1 land development

Upload: ammahi789

Post on 05-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 1 Land Development

    1/46

  • 8/2/2019 1 Land Development

    2/46

    1

    Table of Contents

    TABLE OF CONTENTS .............................................................................................................................. 1

    LIST OF TABLES: ..................................................................................................................................... 3

    LIST OF FIGURES: .................................................................................................................................... 3

    INTRODUCTION: .................................................................................................................................... 5

    1. SITE ANALYSIS ................................................................................................................................. 7

    1.1. COMMUNITY PROFILE: ....................................................................................................................... 7

    1.2. VEGETATION: ................................................................................................................................... 8

    1.3. SOLAR ORIENTATION: ........................................................................................................................ 8

    1.4. TEMPERATURES: ............................................................................................................................... 9

    1.5. PREVAILING WIND............................................................................................................................. 9

    1.5.1. WINTER: ................................................................................................................................................. 9

    1.5.2. SPRING:................................................................................................................................................. 10

    1.5.3. SUMMER: .............................................................................................................................................. 10

    1.5.4. AUTUMN: .............................................................................................................................................. 10

    1.6. HYDRO-GEOLOGY ........................................................................................................................... 10

    1.7. PUBLIC INFRASTRUCTURE: ................................................................................................................. 11

    1.8. PUBLIC SERVICES............................................................................................................................. 111.8.1. EDUCATIONAL SERVICES ........................................................................................................................... 11

    1.8.2. HEALTH SERVICES.................................................................................................................................... 12

    1.8.3. COMMERCIAL SERVICES: ........................................................................................................................... 12

    1.8.4. TRANSPORTATION SERVICES: ..................................................................................................................... 12

    2. SUBDIVISION DESIGN: ................................................................................................................... 13

    2.1. SUBDIVISION PARTS: ....................................................................................................................... 13

    2.1.1. GREEN AREAS: ........................................................................................................................................ 13

    2.1.2. LOCAL SHOPPING CENTER: ........................................................................................................................ 13

    2.1.3. INTERNAL STREET SYSTEM: ........................................................................................................................ 13

    2.1.4. VILLAS AND MULTI STORIES BUILDINGS: ...................................................................................................... 14

    2.2. SURROUNDINGS: ............................................................................................................................ 14

    3. ENVIRONMENTAL IMPACT STUDY .................................................................................................. 15

    3.1. FLORA.......................................................................................................................................... 16

    3.2. FAUNA ......................................................................................................................................... 17

    3.3. AIR POLLUTION .............................................................................................................................. 17

    3.4. NOISE POLLUTION........................................................................................................................... 18

  • 8/2/2019 1 Land Development

    3/46

    2

    3.5. DISPOSED AREA.............................................................................................................................. 19

    3.6. SOIL CONTAMINATION ..................................................................................................................... 20

    3.7. UNDERGROUND WATER CONTAMINATION: ........................................................................................... 21

    4. WATER SYSTEMS DESIGN ............................................................................................................... 22

    4.1. THEORY: ....................................................................................................................................... 22

    4.2. PRESSURIZED SYSTEMS (WATER SUPPLY): ............................................................................................ 22

    4.2.1. DESIGN CRITERIA: ................................................................................................................................... 22

    4.2.2. CALCULATIONS METHODOLOGY: ............................................................................................................... 23

    4.2.3. RESULTS: ............................................................................................................................................... 24

    4.3. GRAVITY SYSTEMS (SANITARY AND STORM WATER): ............................................................................... 25

    4.3.1. SANITARY WATER: .................................................................................................................................. 25

    4.3.2. STORM WATER:...................................................................................................................................... 28

    5. TRAFFIC IMPACT STUDY ................................................................................................................. 31

    5.1. PURPOSE OF THE STUDY ................................................................................................................... 31

    5.2. EXISTING TRAFFIC ........................................................................................................................... 31

    5.3. EVALUATION OF A ROAD................................................................................................................... 31

    5.3.1. FACTORS THAT THAT AFFECT LEVEL OF SERVICE: ........................................................................................... 32

    5.4. TRIP GENERATION: .......................................................................................................................... 32

    5.5. SAMPLE OF CALCULATION................................................................................................................. 33

    5.6. TRAFFIC VOLUMES .......................................................................................................................... 33

    5.7. ALTERNATIVES ............................................................................................................................... 335.7.1. SIGNS CONTROL SOLUTION: ...................................................................................................................... 33

    5.7.2. UN-SIGNALIZED INTERSECTION: ................................................................................................................. 34

    5.7.3. SIGNALIZED INTERSECTION ( ONLY ONE APPROACH IS SIGNALIZED ) .................................................................. 35

    5.7.4. ROUNDABOUT SOLUTION ......................................................................................................................... 35

    5.7.5. SIGNALIZED INTERSECTION(BOTH APPROACHES ARE SIGNALIZED) .................................................................... 35

    5.8. PREFERRED SOLUTION...................................................................................................................... 36

    5.9. CONCLUSION ................................................................................................................................. 36

    6. GEOMETRIC DESIGN ...................................................................................................................... 37

    6.1. THEORY: ....................................................................................................................................... 37

    6.1.1. GENERAL CONCEPTS: ............................................................................................................................... 37

    6.1.2. HORIZONTAL ALIGNMENT: ....................................................................................................................... 37

    6.1.3. VERTICAL ALIGNMENT: ............................................................................................................................ 40

    6.2. DESIGN CRITERIA: ........................................................................................................................... 42

    6.2.1. UNIVERSITY ROAD: .................................................................................................................................. 42

    6.2.2. LOCAL STREETS: ...................................................................................................................................... 43

    6.3. RESULTS AND TABLES: ...................................................................................................................... 43

    6.3.1. UNIVERSITY ROAD: .................................................................................................................................. 436.3.2. FIRST STREET: ......................................................................................................................................... 44

  • 8/2/2019 1 Land Development

    4/46

    3

    6.3.3. SECOND STREET: ..................................................................................................................................... 44

    6.3.4. THIRD STREET:........................................................................................................................................ 45

    6.3.5MALL STREET: ............................................................................................................................................ 45

    List of Tables:Table 1: Hazen Coefficients for typical pipes .................................................................................................................... 23

    Table 2: Pipes Data as given by Bentley waterCAD .......................................................................................................... 24

    Table 3: Junctions Data ......................................................... ................................................................. ........................... 24

    Table 4: Reservior Data ......................................................... ................................................................. ........................... 24

    Table 5: Manning Coefficient for Typical pipes ................................................................ ................................................. 25

    Table 6: Pipes Data taken from sewerCAD ....................................................................................................................... 27

    Table 7: Manholes Data taken from sewerCAD ................................................................ ................................................ 27

    Table 8: Hand Calculations Results .................................................................................. ................................................. 27

    Table 9: Pipes Data given by stormCAD ................................................................ ............................................................ 30

    Table 10: Inlets Data given by stormCAD ......................................................................................................................... 30

    Table 11: Number of expected trips at peak hours .......................................................... ................................................. 32

    Table 12: Traffic Distribution ............................................................................................................................................ 33

    Table 13: Design criteria for the main road ........................................................................................... ........................... 42

    Table 14: Design criteria for the local roads .......................................................................................... ........................... 43

    Table 15: Horizontal Alignment Data ............................................................................................................................... 43

    Table 16: Superelevation Data.......................................................................................................................................... 43

    Table 17: Vertical Alignment (Profile) Data ...................................................................................................................... 44

    Table 18: Horizontal Alignment Data ............................................................................................................................... 44

    Table 19: Vertical Alignment (Profile) Data ...................................................................................................................... 44

    Table 20: Horizontal Alignment Data ............................................................................................................................... 44Table 21: Vertical Alignment (Profile) Data ...................................................................................................................... 45

    Table 22: Vertical Alignment (Profile) Data ...................................................................................................................... 45

    Table 23: Vertical Alignment (Profile) Data ...................................................................................................................... 45

    List of Figures:

    Figure 1: Local Family ______________________________________________________________________________ 7

    Figure 3: small trees _______________________________________________________________________________ 8

    Figure 2: desert thorn ______________________________________________________________________________ 8

    Figure 4: Solar Orientation __________________________________________________________________________ 8

    Figure 5: Development location and the surrounding services _____________________________________________ 11

    Figure 6: Native plants ____________________________________________________________________________ 16

    Figure 7: Sources of air pollution ____________________________________________________________________ 17

    Figure 8: Disposal areas ___________________________________________________________________________ 19

    Figure 9: Contaminated soil ________________________________________________________________________ 20

    Figure 10: Bioremediation __________________________________________________________________________ 20

