1.0 | Site Report Wednesday, 4 Dec 2019
Project DetailsProject No: Dec19 Contract No:
Client: Constructionarium Client Representative: Harry Hartman
Contractor: Team One Contractor Repentative:
Shift DetailsShifts Worked: Day Afternoon Night
Weather DetailsWeather location: Tarragindi, AU (latitude: -27.546981 longitude: 153.020882)Date Mean Temp (°C) Min Temp (°C) Max Temp (°C) Relative Humidity (%) Rainfall (mm) Wind Speed (km/h) Wind Direction (°)
4 Dec 2019 25.5 17.5 34.2 39.1% 0.0 8.6 177.0
Note: The highlighted row represents today's weather data which may be incomplete.
Comments:
Health and SafetyExposure hours(from timesheets)
135.50 Exposure headcount(from timesheets)
17
Work ProgressActivity Activity Name Revised
Planned Start
Actual Start
RevisedPlanned
Finish
Actual Finish
ActualQuantity in Period
ActualQuantity to Date
Labour in Period
Labourto Date
PRELIMS - Construction Setup
3.00 Construction Setup 3 Dec2019
3 Dec2019
3 Dec2019
60.00(percentage)
13.00 23.50
Rhys (Rhys) Janssen: Head stocks at correct heights and torqued down
Alexander (Alex) Ibarra: Headstocks installed and levelling process continuing
Boris Tusevljak: Headstock in
Rory O'Keeffe: Headstocks Installed!
Harrison Thomson: Installation of headstocks to pier via crane lift
Harrison Thomson: Road safety furniture installation, lowering of bunting to allow for crane access
PRELIMS - Construction Setup Totals 60.00(percentage)
13.00 23.50
PRELIMS - Preliminaries
1.00 Preliminaries 2 Dec2019
2 Dec2019
2 Dec2019
70.00(percentage)
132.00
Danah Crichton: Leveling cross beams
Rhys (Rhys) Janssen: Getting SWMS signed
Lee McCann: Ensuring all heads are accounted for prior to the day.
Alexander (Alex) Ibarra: Pre-start meeting preparing for the day
1.011 Staff Overheads 2 Dec2019
2 Dec2019
6 Dec2019
20.00(percentage)
13.00 25.00
Doris Tang: Lunch & Learn presented by Alex: indigenous cultural learning
Rory O'Keeffe: We're back in front!
PRELIMS - Preliminaries Totals 90.00(percentage)
13.00 157.00
☐ ☐ ☐
Site ReportConstructionarium 2019
Page 1 of 22
STAGE A - Bridge Stage A - LHS Endspan
4.3414 Connect Deck to Frame with Bolts 3 Dec2019
4 Dec2019
4 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
4.3313 Connect Deck to Frame with Bolts 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
4.3415 Install Last Frame 4 Dec2019
4 Dec2019
4 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
4.3411 Install Permanent & Temp Bracing 3 Dec2019
3 Dec2019
4 Dec2019
4 Dec2019
50.00(percentage)
100.00(percentage)
4.3516 Lift Final Component into Place and Install 4 Dec2019
4 Dec2019
4 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
STAGE A - Bridge Stage A - LHS Endspan Totals 350.00(percentage)
500.00(percentage)
STAGE A - Construction Setup
3.313 Prepare Prop for Stage A 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
3.315 Secure Stage A & Prop 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
3.311 Survey Headstock 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
3.312 Temporary Works For Stage A 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
3.314 Wooden Temporary Beams in Place for Stage A 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
STAGE A - Construction Setup Totals 500.00(percentage)
STAGE B - Bridge Stage B - RHS Endspan
5.00 Bridge Stage B - RHS Endspan 4 Dec2019
4 Dec2019
4 Dec2019
74.50 74.50
Michael (Gunny) Gunn: Rory confirming how good of a job we did today $$$
Rhys (Rhys) Janssen: Stage A and B lifted into position, some bolts torqued, need quality check on the 5/12/19 to ensure are bolts are tightened
Saurabh Bokde: Big crane is here.
