100 pmi questions
TRANSCRIPT
-
8/9/2019 100 PMI Questions
1/71
Question No : 101
In your project, some of the benefits of a well-constructed scope statement are all the follo
Choice 1 Proides a documented basis for ma!ing future project decisions
Choice 2 "eelops common understanding of project scope among sta!eholders
Choice 3 Proides !nowledge of projectjustification, delierables, and objecties
Choice 4 Proides a basis for time and costestimates
Correct Choice : 4
Justification :
#or! brea!down structure $which is an output from Create #%& process' helps in proidinestimates(
)ptions *, +, and are benefits of a well-constructed scope statement(
Reference: Pstudy(com commentsQuestion No : 102
.ou are the project manager of a high priority project, which will re/uire more than *,000 tehumanresource planning,you would li!e to applyproen principles to shorten the time neeplan and ma!e it effectie( In this conte1t, you will benefit if you consult an e1pert in the fiel
Choice 1 2etwor!ing and team formation
Choice 2 3uman resource theory
Choice 3 )rgani4ational theory
Choice 4 Project organi4ation charts
Correct Choice : 3
Justification :
)rgani4ational theory proides information regarding the way in which people, teams, and oEffectie use of this information can shorten the amount of time, cost, and effort needed to
http://www.pmstudy.com/2011PMP/sim1/101ans.asphttp://www.pmstudy.com/2011PMP/sim1/101ans.asphttp://www.pmstudy.com/2011PMP/sim1/101ans.asphttp://www.pmstudy.com/2011PMP/sim1/101ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/101ans.asphttp://www.pmstudy.com/2011PMP/sim1/101ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/102ans.asphttp://www.pmstudy.com/2011PMP/sim1/101ans.asp -
8/9/2019 100 PMI Questions
2/71
planning outputs and improe the li!elihood that the planning will be effectie(
Question No : 103
The following is the data for a CPI5 project you are managing:
Target cost is 6 *00,00078ctual cost is 6 90,000Target fee is 6 +0,0007a1imum fee is 6 +,0007&haring ratio is ;0:+,000
Correct Choice : 3
Justification:
Target cost$TC' ? 6 *00,000Target fee $T5' ? 6 +0,000a1imum fee ? 6 +,000&haring ratio?;0:
-
8/9/2019 100 PMI Questions
3/71
Choice 2 Cost baseline
Choice 3 &chedule management plan
Choice 4
&chedule data
Correct Choice : 4
Justification :
Elements of the project management plan that may be updated include, but are not limited management plan, and cost baseline( &chedule data is the project document that gets updthe Control&chedule process(
Reference: P%)FG Huide 5ourth Edition, Page *;9
Question No : 169
http://www.pmstudy.com/2011PMP/sim1/168ans.asphttp://www.pmstudy.com/2011PMP/sim1/168ans.asphttp://www.pmstudy.com/2011PMP/sim1/168ans.asphttp://www.pmstudy.com/2011PMP/sim1/168ans.asphttp://www.pmstudy.com/2011PMP/sim1/168ans.asphttp://www.pmstudy.com/2011PMP/sim1/168ans.asp -
8/9/2019 100 PMI Questions
47/71
In your project, you are defining and documentingsta!eholdersJ needs to meet the project obje
ery important as the projectJs success is directly influenced by the care ta!en during this proc
be ery diligent when you:
Choice 1 Identify &ta!eholders
Choice 2 Collect Be/uirements
Choice 3 Create Project Charter
Choice 4 Create Project anagementPlan
Correct Choice : 2
Justification :
Collect Be/uirements is the process of defining and documenting sta!eholdersJ needs to meet
projectJs success is directly influenced by the care ta!en in capturing and managing project an
Be/uirements include the /uantified and documented needs and e1pectations of the sponsor, sta!eholders(
Beference: P%)FG Huide 5ourth Edition, Page *0
Question No : 170
.our sponsor beliees in N&8BTN goals for ealuating the objectiesor goals for your projec
includes all the following !eywords EXCEPT:
Choice 1 &ignificant
Choice 2 easurable
Choice 3 Beleant
