ctf3 measurements and plans r. corsini for the ctf3 team
DESCRIPTION
CTF3 measurements and plans R. Corsini for the CTF3 Team. Talk Outline : Summary Status of feasibility benchmarks in CTF3 Drive beam generation PETS & RF Structures Two-beam issues Plans for 2012. 1. CTF3 - 2011. - PowerPoint PPT PresentationTRANSCRIPT
R. Corsini, CLIC Project Meeting, 9 Dec 2011
CTF3 measurements and plans
R. Corsini for the CTF3 Team
1
Talk Outline:
1. Summary
2. Status of feasibility benchmarks in CTF3
• Drive beam generation• PETS & RF Structures• Two-beam issues
3. Plans for 2012
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Test Beam Line (TBL) in CTF3
• Many improvements on optics, hardware, feed-backs, beam stability, reproducibility…
• PETS operation to power levels (~250 MW) well above CLIC goal, at nominal CLIC pulse length.
• Measured gradient in two-beam acceleration test 145 MV/m (CLIC nominal gradient of 100 MV/m)
• Nine PETS tanks installed in the Test Beam Line (TBL), 20 A decelerated by ~ 25%, matching well with expectations
• First successful test of PETS with on-off mechanism
• First measurements of break-down kicks in TBTS
Two-beam acceleration in TBTS
Optics model checks in Combiner Ring
200 400 600 800 1000
50
100
150
200
250
CLIC target pulse
12 GHz RF power
135 MW
Power Extraction Structure (PETS)
P
[MW
]
t [ns]
CTF3 - 2011
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Barranco JavierConstance
BenjaminIkarios EmmanouilPersson TobiasSkowronski PiotrSterbini GuidoBolzon BenoitBurger StephaneFavier MathildeGuillot-Vignot
FranckLefevre ThibautOlvegaard MajaRabiller AurelieSoby LarsDobers TobiasChevallay Eric
Csatari Marta
Fedosseev ValentinHessler Christoph
Putz SvenPaju Esa AnteroAllard DanielMonteiro JoseRavida GianfrancoRey Stephane FranckRinolfi LouisRossat GhislainSyratchev IgorTimeo LucaWiszniowski ThierryFarabolini WilfridPeauger FranckRuber RogerPalaia AndreaGerbershagen
AlexanderMarin Lacoma EduardoLillestol ReidarJacewicz Marek…
Draper MichaelGamba DavideTecker FrankDubrovskiy AlexeyPasinelli SergioRiddone GermanaSamochkine
AlexandreKovermann JanKononenko OlekseyAndersson AlexandraCurt StephaneDoebert SteffenGeschonke GuntherLivesley StephenMcmonagle GerardBarnes Michael JohnHourican MichaelDe Oliveira LoicDavid Nicolas Andre
Many, many thanks to the CTF3 team & all collaborators from within & outside CERN
R. Corsini, CLIC Project Meeting, 9 Dec 2011
System Item Feasibility Issue Unit Nominal Achieved How Feasibility CommentsFully loaded accel effic % 97 95 CTF3 Freq&Current multipl - 2*3*4 2*4 CTF3
Combined beam current (12 GHz) A 4.5*24=100 3.5*8=28 CTF3
Combined pulse length (12 GHz) nsec 240 140 CTF3Intensity stability 1.E-03 0.75 < 0.6 CTF3 End of DBA. To be demonstrated for combined beam in 2011
Drive beam linac RF phase stability Deg (1GHZ) 0.05 0.035 CTF3, XFEL Achieved in CTF3, XFEL design
PETS RF Power MW 130 >130 TBTS/SLAC
PETS Pulse length ns 170 >170 TBTS/SLAC
PETS Breakdown rate /m < 1·10-7 ≤ 2.4 10-7 TBTS/SLAC
PETS ON/OFF - @ 50Hz - CTF3/TBTS 2011 Prototype under fabrication for tests with beam
Drive beam to RF efficiency % 90% - CTF3/TBL2012
TBL with 8 (16) PETS in 2011(12) for 30(50%) efficiency. Benchmark beam simulation for safe extrapolation of high efficiency at high drive beam energy(2GeV).
