Session 14Capacity Management

http://www.pom.edu/mpc/lectures_in_manufacturing_planning.htm

lecture session 15 • Capacity Planning Issues

• Finite Capacity Planning Example

• Twin Disc Capacity Bills Example

• Applicon Capacity Bills Example

• Concluding Principles

Page 2: 1 Session 14 Capacity Management  lecture session 15

2

Capacity Planning Issues

• To determine the capacity required to achieve the MPS relative to the capacity available

• To make necessary capacity adjustments before creating crises

• To determine an the appropriate level of safety capacity

• To determine the required level of detail and the critical machines and work centers

• To use an appropriate technique given the tradeoff between accuracy and computational effort

Page 3: 1 Session 14 Capacity Management  lecture session 15

3

Finite Capacity Planning Example

The Single Square Company summarizes the capacity requirements for three of its key resources from each of its three product lines. A typical report (before any action is taken) is shown on the next slide.

Page 4: 1 Session 14 Capacity Management  lecture session 15

4

Finite Capacity Planning Example(Continued)

Key resource type Percent capacity by line Machine Number Shifts A B C Total RemarksDrill 1 1 3 22 13 24 59Drill 2 2 3 36 48 36 120Drill 3 1 1 52 24 21 97

Filer 1 2 3 2 0 14 16Filer 2 3 3 12 20 8 40

Dryer 1 2 2 28 36 51 116Dryer 2 2 2 72 51 43 116Dryer 3 2 1 84 27 24 135

a. What actions would you recommend? (Assume each machine type is equivalent in terms of capacity.)

b. What other observations would you have for management, based on the preceding report?

Page 5: 1 Session 14 Capacity Management  lecture session 15

5

Finite Capacity Planning Example: Single Square Company

Key Resource Type % Capacity by LineMachine Number Shifts Total A B C Tot. Equiv.

RemarksDrill 1 1 3 3 22 13 24 59 1.77

Req'd.Drill 2 2 3 6 36 48 36 120 7.20 MoveDrill 3 1 1 1 52 24 21 97 .97 from

10 9.94 2 to 1

Filer 1 2 3 6 2 0 14 16 .96 Excess

Filer 2 3 3 9 12 20 8 40 3.60 _capacity

15 4.56

Dryer 1 2 2 4 28 36 52 116 4.64 Increase

Dryer 2 2 2 4 72 51 43 166 6.64 to three

Dryer 3 2 1 2 84 27 24 135 2.70 shifts 10 13.98

Page 6: 1 Session 14 Capacity Management  lecture session 15

6

Finite Capacity Planning Example: Single Square Company (continued)

a. There is enough capacity now in the Drill and Filer areas. To correct the imbalance in the Drills, it is necessary to move some of the load from Drill 2 to Drill 1. In the case of the Dryers, it is necessary to increase capacity. Adding shifts will provide enough for the current load.

b. Why is there so much capacity for the Filers? They can be brought back to one shift and are okay. Secondly, if there is any upward trend in the loads for the Dryers, it behooves management to begin to worry about where they can get additional dryer capacity.

Page 7: 1 Session 14 Capacity Management  lecture session 15

7

Twin Disc Capacity Bill Report

Page 8: 1 Session 14 Capacity Management  lecture session 15

8

Twin Disc Capacity Bill Example

Suppose, in the Twin Disc example, it was decided to move all production for product lines F and I from the Maag grinder (CEA) to the Reishauer grinder (CAB). What's the resulting total percentage of capacity for each machine and the amount for product lines F and I? (Note the Reishauer is three times faster than the Maag grinder so the Maag takes three times as many hours to complete a job.) Assume setup time is negligible.