Rory O'Keeffe: Second Major Lift! Great progress today, congratulations to PM Danah!
Shaghayegh Balali: Connect bracing with bolts using wrench
Harrison Thomson: Stage b completed, needs to undergo inspection before lifting into position
Shaghayegh Balali: Stage B
Alexander (Alex) Ibarra: first section lift
Alexander (Alex) Ibarra: second lift successfully complete
Narayanan Krishnan: stage B set up
Humza Aijaz: Client delays
Rhys (Rhys) Janssen: Abutment B headstock ready to install
Humza Aijaz: Indirect staff members working hard as they sip on their Chai Latte
Harrison Thomson: Installation of Cross bracing
Humza Aijaz: Temp bracing
Rhys (Rhys) Janssen: Connecting side trusses to deck frame
Harrison Thomson: Movement of second steel truss for Stage B
Boris Tusevljak: Simultaneous A and B stick build
Narayanan Krishnan: Set up of stage B
Doris Tang: Lollipop traffic control road closure
Humza Aijaz: Temp works in progress
Saurabh Bokde: Lift 1 - Day 2 construction
Saurabh Bokde: Implementing TMP
Doris Tang: Day 6 (build day 3) 8am toolbox meeting- roles for each person- what we’re working on- safety SWMS
Saurabh Bokde: Pre-start day 3 construction
Site ReportConstructionarium 2019
Page 2 of 22
5.4313 Connect Deck to LHS Frame with Bolts 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.438 Connect Deck to RHS Frame with Bolts 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.4414 Connect Timber Deck to Frame with Bolts 3 Dec2019
4 Dec2019
4 Dec2019
5.4415 Install Last Frame 4 Dec2019
4 Dec2019
4 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.4411 Install Permanent & Temp Bracing 3 Dec2019
4 Dec2019
4 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.4516 Lift Final Component into Place and Install 4 Dec2019
4 Dec2019
4 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.426 Lift Stage B Deck to Assembly Area 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.4312 Lift Stage B Left Frame to Assembly Area 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.437 Lift Stage B Right Frame to Assembly Area 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.4310 Prop Left Frame to Concrete Block 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
5.439 Prop Right Frame to Concrete Block 3 Dec2019
4 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
STAGE B - Bridge Stage B - RHS Endspan Totals 1000.00(percentage)
1000.00(percentage)
74.50 74.50
STAGE B - Construction Setup
3.413 Prepare Prop for Stage B 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.415 Secure Stage B & Prop 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.411 Sign Off Headstocks 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.412 Temporary Works for Stage B 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.414 Wooden Temporary Beams in Place for Stage B 3 Dec2019
3 Dec2019
3 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
STAGE B - Construction Setup Totals 500.00(percentage)
500.00(percentage)
STAGE C - Bridge Stage C - Middle Section
6.5313 Connect Deck to LHS Frame with Bolts 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.538 Connect Deck to RHS Frame with Bolts 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.5411 Install Permanent & Temp Bracing 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.526 Lift Stage C Deck to Assembly Area 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.5312 Lift Stage C Left Frame to Assembly Area 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.537 Lift Stage C Right Frame to Assembly Area 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.5310 Prop Left Frame to Concrete Block 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
6.539 Prop Right Frame to Concrete Block 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
STAGE C - Bridge Stage C - Middle Section Totals 800.00(percentage)
800.00(percentage)
STAGE C - Construction Setup
3.511 Install Headstock 5 Dec2019
3 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.513 Prepare Prop for Stage C 4 Dec2019
3 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.515 Secure Stage C & Prop 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.512 Temporary Works for Stage C 4 Dec2019
3 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
3.514 Wooden Temporary Beams in Place for Stage C 5 Dec2019
4 Dec2019
5 Dec2019
4 Dec2019
100.00(percentage)
100.00(percentage)
STAGE C - Construction Setup Totals 500.00(percentage)
500.00(percentage)
Site ReportConstructionarium 2019
Page 3 of 22
EventsEvent Event Type Event Name
EventExpected
FinishRelatedActivity
Related Activity Name Status EstimatedLabour
EstimatedDuration
PRELIMS - Construction Setup
1 Delay - Client Delay from Crane availability 3 Dec2019
3.00 Construction Setup started
STAGE B - Bridge Stage B - RHS Endspan
2 Delay - Client Site Tour from CTC 4 Dec2019
5.00 Bridge Stage B - RHSEndspan
open
Boris Tusevljak: Site tour start at 1015
Site ReportConstructionarium 2019
Page 4 of 22
Appendix A - Photos
Activity 5.00: Bridge Stage B - RHS Endspan: Rory confirminghow good of a job we did today $$$
Activity 5.00: Bridge Stage B - RHS Endspan: Stage A and Blifted into position, some bolts torqued, need quality check onthe 5/12/19 to ensure are bolts are tightened
Activity 4.00: Bridge Stage A - LHS Endspan: First section liftonto headstocks
Activity 5.00: Bridge Stage B - RHS Endspan: Big crane ishere.
