OVERVIEW OF

CHENNAI METRO RAIL LIMITED

PHASE 1

Page 2: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

2

CHENNAI CITY MAP

Page 3: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

3

PRESENT TRAFFIC SCENARIO IN

CHENNAI CITY

Page 4: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

4

Main Arterial Roads In Chennai City

Anna Salai / Mount Road

E V R Salai / Poonamalle High Road

Inner Ring Road / Jawaharlal Nehru Road/100 feet Road

Page 5: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

5

Distribution Of Road Net Work In Chennai City

Right Of Way (ROW)

ROW(m) Length(km) Percentage

<10* 6.43 1.74

10-15* 146.15 39.44

15-20* 159.06 42.93

20-30 57.83** 15.61

30-40 1.05 0.28

Total 370.52 100.00

* ROW of 84 % of the city roads <20 m** Out of this 57.83km, Phase I Metro will run through 40km

Page 6: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

6

Growth of Population in Chennai City / CMA

1971 1981 1991 2001 2008

Chennai City 2.64 3.29 3.84 4.32 4.75

Other than City 0.86 1.32 1.98 2.72 3.52

CMA 3.50 4.61 5.82 7.04 8.27

In Million

Page 7: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

7

CHENNAI CITY LIMTS

Page 8: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

8

Steady increase in the growth of Bus transport

Year Routes Fleet Bus Fleet per One Lakh Population

1980-81 298 1794 25

1990-91 439 2296 34

2000-01 580 2816 40

2008-09 640 3300 40

Page 9: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

9

Share Of Public Transport

The share of public transport has reduced

1992- 60%

2003- 53%

2008- 41%

Ideally this should be 70%

Page 10: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

10

Growth of Vehicle Population

1984 1992 2000 2008

Cars 24%(34,000)

21%(1,20,000)

20%(2,28,000)

19%(5,04,000)

Twowheelers

61%(87,000)

71%(4,05,000)

73%(8,32,000)

76%(20,15,000)

Page 11: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

11

Road vehicles, especially two wheelers have substantially increased.

Whereas the infrastructure facilities of the city not proportionately increased.

Due to increase in vehicle population, the average journey time has increased

Growth of Vehicle Population

Page 12: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

3%

▄Chennai is the fourth- largest city in India with a population of about 8 million

▄11 million trips in a day, of which about 6 million vehicular trip

▄Many areas in city and suburbs are not served by rail based system

▄Suburban and MRTS traffic have increased, but NOT in tune with the traffic

demand

▄Rail network expansion failed to keep pace with demand resulting in severe

congestion on road network & Environmental pollution

Present Scenario of Transport Infrastructure

12

26% 71%

Page 13: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

13

The options are…………

1. ROAD BASED SYSTEM

2. RAIL BASED MASS TRANSIT SYSTEM

Page 14: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

14

ROAD BASED SYSTEM

Widening of Roads Involves large scale land and building acquisition in the heart of the City- not feasible

Elevated Bus bay systemDedicated bus bays/expressways not feasible because: -numerous existing flyovers ;

-city landscape intervened with commercial/residential buildings and walkways

Page 15: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

15

RAIL BASED MASS TRANSIT SYSTEM

Mono Rail: Suitable as a feeder serviceLimited capacity <10000 phpdt

Light Rail Transit (LRT): Suitable for low to medium capacity trafficbetween 10000 and 25000 phpdt

The arterial roads of Chennai is already having traffic in the order of 30000phpdt and growing steadily

Page 16: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

16

RAIL BASED MASS TRANSIT SYSTEM

Medium Capacity Metro System

Suitable for traffic demand of 30000-40000 phpdt

Most economically suited system for the saturated corridors of the Chennai City

Page 17: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

17

Advantages of Metro System Requires 1/5th energy per passenger km compared to road

based system

More reliable, Comfortable and Safer

Fully air conditioned

Carries same amount of traffic as 7 lanes of bus traffic or 22 lanes of private cars

Reduces journey time by 50 to75%

Washermanpet to Airport

-by road will take 90 to 100 minutes

-Metro Rail will take 45 minutes

Page 18: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

18

Advantages of Metro System

Tangible & non Tangible SavingsSocio Economic Benefits

Vehicle operating costs (VOC) savedPassenger time savedLess air and noise pollutionReduction in number of road accidentsReduction in Road infrastructure and consequent

maintenanceChennai city will be placed in global Metro map

Page 19: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

19

CHENNAI METRO SELECTION OF CORRIDOR

Detailed Feasibility Study was carried out, and 7 (Seven) corridors prioritised

Detailed traffic survey was done for the

3 (Three) main corridors

Page 20: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Cor

r 1Corr 7

Corr 2

Corr 3

Co

rr 3

Corr 4

Co

rr 5

Corr 6

Corr 1

CHENNAI METRO SELECTION OF CORRIDOR

Page 21: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

CHENNAI METRO SELECTION OF CORRIDOR

CORRIDOR - 1

Airport - GST Road- Anna Salai- Central - Broad Way- Washermanpet- Tiruvottiur

CORRIDOR - 2

Alandur - JN Road - Koyambedu - EVR Salai - Egmore - Chennai Central - Fort – Beach Station

