Page 1: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

1

WORK FORCE ADJUSTMENT Moving forward post

budget 2012

3 April, 2012

ADM HR-Civ

Page 2: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

2

Purpose

• Provide UMCC members with an overview of work done to date to prepare the Department to implement work force adjustment

• Share planned strategy for selection for retention and alternation processes

Page 3: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

3

Outline of Presentation

• Preparing for Workforce Adjustment

• Implementation Strategy

• Selection for retention

• Alternation

• Next steps

Page 4: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

4

Preparing for Work Force Adjustment

Training and Briefings:

• Canada School of Public Service

• ADM HR-Civ Service Providers/Managers

• ADM HR-Civ developed Webinars/e-learning module for HR practitioners and managers

• Learning and Career Centre courses and services:

– Workforce management for managers, change management, resume and interview preparation, learning plan development, general financial information.

Page 5: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

5

Preparing for Work Force Adjustment cont’d

Tools and Resources:

• Defence Team and ADM (HR-Civ) Websites updated

• Resources on change and leading difficult conversations available on-line

• Employee Information Tool Kit

• FAQs

• Employee Assistance Program

• Educational Allowance supported by centralized unit

• WFA coordinators network established across the country

Page 6: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

6

Implementation Strategy

• 4 April 2012: local bargaining agents representatives will be met with and employees will start being informed, in groups and individually.

• It is expected that all employees will be met by 13 April 2012

• For impacted occupational groups in stressed trades, discussions have already started between HR and management to identify placement opportunities.

• Starting 10 April 2012: letters will be issued– Where selection for retention processes are not required, employees

will receive surplus letters.– Where SRLO is required, employees will be declared affected first

while process is being conducted

• It is expected that all letters will be issued by the end of April 2012

Page 7: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

7

Selection for Retention – way ahead

• Prior to letters being issued, managers will be having discussions with their employees.

• The area of adjustment will be confirmed.

• Managers are currently working with their HR service provider to develop their selection for retention strategies which include:

– Statements of merit criteria

– Assessment methods and timelines

• Processes will commence at the end of April to be conducted through May-June.

Page 8: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

8

Alternation

• DND will maximize use of alternation wherever possible.

• Initial focus will be internal to DND.

• GC Forum tool is already available and employees can register now.

• WFA coordinators will work with employees who do not have access to computers to enter their names in the system.

• Alternation tool internal to DND is being developed and will be presented at next WFACC – roll out is planned for 16 April 12.

• DM email to all employees will be sent out informing employees about alternation and providing guidance on how to participate.

• HR community is ready to deliver presentations on alternation where it is required.

• Checklist was prepared for employees to support them in contacting the Pension Office to determine their pension eligibility.

Page 9: 1 WORK FORCE ADJUSTMENT Moving forward post budget 2012 3 April, 2012 ADM HR-Civ

9

Next Steps

• Finalize internal to DND alternation program (system, communications)

• Hold 2nd Work Force Adjustment Committee – tentatively scheduled for 12 April 12

• Re-issue communications on EAP

• Exercise tight staffing controls to optimize the workforce based on the employability strategy principles