Activity 4.00: Bridge Stage A - LHS Endspan: Indigenouslectures Activity 4.00: Bridge Stage A - LHS Endspan: It’s ready
Site ReportConstructionarium 2019
Page 5 of 22
Activity 5.00: Bridge Stage B - RHS Endspan: Second MajorLift! Great progress today, congratulations to PM Danah!
Activity 4.00: Bridge Stage A - LHS Endspan: 25T perfect forthe job!
Activity 4.00: Bridge Stage A - LHS Endspan: InstallationActivity 4.00: Bridge Stage A - LHS Endspan: But first let metake a selfie
Activity 4.00: Bridge Stage A - LHS Endspan: Commencementof lift into place Activity 4.00: Bridge Stage A - LHS Endspan: First stage lift
Site ReportConstructionarium 2019
Page 6 of 22
Activity 4.00: Bridge Stage A - LHS Endspan: Preparation forpart A lift
Activity 3.00: Construction Setup: Head stocks at correctheights and torqued down
Activity 6.00: Bridge Stage C - Middle Section: Proppingsection C Activity 6.00: Bridge Stage C - Middle Section: Lifting
Activity 1.00: Preliminaries: Leveling cross beamsActivity 4.00: Bridge Stage A - LHS Endspan: Flooring sectionA
Site ReportConstructionarium 2019
Page 7 of 22
Activity 3.00: Construction Setup: Headstocks installed andlevelling process continuing
Activity 6.00: Bridge Stage C - Middle Section: First Deckinglift complete
Activity 3.00: Construction Setup: Headstock inActivity 4.00: Bridge Stage A - LHS Endspan: BracingInstalled!
Activity 4.00: Bridge Stage A - LHS Endspan: Quality check Activity 4.00: Bridge Stage A - LHS Endspan: Scaffolding work
Site ReportConstructionarium 2019
Page 8 of 22
Activity 1.011: Staff Overheads: Lunch & Learn presented byAlex: indigenous cultural learning
Activity 4.00: Bridge Stage A - LHS Endspan: Ex changemanager turned project controls leader reminding us to takephotos of everything
Activity 5.00: Bridge Stage B - RHS Endspan: Connectbracing with bolts using wrench
Activity 5.00: Bridge Stage B - RHS Endspan: Stage bcompleted, needs to undergo inspection before lifting intoposition
Activity 4.00: Bridge Stage A - LHS Endspan: Filed tripActivity 4.00: Bridge Stage A - LHS Endspan: LHS floor beingprepared for installation into final position
Site ReportConstructionarium 2019
Page 9 of 22
Activity 4.00: Bridge Stage A - LHS Endspan: LHS bracingcomplete
Activity 4.00: Bridge Stage A - LHS Endspan: LHS headstocklowered and leveled Awaiting bolt down
Activity 5.00: Bridge Stage B - RHS Endspan: Stage BActivity 4.00: Bridge Stage A - LHS Endspan: Adjustment ofheadstock height to level (LHS A)
Activity 4.00: Bridge Stage A - LHS Endspan: Cross beamsLHS (a&b) lowered in place
Activity 4.00: Bridge Stage A - LHS Endspan: Task cardmanual handling and levelling signed for all workersassociated
Site ReportConstructionarium 2019
Page 10 of 22
Activity 3.00: Construction Setup: Headstocks Installed!Activity 4.00: Bridge Stage A - LHS Endspan: Final bolts beingtightened on LHS