RF pulse shape control % < 0.1% - CTF3/TBTS 2011-2012
Structure Acc field MV/m 100 100Structure Flat Top Pulse length ns 170 170 Structure Breakdown rate /m MV/m.ns < 3·10-7 5·10-5(D) 2011Rf to beam transfer efficiency % 27 15 2011
Power production in Two Beam Test Stand (TBTS)
Probe beam acceleration by Two Beam Test Stand(TBTS)
Drive to main beam timing stability psec 0.05 - CTF3 2012
Main to main beam timing stability psec 0.07 - XFEL? 2012
Emitttance generation H/V nm 500/5 3000/12 Damping Ring design nom perf. Relax emitt achieved ATF
Emittance preservation: Blow-upH/V
nm 160/15 160/15 2011-12 Simulation + alignment/stability
Main Linac components microns 15 2011Final-Doublet microns 2 to 8 2011
Quad Main Linac nm>1 Hz 1.5
Final Doublet (assuming feedbacks) nm>4 Hz 0.2drive beam power [email protected] beam power of [email protected]
Operation and Machine Protection System (MPS)
CTF3 simulations
2011 Report integrating LHC experience under preparation
Principle demonstrated in CTF2, to be adapted to long distances and integrated in Two Beam Module in 2010
Vertical stabilisation
0.13 (principle)
Stabilisation Test Bench
2011-12 Adaptation to quad prototype and detector environment in 2010. Integrated in Two Beam Module with beam till 2012.
2011
Ultra low beam
emittance & sizes
Ultra low Emittances
ATF, NSLS/SLS + simulation
Alignment 10 (princ.) Alignement & Mod.Test Bench
Two Beam Acceleration
Power producton and probe beamacceleration in Two beam module MV/m - ns 100 - 170 106 - 170 TBTS
Two Beam Acceleration
Drive beam generation
Accelerating Structures
(CAS)
CTF3 Test Stand, SLAC,
KEK
Nominal performances of 3 structures without damping. 1 structure equipped with damping features under RF conditionning to reduce breakdown rate.
Novel scheme fully demonstrated in CTF3 in spite of lower current since beam dynamics more sensitive than nominal
due to lower energy (250MeV/2Gev)
Beam Driven RF
power generation
BD rate at nominal power and pulse lenght, measured on Klystron driven PETS. Beam driven tests under way in CTF3
System Item Feasibility Issue Unit Nominal Achieved How Feasibility CommentsFully loaded accel effic % 97 95 CTF3 Freq&Current multipl - 2*3*4 2*4 CTF3
Combined beam current (12 GHz) A 4.5*24=100 3.5*8=28 CTF3
Combined pulse length (12 GHz) nsec 240 140 CTF3Intensity stability 1.E-03 0.75 < 0.6 CTF3 End of DBA. To be demonstrated for combined beam in 2011
Drive beam linac RF phase stability Deg (1GHZ) 0.05 0.035 CTF3, XFEL Achieved in CTF3, XFEL design
PETS RF Power MW 130 >130 TBTS/SLAC
PETS Pulse length ns 170 >170 TBTS/SLAC
PETS Breakdown rate /m < 1·10-7 ≤ 2.4 10-7 TBTS/SLAC
PETS ON/OFF - @ 50Hz - CTF3/TBTS 2011 Prototype under fabrication for tests with beam
Drive beam to RF efficiency % 90% - CTF3/TBL2012
TBL with 8 (16) PETS in 2011(12) for 30(50%) efficiency. Benchmark beam simulation for safe extrapolation of high efficiency at high drive beam energy(2GeV).