    Figure 11: Soil Containment ________________________________________________________________________ 20

    Figure 12: Phytoremediation________________________________________________________________________ 20

    Figure 14: Synchro simulator _______________________________________________________________________ 35

    Figure 15: Horizontal Curve Parameters _______________________________________________________________ 38

    Figure 16: Horizontal curve parameters _______________________________________________________________ 38

    http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225349http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225349http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225353http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225353http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225390http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225390http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225391http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225391http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225392http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225392http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225393http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225393http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225395http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225395http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225396http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225396http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225397http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225397http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225398http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225398http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225399http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225399http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225400http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225400http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225403http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225403http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225404http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225404http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225404http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225403http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225400http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225399http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225398http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225397http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225396http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225395http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225393http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225392http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225391http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225390http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225353http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225349
  • 8/2/2019 1 Land Development

    5/46

    4

    Figure 17: Superelevation transition __________________________________________________________________ 39

    Figure 18: Crest curve parameters ___________________________________________________________________ 40

    Figure 19: Crest curve parameters ___________________________________________________________________ 41

    http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225404http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225404http://c/Users/XPS/Desktop/Senior%20Project%20P1/FinalReports/Reports/Land%20Development.docx%23_Toc312225404
  • 8/2/2019 1 Land Development

    6/46

    5

    Introduction:

    This part will describe the processes of predesign stages and studies which are

    very important to be help before starting and design problem. These studies and the

    related design problems are explained in summery below:

    1. Site Analysis.Site analysis is very important before starting any work in the desired land to

    be developed. It enables the engineer to know the condition of the land in terms of

    environment, soil and ground water, the community which will benefit from this

    land, and the all public services (i.e. educational, health services, etc.) around the

    land.

    2. Subdivision Design.After knowing and stating all mentioned parameters, it will be easy to do the

    subdivision and urban planning. Subdivision design is to locate and orient the

    buildings according to the requirements studied in site analysis, to define the

    alignments of streets and pipe systems, and to define the location of the green areas

    considering that this land development is environmental friendly.

    3. Environmental Impact Study.This part is so important knowing that the world is directed to consedering the

    effect of any human activty. EIS is to study the effect of this project on the

    surrounding environment in terms of flora, funa, air quality, noise, soil, and

    underground water.

    4. Water systems design.Any presence of human being, water supplement and drainage should be taken

    in consederation. This project will solve the water systems (i.e. water supplement,

    sanetary water drainage, and storm water drainage) design problems.

  • 8/2/2019 1 Land Development

    7/46

    6

    5. Traffic Impact Study.Any human activity needs transportation regardless to the mode of

    transportation. This part will study the affect of land users mobile movements on the

    existing traffic. And to finde a solution if any problem presents in terms of traffic

    quality and accessibility.

    6. Roadway Geometric Design.To make the mobile movements easy and safe roads should be designed and

    paved in safe and efficient way. Geometric design of the road is to design vertical and

    horizontal curves, and cross sections.

  • 8/2/2019 1 Land Development

    8/46

    7

    1.Site Analysis1.1. Community profile:

    This part of study will classify the people who will live in the new

    development into different categories taking in consideration their ages, financial

    situation, their careers and social status. This will help a lot in the housing issues.

    Having a quick survey and study of the people who are living in the surrounding

    areas can really give an estimation of the people who will live in the new

    development that will be built.

    As Shown in the figure above the average family members in the surrounding

    area vary from 5 to 6 members plus a servant and a driver and sometimes none of

    these exists. This is considered as an ideal family for local people who live in Villa.

    The villas are found in Mughaidir Suburb including (Turfana, Al Rifaa, Al Darari,Al Talaa, Al Shahba and AlKhezammia). This type of families has a very good

    financial status. One family can have three cars.

    The four-member family is the ideal example to the families living in the new

    buildings on the both sides of the 5th

    Industrial Road. Some of these families (Doctors

    and Teachers families) live in the villas within the University City. Their financial

    status ranges between the medium and high level. Most of these families have one

    car.Most of the single students live in the men

    hostel and the women hostel in Sharjah University

    and the American University of Sharjah. Some of

    the students have been found living in the new

    buildings on the side of Al Madaen Road

    extension going to Sharjah University City. They

    have a medium or good financial status. Some of

    these students use the university buses in their wayfrom and to the university. Some of these students

    have cars.

    These layers of families can give a future view for the social situation and the

    families that will be found living in the new development and will help us a lot in the

    designing process.

    Figure 1: Local Family

  • 8/2/2019 1 Land Development

    9/46

    8

    1.2. Vegetation:Vegetation is a general term for the plant life of a region; it refers to the ground

    cover provided by plants .So this part related to the type of the plants, trees and grass

    within or around our development.

    Most of the existing plants are desert plants, such us small trees that grows

    Beside (small water lakes) also there are other types of plants can adopt themselves to

    live on the sand-hills around the site, however there is a lot of desert thorn within the

    site.

    In addition to that there is a wonderful green cover spreads in the UniversityCity which is very close to the development.

    In the development there will be a big park include Plame trees and different

    types of flowers and plants. however, this plants will be provided with a very good

    irrigation system to be able to grow and survive during the hot weather. Also this

    green cover will provide the development with very nice view.

    1.3. Solar orientation:Correct solar orientation adds significantly to

    the comfort of the lifestyle of a building's occupants,

    increasing the energy efficiency & will be cheaper

    looking for the long-term cost. Being able to control

    the amount of sun that enters a building is an

    important design aspect.

    Figure 2: small treesFigure 3: desert thorn

    Figure 4: Solar Orientation

    http://en.wikipedia.org/wiki/Ground_coverhttp://en.wikipedia.org/wiki/Ground_coverhttp://en.wikipedia.org/wiki/Ground_coverhttp://en.wikipedia.org/wiki/Ground_cover
  • 8/2/2019 1 Land Development

    10/46

    9

    The sun also rises-up and sets in the North-East and North-West in winter and

    rises-up and sets in the South-East and South-West in summer. This fact can also be

    used in the design of a building to control the amount of sunshine entering a building.

    The amount of sunlight in summer and winter is also dependent on the latitude

    of the site. The further away from the equator the greater the variation in sunlightbetween summer and winter. At the north and South Pole there is constant day in

    summer and constant night in winter. At the equator the sun goes from north

    orientation in winter to south orientation in summer.

    1.4. Temperatures:The summer months, from June to September, are too hot for comfort. Midday

    temperatures range from 35C to 42C, and occasionally top 51C at the height of

    summer. During this period there is a sharp drop in night time temperatures, with

    these falling to roughly half the midday readings, i.e. 16C to 23C, and providing a

    welcome respite from the searing heat of the day. Gulf waters exert a modifying

    influence on coastal zones, which experience less dramatic diurnal fluctuations in

    temperature, and higher humidity than inland regions.

    Although the evenings are not so cool, coastal towns do have the advantage ofpleasantly refreshing sea-breezes. Mountainous regions are also cooler and less

    humid. From December to March, the climate is considerably more equable with

    midday temperatures ranging from 25 to 35C and falling to as low as 9C at night.

    1.5. Prevailing windThis section studies the blowing directions and the speeds of the winds during

    the four seasons of the year. This helps in Designing the buildings and effect on the

    climate in the long-term period.

    1.5.1.Winter:Northwesterly wind called (Al-Shamal) is the local name. Land breeze is 4 to 8

    knots southeasterly. Sea breeze is an 8 to 13 knots west to northwesterly. It sets in by

    midday and dies quickly after sunset. Northern Emirates winds more than 100kilometers away can sometimes be seen. Mean wind speed in excess of 20 knots is

  • 8/2/2019 1 Land Development

    11/46

    10

    rare and usually only for a few hours. During thunderstorms, gusts of more than 70

    knots have been recorded.

    1.5.2.Spring:The sea breeze phenomenon tends to be stronger during the spring because of

    the higher land sea temperature contrast (Variation). On rare occasions, a strong

    southeasterly wind can overcome the sea breeze causing high temperatures and low

    humidity. At the end of May the Forty Days Shamal often becomes the major

    feature of the weather.

    1.5.3.Summer:The northwesterly wind strengthens over the Arabian Gulf and this increase in

    frequency and persistence of the northwest wind is known as the Forty Day

    Shamal.

    1.5.4.Autumn:Winds are generally light. Land Sea breezes being weak during this period.

    During November the winds moves from the mountains to the north and east.

    1.6. Hydro-GeologyThe ground-water level in the area consisting of the University City, especially

    the University of Sharjah, the old waste disposal site, and other surrounding areas

    has been elevated locally. At the University of Sharjah, the high groundwater level

    has caused serious flooding problems in some of the underground the basements.