Activity 5.00: Bridge Stage B - RHS Endspan: first section liftActivity 3.00: Construction Setup: Installation of headstocks topier via crane lift
Activity 5.00: Bridge Stage B - RHS Endspan: second liftsuccessfully complete Activity 5.00: Bridge Stage B - RHS Endspan: stage B set up
Site ReportConstructionarium 2019
Page 11 of 22
Event 2: Site Tour from CTC: Site tour start at 1015 Activity 5.00: Bridge Stage B - RHS Endspan: Client delays
Activity 4.00: Bridge Stage A - LHS Endspan: Stage A almostcompleted and looking good
Activity 5.00: Bridge Stage B - RHS Endspan: Abutment Bheadstock ready to install
Activity 5.00: Bridge Stage B - RHS Endspan: Indirect staffmembers working hard as they sip on their Chai Latte Activity 4.00: Bridge Stage A - LHS Endspan: Slow and steady
Site ReportConstructionarium 2019
Page 12 of 22
Activity 4.00: Bridge Stage A - LHS Endspan: Traffic controllerActivity 5.00: Bridge Stage B - RHS Endspan: Installation ofCross bracing
Activity 1.011: Staff Overheads: We're back in front! Activity 5.00: Bridge Stage B - RHS Endspan: Temp bracing
Activity 5.00: Bridge Stage B - RHS Endspan: Connectingside trusses to deck frame
Activity 4.00: Bridge Stage A - LHS Endspan: Michael fixingthe bracing, lack of wrench availavility noted as materialsmanager.
Site ReportConstructionarium 2019
Page 13 of 22
Activity 5.00: Bridge Stage B - RHS Endspan: Movement ofsecond steel truss for Stage B
Activity 5.00: Bridge Stage B - RHS Endspan: Simultaneous Aand B stick build
Activity 5.00: Bridge Stage B - RHS Endspan: Simultaneous Aand B stick build Activity 4.00: Bridge Stage A - LHS Endspan: Quality check
Activity 4.00: Bridge Stage A - LHS Endspan: Heat expansionor misalignment
Activity 5.00: Bridge Stage B - RHS Endspan: Set up of stageB
Site ReportConstructionarium 2019
Page 14 of 22
Activity 5.00: Bridge Stage B - RHS Endspan: Lollipop trafficcontrol road closure
Activity 4.00: Bridge Stage A - LHS Endspan: Completedsurveying @8:49 hours
Activity 5.00: Bridge Stage B - RHS Endspan: Temp works inprogress
Activity 5.00: Bridge Stage B - RHS Endspan: Lift 1 - Day 2construction
Activity 3.00: Construction Setup: Road safety furnitureinstallation, lowering of bunting to allow for crane access
Activity 4.00: Bridge Stage A - LHS Endspan: Traffic setupcompleted @8:30 hours
Site ReportConstructionarium 2019
Page 15 of 22
Activity 5.00: Bridge Stage B - RHS Endspan: ImplementingTMP
Activity 5.00: Bridge Stage B - RHS Endspan: Day 6 (buildday 3) 8am toolbox meeting - roles for each person - whatwe’re working on - safety SWMS
Activity 5.00: Bridge Stage B - RHS Endspan: Pre-start day 3construction Activity 1.00: Preliminaries: Getting SWMS signed
Activity 1.00: Preliminaries: Ensuring all heads are accountedfor prior to the day.
