bunch 100% transmission thru the 1st

cavity Problems with RF phase

adjustmentFinished on Dec 11 Laser brokenSee Wilfrid Farabolini talk on Wednesday

Page 33: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting33

Optics Studies andModel Validation

The main reason for extensive optics measurements is verification that the model predicted optics well agrees with the measured one, and if they don’t Machine was not build according to the specification There is a bug in the model One can not back-hand the setup with the model

calculationsWe performed the following optics measurements Dispersion Response Matrix Tunes Combiner Ring Length Bunch length Quadrupole current to K1 coefficient

Page 34: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting34

Linac Model Validation Current Status and Remaining Problems

Page 35: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Linac Model Validation Current Status and Remaining Problems

There is some optics error in the area of girder 7 and 8 We see it as phase slippage in response matrix But also when we rematch the linac, the Twiss

parameters measured afterwards are slightly different from the expected ones

The magnetic fields on the pole surfaces where verified and are consistent with all the other magnets of this familyMore work is needed to nail down the problem Additional data, for example response matrix with

different quad families off, would certainly help However, in principle we have already sufficient data to

be able to find it with off-line analysis and systematic analysis should reveal the problem

27 Jan 2009CTF3 Collaboration Meeting35

Page 36: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

TL1 Model Validation Discovered Bugs

27 Jan 2009CTF3 Collaboration Meeting36

The measured dispersion pattern in TL1 always was showing slight (just outside the error-bar) but systematic discrepancy at the last BPMFinally with the high precision response matrix measurement we found wrong current to gradient coefficient for CT.QDF0720 Wrong drift length because of the same variable name

used in CR

Page 37: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

TL1 Model Validation Current Status and Remaining Problems

We consider TL1 commissioned and its model quite well

validated, although some small discrepancies remain

27 Jan 2009CTF3 Collaboration Meeting37

Page 38: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

CR Model ValidationDiscovered Bugs

27 Jan 2009CTF3 Collaboration Meeting38

Already during 2007 runs response matrix study allowed to find few problems with the CR model Current to gradient coefficient for J type magnets (4%) Cross-cabled control units for quadrupole’s power

convertersSome discrepancies were still present They were not localized in a precise location Large statistical uncertainties

originating in the gun instability did not allow to find the subtle problems quickly

Further higher precision measurements were needed to nail down the remaining discrepancies

Page 39: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Since CR has two fold symmetry the responses should be symmetric An they are (more or less)

http://skowron.web.cern.ch/skowron/results/cr_respmtx/20081209CR/symm.html There is no error due to single quad or family Almost certainly the error has to be related to wrong

magnetic coefficient of a type

CR Model ValidationResponse Matrix Results

Page 40: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting40

CR Model Validation Current Status and Remaining Problems

Lowering 10% quadrupolar strength for combined function magnets

andIncreasing focusing of J type by 5.5%

gives good agreement between the model and RM data ...

http://skowron.web.cern.ch/skowron/results/cr_respmtx/20081209CR/hor.htmlhttp://skowron.web.cern.ch/skowron/results/cr_respmtx/20081209CR/ver.html

... and with other measurements

Page 41: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting41

CR Model Validation Dispersion measurements

Page 42: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting42

CR Model Validation Tune measurements

Page 43: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

CR Model Validation Old Response Measurements

At different energies and optics

85MeV August 2008

104MeV November 2007

Page 44: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting44

CR Model Validation Current Status and Remaining Problems

However Does not describe some of old (with the old deflectors)

tune measurements It is hard to believe that focusing of this magnets is not

what expectedThey were used in EPAMeasured before installation in EPA and before installation in CTF

And the results are coherentFocusing in this case is an strictly geometric issue

For given bending angle it must have given k1We have 3 of this magnets in TL1, and over there we do not see any problems

We need to spend some more time on this problem

Page 45: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Orbit corrections

Successful application of orbit correction in CR See the next talk for more details

27 Jan 2009CTF3 Collaboration Meeting45

Before the correction

After the correction

Page 46: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

TL2 model validationMeasurements

We have attempted to do the optics measurements in TL2, however they are uncertain due to Problems with BPM readings Limited dynamic aperture

The optics was set „by hand”Any „kick” or „scaling” was leading to the beam losses