http://www.pmstudy.com/2011PMP/sim1/169ans.asphttp://www.pmstudy.com/2011PMP/sim1/169ans.asphttp://www.pmstudy.com/2011PMP/sim1/170ans.asphttp://www.pmstudy.com/2011PMP/sim1/169ans.asphttp://www.pmstudy.com/2011PMP/sim1/169ans.asphttp://www.pmstudy.com/2011PMP/sim1/170ans.asp -
8/9/2019 100 PMI Questions
48/71
Choice 4 8ttainable
Correct Choice : 1
Justification:
&8BT Hoals: The performance goals should be &8BT- &pecific, easurable, 8chieable
specific(
Beference: Pstudy(com comments
Question No : 171
8 documented direction to perform an actiity that can reduce the probabilityof negatie conse
project ris!s is called:
Choice 1 Correctieaction
Choice 2 Preentie action
Choice 3 "efect repair
Choice 4 Bis! mitigation
Correct Choice : 2
Justification :
Preentie action: 8 documented direction to perform an actiity that can reduce the probabilit
associated with project ris!s(
http://www.pmstudy.com/2011PMP/sim1/170ans.asphttp://www.pmstudy.com/2011PMP/sim1/170ans.asphttp://www.pmstudy.com/2011PMP/sim1/171ans.asphttp://www.pmstudy.com/2011PMP/sim1/171ans.asphttp://www.pmstudy.com/2011PMP/sim1/170ans.asphttp://www.pmstudy.com/2011PMP/sim1/170ans.asphttp://www.pmstudy.com/2011PMP/sim1/171ans.asphttp://www.pmstudy.com/2011PMP/sim1/171ans.asp -
8/9/2019 100 PMI Questions
49/71
Reference: P%)FG Huide 5ourth Edition, page >+
Question No : 172
.ou are monitoring the technical performance of your website( Past data on the number of use
you forecast how your websitewould perform if the number of users increases in the future( Th
Choice 1 "esign of e1periments
Choice 2 Control chart
Choice 3 )rgani4ational process assets
Choice 4 Trend analysis
Correct Choice : 4
Justification :
Trend analysis is performed using run charts and inoles mathematical techni/ues to forecasthistorical results( Trend analysis is often used to monitor technical performance, i(e(, how many
identified, and how many remain uncorrected and cost and schedule performance, i(e(, how ma
werecompletedwith significant ariances(
Reference: P%)FG Huide 5ourth Edition, Page +** and +*+
Question No : 173
#hich of the following is not true about conducting procurement negotiations=
Choice 1 Theproject managershould be the lead negotiator(
Choice 2 &ubjects coered may include responsibilities, authority to ma!e changes, applicable
http://www.pmstudy.com/2011PMP/sim1/172ans.asphttp://www.pmstudy.com/2011PMP/sim1/172ans.asphttp://www.pmstudy.com/2011PMP/sim1/172ans.asphttp://www.pmstudy.com/2011PMP/sim1/173ans.asphttp://www.pmstudy.com/2011PMP/sim1/173ans.asphttp://www.pmstudy.com/2011PMP/sim1/172ans.asphttp://www.pmstudy.com/2011PMP/sim1/172ans.asphttp://www.pmstudy.com/2011PMP/sim1/172ans.asphttp://www.pmstudy.com/2011PMP/sim1/173ans.asp -
8/9/2019 100 PMI Questions
50/71
Choice 35or comple1 procurement items, contract negotiationscan be an independent proces
own(
Choice 4 2egotiations should clarify the structure, re/uirements, and other terms of the purcha
Correct Choice : 1
Justification :
The project manager may not be the lead negotiator on procurements( The project manager an
projectmanagementteam may be present during negotiations to proide assistance, and if nee
projectSs technical, /uality, and management re/uirements(
Reference: P%)FG Huide 5ourth Edition, Page 2umber:
Question No : 174
8s a project manager, you are re/uired to produce project performance reports on a regular ba
atCompletionis 6M0,000, planned alue is 6*00,000, schedule ariance is 60,000, and cost
percentage complete and estimate at completion in your project=
Choice 1 *9, 6 00,000
Choice 2 *M(, 6
-
8/9/2019 100 PMI Questions
51/71
Justification :
&L ? EL K PL
EL ? &L D PL
? 0,000 D *00,000
? *0,000
CL? EL K 8C
8C?EL- CL ?*0,000 K 0,000
? 90,000
PercentageComplete? EL%8C 1 *00
? *0,000M0,0001*00?*M(
CPI?EL8C
? *0,00090,000?*(;+
E8C? 8C D $%8C-EL'CPI
? 90,000 D $M0,000 K *0,000'*(;+
? 90,000D$;+0,000'*(;+
?