Activity 1.00: Preliminaries: Pre-start meeting preparing for theday
Site ReportConstructionarium 2019
Page 16 of 22
Supervisor: Wed, 04 Dec 2019
Appendix B - Timesheets
Name Work Role Usage Code Work Allocation Hours Approval
Alexander (Alex) Ibarra (Team 1)
General Labourer N 3.00 - Construction Setup 4.00
N 5.00 - Bridge Stage B - RHS Endspan 3.50
Total Hours 7.50
Ammar Abdurrahman (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Boris Tusevljak (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Danah Crichton (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 3.00 - Construction Setup 1.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
N 6.00 - Bridge Stage C - Middle Section 1.00
Total Hours 8.00
Daniel Oberthur (Team 1)
General Labourer LWP 1.011 - Staff Overheads 8.00
Total Hours 8.00
Doris Tang (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 3.00 - Construction Setup 4.00
N 5.00 - Bridge Stage B - RHS Endspan 3.50
Total Hours 8.00
Harrison Thomson (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Humza Aijaz (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 5.00 - Bridge Stage B - RHS Endspan 5.50
N 6.00 - Bridge Stage C - Middle Section 2.00
Total Hours 8.00
Lee McCann (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 3.50
N 6.00 - Bridge Stage C - Middle Section 2.00
Total Hours 8.00
Michael (Gunny) Gunn (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Narayanan Krishnan (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Rhys (Rhys) Janssen (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 3.00 - Construction Setup 4.00
N 5.00 - Bridge Stage B - RHS Endspan 3.50
Total Hours 8.00
Rory O'Keeffe (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 3.50
N 6.00 - Bridge Stage C - Middle Section 2.00
Total Hours 8.00
Saurabh Bokde General Labourer N 2 - Site Tour from CTC 0.50
Site ReportConstructionarium 2019
Page 17 of 22
(Team 1) N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Shaghayegh Balali (Team 1)
General Labourer N 2 - Site Tour from CTC 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Theja Dilshan WijesingheMinigammana Vidanelage (Team 1)
General Labourer N 2.00 - Procurement 0.50
N 4.00 - Bridge Stage A - LHS Endspan 2.00
N 5.00 - Bridge Stage B - RHS Endspan 5.50
Total Hours 8.00
Trent Day (Team 1)
General Labourer LWP 1.011 - Staff Overheads 5.00
N 4.00 - Bridge Stage A - LHS Endspan 1.00
N 5.00 - Bridge Stage B - RHS Endspan 2.00
Total Hours 8.00
Site ReportConstructionarium 2019
Page 18 of 22
Appendix C - Equipment UsageThere is no timesheet data for any equipment items on this day.
Site ReportConstructionarium 2019
Page 19 of 22
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1
Appendix D - DocketsDocket: TEA-F-AA-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
AmmarAbdurrahman
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ConstructionManager
2: Site Tour from CTC 0.50 hours
AmmarAbdurrahman
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ConstructionManager
4.00: Bridge Stage A - LHSEndspan
2.00 hours
AmmarAbdurrahman
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ConstructionManager
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-AI-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
Alexander (Alex)Ibarra
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
3.00: Construction Setup 4.00 hours
Alexander (Alex)Ibarra
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
3.50 hours
Docket: TEA-F-BT-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
BorisTusevljak
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal Project ControlsManager
2: Site Tour from CTC 0.50 hours
BorisTusevljak
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal Project ControlsManager
4.00: Bridge Stage A - LHSEndspan
2.00 hours
BorisTusevljak
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal Project ControlsManager
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-DC-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
DanahCrichton
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ProjectManager
2: Site Tour from CTC 0.50 hours
DanahCrichton
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ProjectManager
3.00: Construction Setup 1.00 hours
DanahCrichton
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ProjectManager
5.00: Bridge Stage B - RHSEndspan
5.50 hours
DanahCrichton
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal ProjectManager
6.00: Bridge Stage C - MiddleSection
1.00 hours
Docket: TEA-F-HA-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
HumzaAijaz
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
2: Site Tour from CTC 0.50 hours
HumzaAijaz
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
5.50 hours
HumzaAijaz
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
