1 gif ++: august beam data taking summary 7/24/2015
TRANSCRIPT
2
I. Redondo
Tentative Plan (index is week from July 6th)
1. July 6,7-8 rails and cables. ==>Drill holes to attach rails,install 5 m of rails (Mimmo, Giorgio, Riccardo, Fabio Yañez, Ignacio)
2. Wednesday access opportunity,⁻ 2 shorter rail sections ready, carriage
advanced
3. Wednesday access opportunity.⁻ Lights has been moved up⁻ Start this week to label and prepare for
transport cables and electronics
4. Wednesday access opportunity, install cables?
⁻ Tested chamber rotation and displacement
5. Week August 3-7⁻ transport frame preparation,⁻ transport trial, installation of (not yet
installed) cables on Wednesday August 5th
⁻ installation of both shorter rails (2.7m+1.6m) under the CSC chamber; opening of the concrete door requested
⁻ start installation of the cables through the shorter passage need RP approval (Roberto G. is checking this for us); it might be that the concrete door should be opened, if we need to move some of steel plates by using the robot;
-Transport of chamber August 10th (Mimmo)
6. -Installation chamber August 12-13 ==>need 4 technicians, cabling, commissioning
⁻ Mechanics,(Mimmo)⁻ Gas (Daniel,AachenTech)⁻ MC installation &commissioning, cooling
commissioning, external NIM muon trigger(Lorenzo&Fabio)
⁻ HV setup (Danielle & Jesus)
7. Commissioning during first week of muon data (outside of the beam).Would need a Filter scan early on.
⁻ This is the best point to decide on the irradiation integration strategy.
• A) extract chamber after muon beam and wait for half filter in October
• B) keep chamber in with only fraction of chamber with HV on, or irradiate at lower HV setting
8. Time for DT with muon data⁻ Move chamber in position ⁻ High stats with various filter points around
HL-LHC levels⁻ HV scan ⁻ Operation⁻ Analysis
7/24/2015
3
I. Redondo
Executive summary
• We were coming from behind⁻ credit goes to the community, large fraction of which,
has make the extra effort to make it happen
• It has been a 2 months sprint… …but we have succeeded to record valuable samples to study:
1. HV currents vs photon irradiation intensityinput for long irradiation program
2. MC Readout response vs photon irradiation intensity3. Muon performance vs
• photon irradiation intensity • Frontend threshold• HV settings
We need to look at the data to see if it is the sample we need or we lack statistics or we need to repeat some of the studies (if opportunity arise).
7/24/2015
4
I. Redondo
Next steps (added after the meeting)
• Study HV current data
• Readout & Trigger Data : list of issues to correct if we reprocess
⁻ YB0 S1 ==> YB0 S2 ⁻ Ndigis <300, Nsegmests <50, alos release cut in number of
hit/layer⁻ Ttrigger 410-==>402⁻ Save more histograms in the root files?⁻ Make sure the PU data is correctly decode⁻ Analyse test pulse run to get t0 uniformity⁻ Check if something has to be done to extract the time
distribution of the beam⁻ …Then we reprocess
• For next test beam: measure precisely external trigger arrival time
7/24/2015
5
I. Redondo7/24/2015
Vertically, chamber acceptance starts 37 cm from the floor
Horizontally chamber acceptance starts 155 cm from the beam, asymmetric
7
I. Redondo
Muon Beam Impressions• First week of beam: out of the beam, low intensity (200mu/spill)• Second week: in the beam(at last), share source status with
Atlas_RPC⁻ Until Friday morning: larger intensity (4000/spill), large contamination⁻ After Friday evening: lowish intensity (600 mu/spill), low contamination⁻ Last day of our week graciously given to CSC
7/24/2015
Muon track
Showers: our event displays helped optimize the beam
Horizontal coo.
Vertical coo.
Horizontal coo.
Horizontal coo.
Horizontal coo.