Within the precision we have we do not see any optics error

Page 47: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting47

Conclusions

2008 runs went relatively smoothly without any major disasters like Vacuum leaks (2 in 2007) Klystrons down for good (2 in 2007)

It seems the problem with the unstable gun disappeared for now But we are not really sure we have found the core of the

problem and that it disappeared for goodNew RF deflectors installed in the Combiner Ring It is confirmed now that there is no sign of the instability

now Immediately managed to get recombination factor 4 There is serious chance to finish its commissioning soon

TL2 and TBTL need more reliable diagnostic for optics measurementsCALIFES commissioning postponed to the next run

Page 48: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting48

Conclusions

The gun Find and repair the problem that makes unstable Consolidation program needs to be completedLinac Establish stable & documented working point Stability studies Diagnostic consolidationTL1 Optics measurements and model validationDelay Loop Beam optics measurements Re-establish the recombination

Page 49: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting49

Conclusions

Finish the commissioning of CR Perform set of optics measurements Validate the machine model Tune and b function dependence of vertical instability

Problem disappeared with the new deflectors Commissioning TL2 TBTS TBL CALIFESTest new devices and techniques EuroTeV BPMs Bunch length measurement with RF pickup Transient compensation Dispersion Free Steering and other automatic

algorithms

Page 50: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

structures 12 GHz

fully loaded acceleration

recombination x 2

phase-coding

bunch length control

recombination x 4

bunch compression

PETS on-off

two-beamacceleration

structures 30 GHz

deceleration stability

2008

2009

2010

2005

2006-2008

2004

Page 51: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009
Page 52: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting52

Backup Slides

BACKUP

Page 53: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting53

Beam setup procedure Linac to girder 4

We start with 3GHz (more stable) beam Traveling Wave Tubes (TWTs) off (a)

Adjust The gun (b) Phases of klystrons 2 and 3 (c) The compressor chicane (d)

Current in bendsThe slit gapto get 4-5 A beam after the chicane (e)

53

(a)(b)

(c) (d) (e)

Page 54: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting54

Beam setup procedureLinac to girder 10

Adjust the phase of MKS05Get somehow the beam up to spectrometer 10 (a) Usually by scaling up and down all the quadruples together

Beam measurements at spectrometer 10 Energy with the slit dump

Vary the bend current to get maximum signalHaving current-momentum coefficient for this angle one gets energy

Twiss parameters using quad scanWe vary quad strengths and measure beam profiles at screen MTV1026

54

(a)

Page 55: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting55

Beam setup procedureOptics Calculation

Having The energy profile along the whole linac

Having input power to each of the accelerating structures and knowing beam current one calculates acceleration in each cavity

Twiss parameters at certain locationwe can calculate the optics along the machine

We have the design optics however the exact magnet setting depends on Beam provided by the injector Energy profile that depends on the klystrons power

55

Page 56: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting56

Beam setup procedureLinac rematch

20 Jan 2008CTF3 Collaboration Meeting, CERN56

Knowing Twiss parameters at the end of the buncher rematch the whole linac up to the Delay Loop to the nominal opticsAdjust phases of klystrons

from 11 to 15 bends in

The stretcher chicaneDelay Loop injection

Page 57: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting57

Beam setup procedureOptics Verification

Perform quad-scans at Spectrometer 10

To verify the rematch Beginning of TL1

Depending on the obtained results rematch whole or part of the linacCheck if the obtained energy agrees with the bends settings

20 Jan 2008CTF3 Collaboration Meeting, CERN57

Page 58: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting58

TL1 and CR optics

Adjust the optics in the Combiner Ring to The beam energy Wiggler currentCalculate isochronous optics in TL1 to match CR

Page 59: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting59

We start with static magnetic injection using two horizontal correctors (a) It allows for only one turn in CRSetup the septa and the orbitSwitch to the injection with the RF deflector (b) It is an iterative procedure that involves

the following stepsSet RF power (amplitude)Find zero crossing phase of the RF deflector

It leaves the orbit unchangedSet the phase +/- 90° and switch off the correctors If kick is too weak or to strong adjust the power

It changes the phaseThat is why the procedure is iterative

(a)

(b)