6.00: Bridge Stage C - MiddleSection
2.00 hours
Docket: TEA-F-HT-20191204-1
Site ReportConstructionarium 2019
Page 20 of 22
Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
HarrisonThomson
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal TrafficController
2: Site Tour from CTC 0.50 hours
HarrisonThomson
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal TrafficController
4.00: Bridge Stage A - LHSEndspan
2.00 hours
HarrisonThomson
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal TrafficController
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-LM-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
LeeMcCann
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
2: Site Tour from CTC 0.50 hours
LeeMcCann
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
4.00: Bridge Stage A - LHSEndspan
2.00 hours
LeeMcCann
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
3.50 hours
LeeMcCann
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
6.00: Bridge Stage C - MiddleSection
2.00 hours
Docket: TEA-F-MG-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
Michael (Gunny)Gunn
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
2: Site Tour from CTC 0.50 hours
Michael (Gunny)Gunn
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
4.00: Bridge Stage A - LHSEndspan
2.00 hours
Michael (Gunny)Gunn
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-NK-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
NarayananKrishnan
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal EngineeringManager
2: Site Tour from CTC 0.50 hours
NarayananKrishnan
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal EngineeringManager
4.00: Bridge Stage A - LHSEndspan
2.00 hours
NarayananKrishnan
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal EngineeringManager
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-RJ-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
Rhys (Rhys)Janssen
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
2: Site Tour from CTC 0.50 hours
Rhys (Rhys)Janssen
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
3.00: Construction Setup 4.00 hours
Rhys (Rhys)Janssen
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
3.50 hours
Docket: TEA-F-RO-20191204-1Docket Date: 4 Dec 2019
Resource Role Type Work Start End Break Usage Rate Code Work Reference Amount UoM
Site ReportConstructionarium 2019
Page 21 of 22
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Company: Team 1Status: Entered
Date Time Time Code
RoryO'Keeffe
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
2: Site Tour from CTC 0.50 hours
RoryO'Keeffe
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
4.00: Bridge Stage A - LHSEndspan
2.00 hours
RoryO'Keeffe
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
3.50 hours
RoryO'Keeffe
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
6.00: Bridge Stage C - MiddleSection
2.00 hours
Docket: TEA-F-SB-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
ShaghayeghBalali
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
2: Site Tour from CTC 0.50 hours
ShaghayeghBalali
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
4.00: Bridge Stage A - LHSEndspan
2.00 hours
ShaghayeghBalali
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-SB-20191204-2Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
SaurabhBokde
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal Project ServicesManager
2: Site Tour from CTC 0.50 hours
SaurabhBokde
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal Project ServicesManager
4.00: Bridge Stage A - LHSEndspan
2.00 hours
SaurabhBokde
GeneralLabourer
Person 4 Dec2019
8:00 am 5:00 pm 1.00 Normal Project ServicesManager
5.00: Bridge Stage B - RHSEndspan
5.50 hours
Docket: TEA-F-TD-20191204-1Docket Date: 4 Dec 2019
Resource Role Type Work Date StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
Trent Day GeneralLabourer
Person 4 Dec2019
8:00 am 12:00 pm 1.00 Normal GeneralLabour
4.00: Bridge Stage A - LHSEndspan
1.00 hours
Trent Day GeneralLabourer
Person 4 Dec2019
8:00 am 12:00 pm 1.00 Normal GeneralLabour
5.00: Bridge Stage B - RHSEndspan
2.00 hours
Docket: TEA-F-TM-20191204-1Docket Date: 4 Dec 2019
Resource Role Type WorkDate
StartTime
EndTime
Break UsageCode
Rate Code Work Reference Amount UoM
Theja Dilshan WijesingheMinigammana Vidanelage
GeneralLabourer
Person 4 Dec2019
8:00am
5:00pm
1.00 Normal GeneralLabour
2.00: Procurement 0.50 hours
Theja Dilshan WijesingheMinigammana Vidanelage
GeneralLabourer
Person 4 Dec2019
8:00am
5:00pm
1.00 Normal GeneralLabour
4.00: Bridge Stage A -LHS Endspan
2.00 hours
Theja Dilshan WijesingheMinigammana Vidanelage
GeneralLabourer
Person 4 Dec2019
8:00am
5:00pm
1.00 Normal GeneralLabour
5.00: Bridge Stage B -RHS Endspan
5.50 hours
Site ReportConstructionarium 2019