    Fluctuations in the groundwater level pose a risk to the structural integrity of the

    University Buildings. The causes of the rising water table in the area may be

    attributed to the following factors:

    Excessive Irrigation Expansion of Green Areas

  • 8/2/2019 1 Land Development

    12/46

    11

    1.7. Public Infrastructure:This is composed of any networks below the soil surface such as waste water

    pipes, drainage pipes, electricity pipes, manholes and in our site that electricity

    station satisfies the needs of the university city and Al Falah Military Camp and

    moreover, The residential buildings and shops. And for the waste water station

    Plant which is close to our site will Serve our development and will serve also the

    residential buildings and University City and Al Falah Military Camp and its

    connected with the sewerage connection already designed with in this project, and for

    the local phone calls for the whole area its connected with Etisalat Cables which are

    located underground.

    1.8. Public servicesNow in this section we are going to discuss some of the facilities that available

    for our residential area (see fig 6):

    Figure 5: Development location and the surrounding services

    1.8.1.Educational servicesFor educational services there are many schools near to the area for different

    levels (primary, preparatory & secondary) & there are universities (Sharjah

  • 8/2/2019 1 Land Development

    13/46

    12

    University & American university of sharjah) which they have many different

    colleges.

    1.8.2.Health servicesFor health services there are two hospitals near the area which are Sharjah

    university hospital & Al-Malaky hospital. They are prepared with the modern

    equipment and successful doctors.

    1.8.3.Commercial services:For commercial needing, a mall will be built inside the residential area that will

    serve the people living inside & outside the area. The mall will have a big

    hypermarket, banks, Food court, Etisalat office & many other services.

    1.8.4.Transportation services:The area that we have is connected directly to the University City road that has

    an access to the emirates road that connects all the emirates together. In the future the

    municipality is planning to develop the area which will be connected to the public

    line services (busses), a bus station & a parking space for taxis.

  • 8/2/2019 1 Land Development

    14/46

    13

    2.Subdivision design:2.1. Subdivision Parts:

    The developing land has been divided in to several parts and areas explained

    below:

    2.1.1.Green areas:Green areas will be divided into two types: small parks inside each villas and

    the main park within the development area. The main park with area = 13270 m2.

    However, the green areas will help in reducing the air and sound pollution and soil

    erosion. It located in south western direction form the center of the development.

    2.1.2.Local shopping center:Shopping center is to be provided to the development with area = 2937 m

    2.this

    shopping center will help the residents to obtain their needs and provide the

    development with additional importance. It located in north eastern direction form

    the center of the development.

    2.1.3. Internal street system:The main objective of the streets in this subdivision is to connect the utilities to

    each other and to the outside facilities. There are two accesses: one for entering and

    the other for exiting. In terms of functional classification of streets there are two

    types has been selected:

    Local: for the internal traffic, with very low design speed of 60 km/h. Theyhave a bicycle lane and walkway lane bounded by line of native trees to reduce

    the traffic noise.

    Collector: for the main road outside the development with medium designspeed of 80 km/h.

  • 8/2/2019 1 Land Development

    15/46

    14

    2.1.4.Villas and multi stories buildings:There are two types of villas:

    43 villas with area of 242m2 for each. 2 villas with area of 540 m2 for each.

    Villas are distribution in eastern side of the development

    In addition to that there is two multi stories buildings with (G+4) one with area

    equal to 1388.5m2

    and the other with area equal to 1628.4 m2

    and located in the

    western side of the development.

    2.2. Surroundings:The subdivision design, which we are going to develop, is in tradition with

    surrounding neighborhoods.

    The development is almost close to the main city of sharjah. And At theboundaries major streets provide good access to other nearest neighborhood.

    its connected to the main city by several arterials road such as Sh. Khalifa ben

    Zaiyed road, Emirates road and airboat road.

    Also the development is very close to the university city and there are manyschools close to the development in addition to many restaurants and shopping

    markets close to the unit.

    Those facilities reduce the traffic movement and then the residents will depend

    on public trans and unmortised trans to reach to their destination and services.

  • 8/2/2019 1 Land Development

    16/46

    15

    3.Environmental Impact StudyAn environmental impact study is a study of the possible positive or negative

    impact that a proposed project may have on the environment, together consisting of

    the natural, social and economic aspects.

    The purpose of the study is to ensure that decision makers consider the ensuing

    environmental impacts when deciding whether to proceed with a project. So it could

    be said that this process for identifying, predicting, evaluating and mitigating the

    biophysical, social, and other relevant effects of development proposals prior to

    major decisions being taken and commitments made.

    There are different positive andnegative impacts on the environmental

    either before or after construction. But

    the Environmental Impact of Building

    Construction can now be predicted.

    For example, the effects of

    environmental pollutants such as

    carbon dioxide (CO2), nitrogen oxides

    (NO2) and sulfur oxides (SO2) areknown to be detrimental to human,

    health, nature and to the air.

    The factors which may effect on the environment of the land are:

    Fauna. Flora. Air pollution. Noise pollution. Underground water. Soil. Disposed area.

    These factors will be explained afterward.

  • 8/2/2019 1 Land Development

    17/46

    16

    3.1. Flora

    Flora indicates the plants that are in a specific area and what are the types of

    those plants.

    The word "flora" refers to the plants occurring within a given region as well as

    to the publication of scientific descriptions of those plants. In order to distinguish

    between the two, the word is often capitalized when a publication is meant. A Flora

    may contain anything from a simple list of the plants occurring in an area to a very

    detailed account of those plants. Floras are different from popular manuals in that

    they attempt to cover all of the plants, rather than only the most common or

    conspicuous ones.

    In this site a survey has been made to get more information about the types of

    plants which exist how can they vary. The result found that these are numerous kinds

    of them and they depend on the underground water to still alive and also on the sun to

    get the energy they need to produce their food. In addition to that the temperature and

    the moisture are high however those types of plants can adopt with that weather.

    While making our land development and our layouts and design we should

    take that under consideration and to ensure that we are preserving those plants

    because plants are very useful in this environmentally friendly development they willtake off the CO2 and it will emit O2 which will makes our climate more clear and

    more healthy, thats why we should preserve and maintain those areas in our layout

    and also to increase the green areas due to its benefits.

    Figure 6: Native plants

  • 8/2/2019 1 Land Development

    18/46

    17

    3.2. FaunaFauna is all of the animal life of any particular region or time; Fauna includes

    all the types of species of animals (i.e. mammals, reptiles, birds, amphibians and fish)

    that exist in one particular place.

    In this site also a survey has been made and it is concluded that there is no

    existence of dangerous species in this locations, especially if it was used to be an old

    land fill.

    Regarding to the other species such as insects and jerboas the locality of the

    development considered this issue in order not to affect their existence.

    3.3. Air Pollution

    Air pollution is the introduction of chemicals, particulate matter, or biological

    materials that cause harm or discomfort to humans or other living organisms, or cause

    damage to the natural environment or built environment, into the atmosphere. Air

    pollution occurs when the air contains gases, dust, fumes or odor in harmful amounts.

    Those amounts could be harmful to the health or comfort of humans and animals or

    which could cause damage to plants and materials.

    In this site the major source of the air pollution are Gases emissions caused

    by cars or buses exhaust and gas outside the nearby industrial area of the region such

    as carbon nitrogen and sulfur oxides.

    In this development, the reduction of air pollution will be taken into

    consideration green areas and gardens cultivation, and by separating residential areas

    from the street by a suitable space to reduce the arrival of toxic gases from cars and

    buses.

    Figure 7: Sources of air pollution

    http://en.wikipedia.org/wiki/Animalhttp://en.wikipedia.org/wiki/Animal
  • 8/2/2019 1 Land Development

    19/46

    18

    3.4. Noise PollutionNoise pollution is a mixture of discordant

    sounds of continuity is desirable, and usually

    occurs due to industrial progress, linked to noise

    pollution or noise is closely linked to places in the

    advanced industrial and private places. And it is

    usually measured sound level measurements, and

    dB (decibel) unit is known worldwide for

    measuring the intensity of sound and noise.

    High noise levels can contribute to cardiovascular effects and exposure to

    moderately high levels during a single eight hour period causes a statistical rise in

    blood pressure of five to ten points and an increase in stress [and vasoconstrictionleading to the increased blood pressure noted above as well as to increased incidence

    of coronary artery disease.

    In this site the major source of the Noise pollution is Sound resulting from

    the aircraft movements "Aircraft noise" because of the near airport. Also the other

    source for noise pollution is "car and buses noise" because of the near main street

    from our area. However, there is noise resulting from the industrial zone near to the

    area but still very low.