CORRIDOR - 3

Ambattur - Ring Road - Arcot Road - Panagal Park - Eldams

Road- Luz Church Road - RK Mutt Road - Adyar Bridge - Lattice

Bridge Road -Thiruvanmiyur

21

Page 22: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

22

Govt. decided to take up Corridor 1 & Corridor 2, under Phase-I based on maximum ridership

Subsequently both these corridors slightly modified-extent reduced.

Corridor 3 will be taken up under Phase-II Extension of Corridor 1 (to Tiruvottiyur) will be taken

up shortly

CHENNAI METRO SELECTION OF CORRIDOR

Page 23: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

U/G Station

Elevated Station

23

CHENNAI METRO RAIL ALIGNMENT

Page 24: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

24

Chennai Metro Rail Project Phase I

Largest infrastructure project ever in Tamil Nadu

Cost - Rs. 14,600 Crores (US $ 3.2 Billion)

59% funding from Japan International Cooperation

Agency, 20% by Central Govt. and 21% by State

Govt.

Page 25: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

25

Implementation Module

A special purpose vehicle formed – Chennai Metro Rail Limited (CMRL)

Stake Holders- Govt of India and Govt of Tamil Nadu

Page 26: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

26

Chennai Metro Rail Phase - 1 Salient Features

Description Under Ground (Km) Elevated (Km) Total (Km)

Corridor I 13.8 8.7 22.5

Corridor II 9.6 11.8 21.4

Total 23.4 20.5 43.9

Description Under Ground (Nos) Elevated (Nos) Total (Nos)

Corridor I 11 6 17

Corridor II 8 7 15

Total 19 13 32

1. No of Corridors – 2 Nos

2. Route length

3. No. of Stations

Page 27: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

27

Under Ground StationsCorridor - 1 Corridor - 2

1 Washermanpet 1 Chennai Central

2 Mannadi 2 Egmore

3 High Court 3 Nehru Park

4 Chennai Central 4 K M C

5 Government Estate 5 Pachaiappa’s College

6 L I C Building 6 Shenoy Nagar

7 Thousand Lights 7 Anna Nagar East

8 Gemini 8 Anna Nagar Tower

9 Teynampet 9 Thirumangalam

10 Chamiers Road

11 Saidapet

Elevated StationsCorridor - 1 Corridor - 2

1 Little Mount 1 Koyambedu

2 Guindy 2 CMBT

3 Alandur 3 Arumbakkam

4 Officers Training Academy

4 Vadapalani

5 Meenambakkam 5 Ashok Nagar - K. K. Nagar

6 Chennai Airport 6 SIDCO

7 Alandur

8 St. Thomas Mount

CHENNAI METRO List of Stations

Page 28: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Integration with other modes of Transport

28

Page 29: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

29

CONNECTIVITY TO BUS STATIONS

WASHERMANPET BUS STATION

ESPLANADE BUS STATION

KOYAMBEDU INTERSTATE BUS TERMINUS

SAIDAPET BUS

STATION

PROPOSED ST.THOMAS MOUNT BUS

STATION

Page 30: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Integration with other modes of Transport

30

Chennai Mofussil Bus Terminus (CMBT) Koyambedu

• Largest Interstate Bus Terminus in Asia

• Handle over 2000 Buses / Day (270 buses parked at a time) • Handle over 2 lakh Passengers / Day

Page 31: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

31

CONNECTIVITY TO CHENNAI AIRPORT

PROPOSED AIRPORT

STATION

Page 32: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

32

Chennai International Airport

• Rs. 2000 Crore Expansion and Modernization of Domestic and International Airports is on going

• Target handling capacity in 2011 - 23 million passengers per annum or 66,000 passengers per day