Beam setup procedure CR Injection

2nd deflector

RF deflector fieldlo

injection lineseptum

localinner orbits

1st deflector

Page 60: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting60

Beam setup procedure CR Injection

To setup a good injection and orbit Short train is injected (~140ns) RF is switched off just after the last bunch is injectedIt allows for long lasting beam circulation in the ring Then it is easier to find a closed orbit It makes possible to apply orbit correction

procedures more efficiently Allows to measure the tunes precisely

Page 61: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting61

Orbit length in CR

The orbit must have the lengthCr = (nt ± ¼) l (it is „-” in our case)so the beam arrives exactly 1st turn: at zero crossing phase 2st turn: at the crest

But opposite amplitude than at the injection

3st turn: at zero crossing againAdjust the length with the wiggler

1st

2nd3rd

2nd deflector

RF deflector fieldlo

injection lineseptum

localinner orbits

1st deflector

lo/4

Page 62: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting62

Beam Setup

In theory the whole procedure could be completed within a couple of weeks If, and only if, the machine is

StableReliable

Whenever any device changes its parameters the procedure needs to be restarted from the point the device sits!

21 Jan 2008

Page 63: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

K1 measurement

We have attempted to measure focusing strength of combined function magnets We look for the magnet current that gives 180° phase

advance between kicker and BPMKnowing energy and distances we get k1

Unfortunately when we did it the gun was still unstable and the result was not precise enough

kickerquad

bpm

Page 64: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

CR Orbit Closure

Page 65: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Schedule 2008 v1

27 Jan 2009CTF3 Collaboration Meeting65

DL, CR, TL2 TBTS

CALIFES

PETS in TBTS

RUN 1

RUN 2

RUN 3

Installation:

tail clipper

Installation:TL2, CALIFES, TBTS, new deflectors

Today

Delayed 2 weeks ?

Linac only

Linac, Ring area, (CLEX)

30 GHzDL & CR

Page 66: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting66

DL, CR, TL2 TBTS

30 GHz30GHz only

CALIFES

DL & CR

PETS in TBTS

RUN 1

RUN 2

RUN 3

Today

Installation:TL2, CALIFES, TBTS, new deflectors

Schedule 2008 v2

Linac only

Linac, Ring area, (CLEX)

Installation:

tail clipper

Page 67: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Gun HV stability

27 Jan 2009CTF3 Collaboration Meeting67

Stable

Unstable

Stable

Unstable

It must be the Gun HV instability since 0290 is only after buncher, whichs phase does not play a role for bunch length

Page 68: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting68

Bunch length

-20 -15 -10 -5 0 5 10 15 200

1020304050607080

Inte

nsity

Bunc

h le

ngth

(mm

)

Klystron 13 Phase(degree)

The bunch length achieved by measuring the intensity of a thin band at middle of screen for each RF deflector phase and fitting a Gaussian distribution. The standard deviation of this chart is related to bunch length by c/f constant. c is speed of light and f=1.5 GHz is frequency of RFD. The errors are large due to the beam jitter but is good for first measurement by this method

RF Deflector Phase(degree)

lb= 2.68±0.60 mm

Page 69: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

27 Jan 2009CTF3 Collaboration Meeting69

We start with static magnetic injection using two horizontal correctors (a) It allows for only one turn in CRSetup the septa and the orbitSwitch to the injection with the RF deflector (b) It is an iterative procedure that involves

the following stepsSet RF power (amplitude)Find zero crossing phase of the RF deflector

It leaves the orbit unchangedSet the phase +/- 90° and switch off the correctors If kick is too weak or to strong adjust the power

It changes the phaseThat is why the procedure is iterative

(a)

(b)

Machine setup – 2nd slide CR Injection

2nd deflector

RF deflector fieldlo

injection lineseptum

localinner orbits

1st deflector

Page 70: 1 General Status of Commissioning Piotr Krzysztof Skowroński CTF3 Collaboration Technical Meeting 27 January 2009

Insufficiently precise modeling of combined function magnets for magnetic lengths for quadrupolar component is shorter then for dipolar one We inherited the model of those magnets from EPA in

which the 3rd way of the magnet modeling was chosenHowever EPA had 16 of them in the ring, and CR has 12Although all parameters were scaled accordingly and it should work for CR equally well as for EPA

The modeling with the straight forward (1st) way give slightly better resultsLowering k1 by 10% compares better with the model

27 Jan 2009CTF3 Collaboration Meeting70

CR Model Validation Focusing of combined function bends