    In this development, the noise reduction has been taken in consideration by

    providing buildings with sound insulation system such as dual-layer glasses for

    windows and sound insulator blocks. Also a green tree belt will be grown around the

    buildings that needed to be calm.

  • 8/2/2019 1 Land Development

    20/46

    19

    3.5. Disposed area

    Soil is a natural body consisting of layers of mineral constituents of variable

    thicknesses, which differ from the parent materials in their morphological, physical,chemical, and mineralogical characteristics. Strictly speaking, soil is the depth of

    regolith that influence and have been influenced by plant roots.

    Soil is composed of particles of broken rocks which have been altered by

    chemical and mechanical processes that include weathering and erosion. Soil differs

    from its parent rock due to interactions between the lithosphere, hydrosphere,

    atmosphere, and the biosphere. It is a mixture ofmineral and organic constituents that

    are in solid, aqueous and gaseous states. Soil is commonly referred to as earth or dirt.

    Soil forms a structure that is filled with pore spaces, and can be thought of as a

    mixture of solids, water and air.

    This site was used to be as a disposal area in the past because it was far from

    the city, but now due to expansion of urban ,this made the area desirable to be build

    & used. As a result, the soil & the underground water were polluted by chemicals &

    solids came from the wastes.

    Figure 8: Disposal areas

    http://en.wikipedia.org/wiki/Mineralhttp://en.wikipedia.org/wiki/Geomorphologyhttp://en.wikipedia.org/wiki/Mineralogicalhttp://en.wikipedia.org/wiki/Rock_(geology)http://en.wikipedia.org/wiki/Weatheringhttp://en.wikipedia.org/wiki/Erosionhttp://en.wikipedia.org/wiki/Lithospherehttp://en.wikipedia.org/wiki/Hydrospherehttp://en.wikipedia.org/wiki/Atmospherehttp://en.wikipedia.org/wiki/Biospherehttp://en.wikipedia.org/wiki/Mineralhttp://en.wikipedia.org/wiki/Organic_matterhttp://en.wikipedia.org/wiki/Dirthttp://en.wikipedia.org/wiki/Dirthttp://en.wikipedia.org/wiki/Organic_matterhttp://en.wikipedia.org/wiki/Mineralhttp://en.wikipedia.org/wiki/Biospherehttp://en.wikipedia.org/wiki/Atmospherehttp://en.wikipedia.org/wiki/Hydrospherehttp://en.wikipedia.org/wiki/Lithospherehttp://en.wikipedia.org/wiki/Erosionhttp://en.wikipedia.org/wiki/Weatheringhttp://en.wikipedia.org/wiki/Rock_(geology)http://en.wikipedia.org/wiki/Mineralogicalhttp://en.wikipedia.org/wiki/Geomorphologyhttp://en.wikipedia.org/wiki/Mineral
  • 8/2/2019 1 Land Development

    21/46

    20

    3.6. Soil contaminationSoil contamination is caused by the presence of human-made chemicals or

    other alteration in the natural soil environment.

    There are several principal strategies for remediation:

    1. Excavate soil and take it to a disposal site awayfrom ready pathways for human or sensitive

    ecosystem contact.

    2. Aeration of soils at the contaminated site (withattendant risk of creating air pollution).

    3. Bioremediation, involving microbial digestionof certain organic chemicals.

    4. Containment of the soil contaminants (such asby capping or paving over in place).

    5. Phytoremediation, or using plants (such aswillow) to extract heavy metals.

    Figure 12: Phytoremediation

    Figure 9: Contaminated soil

    Figure 10: Bioremediation

    Figure 11: Soil Containment

    http://en.wikipedia.org/wiki/Air_pollutionhttp://en.wikipedia.org/wiki/Bioremediationhttp://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://en.wikipedia.org/wiki/Bioremediationhttp://en.wikipedia.org/wiki/Air_pollutionhttp://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=http://www.google.ae/imgres?q=%E2%80%A2Phytoremediation&hl=ar&biw=1024&bih=571&gbv=2&tbm=isch&tbnid=OCE1qODVXpGyzM:&imgrefurl=http://arabidopsis.info/students/dom/mainpage.html&docid=z9BfDW9bwSA_pM&imgurl=http://arabidopsis.info/students/dom/phyto1.jpg&w=450&h=336&ei=bNzDTrPlJI3KtAa_o7zSCw&zoom=
  • 8/2/2019 1 Land Development

    22/46

    21

    3.7. Underground water contamination:Groundwater contamination occurs when man-made products such as gasoline,

    oil, and chemicals get into the groundwater and cause it to become unsafe and unfitfor human use.

    So the site has contaminated underground water from the wastes which might

    rise to a level that will affect the foundations of the buildings that will be built in the

    project.

  • 8/2/2019 1 Land Development

    23/46

    22

    4.Water Systems Design4.1. Theory:

    Water pipes systems could be divided into two main types:

    1. Pressurized systems2. Gravity systems

    Pressurized systems are depending on the head pressure between the system

    components in order to maintain a steady-state flow. It is used mainly in water

    supplement systems.

    On the other hand, the gravity systems are depending on the gravitational force

    to maintain the flow. It is mainly used in drainage systems such as sanitary and storm

    water.

    4.2. Pressurized Systems (Water Supply):The water network pipes distribution was designed as a loop, in order to

    perform maintenance, if needed without disconnecting any part in the network.

    The water demand is calculated by determining the number of houses, number

    of multistory buildings, then calculating the number of persons and the water need

    per person on each junction.

    And by inputting the demand and the elevation of the junctions, then assuming

    the diameters of the pipes and the elevation of the reservoir on the waterCAD, then

    the waterCAD calculated the velocity in the pipes and the pressure on the junctions.

    4.2.1.Design Criteria:The Constraints were to make the pressure on the junction at least 1 bar.

    1. The pipes are 150 mm diameter.2. Maximum pipe velocity is: 2.37 m\s.3. Minimum pipe velocity is: 0.2 m\s.4. Maximum junction pressure is: 143.55 Kpa.5. Minimum junction pressure is: 249.59 Kpa.

  • 8/2/2019 1 Land Development

    24/46

    23

    6. Reservoir level: 165 m.4.2.2.Calculations Methodology:

    To calculate the diameter of the pipes in

    water supplement system there are two

    equations:

    1. D'Arcy-Weisbach Equation for Pressureand Head Loss.

    2. Hazen-Williams Equation - calculatingFriction Head Loss in Water Pipes.

    DArcys low stated that the pressure loss

    in a pipe is calculated by:

    , where: p = pressure loss(Pa, N/m

    2), = D'Arcy-Weisbach friction

    coefficient, l = length of duct or pipe (m), dh =

    hydraulic diameter (m), and = density (kg/m3).

    The D'Arcy-Weisbach equation is valid for fully

    developed, steady state and incompressible flow.

    The friction factor or coefficient - -depends on the flow, if it is laminar, transient or

    turbulent (the Reynolds Number) - and the roughness of the tube or duct. The friction

    coefficient can be calculated by the Colebrooke Equation or by using the Moody

    Diagram. The disadvantage of this equation is that it needs to do iterations to reach to

    the optimum diameter unlike Hazens equation but it still more accurate.

    Hazen-Williams Equation is an empirical and straight forward equation to

    calculate and avoid the iteration and, trial and error process. It is states that the head

    loss is calculated by: , where p = pressure loss over a length of pipe(m), L = length of pipe (m), Q = volumetric flow rate (m

    3/s), and d = inside pipe

    diameter, m (meters).

    To calculate the flow, the demand per person per day should be known

    depending on statistics and surveys done on similar areas.