RF pulse shape control % < 0.1% - CTF3/TBTS 2011-2012
Structure Acc field MV/m 100 100Structure Flat Top Pulse length ns 170 170 Structure Breakdown rate /m MV/m.ns < 3·10-7 5·10-5(D) 2011Rf to beam transfer efficiency % 27 15 2011
Power production in Two Beam Test Stand (TBTS)
Probe beam acceleration by Two Beam Test Stand(TBTS)
Drive to main beam timing stability psec 0.05 - CTF3 2012
Main to main beam timing stability psec 0.07 - XFEL? 2012
Emitttance generation H/V nm 500/5 3000/12 Damping Ring design nom perf. Relax emitt achieved ATF
Emittance preservation: Blow-upH/V
nm 160/15 160/15 2011-12 Simulation + alignment/stability
Main Linac components microns 15 2011Final-Doublet microns 2 to 8 2011
Quad Main Linac nm>1 Hz 1.5
Final Doublet (assuming feedbacks) nm>4 Hz 0.2drive beam power [email protected] beam power of [email protected]
Operation and Machine Protection System (MPS)
CTF3 simulations
2011 Report integrating LHC experience under preparation
Principle demonstrated in CTF2, to be adapted to long distances and integrated in Two Beam Module in 2010
Vertical stabilisation
0.13 (principle)
Stabilisation Test Bench
2011-12 Adaptation to quad prototype and detector environment in 2010. Integrated in Two Beam Module with beam till 2012.
2011
Ultra low beam
emittance & sizes
Ultra low Emittances
ATF, NSLS/SLS + simulation
Alignment 10 (princ.) Alignement & Mod.Test Bench
Two Beam Acceleration
Power producton and probe beamacceleration in Two beam module MV/m - ns 100 - 170 106 - 170 TBTS
Two Beam Acceleration
Drive beam generation
Accelerating Structures
(CAS)
CTF3 Test Stand, SLAC,
KEK
Nominal performances of 3 structures without damping. 1 structure equipped with damping features under RF conditionning to reduce breakdown rate.
Novel scheme fully demonstrated in CTF3 in spite of lower current since beam dynamics more sensitive than nominal
due to lower energy (250MeV/2Gev)
Beam Driven RF
power generation
BD rate at nominal power and pulse lenght, measured on Klystron driven PETS. Beam driven tests under way in CTF3
CTF3
CLIC Feasibility Benchmarks
4
Technical system tests and
simulations
RF Test StandsSLAC – KEK -CERN
Nextef – RF test stand KEK
R. Corsini, CLIC Project Meeting, 9 Dec 2011
High current, full-loaded linac operation
• 95 % RF to beam efficiency measured
• No instabilities
High current, full-loaded linac operation
• 95 % RF to beam efficiency measured
• No instabilities
10 m
RF pulse at output
RF pulse at structure input
1.5 µs beam pulse
Achievements – Drive Beam Generation
MKS03 MKS07MKS06MKS05
Spectrometer 10Spectrometer 4SiC load
damping slot
Dipole modes suppressed by slotted iris damping (first dipole’s Q factor < 20)and HOM frequency detuning
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Drive Beam Generation
Beam recombination
• Fast bunch phase switch in SHB system
• Operation of isochronous rings and beam lines
R. Corsini, CLIC Project Meeting, 9 Dec 2011
333 ps
Streak camera image of the beam, illustrating the bunch combination process
t
x
83 ps
Achievements – Drive Beam Generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Drive Beam Generation
Beam recombination
• Factor 8 recombination by RF deflector injection
Beam recombination
• Factor 8 recombination by RF deflector injection
P0 , n0
P0 , f 0
2 × P0 , 2 × f 0
TransverseRF Deflector, f 0
DeflectingField
6 & 7 December 2011
6 & 7 December 2011
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Problems: • TWT availability – still working with 2 SHB only – plus day-to-day power fluctuations
• Mainly working with 3 GHz beam for most of the year
• Difficult DL set-up after last stop – suspect misaligned quadrupole (+ radiation alarm problem)
Eventually able to get good recombination (current record), but:
• Bad pulse shape (phase switches?)
• Still limited acceptance -> stability was improved, but it is still not good enough
Future work:
• Measure and realign DL quad(s)
• Work on phase switches, gun current compensation, back to 3 TWTs, improve trajectories
Achievements – Drive Beam Generation
P. Skowronski
DL current
H
V
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Beam recombination - Emittance
Best results in CLEX for factor 4: eH= 250 um eV= 140 um
for factor 8: eH= 640 um eV= 170 um
Different turns are ~ ok, no unknown effectsEmittance increase due to non perfect combination
Achievements – Drive Beam Generation
• Improve measurements• Correct dispersion (linear,
nonlinear)• Correct multi-turn orbit• Control beta-beating
End 2011 ?
Horiz. Vert.