• Expected traffic flow to Airport in 2011- 1 lakh / day

• Cannot be handled by Road

• CHENNAI METRO the only alternative

Integration with other modes of Transport

Page 33: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

33

WASHERMANPET

WASHERMANPET METRO STATION

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 2

CORRIDOR 1

Page 34: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

34

HIGH COURT

FORT STATION

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 2

CORRIDOR 1

Page 35: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

35

HIGH COURT

ELEVATED SKY WALK FROM HIGHCOURT

STATION TO FORT STATION FOOT BRIDGE

Page 36: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

36

CHENNAI CENTRAL

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 1

CORRIDOR 2

CENTRAL METRO STATION

Page 37: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

CHENNAI CENTRALSUB URBAN (MMC)

37

Chennai Central Station

(long distance)

1.75 lakh passengers / day

MMTC Suburban Station

4.75 lakh passengers / day

Park Suburban Station 4.4

lakh passengers / dayPark MRTS Station 25,000

passengers / day

Page 38: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

38

EGMORE

EGMORE METRO

STATION

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 2

CORRIDOR 1

Egmore Station (long distance) 1.0 lakh

passengers / day

Page 39: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

39

GOVERNMENT ESTATE

CHINTHADRIPET

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 2

CORRIDOR 1

Page 40: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

GOVERNMENT ESTATE

NEW SUBWAY CONNECTING THE EXISTING SUBWAY AT ANNA SALAI WITH

CHINTHADRIPET MRTS STATION

40

Page 41: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

41

GUINDY METRO STATION

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 2

CORRIDOR 1

Page 42: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

42

ST. THOMAS MOUNT

INTEGRATED STATION FOR MRTS AND METRO

INTEGRATION WITH EXISTING SUB-URBAN AND MRTS STATIONS

CORRIDOR 1

CORRIDOR 2

Page 43: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

▄Length of the route : 20.5 km (Elevated)

: 23.5 km (Under Ground)

▄Gauge (standard) : 1.435m

▄Tunnel Dia : 5.8m (Internal Diameter)

▄Traction Power : 25 Kv A.C

▄Rail Profile : 60kg (UIC 60)

▄Track Structure : Slab Track / Plinth

▄Track Centre (Under Ground) : 14.05m / 14.50m

▄Track Centre (Elevated) : 4.10m

▄Car Depot location : Koyambedu

43

Chennai Metro Technical Details

Page 44: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

44

Typical Underground Station Section

Page 45: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Chennai Central Station - Corridor 2 over Corridor 1

45

Page 46: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

46

Underground Station Platform

Page 47: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

47

STATION INSIDE VIEW

Page 48: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

48

STATION INSIDE VIEW

Page 49: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

49

Typical Bored Tunnel Section.

Page 50: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

50

INSIDE VIEW OF TUNNELInside View of Tunnel

Page 51: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Cross Section of a typical Cross Passage

51

Cross Passages are provided every 244m

Page 52: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

52

Typical Elevated Viaduct Section

Page 53: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

53

Viaduct Section-in progress

Page 54: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Typical Elevated Station

Construction by Station Contractor

Construction by Viaduct Contractor

54

Page 55: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Alandur Station - Corridor 2 over Corridor 1

55

Page 56: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

56

Elevated Station

Page 57: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

57

Elevated Station Platform

Page 58: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

58

METRO RAIL INSIDE VIEW

58

Page 59: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

59

METRO RAIL INSIDE VIEW

59

Page 60: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

METRO Rail Depot

60

Page 61: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

METRO Rail Depot

61

Page 62: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

62

Progress - Civil Contracts

Elevated :- 3 Viaduct contracts – work in progress- 2 Elevated station contracts (10 stations)- awarded- 2 Elevated station contracts ( 3 stations)- tender will be

called for shortly- Depot – Tender return early August 2010

Under Ground :- 5 Contract packages (19 stations and 18km tunnels)-

Tender return early August 2010

Page 63: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

63

Progress - Systems Contracts

- Rolling Stock – Bid evaluation- Power Supply and Overhead Equipment, Track Works -

Call for Tender - Signaling, Platform Screen Doors and Telecommunication, Lifts and Escalators – Tender will be called for shortly- Tunnel Ventilation and Under Ground Station Air

Conditioning System, AFC Equipment – P Q Evaluation

Physical Work Completion for Elevated Portion: 2012 -13 Underground Portion: 2014-15

Page 64: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Chennai Metro – Future WorksCorridor 1 Extension to Tiruvottiyur

64

Preliminary study completed, Financial Sanction in progress

Page 65: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

Cor

r 1Corr 7

Corr 2

Corr 3

Co

rr 3

Corr 4

Co

rr 5

Corr 6

Corr 1

Chennai Metro – Future WorksCorridors 3 & 4 - Feasibility study completed, now under active

consideration

65

Page 66: 1 OVERVIEW OF CHENNAI METRO RAIL LIMITED PHASE 1

66

Chennai Metro Rail Project