    Table 1: Hazen Coefficients for typical pipes

    Material Hazen-WilliamsCoefficient

    Asbestos Cement 140

    Brass 130 - 140

    Brick sewer 90 - 100

    Cast-Iron - new unlined

    (CIP)130

    Cast-Iron 10 years old 107 - 113

    Cast-Iron 20 years old 89 - 100

    Cast-Iron 30 years old 75 - 90

    Cast-Iron 40 years old 64-83

    Cast-Iron, asphalt coated 100

    Cast-Iron, cement lined 140

    Cast-Iron, bituminous lined 140

    Concrete 100 - 140

    Copper 130 - 140

    Fiber Glass Pipe - FRP 150

    Galvanized iron 120

    Polyvinyl chloride, PVC,

    CPVC150

  • 8/2/2019 1 Land Development

    25/46

    24

    4.2.3.Results:Table 2: Pipes Data as given by Bentley waterCAD

    Table 3: Junctions Data

    Table 4: Reservior Data

    LabelLength

    (m)

    Diameter

    (mm)Material

    Discharge

    (m/day)

    Upstream

    Structure Hydraulic

    Grade

    (m)

    Downstream

    Structure Hydraulic

    Grade

    (m)

    Pressure Pipe

    Headloss

    (m)

    Headloss Gradient

    (m/km)

    Velocity

    (m/s)

    P-1 22.56 50 PVC 402 165 162.66 2.34 103.62 2.37

    P-2 165.2 50 PVC 176 162.66 158.97 3.69 22.36 1.03

    P-3 121.31 20 PVC 30 158.97 149.95 9.02 74.37 1.11

    P-4 78.33 20 PVC 18 149.95 147.81 2.14 27.33 0.65

    P-5 117.96 20 PVC -8 147.81 148.49 0.69 5.83 0.28

    P-6 209.7 20 PVC -23 148.49 157.92 9.43 44.97 0.85

    P-7 143.87 50 PVC -59 157.92 158.35 0.42 2.94 0.35

    P-8 120.7 50 PVC -226 158.35 162.66 4.32 35.76 1.33

    P-9 198.12 20 PVC -5 158.35 158.97 0.62 3.14 0.2

    P-10 78.64 20 PVC 41 158.97 148.49 10.48 133.21 1.52

    Label

    Elevation

    (m) Type

    Demand (Calculated)

    (m/day)

    Calculated Hydraulic Grade

    (m)

    Pressure

    (kPa)

    J-1 137.16 Demand 0 162.66 249.59

    J-2 131.06 Demand 99 158.97 273.1

    J-3 128.02 Demand 13 149.95 214.63

    J-4 128.02 Demand 25 147.81 193.68

    J-5 131.06 Demand 57 148.49 170.57

    J-6 143.26 Demand 36 157.92 143.55

    J-7 141.73 Demand 173 158.35 162.6

    Label Elevation (m) Inflow (m/day) Calculated Hydraulic Grade (m)

    R-1 165 -402 165

  • 8/2/2019 1 Land Development

    26/46

    25

    4.3. Gravity systems (Sanitary and Storm Water):Sanitary and storm water drainage

    systems are dependent on slop of the pipes

    systems which allow the gravity force to

    function to move the flow. The task here as

    engineers is to design for the pipes diameter

    and slops according to a specified design

    criteria. Discharge flow in sanitary water

    systems depends on water consumption in

    different buildings. While the flow in stormwater systems depends in the catchment areas

    and land topography, rainfall intensity, and

    land runoff factors.

    4.3.1.Sanitary Water:4.3.1.1. Design Criteria:1. Pipe cover:1.2m.2. Maximum velocity :5m/s.3. Minimum velocity: 0.6 m/s.4. Part full design:75%.5. Maximum slope:0.06 m/m.6. Minimum slope:0.007 m/m.7. Pipe matching: Crowns.4.3.1.2. Calculations Methodology:

    Manning equation is used for calculating the gravity pipes parameters. It states

    that the speed of the flow is given by:

    , and the flow is equal to

    , where = cross-sectional average velocity (ft/s, m/s), kn = 1.486 forEnglish units and kn = 1.0 for SI units,A = cross sectional area of flow (ft

    2, m

    2), n =

    Manning coefficient of roughness,R = hydraulic radius (ft, m), and S = slope of pipe

    (ft/ft, m/m).

    Surface MaterialManning's Roughness

    Coefficient

    Asbestos cement 0.011

    Asphalt 0.016

    Brass 0.011

    Cast-iron, new 0.012

    Earth 0.025

    Earth channel - clean 0.022

    Galvanized iron 0.016

    Glass 0.01

    Gravel 0.029

    Lead 0.011

    Masonry 0.025

    Metal - corrugated 0.022

    Natural streams -

    clean and straight0.03

    Polyvinyl Chloride

    PVC - with smooth

    inner walls

    0.009 - 0.011

    Steel - Coal-tar

    enamel 0.01

    Steel - smooth 0.012

    Table 5: Manning Coefficient for Typical pipes

  • 8/2/2019 1 Land Development

    27/46

    26

    Manning coefficients are represented in table-5. Hydraulic radius can be

    expressed as , where:A = cross sectional area of flow (ft2,m

    2), and P = wetted

    perimeter (ft, m).

    To calculate the discharge flow

    , where: h = number of

    buildings which has the same consumption, C = consumption per each person, P =

    number of population per each building, and PF = consumption peak factor.

    For subsequent pipes the cumulative flow rate should be considered in the

    calculations

    4.3.1.3. Sample of Calculations:Consider the first pipe which connects manhole 1 with manhole 2

    Number of houses h = 10 Number of population per house = 8 Consumption per person per house = 350 (L/d) Peak Factor = 1.5

    o Ground slop = 6.1% Manning coefficient = 0.013 for Asbestoses Concrete

    o Using manning equation:

    o Calculate velocity for full flow (i.e. when D = 2.93 cm)

    o

    o Determine the flow rate Q2 and flow speed 2 for D = 20 cm.

    o

    o Calculate partial flow

    .

    Use the partial flow-velocity graph to find .

  • 8/2/2019 1 Land Development

    28/46

    27

    Determine .4.3.1.4. Results:

    Table 6: Pipes Data taken from sewerCAD

    Table 7: Manholes Data taken from sewerCAD

    Table 8: Hand Calculations Results

    LabelUpstream

    Node

    Upstream Invert

    Elevation (m)

    Downstream

    Node

    Downstream Invert

    Elevation (m)

    Constructed

    Slope (m/m)

    Bend Angle

    (radians)

    Length

    (m)

    Section

    ShapeMaterial

    Section

    Size

    P-1 MH-1 140.63 MH-2 136.95 0.045367 0.01 81.06 Circular PVC 100 mm

    P-2 MH-2 136.95 MH-3 132.1 0.06 0.02 80.95 Circular PVC 100 mm

    P-3 MH-3 132.1 MH-4 131.19 0.007724 1.59 117.68 Circular PVC 100 mm

    P-4 MH-4 131.19 MH-5 130.59 0.007724 1.64 76.77 Circular PVC 100 mm

    P-5 MH-6 132.1 MH-5 130.59 0.012812 0.04 117.23 Circular PVC 100 mm

    P-6 MH-7 136.83 MH-6 132.1 0.06 0.06 78.94 Circular PVC 100 mm

    P-7 MH-8 140.63 MH-7 136.83 0.048517 0.02 78.28 Circular PVC 100 mm

    P-8 MH-5 130.59 O-1 128.9 0.050748 0 33.41 Circular PVC 100 mm

    LabelGround

    Elevation (m)

    Total Flow

    (l/d)

    Hydraulic Grade

    Line In (m)

    Hydraulic Grade

    Line Out (m)

    Velocity

    In (m/s)

    Velocity

    Out (m/s)

    MH-1 141.43 41,990.40 140.24 140.24 0.34 0.34

    MH-2 136.55 79,833.60 135.37 135.37 0.41 0.41

    MH-3 131.98 121,824.00 130.81 130.81 0.45 0.45

    MH-4 132.89 121,824.00 129.75 129.75 0.45 0.45

    MH-8 128.02 1,160,352.00 126.92 126.92 0.77 0.77

    MH-7 131.06 1,038,528.00 129.95 129.95 0.83 0.83

    MH-6 136.55 1,017,532.80 135.44 135.44 0.83 0.83

    MH-5 141.12 179,366.40 139.96 139.96 0.51 0.51

    Pipe From To# of

    houses

    # people /

    house

    Consumption / d / P

    (L/d)P.F.