Measurements in TL2 - uncombined
Uncombined beam
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Vertical Horizontal
Factor 4 Factor 8 Factor 4 Factor 8
Emittance – last measurements in CLEX • No time for optimization
• Main issue: different trajectories for DL & bypass beams and ring orbit closure (differences of the order of 1 s)
• Vertical: main effect from DL, small effect from ring• Horizontal: ring closure is dominant
• Similar Twiss parameters for factor 4 and factor 8 combination (small betatron mismatch)
Achievements – Drive Beam Generation
F. Tecker, P. Skowronski, S. Doebert, R. Lillestol
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Factor 4Factor 8
B. Constance
Achievements – Drive Beam Generation
Beam profile during emittance measurements
Improved quad scan
program
R. Corsini, CLIC Project Meeting, 9 Dec 2011
• Improve measurements• Tune chicane to small R56• Measurements in CLEX
End 2011 ? Improve in 2012
Beam recombination – Bunch lenght
nominal in CLEX 1 mm sigma
In the past, well below 1 mm sigma measured at the end of the linac (tuned chicane)
Recent results (preliminary): 1.5 to 4 mm sigma for CR and CLEX (natural chicane)
Achievements – Drive Beam Generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Drive Beam Generation
Phase stability 2.5° @ 12GHz0.2° @ 1GHz
Phase stability 2.5° @ 12GHz0.2° @ 1GHz
Emittance εx,y ≤ 150μm
Transverse jitter ≤ 0.3σ
Emittance εx,y ≤ 150μm
Transverse jitter ≤ 0.3σ
Current stability 0.75 10-3
Phase stability 0.2° @ 12GHz
Bunch length stability 1%
Current stability 0.75 10-3
Phase stability 0.2° @ 12GHz
Bunch length stability 1%
RF power stability 0.2%RF phase stability 0.05°Current stability 0.1%
RF power stability 0.2%RF phase stability 0.05°Current stability 0.1%
CLIC Drive Beam requirements
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Drive Beam Generation
Pulse charge measured at end of the linac
After factor 8 combination~ 1% jitter
Tolerance
Measured
Beam current
0.075% 0.054%
RF Power 0.2% 0.16% - 0.21%
RF Phase 0.05° 0.035° - 0.07°
“Good” CTF3 klystron
• pulse-to-pulse jitter• 10 ns time slices along the RF
pulse• with respect to local phase
reference• Improve and document current
stability for combination factor 4• Improve stability for combination
factor 8 – at the permil level• Means: improve acceptance
(dispersion, orbit, beta-beating)• Reduce energy spread – bunch
length
End 2011 – Mid 2012 G. Sterbini, A. Dubrovsky
R. Corsini, CLIC Project Meeting, 9 Dec 2011
5 10-4
1 10-3
3 to 4 10-3
Achievements – Drive Beam Generation
Charge stability – Factor 4
18th November 2011
T. Persson
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Total loss from cleaning chicane to TBTS ~ 15% BPM
s
BPIs
T. Persson18th November 2011
Charge losses – Factor 4
Achievements – Drive Beam Generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Charge stability – Factor 8
1 10-2
6th December 2011
T. Persson
Achievements – Drive Beam Generation
DL ~ 1 10-3
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Charge stability – Factor 4with noise estimate
T. Persson 6th December 2011
< 1 10-3
Achievements – Drive Beam Generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011
[MW
][a
rb]
Feed-backs, stability
RF power feedback, MKS 13RF power feedback, MKS 13
Tobias Persson, Piotr Skowronski
Achievements – Drive Beam Generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Feed-backs, stabilityRF power feedback, effect on beam
RF power feedback, effect on beam
Tobias Persson, Piotr Skowronski
Achievements – Drive Beam Generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Beam driven RF power generation
PETS rapidly (~ 3 x 105 pulses) reached record >200 MW peak RF power level,
providing reliably pulses ~ 1o0 MW peak to accelerating structure.
About twice the power needed to demonstrate 100 MV/m acceleration in a two-beam experiment with TD24 structure.
22
Breakdown rate ?
• Analyze data for evaluation of present break-down rate
• Dedicated measurement at high powers – increased rep rate
• Document
End 2011 – Mid 2012
200 400 600 800 1000
50
100
150
200
250
CLIC target pulse
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Beam driven RF power generation
23
On-off mechanism
Installation in CTF3 TBTS under way now.Test starting from next week.