8 Muon distribution for one track events
Before Friday~1/2 shower contamination
After FridayLow shower contamination
If we get another muon beam it t would be extremely useful to give fast feedback to the line operator since the beam was not optimal in terms of intensity (low) and contamination:• Contamination fraction• beam spot• extract the time distribution of the beam
9
I. Redondo7/24/2015
Data samples
Higher stats samples (typically 1 h/runs, 50k-100 k triggers each run)
http://dt-sx5.web.cern.ch/dtsx5/Results/GIF2015/runtables_dtgif2015_scans.html
TDC SEU ntocieable at F10
F100 is HL-HLC background level
10
I. Redondo7/24/2015
Data sampleshttp://dt-sx5.web.cern.ch/dtsx5/Results/GIF2015/runtables_dtgif2015_scans.html
11
I. Redondo
To search Information
• https://twiki.cern.ch/twiki/bin/view/CMS/DtGIFHV
• DT Gif++ elog• Gif++ elog http://noite01.cern.ch/• Summary tables produced by Oscar &Gianni
with links to PoA directories ⁻ http://dt-sx5.web.cern.ch/dtsx5/Results/GIF2015/runtables_dtgif2015_scans.html
• Excel sheet sheet filled by the shifters with Jesus' form with all the data taking conditions https://docs.google.com/spreadsheets/d/12V7gdTnhpQiOX_dfW77Aii_Kdol10828JN5oDp8pRVo/edit#gid=516798429
• Data products generated by shifters using Cruz/Anna/Cristinas’ codes:
⁻ POA plots⁻ POA root files (2)⁻ DT ntuple
7/24/2015
12
I. Redondo
To work at Gif++1. Dosimeter (or temporary dosimeter, 2 months/year validity)
⁻ To enter the bunker active dosimeter, to be asked in b55
2. Two EDH access request: (Niels back from vacation)⁻ GIF++ Zone Turnstile (EHN1-GIF) (i.e. “bunker”)⁻ Control Room HNA-487 (0887-1-R87)
• In order to access to the Control Room HNA - 487 (0887-1-R87) by means of an ID card, after EDH approval it is needed also to 'activate' the ID card monthly, by one of the many READERS available at Prevessin. One is in the cafeteria at 1st floor of bld 887 (first floor, Jura side).
• Toilets are on the Jura side, first floor.
3. Follow e-courses (https://sir.cern.ch/sir/f?p=106:1:213917875603410)⁻ CERN Beam Facilities (12 min e-course)⁻ CERN Safety introduction⁻ CERN Radiation Protection-Supervised area”
4. Safety shoes+helmet are mandatory already in the hall ⁻ also in bunker
5. To enter bunker, ask Daniel Teyssier to be included in the impact #63162
https://impact.cern.ch/impact/secure/index.gsp?place=editActivity:63162
NB: Shifters do not need to enter the bunker
7/24/2015
13
I. Redondo
Gif++ is in Prevessin bat 887
1. Dosimeter (or tempora
7/24/2015
Lab entranceHall entrance
16
I. Redondo
Asynchronously, also during July:
a. Transport chamber horizontally and rotate at Gif++ ok
b. Define HV setup (have to be ready before the 12th) (Danielle&Jesus) okish
c. HV current data analysis: overall trend, but also discharges okish
d. Temperature data (from MC, other?) analysis okish
e. prepare Computer setup at Gif, ethernet
connections, (Lauri,Summer student) ok
f. Prepare offlline analysis of DT data (Cruz) ok
g. Define measurement program: ⁻ Filter scan (chamber
response to photons)⁻ Noise study (Performance
of chamber at HL-LHC)⁻ Study lower HV setpoint
under noise⁻ Performance after ~HL-
LHC integrate dose (HV currents& chamber performance)
7/24/2015
17
I. Redondo
Availability at CERN (each digit a week, empty unknown)
Domenico Dattola 1111 11Giorgio Cotto 1111 11Vincenzo Giordano 0000 1100Francisco Yañez 1000 0000David Francia 0000 1100AachenTech 0000 0100Jesus Puerta 0000 0100 Possible ==> 12/08.Cristina Fernandez August from remoteIgnacio Redondo 1111 0011 Possible 12/08==> Daniel Teyssier 0111Gianni Masetti 0001Luigi Guiducci 0000 1110 Partially (L1 DOC) Marco Dallavalle 0101Daniele Fasannella 0000 1110Fabio Montecassiano 0000 0100 (also remote beginning of 0000 0010 )Lorenzo Barcellan 0000 0100Lauri Hamarik (summer student) 1111 1111Maria Del Ma Barrio(CIEMAT student) 0000 0010 (18-26/08)Mary Cruz Fouz 1111 1000 (remote)Francesca Cavallo 0000 1100 (partially)7/24/2015
18
I. Redondo
Operation during Muon Beam (26/8 17:00-1/9 8:00)
1. Operation of the filter from controller in Gif++ control room.⁻ We have to learn and document how
to use it. ok
2. Muon beam: ⁻ procedure to interact with Gif
community and accelerator operators to fix the muon/spill to what we need
3. Operation of the "DAQ“⁻ Franco labview, there is manual,
Daniel Teyssier knows how-to) ok
4. Transfer of data analysis area (dtdqm workspace in lxplus?) tbd
5. Shifter calendar, training, transport (navette Prevessin) tbd
Data taking program
6. We need to schedule one or several filter scans between the time the chamber is operational (~14/8) and the beginning of the muon beam (for CSC) on 19. Afterwards it will be difficult to do that until our beam time on the 26.⁻ One filter scan just to see the HV
currents vs filter can be done even if the Minicrate and data taking is not working
⁻ A second one with longer integration times to measure background noise from the data stream
7. Once the analyse for muons is working( after the 26) we can scan in HV settings. It would be nice to have defined what we would like to do maximally. How many muons per HV setting point, which ranges we want to explore in each of the 3 quantities,...etc.7/24/2015
20
I. Redondo
Beam trigger
3/11/2015
64 NIMoutputs
Discriminator
Coincidence
ATLAS-RPC trigger
Scalers unit
CAEN 6 U crate for LVDS trigger
21
I. Redondo
Beam trigger II
• Official Experts :⁻ Yan Benhammon & Gaetan Lieb(leaving)⁻ Users are customizing
• NIM signal• Upstream and downstream scintillators with
118ns/195.5ns, TOF expected ~ 50 ns, coincidence window ~40 ns
⁻ Latency ~200 ns?