    Q

    (m3/s)S

    D

    (cm)

    v

    (m/s)

    New Slop

    for v = 0.6 m/sD2 Q2 v2 Q1/Q2 Vp/V2 Vp

    1 MH1 MH2 10 8 350 1.5 0.00048611 6.10% 2.936933 0.718 6.10% 20 0.0810 2.5780 0.0060 0.1 0.258

    2 MH2 MH3 9 8 350 1.5 0.00092361 5.72% 3.781657 0.822 5.72% 20 0.0784 2.4961 0.0118 0.29 0.724

    3 MH3 MH4 10 8 350 1.5 0.00140972 0.91% 6.248507 0.460 1.56% 20 0.0409 1.3031 0.0344 0.46 0.599

    MH5 MH6 7 8 350 1.5MH5 MH6 Center 500 200 1.5

    4 MH5 MH6 0.00207639 1.91% 6.296144 0.667 1.91% 20 0.0453 1.4411 0.0459 0.57 0.821

    MH6 MH7 4 8 350 1.5

    MH6 MH7 2 64 350 1.5

    5 MH6 MH7 0.01177778 3.81% 10.5996 1.335 3.81% 20 0.0640 2.0381 0.1839 0.77 1.569

    6 MH7 MH8 5 8 350 1.5 0.01202083 5.49% 9.975238 1.538 5.49% 20 0.0768 2.4457 0.1565 0.74 1.810

    7 MH4 MH8 0.00140972 5.72% 4.431479 0.914 5.72% 20 0.0784 2.4961 0.0180 0.36 0.899

    8 MH8 Final 0.01343056 0.30% 17.93329 0.532 0.38% 20 0.0203 0.6453 0.6625 0.75 0.484

    Total

    Total

  • 8/2/2019 1 Land Development

    29/46

    28

    4.3.2.Storm Water:4.3.2.1. Design Criteria: pipe cover: 1.2m. Maximum velocity: 2.5 m\s. Minimum velocity: 0.6 m\s. Part full design: 100%. Maximum slope: 0.06. Minimum slope: 0.006. Pipe matching: Crowns. Intensity: 5 years- 10 minutes100mm. Runoff coefficient: 0.54.3.2.2. Calculations Methodology:

    Manning equation is used for calculating the gravity pipes parameters. It states

    that the speed of the flow is given by:

    , and the flow is equal to

    , where = cross-sectional average velocity (ft/s, m/s), kn = 1.486 forEnglish units and kn = 1.0 for SI units,A = cross sectional area of flow (ft

    2, m

    2), n =

    Manning coefficient of roughness,R = hydraulic radius (ft, m), and S = slope of pipe(ft/ft, m/m).

    Manning coefficients are represented in table-5. Hydraulic radius can be

    expressed as , where:A = cross sectional area of flow (ft2,m

    2), and P = wetted

    perimeter (ft, m).

    To calculate the discharge flow , where: C= runoff factor, which isdependent on the land type and pavement material, I= Rainfall intensity in specified

    period, andA is the catchment area of the drainage inlet.

    For subsequent pipes the cumulative flow rate should be considered in the

    calculations.

  • 8/2/2019 1 Land Development

    30/46

    29

    4.3.2.3. Sample of Calculations:Consider the first pipe which connects manhole 1 with manhole 2

    Runoff coefficient = 0.5 Intensity = for 10 min. in five years. Catchment area = 7954.6 m2.

    o . Ground slop = 5.04% Manning coefficient = 0.013 for Asbestoses Concrete

    o Using manning equation:

    o

    Calculate velocity for full flow (i.e. when D = 2.93 cm)o

    o

    Determine the flow rate Q2 and flow speed 2 for D = 20 cm.o

    o Calculate partial flow

    .

    Use the partial flow-velocity graph to find .Determine

    .

  • 8/2/2019 1 Land Development

    31/46

    30

    4.3.2.4. Results:

    Table 9: Pipes Data given by stormCAD

    Table 10: Inlets Data given by stormCAD

    Label Upstream Node

    Downstr

    eam

    Node

    Upstream

    Inlet Area

    (m)

    Upstrea

    m Inlet

    CA (m)

    Construct

    ed Slope

    (m/m)

    Downstream

    Invert

    Elevation (m)

    Maximum

    Slope

    (m/m)

    Minimum

    Slope

    (m/m)

    Section Size

    Description

    Velocity

    In (m/s)

    Velocity

    Out (m/s)P-11 I-12 O-1 1,549 775 0.06 122.55 0.06 0.006 315 4.05 4.9

    P-2 I-2 I-6 8,000 4,000 0.034441 134.18 0.06 0.006 250 mm 2.22 2.22

    P-4 I-6 I-7 5,600 2,800 0.041469 131.08 0.06 0.006 315 2.61 2.59

    P-8 I-7 I-8 4,200 2,100 0.006 130.78 0.06 0.006 315 3.39 3.39

    P-14 I-23 I-8 5,289 0 0.03 130.88 0.06 0.006 200 mm 0 0

    P-16 I-8 I-12 1,946 973 0.059664 126.51 0.06 0.006 315 3.76 4.93

    P-13 I-14 I-15 9,800 4,900 0.04593 132.03 0.06 0.006 250 mm 2.7 2.69

    P-15 I-15 I-17 6,400 3,200 0.06 127.12 0.06 0.006 315 4.15 5.01

    P-17 I-17 O-2 2,800 1,400 0.06 122.55 0.06 0.006 315 4.96 4.96

    P-18 I-19 I-15 2,200 1,100 0.03806 132.03 0.06 0.006 250 mm 1.65 1.54

    P-20 I-21 I-19 3,400 1,700 0.01051 134.18 0.06 0.006 250 mm 1.26 1

    LabelCalculated

    Station (m)

    Ground

    Elevation (m)

    Sump

    Elevation (m)Inlet CA (m)

    I-12 0+37 128.02 124.77 775

    I-17 0+41 128.63 124.98 1,400

    I-8 1+09 132.59 130.78 973

    I-7 1+60 132.59 131.08 2,100

    I-15 1+22 134.11 131.98 3,200

    I-23 1+70 134.11 132.71 0

    I-6 2+33 135.64 134.13 2,800

    I-19 1+78 135.64 134.18 1,100

    I-21 2+36 136.25 134.79 1,700

    I-14 2+02 137.16 135.71 4,900

    I-2 3+22 138.68 137.23 4,000

  • 8/2/2019 1 Land Development

    32/46

    31

    5.Traffic Impact Study5.1. Purpose of the study

    To provide a suitable subdivision design we should take in considerations all

    the current issues. In this report we will concern in the traffic analysis part. Our goal

    is to attempts all possible means to relieve traffic congestion in that road after the

    development. Different road characteristics affect the service level of the road,

    Planning and implementing a suitable design solution for traffic problems involves

    collecting required data and selecting the proper design that fits the need. This report

    focuses on the traffic congestion problems at that current road, we will attempt

    different alternatives that could eliminate the excessive delays and move traffic

    smother.

    5.2. Existing TrafficCurrently, there is a huge demand of traffic going through the main road due to

    its strategic location and importance, and this huge demand exceeds the capacity of

    the intersection, as a result traffic jams occurs. In addition, more delay is caused by

    vehicles traveling through that road due to the fact that it is connecting University

    City by schools and buildings surrounding. The current road conditions are consistingof four lanes (2 lanes/directions). After the development is been ready we will expect

    more volumes in the main road so adjustments are needed to be done.

    5.3. Evaluation of a roadLevel of Service: Is a qualitative measure describing operational conditions

    within a traffic stream and their perception by motorists and/or passengers.

    There are six level of service used to describe any facility in the road, Listed

    below the definition of each LOS:

    1. LOS A: free-flow operation and high maneuverability.2. LOS B: Reasonably free flow, Ability to maneuver is only slightly restricted

    and Effects of minor incidents still easily absorbed.

  • 8/2/2019 1 Land Development

    33/46

    32

    3. LOS C: Speeds at or near FFS, Queues may form behind any significantblockage.

    4. LOS D: Speeds decline slightly with increasing flows, Density increases morequickly. And Freedom to maneuver is more noticeably limited.

    5. LOS E: Operation near or at capacity, No usable gaps in the traffic stream.6. LOS F: Traffic Jam Scenario, Demand > capacity.5.3.1.Factors that that affect Level of service:1. Speed.2. Lane width.3. Lateral obstructions.4. Grade.5. Traffic composition.6. Driver Population.

    5.4.

    Trip Generation:

    For Estimating how many trips can be generated from this development there

    is a Trip generation manual that specifies each category and estimating how many

    trips can be generated, For example in this development we are having three

    categories to estimate the daily traffic which are:

    Table 11: Number of expected trips at peak hours

    Category Expected Unit Daily Trips PM Peak trips PM-IN PM-Out

    Single Family house 45 431 45 29 17Low Rise Apartments 128 844 74 48 26

    Shopping Center 31.3 1344 105 52 54

    129 97Total

  • 8/2/2019 1 Land Development

    34/46

    33

    5.5. Sample of Calculation1. For Low rise expected units: We have 2 buildings each is 4 story buildings,

    each floor with 4 flats, each Apartment with 4 people (total= 2 x 4 x 4 x 4 =

    128).

    2. For single family house(Villa) we have a total of 45 villa3. For the shopping center the area is 31300 ft2 but in the excel sheet we should

    enter per thousand feet.

    5.6. Traffic VolumesDevelopment Volume: The required peak our volume is now specified. For

    the entry to the development we have total of 129 veh/hr. and for the exit Approach

    we have 97 veh/hr. Those numbers are estimated from the Trip generation excel

    sheet.

    NB Towards University City Volume: Based on the traffic counts we have a

    total of 900 veh/hr towards the university in the peak times.