Issues:
• Reliable power production
• Ability to control output power
• Conditioning• Initial test – no structure
connected• Connect structure• Full test, including use as
recirculation loop
End 2011 ?
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Igor Syratchev, Alexei Dubrowski
Power to the structure
Power extracted from the drive beam
ON
OFF
Achievements – Beam driven RF power generation
In CTF3 a movable short is added, to allow for recirculation mode
PETS On-Off concept
R. Corsini, CLIC Project Meeting, 9 Dec 2011
ONOFF
PETS outputStructure input
(as predicted by computer simulation)
TBTS PETS layout with internal recirculation to test the ON/OFF concept
Movable RF short circuit (to tune the resonant length)
Variable reflector (to tune the recirculation coupling)
Igor Syratchev
Achievements – Beam driven RF power generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011
30 October (logbook pictures)
Power
PMT signal
Current
45 MW
150 MW
80 MW
CTF3 Achievements – Beam driven RF power generation
Igor Syratchev, Alexei Dubrowski
PETS On-Off conditioning
Vacuum gauges
Peak power
Pulse length at 50% level
R. Corsini, CLIC Project Meeting, 9 Dec 2011CTF3 Achievements – Beam driven RF power
generation
Igor Syratchev, Alexei Dubrowski
PETS On-Off operation – high current, high power
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Simulation vs. experiment
Achievements – Beam driven RF power generation
0N
0FF
Combination x 4 0N
0FF
0N
0FF
Beam current PETS, forward RF
RF to structurePETS, reflected RF
Signal evolution during On-Off
Igor Syratchev, Alexei Dubrowski
PETS On-Off mechanism - results
PETS output, forward
Spectra comparison
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Beam driven RF power generation
29
16 PETS maximum
4 PETS installed and tested4 5 being installed in September12 to 16 next year
50 100 150 200 250 300 350 400 450108
110
112
114
116
118
120
122
time (ns)
Be
am
En
erg
y (
Me
V)
Prediction from rf power
Prediction from beam currentSegmented dump measurement
Up to 19 A current
• optics understood• no losses in TBL
Good agreement
• power production
• beam current• beam deceleration
• Deceleration with 9 PETS, 20 A (end 2011)
• Deceleration with 12 PETS, > 20 A (mid 2012)
• Final test, 16 PETS (end 2012)
9 PETS – 20 ANovember 2011
9 PETS – 20 ANovember 2011
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Steffen Doebert, Reidar Lillestol
TBLTL2
Achievements – Beam driven RF power generation
High current transport in TBL
Factor 4
Factor 8
Factor 8
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Beam driven RF power generation
Reidar Lillestol
High current power production in TBL
More than half a GW of 12 GHz power!
R. Corsini, CLIC Project Meeting, 9 Dec 2011
~ 30 MeV
25%
Incoming energy 117 MeV, field form factor 0.9 (average) Steffen Doebert
Achievements – Beam driven RF power generation
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Beam driven RF power generation
33
CLIC target pulse
Beam loading compensation ramp
• Create precise ramp by fine tuning of phase switches timing
• Show control of ramp to the desired degree (limited by number of free parameters)
• Eventually test acceleration with probe beam (short pulse, scan method)
• Initial tests, end 2011• Eventual
improvements/upgrades, shut down 2011/2012
• Full test, including probe beam acceleration, mid/end 2012
20122012
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Two-Beam Acceleration
34
TD24TD24Two-Beam Acceleration demonstration in CTF3 Two-Beam Test Stand
Drive beam OFF
Drive beam ON
Maximum probe beam acceleration measured: 31 MeV
Corresponding to a gradient of 145 MV/m
Maximum probe beam acceleration measured: 31 MeV
Corresponding to a gradient of 145 MV/m
R. Corsini, CLIC Project Meeting, 9 Dec 2011
kick angle = 400 µradkick angle = 340 µrad
Measured on OTR screen CA.MTV0790 (~4.9 m from the accelerating structure).