-
8/9/2019 100 PMI Questions
52/71
Correct Choice : 1
Justification:
Identify Bis!s happens during Planning Process Hroup(
Reference: P%)FG Huide 5ourth Edition, Page 2umber:
-
8/9/2019 100 PMI Questions
53/71
Reference: P%)FG Huide 5ourth Edition, Page *;+
Question No : 177
#hen your company buyscomputersfrom "ell, you also pay e1tra for a three year warranty w
manufacturing defects will be ta!en care of by "ell( The ris! response strategy used is:
Choice 1 E1ploit
Choice 2 8oid
Choice 3 itigate
Choice 4 Transfer
Correct Choice : 4
Justification :
Transfer( Bis! transfer re/uires shifting some or all of the negatie impact of a threat, along wita third partyV Transference tools can be /uite dierse and include, but are not limited to, the u
bonds, warranties, guarantees, etc(
Beference: P%)FG Huide 5ourth Edition, Page 0
Question No : 178
In your project, you are performing seeral actions to e1ecute the project managementplan and to com
project scope statement( .ou will be inoled in:
Choice 1 Ta!ing correctie or preentie action to control the project performance
http://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/178ans.asphttp://www.pmstudy.com/2011PMP/sim1/178ans.asphttp://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/177ans.asphttp://www.pmstudy.com/2011PMP/sim1/178ans.asphttp://www.pmstudy.com/2011PMP/sim1/178ans.asp -
8/9/2019 100 PMI Questions
54/71
Choice 2 &ettling or closing any contract agreement established for the project
Choice 3 Creating a document that will formally authori4e the project
Choice 4 Collecting wor! performance information about the completion status of the delierables and w
Correct Choice : 4
Justification :
)ption
-
8/9/2019 100 PMI Questions
55/71
Choice 3 5ailure costs
Choice 4 Performance costs
Correct Choice : 3
Justification :
5ailure costs $cost of non-conformance' include costs to rewor! products, components, or proc
costs of warranty wor! and waste7 and costs due to loss of reputation(
Reference: P%)FG Huide 5ourth Edition, Page
-
8/9/2019 100 PMI Questions
56/71
Reference: P%)FG Huide 5ourth Edition, Page
Question No : 181
5or your project, find the to-complete performance inde1 $TCPI' based on the gien dat
%udget at completionof the project ? M00,000
Cost ariance of the project ? +,000Earned alueof the project ? +00,000
Estimate to Completehas now been reised to
Choice 2 *(*M;
Choice 3 *(
Choice 4 -*(
Correct Choice : 2
Justification :
CL?EL-8C
8C?EL-CL
?+00,000-+,000
?*M,000
Question No : 182
.ou are a project manager( .ou hae completedthe project( #hile reiewing the costs, you obbudget was utili4ed for actiities performed in processes relating to one particular process grou
Choice 1 Planning ProcessHroup
http://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/182ans.asphttp://www.pmstudy.com/2011PMP/sim1/182ans.asphttp://www.pmstudy.com/2011PMP/sim1/182ans.asphttp://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/181ans.asphttp://www.pmstudy.com/2011PMP/sim1/182ans.asphttp://www.pmstudy.com/2011PMP/sim1/182ans.asphttp://www.pmstudy.com/2011PMP/sim1/182ans.asp -
8/9/2019 100 PMI Questions
57/71
Choice 2 E1ecuting Process Hroup
Choice 3 onitoring and Controlling Process Hroup
Choice 4 Closing Process Hroup
Correct Choice : 2
Justification :
8 large portion of the projectJs budget will be e1pended in performing the E1ecuting Process H
Reference: P%)FG Huide 5ourth Edition, Page ;
Question No : 183
In your project you had planned to hae Tas!s 8, % W C completed already, howeer tas!s 8, %
and 0 completerespectiely( The alue of each day of wor! is 6*00( Qsing the 0-*00 Bule an
calculate the &PI:
Tas!s 8, %, C, and " hae duration of , ,
-
8/9/2019 100 PMI Questions
58/71
Justification :
To calculate &PI, you just use the e/uation &PI ? ELPL( In this case EL would ? days( %ecause we a
can only say that Tas! 8 counts towards earned alue$alue of wor! completed'( #e say that Tas! 8 ha