    SB Exiting from the University City: Its estimated based on some

    conditions. In this situation its estimated to be 600 veh/hr, since majority of drivers

    travel to different alternative which has no roundabout and signals.

    Table 12: Traffic Distribution

    5.7. AlternativesChoosing one Access only for IN AND OUT Vehicles (moved in the same

    Access):

    5.7.1.Signs Control Solution:Through volume: 900vph

    Right turn from the shared lane: 129vph

    Road Approach University City Rd,SB University city NB Development IN AND OUT

    Traffic Direction NBT SBT IN OUT

    Peak hour Volume 900 600 129 97

  • 8/2/2019 1 Land Development

    35/46

    34

    We found by Simulations in Synchro 7 that the Level of service For NBApproach that will consist of 2 lanes per direction, one of them is a shared

    lane will give us LOS A, with a link speed 50 mph (allowed to enter the

    development from the shared lane).

    Through Volume: 600vph

    We found by Simulations in Synchro 7 that the Level of service For SBApproachthat will consist of 2 lanes per direction, will give us LOS A, with

    a link speed 50 mph.(Not allowed to enter the development it should follow

    the existing roundabout to turn to the development)since the distance is close

    to the roundabout.

    Right turn volume: 97 vph

    We found by Simulations in Synchro 7 that the Level of service for thedevelopment lane (consist of 2lanes, One lane per direction) since the volume

    is not a critical volume ones will give us LOS B, with a link speed 40 mph.

    Sign Solution will work at this particular section but for the long termsolution we are expecting more volumes than the current ones, so it will

    not handle the traffic in the future.

    Choosing two Accesses one for IN and the other for OUT Vehicles:

    5.7.2.Un-signalized Intersection:We Found by simulations that the level of service for the development road

    will approach to D because we have permitted the left exclusive turn lane and the

    right exclusive turn lane by using stop sign and that will cause much delay since they

    will wait until there is no vehicle then they can move right or left using stop sign.

    This solution is not applicable because most drivers might not obey the rules and may

    make uterus at this particular intersection. Its not applicable in Arabs Countries since

    drivers are not educated in the proper way.

  • 8/2/2019 1 Land Development

    36/46

    35

    5.7.3.Signalized Intersection ( only one approach is signalized )We found again by simulations that the level of service using a traffic signal

    will lead to A service which is perfect since we allowed for protected phases that

    vehicles can travel smoothly. The intersection delay was around 11 seconds which is

    good. This type of signals called semi Actuated, it means that it will allow the

    through vehicle to pass through unless there is a call for left and right turn vehicles.

    Here is this section we allowed the 129 vehicle to enter from one approach of a

    shared lane which is the NB, But for Exit vehicles we have total of 97 vehicles so we

    have to divide them into two groups based on who will turn left or right. This one is

    done by assumption, Here in this situation the volume left turn vehicles are much

    more than the right so we took for the left turning vehicles a total of 60 vehicles. And

    for the right a total of 37 vehicles. The level of service was A for this particular

    intersection.

    5.7.4.Roundabout SolutionThe roundabout has been an attempted solution and it works and gives

    preferable level of service but the problem is that in the main road itself there is

    currently 2 roundabouts if we increase them this will increase in cost and delay.

    5.7.5.Signalized intersection(Both approaches are signalized)

    Figure 13: Synchro simulator

    Both signals are taken as a semi Actuated Un-coordinated

    1

  • 8/2/2019 1 Land Development

    37/46

    36

    As there in Node#1 there are 3 approaches that will be held on that particular

    intersection. The NB approach towards the University City will exist of 2 lanes

    through vehicles and 1 exclusive right turn lane. However for the south bound there

    will be 2 lanes for through vehicles and 1 lane for left turn channelized lane 200 ft.

    storage length. For the development Lane there will be 2 lanes in it not allowed to

    Exit only they are entrance lanes for the NB & for SB.

    Regarding to Node#2 there are 3 approaches that will be held on that particular

    intersection. The NB approach towards the University City will consist of 2 through

    lanes. The south bound approach will consist of 2 through lanes .For the development

    lane there will be 2 exclusive left turn lanes and 1 exclusive channelized right turn

    lane. Volume will equal to 60 vph for the left turn and 37 vph for the right turn.

    It is found by Simulations in synchro 7 that the Level of Service is A for both

    nodes. And thus this is an ideal solution and will count for the long term. The type of

    signal used is semi Actuated signal

    5.8. Preferred SolutionIts preferred to use a signalized intersection for both Nodes. Since it counts

    the long term problems in increasing the volumes of traffic. The total delay for Node

    #1 is 2.3 sec and the total delay for node# 2 is 4.2sec. The Level of service for bothnodes was A.

    5.9. ConclusionIn conclusion, To provide a safe and easy way of movement we have to think

    deeply, Many benefits such as reduction of energy consumption and relieving traffic

    congestion will be gained if we install the devices truthly and in a perfect conditions.

    So our Aim to build a sustainable division layout is met and its now environmentally

    friendly. Our goal is always is to serve our people and avoid any traffic delay.

  • 8/2/2019 1 Land Development

    38/46

    37

    6.Geometric Design6.1. Theory:6.1.1.General Concepts:

    The design process was according to AASHTO 2001 using AutoCAD Civil 3D2012 software program.

    Geometric Design of a road is the positioning of the physical elements of the

    roadway according to standards and constrains, so that smooth-flow and crash-free

    facilities are provided. (Wikipedia definition)

    Before starting any design problem the design criteria should be defined in

    order to have a correct and safe design.

    In road geometric design there are specific control criteria which puts a guide

    lines to start the design process. American Association of State Highway and

    Transportation Officials (AASHTO) is one of the most common used codes in

    America and in the middle eastern region.

    Road geometric design is divided into three main components:

    1. Horizontal Alignment2. Vertical Alignment3. Cross Section

    They will be explained in details bellow.

    6.1.2.Horizontal Alignment:Is a series of straight segments called (tangents) and connecting horizontal

    curves. Curves are controlled by the functional classification, design speed, andsuperelevation of the road. There are two typed of horizontal curves:

    Circular curves. Spiral (transition) curves.

    6.1.2.1. Definitions: Circular curve: curves with constant radius along its length. Spiral curve: curves with variable radius along its length.

  • 8/2/2019 1 Land Development

    39/46

    38

    Superelevation: is tilting the roadway to help offset centripetal forcesdeveloped as the vehicle goes around a curve.

    PC: Point of curve, where the curve starts. PI: Point of intersection of two tangents.

    PT: Point of tangent, where tangent starts. Deflection Angle: is the angle formed between two

    tangents (see fig-1).

    Stopping Sight Distance (SSD): Distance required bythe driver to stop his vehicle.

    6.1.2.2. Design Process:1. Select tangents, PIs, and general curves making sure

    you meet minimum radius criteria.

    2. Determine radius of the curve (R).3. Measure angle () between tangents.4. Determine length of the curve (L) and Tangent (T).5. Determine station alignment: stations for PC, PI, PT.6. Calculate spiral (transition) lengths (Ls), if needed.7. Check for widening of curves (Check SSD requirements).8. Develop edge profiles (superelevation runoffs).9. Add information to plans.

    6.1.2.3. Calculations: Minimum radius of curve , where v:

    design speed, g: gravitational acceleration, e:

    superelevation value, and f: side friction

    coefficient.

    Tangent length given by: Curve length given by:

    , where t: perception

    reaction time, and G: the cross slope of the road.

    Figure 14: Horizontal Curve

    Parameters

    Figure 15: Horizontal curve parameters

  • 8/2/2019 1 Land Development

    40/46

    39

    6.1.2.4. Superelevation:Curve superelevation is divided into two parts:

    1. Tangent Runout:Length of roadway needed to accomplish a change in outside lane cross-

    section from normal crown to flat (zero slope), or vice versa. It is given by: , where eNC: normal cross slope rate in percent, ed: design superelevation rate inpercent, andLr: superelevation runoff.

    2. Superelevation Runoff:Length of roadway needed to accomplish a change in outside lane cross-

    section from flat (zero slope) to full superelevation, or vice versa. It is given by:

    Where w: is the lane width, n1: is the number of lanes, and bw: is the adjustment

    factor for number of lane rotated. (see fig-2)

    Figure 16: Superelevation transition

    6.1.2.5. Curve Widening:Curve widening is needed duo to the following reasons:

    Wheels off-tracking, rear wheels do not follow exactly the samepath/trajectories of front wheels.

    Vehicles front overhang requires an additional lateral space.

  • 8/2/2019 1 Land Development

    41/46

    40

    Difficulty of driving on curves justifies wider lateral clearance. Tendency of drivers to steer away from the pavements edge.