7/24/2015
25
I. Redondo
Area prepared for installation, cable layed along cable tray
7/24/2015
• Rails are now installed in final position and anchored on the GIF Bunker false floor structure and tiles.
• All the cables, gas and cooling tubes has been installed and organized in 4 corrugated tubes to easily allow move of the Chamber.
• In this next days we planned to complete the services ancillaries parts and set up all the equipment required for Chamber operation.
• The installation start Wednesday 12th ; cabling of should be completed by Thursday 13th.
27
I. Redondo
News
• Chamber moves! Two last rails sections ready, assembled on support platform.
⁻ Rails be installed August 5, Mimmo coordinates installation.
• Chamber to be installed following week, August 12th.
• Lights in bunker has been moved up• RP clearance for the new (shorter) passage
⁻ Nicolas B. have scheduled the beginning of cable tray installation next Wed 29/7 8h30 material did not arrived, move to August5th
⁻ Expected duration is half a day, 2 hours⁻ 2pm-4pm to install the first cables not possible
Agreed with Gif++ management August 5th shutdown may be extended to August 6th morning.
7/24/2015
28
3/11/2015
I. Redondo
~Beam coordinate on floor
5m rail
Installation of MB1 chamber in Gif++ for August
• Performance of chamber at HL-LHC noise levels• Study lower HV setpoint under noise
• Performance after ~HL-LHC integrate dose ⁻ HV currents & chamber performance
Installation of mechanical support (“rails”) well advanced
29
I. Redondo
News• Safety document IESEC submitted • First piece of rail (5m) finished today!
⁻ Amazing effort from Mimmo, Giorgio, Sandro, Abdel and Yañez.
⁻ Transported 8/7/15 morning
• Drilling on the floor by Torino mechanics (Riccardo&Fabio) finshed on time on same day noonish
⁻ Floor plates fixed to the floor⁻ 5 m rail located in position next to North
Wall, as requested by CSC.⁻ When the 2 other short pieces and
interfaces are ready we should ask the CSC to move again, if we are to reach the Muon beam
⁻ try to make it coincide with a planned CSC movement in July
• Passage for cables will not be ready for this week
⁻ Pending RP approval⁻ Will install cables some Wednesday in July
when passage ready7/24/2015
30
I. Redondo
News
• Lights in bunker has been moved up• RP clearance for the new (shorter) passage
⁻ Nicolas B. have scheduled the beginning of cable tray installation next Wed 29/7 8h30 material did not arrived, move to August5th
⁻ Expected duration is half a day, 2 hours⁻ 2pm-4pm to install the first cables not possible
• Two last rails sections ready⁻ To be installed August 5 after checking movement with
chamber at P5 next week ⁻ In preparation, we have labeled and uncabled SX5
chamber today• Gas and cooling will be disconnected next week
7/24/2015
31
I. Redondo7/24/2015
~Beam coordinate on floor
Back CSC trolley2.2 mx 0.9 m
Will be on ~ half m legs to reach beam
Rails limit its movement, no
conflict with rails when in position,
5m rail
This row of plates (5) have been fixedTo the floor I-beams on the left, will be clamped (required holes drilled) on the right
Thanks to the installation team!