Andrea Palaia, Wilfrid Farabolini, Javier BarrancoBreak-down kicks
Achievements – Two-Beam Acceleration
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Andrea Palaia
Break-down kicks,distribution
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Accelerating Structures
37
• Continue conditioning/BDR measurements of TD24 in the shadow of other experiments
• Profit to improve power production stability/availability/rep rate
• Continue BD kick measurements
• Install couple of new structures, TD24 with wake-field monitors in winter shut-down 2011-2012
• First module should go in during winter shut-down 2012-2013
R. Corsini, CLIC Project Meeting, 9 Dec 2011Achievements – Accelerating Structures
38
New Data
Alexei DubrowskiWilfrid Farabolini
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Bunch length control < 1 mm rms (end of linac)
Full beam loading (95% transfer) high current acceleration (up to 5 A)
Ring isochronicity ap < 10-4
Sub-Harmonic bunching with fast (< 6ns) 180 phase switch(8.5% satellites)
Control of ring length to better than 0.5 mm
Factor 2 combination in Delay Loop (from 3.5 to 7 A)
Bunch train recombination factor 4 in Combiner Ring (from 3 to 12 A)
Beam current stability ~ 0.1 % end-of-linac,~ 0.2 % combiner ring
Transverse rms emittance 100 p mm mrad (end of linac)
Bunch train recombination 2 x 4 in DL and CR (from 3.5 to 28 A)
Transverse rms emittance < 150 p mm mrad (combined beam)
Bunch length control < 1 mm rms (combined beam)
Beam current stability ~ 0.2 % for fully combined beam
CTF3 Achievements – What is still missing for feasibility – Drive Beam Generation
~ 0.05 % end-of-linac !
39
CTF3 Achievements – Drive Beam
~ 0.1 % factor 4~ 0.1% factor 2 after DL
~ 1 %
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Beam-powered test of a PETS with external recirculation to 170 MW, <200 ns - ~10 A beam currentPower & drive beam energy loss measurements.
CTF3 Achievements – What is still missing for feasibility – TBL / TBTS / CALIFES
Beam-powered test of a PETS to nominal parameters (135 MW, 240 ns) with external recirculation (10 A) and without (20 A) – including probe beamImproved power & drive beam energy loss measurements
Break-down kick measurements
PETS On-off mechanism demonstration
Drive beam phase
8 (12 > 16) PETS + spectrometer installed to verify transport of a 28 A beam with up to 30% of energy extracted.
Probe beam acceleration to 100 MV/m. (up to 145 MV/m measured)
40
CTF3 Achievements – Two-Beam issues
9 PETS20 A beam25% deceleration
R. Corsini, CLIC Project Meeting, 9 Dec 2011Outlook
Drive Beam:
- Flatness, RF pulse shape control (main beam loading), - Charge & energy stability)- Emittance- Bunch length- Phase monitor qualification, DB phase stability studies
TBL:
- 12 PETS, > 20 A deceleration- Dispersion free steering, optics studies- Possibly, new PETS prototype for TBL+ (input coupler, mini-tank)
TBTS:
- PETS on/off final test, BDR control- New structures, conditioning & BDR measurements- Wakefield monitors tests- BD studies (flashbox)- Continuation of BD kicks measurements
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Thanks again
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Breakdown rate at 100 MV/m (unloaded) accelerating gradient and scaled to 180 ns pulse length
Measurements scaled according to
SLAC Tests
SLAC Tests
CERN built,old procedure
CERN built,old procedure
UndampedUndamped
DampedDamped
1st generation, moderate efficiency
1st generation, moderate efficiency
2nd generation,high efficiency
2nd generation,high efficiency
43
Accelerating Structure - Experimental results
CTF3 Two-Beam
CTF3 Two-Beam
KEK Tests
KEK Tests
R. Corsini, CLIC Project Meeting, 9 Dec 2011Beam Recombination
Factor 8Factor 8
Factor 4Factor 4
R. Corsini, CLIC Project Meeting, 9 Dec 2011Gun current Correction