Page 9: 1 Session 14 Capacity Management  lecture session 15

9

Twin Disc Capacity Bill Example

For Line IGrinding Hours

On Maag = 3044 x .08 = 243.52On Reishauer = 243.52/3 = 81.17% of Reishauer = 81.17/950 = 9New % of Line I on Reishauer = 9 + 1 = 10%New % of Line I on Maag = 0%

For Line F:Grinding Hours

On Maag = 3044 x .05 = 152.20On Reishauer = 152.20/3 = 50.73% of Reishauer = 50.73/950 = 5New % of Line F on Reishauer = 5 + 2 = 7%New % of Line F on Maag = 0%

New Totals:New total for Reishauer = 69 + 9 + 5 = 83%New total for Maag = 113- 8 - 5 = 100%

Page 10: 1 Session 14 Capacity Management  lecture session 15

10

Applicon Capacity Status Report

Page 11: 1 Session 14 Capacity Management  lecture session 15

11

Applicon Capacity Bill Example

Applicon has the following capacity bills for items 207 and 208:

207 208Work center Hours/unit Work center Hours/unit ALF-A 0.5 ALF-T 0.3 HLT-A 1.0 HLT-T 0.8 MIS-A 0.8 MIS-T 0.6 MVX-A 0.8 MVX-T 0.5 PCB-A 0.5 PCB-P 0.9 PCB-P 1.0 PCB-T 1.4

Page 12: 1 Session 14 Capacity Management  lecture session 15

12

Applicon Capacity Bill Example

a. A customer wants to know if Applicon can deliver 100 units each of items 207 and 208 during the next month (20 working days). Assume there are adequate materials, work center MVX-T'S crew has been increased to one full person (making standard capacity = 160), the increase has come by reducing MVX-A to 6.5 persons. and no other orders have been booked. Use the standard capacity data and conditions in the previous slides as the basis for your analysis.

b. Suppose the customer (in part a. above) decided to delay the order for several months. How many units of item 207 alone could be added to the MPS in the next month? How about item 208?

Page 13: 1 Session 14 Capacity Management  lecture session 15

13

Applicon

Analysis: For Item 207

Work Center Units Possible

ALF-A (480 - 70)/0.5 = 820 unitsHLT-A (800 - 438)/1.0 = 362 unitsMIS-A (800 - 270)/0.8 = 662 unitsMVX-A (1120 - 80 - 399)/0.8 = 801 unitsPCB-A (160 - 52)/0.5 = 216 unitsPCB-P (960 - 408)/1.0 = 552 units

BUT this is if only item 207 is made.

Page 14: 1 Session 14 Capacity Management  lecture session 15

14

AppliconIf BOTH items are made in equal quantities, PCB-P is a shared work center so:

PCB-P (960 - 408)/(1.0 + 0.9) = 291 of each.

For Item 208

Work Center Units PossibleALF-T (80 - 5)/0.3 = 250 unitsHLT-T (160 - 85)/0.8 = 94 unitsMIS-T (80 - 14)/0.6 = 110 unitsMVX-T (160 - 79)/0.5 = 162 unitsPCB-P (960 - 408)/(1.0 + 0.9) = 291 unitsPCB-T (1680 - 918)/1.4 = 544 units

Page 15: 1 Session 14 Capacity Management  lecture session 15

15

Applicon

a. The analysis says that 100 units of each cannot be added to the MPS without something else being done. The problem is with item 208 in work center HLT-T. To make 100 units of item 208, work center HLT-T will have to work overtime-unless capacity can be provided from a less highly utilized work center or perhaps greater productivity can be gained in some other way.

b. The analysis shows that 216 units of item 207 or a total of 94 units of item 208 can be made.

Page 16: 1 Session 14 Capacity Management  lecture session 15

16

Concluding Principles• Capacity plans must be developed concurrently with material

plans if the material plans are to be realized.

• The capacity measure should reflect realizable output from the key resources.

• It's not always capacity that should change when capacity availability doesn't equal need.

• Capacity not only must be planned, but use of that capacity must also be monitored and controlled.

• Capacity planning techniques can be applied to selected key resources (which need not correspond to production work centers).

Page 17: 1 Session 14 Capacity Management  lecture session 15

17

Concluding Principles

• The particular capacity planning technique(s) chosen must match the level of detail and actual company circumstances to permit making effective management decisions.

• The more detail in the capacity planning system, the more data and data base maintenance are required.

• The better the resource and production planning process, the less difficult the capacity planning process.

• The better the shop-floor system, the less short-term capacity planning is required.

• Capacity planning can be simplified in a JIT environment.