    6.1.3.Vertical Alignment:Is a straight segments of the road called grades connected by vertical curves. It

    controlled by land topography, design vehicles, and sight distances such as: stopping

    sight distance (SSD), passing sight distance (PSD), and decision sight distance

    (DSD). There are two types of vertical curves:

    Sag Curves. Crest Curve.

    6.1.3.1. Definitions: Sag Curves: concave-up curve. Crest Curve: concave-down curve. PVI = Point of Vertical Intersection. PVC = Point of Vertical Curvature. PVT = Point of Vertical Tangency. L = Length of vertical curve measured as straight line from PVC to PVT. Y = Offset of curve from initial grade line. Ym= mid-curve offset. Yf= end-curve offset. G1= Grade of initial tangent, %. G2= Grade of final tangent, %.

    Figure 17: Crest curve parameters

  • 8/2/2019 1 Land Development

    42/46

    41

    Figure 18: Crest curve parameters

    6.1.3.2. Design Procedure:1. Determine the minimum length of curve to satisfy sight distance requirements

    and other criteria.

    2. Determine from the layout plans the station and elevation of the PVI (the pointwhere the grades intersect).

    3. Compute the elevations of the PVC (or BVC) and end of vertical curve (EVCor PVT).

    4. Compute the offsets, Y, from the tangent to the curve at equal distances orstations.

    5. Compute elevations on the curve for each station as: elevation of the tangent offset from tangent, Y. For crest curves the offset is (-) and for sag curves the

    offset is (+).

    6. Compute the location and elevation of highest/lowest point on curve.

    6.1.2.3. Calculations:To determine length of the crest curve:

    ||() , where | |, S: sight distance, h1:Height of drivers eye, and h2: Height of object.

    ||() .

  • 8/2/2019 1 Land Development

    43/46

    42

    Elevation at any point given by: , where: , ,and .

    High point (on crest curve) and Low point (on sag curve) given by: . Offset of G

    1tangent from the curve at any pointx is given by:

    .

    . .

    6.2. Design Criteria:6.2.1.

    University Road:

    Table 13: Design criteria for the main road

    Criteria Value

    Functional Classification Collector

    Design Speed 80 km/h

    LOS D

    Lane Width 3.6 m

    Design Vehicle WB-12 (Intermediate Semitrailer)

    Maximum Grade 8%Maximum Superelevation 4%

  • 8/2/2019 1 Land Development

    44/46

    43

    6.2.2.Local Streets:Table 14: Design criteria for the local roads

    Criteria Value

    Functional Classification Local

    Design Speed 60 km/hLOS D

    Lane Width 3.6 m

    Design Vehicle SU (Singe-Unit Truck)

    Maximum Grade 8%

    Maximum Superelevation N/A

    6.3. Results and Tables:Design has been done using Autodesk AutoCAD Civil 3D 2012 and the

    following results imported from the program.

    6.3.1.University Road:Table 15: Horizontal Alignment Data

    Table 16: Superelevation Data

    Type Length Radius Minimum Radius Start Station End Station Delta angle Chord length PI Station

    Line 100.997m 0+000.00m 0+101.00m

    Curve 167.658m 350.000m 280.000m 0+101.00m 0+268.66m 27.4460 (d) 166.060m 0+186.47mLine 42.001m 0+268.66m 0+310.66m

    Superelevation

    CurveStart Station End Station Length

    Left Outside

    Shoulder

    Rate of

    Change(LOS)

    Left Outside

    Lane

    Rate of

    Change(LO)

    Left Inside

    Lane

    Rate of

    Change(LI)

    Right Inside

    Lane

    Rate of

    Change(RI)

    Right Outside

    Lane

    Rate of

    Change(RO)

    Right Outside

    Shoulder

    Curve.1

    Transition In

    Region0+018.58m 0+115.33m 96.750m

    End Normal

    Shoulder0+018.58m -5.00% 0 -2.00% 0 -2.00% 0 -2.00% 0 -2.00% 0 -5.00%

    Runout 0+050.83m 0+072.33m 21.500m

    End Normal

    Crown0+050.83m -2.00% 0.093 -2.00% 0 -2.00% 0 -2.00% 0 -2.00% 0 -5.00%

    Level Crown 0+072.33m 0.00% 0.093 0.00% 0.093 -2.00% 0 0.00% 0.093 -2.00% 0 -5.00%

    Runoff 0+072.33m 0+115.33m 43.000m

    Level Crown 0+072.33m 0.00% 0.093 0.00% 0.093 -2.00% 0 0.00% 0.093 -2.00% 0 -5.00%

    Reverse Crown 0+093.83m 2.00% 0.093 2.00% 0.093 -2.00% 0 2.00% 0.093 -2.00% 0 -5.00%

    Begin Curve 0+101.00m

    Begin Full Super 0+115.33m 4.00% 0.093 4.00% 0.093 -4.00% -0.093 4.00% 0.093 -4.00% -0.093 -5.00%

    Transition Out

    Region0+254.32m 0+351.07m 96.750m

    Runoff 0+254.32m 0+297.32m 43.000m

    End Full Super 0+254.32m 4.00% 0 4.00% 0 -4.00% 0 4.00% 0 -4.00% 0 -5.00%

    End Curve 0+268.66m

    Reverse Crown 0+275.82m 2.00% -0.093 2.00% -0.093 -2.00% 0.093 2.00% -0.093 -2.00% 0.093 -5.00%

    Level Crown 0+297.32m 0.00% -0.093 0.00% -0.093 -2.00% 0 0.00% -0.093 -2.00% 0 -5.00%

    Runout 0+297.32m 0+318.82m 21.500m

    Level Crown 0+297.32m 0.00% -0.093 0.00% -0.093 -2.00% 0 0.00% -0.093 -2.00% 0 -5.00%

    Begin Normal

    Crown0+318.82m -2.00% -0.093 -2.00% -0.093 -2.00% 0 -2.00% -0.093 -2.00% 0 -5.00%

    Begin Normal

    Shoulder0+351.07m -5.00% -0.093 -2.00% 0 -2.00% 0 -2.00% 0 -2.00% 0 -5.00%

  • 8/2/2019 1 Land Development

    45/46

    44

    Table 17: Vertical Alignment (Profile) Data

    6.3.2.First Street:Table 18: Horizontal Alignment Data

    Table 19: Vertical Alignment (Profile) Data

    6.3.3.Second Street:Table 20: Horizontal Alignment Data

    No. PVI Station PVI Elevation Grade In Grade OutA (Grade

    Change)

    Profile Curve

    Type

    Profile

    Curve

    Length

    K Value

    Minimum K for

    Stopping Sight

    Distance

    Minimum K for

    Passing Sight

    Distance

    Minimum K for

    Headlight Sight

    Distance

    Curve

    Radius

    Design

    Speed

    1 0+000.00m 134.838m 1.21%

    2 0+069.48m 135.677m 1.21% 5.00% 3.79% Sag 120.000m 31.631 30 3163.089m 80 km/h

    3 0+188.85m 141.648m 5.00% 1.11% 3.89% Crest 101.232m 26 26 338 2600.000m 80 km/h

    4 0+310.66m 142.997m 1.11%

    Type Length Radius Start Station End Station Delta angle Chord length PI Station

    Line 48.245m 0+000.00m 0+048.24m

    Line 27.393m 0+048.24m 0+075.64mCurve 61.352m 60.000m 0+075.64m 0+136.99m 58.5869 (d) 58.714m 0+109.30m

    Line 27.839m 0+136.99m 0+164.83m

    Line 78.730m 0+164.83m 0+243.56m

    No. PVI Station PVI Elevation Grade In Grade OutA (Grade

    Change)

    Profile

    Curve Type

    Profile

    Curve

    Length

    K Value

    Minimum K for

    Stopping Sight

    Distance

    Minimum K for

    Passing Sight

    Distance

    Minimum K for

    Headlight Sight

    Distance

    Curve

    Radius

    Design

    Speed

    1 0+000.00m 135.408m - 0.85%

    2 0+052.66m 134.958m -0.85% -2.50% 1.64% Crest 82.036m 50 4 84 5000.000m 40 km/h

    3 0+182.69m 131.713m -2.50% 1.31% 3.81% Sag 76.140m 20 9 2000.000m 40 km/h

    4 0+243.56m 132.511m 1.31%

    Type Length Transition Length Table Radius Start Station End Station Delta angle Chord length PI Station

    Line 108.370m 0+000.00m 0+108.37m

    Line 81.792m 0+108.37m 0+190.16m

    Line 47.523m 0+190.16m 0+237.69m

    Curve 46.129m 2 Lane