Alexandra Andersson
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Gun adjusted, no switchesGun adjusted, no switches
Switches introducedSwitches introducedSwitches, gun re-adjustedSwitches, gun re-adjusted
Compensation of phase switches
Alexandra Andersson, Frank Tecker, Piotr Skowronski
R. Corsini, CLIC Project Meeting, 9 Dec 2011
No switchesNo switches
SwitchesSwitches
Compensation of phase switches
Frank Tecker, Piotr Skowronski
R. Corsini, CLIC Project Meeting, 9 Dec 2011Optics studies, orbit correction
Ben Constance
Guido Sterbini, Ben Constance
Model checks in CRModel checks in CR
Orbit correction in TL1 - CROrbit correction in TL1 - CR
R. Corsini, CLIC Project Meeting, 9 Dec 2011TBL with 9 PETS tanks
Steffen Doebert, Reidar Lillestol
R. Corsini, CLIC Project Meeting, 9 Dec 2011TBL with 9 PETS tanks
Reidar Lillestol
R. Corsini, CLIC Project Meeting, 9 Dec 2011TBTS first operation with Petsonov
PETS OnPETS On PETS OffPETS Off
Igor Syratchev, Alexei Dubrowski
R. Corsini, CLIC Project Meeting, 9 Dec 2011TBTS first operation with Petsonov
Igor Syratchev, Alexei Dubrowski
Petsonov used in recirculating mode
Petsonov used in recirculating mode
Conditioning - vacuumConditioning - vacuum
R. Corsini, CLIC Project Meeting, 9 Dec 2011
Reidar Lillestol
Emittance at TBL entry
R. Corsini, CLIC Project Meeting, 9 Dec 2011
CLIC RF Power Source Layout
Drive Beam Acceleratorefficient acceleration in fully loaded linac
Power Extraction
Drive Beam Decelerator Section (2 24 in total)
Combiner Ring 3
Combiner Ring 4pulse compression & frequency multiplication
pulse compression & frequency multiplication
Delay Loop 2gap creation, pulse compression & frequency multiplication
RF Transverse Deflectors
140 ms train length - 24 24 sub-pulses4.2 A - 2.4 GeV – 60 cm between bunches
240 ns
24 pulses – 101 A – 2.5 cm between bunches
240 ns5.8 ms
Drive beam time structure - initial Drive beam time structure - final
54
The CLIC RF Power Source Concept
R. Corsini, CLIC Project Meeting, 9 Dec 2011CLIC Test Facility (CTF3)
DRIVE BEAM LINAC
CLEXCLIC EXperimental Area
DELAY LOOP
COMBINERRING
CTF3 – Layout
10 m
4 A – 1.2 ms150 Mev
28 A – 140 ns150 Mev
Two-Beam Test Stand (TBTS)
Test Beam Line (TBL)
55
Scaled model of CLIC RF power source - built partly re-using existing infrastructure
• Made it affordable• Different parameters – in some cases issues more difficult than in CLIC
Scaled model of CLIC RF power source - built partly re-using existing infrastructure
• Made it affordable• Different parameters – in some cases issues more difficult than in CLIC
R. Corsini, CLIC Project Meeting, 9 Dec 2011
What do we learn in CTF3, relevant for the CLIC RF power source ?
System quantity/issue CTF3 CLIC
Injector/linac bunch charge 2-3 nC 7.7 nCcurrent 3.5 - 4.5 A 4.2 Apulse length 1.4 ms 140 ms
phase coding samefrequency 3 GHz 1 GHztransverse stability about the same - CTF3 ``too stable ´´
Delay loop/ring final current 30 A 110 Abeam energy 150 MeV 2.4 GeVcombination 2 - 4 2 - 3, 4CSR, wakes worse in CTF3 (lower energy)Deflector instability about the same
Power production (PETS) Aperture 23 mm 23 mmLength 1 m 23 cmPower > 135 MW 135 MWPulse length 140 ns (240 with recirculation) 240 ns
Decelerator Fractional loss 50-60 % 90%Final energy 70 MeV 240 MeVwakes, stability somehow ``masked´´ in CTF3beam envelope much larger in CTF3
In general, most of unwanted effects are equivalent or worse in CTF3 because of the low energy, however in CLIC the beam power is much larger (heating, activation, machine protection)Needed tolerances on the final drive beam parameters (phase, current, energy stability...) are more stringent in CLIC – some could be demonstrated in CTF3 as well
A non-exhaustive list easier more difficult
CLIC Test Facility (CTF3)