$or 600', and Tas! % only counts as 0 $een though it is currently at 90 completionbecause of the
for this tas!'( PL would be *+ days $or 6*+00' because we planned to hae Tas!s 8, % W C done by thi
0(+( #e are behind schedule( This logic would also wor! if they gae you 66 alues in the table instea
Beference: Pstudy comments
Question No : 184
.our project teamhad a meeting with the customer $during Lerify &cope process' for getting fo
projectdelierables( This actiity refers to which process group=
Choice 1 Closing
Choice 2 E1ecuting
Choice 3 Planning
Choice 4 onitoring and Controlling
CorrectChoice : 4
Justification :
Lerify &cope is done as part of onitoring and Controlling Process Hroup(
Reference: P%)FG Huide 5ourth Edition, Page 2umber:;0, figure -9
Question No : 185
8ccording to cClellandJs theory, managers are not motiated by:
http://www.pmstudy.com/2011PMP/sim1/183ans.asphttp://www.pmstudy.com/2011PMP/sim1/183ans.asphttp://www.pmstudy.com/2011PMP/sim1/183ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asphttp://www.pmstudy.com/2011PMP/sim1/183ans.asphttp://www.pmstudy.com/2011PMP/sim1/183ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asphttp://www.pmstudy.com/2011PMP/sim1/184ans.asp -
8/9/2019 100 PMI Questions
59/71
Choice 1 2eed for achieement
Choice 2 2eed for power
Choice 3 2eed for affiliation
Choice 4 2eed for recognition
CorrectChoice : 4
Justification:
8ccording to "aid cClellandJs theory $also called 8chieement otiation Theory', mana
- 2eed for achieement
- 2eed for power
- 2eed for affiliation
Beference: Pstudy(com comments
Question No : 186
8ssuming that the critical path of your project has duration of ten days, which of the following c
timelines=
Choice 1If the project has one critical path, you are able to decrease the duration of the critica
new tool(
Choice 2 If the project has one critical path, you hae to increase the duration of the critical pat
Choice 3If the project has two critical paths, you are able to decrease the duration of one critic
new tool(
Choice 4 If the project has two critical paths, you hae to increase the duration of one critical pa
http://www.pmstudy.com/2011PMP/sim1/185ans.asphttp://www.pmstudy.com/2011PMP/sim1/185ans.asphttp://www.pmstudy.com/2011PMP/sim1/185ans.asphttp://www.pmstudy.com/2011PMP/sim1/185ans.asphttp://www.pmstudy.com/2011PMP/sim1/185ans.asphttp://www.pmstudy.com/2011PMP/sim1/185ans.asphttp://www.pmstudy.com/2011PMP/sim1/185ans.asp -
8/9/2019 100 PMI Questions
60/71
Correct Choice : 3
Justification:
)ption*: This will decrease the duration of the project by * day because the critical path decre
)ption +: This will increase the duration of the project by * day, because the critical path increa
)ption : This will not decrease the duration of the project( This is because een if one critical p
the other critical path retains the same duration of days7 so the oerall duration of the project
)ption
-
8/9/2019 100 PMI Questions
61/71
deeloped and always prior to the start of planning(
Reference: P%)FG Huide 5ourth Edition, Page 2umber:M
Pstudy(com comments: The project manager is responsible for the whole project from initiatio
Question No : 188
8 ris! that remains after ris! responses hae been implemented is referred to as:
Choice 1 &econdary ris!
Choice 2 Besidualris!
Choice 3 5allbac! Plan
Choice 4 8ccepted ris!
CorrectChoice : 2
Justification:
Besidual Bis!( 8 ris! that remains after ris! responses hae been implemented(
Beference: P%)FG Huide 5ourth Edition, Page
-
8/9/2019 100 PMI Questions
62/71
Choice 2 )rgani4ation hierarchy
Choice 3
Besource brea!down structure
Choice 4 Project brea!down structure
Correct Choice : 3
Justification :
Besource brea!down structure $B%&' is a hierarchical structure of resources by resource categ
resource leeling schedules and to deelop resource-limited schedules, and which may be use
projecthuman resourceassignments(
Beference: P%)FG Huide 5ourth Edition, Page
-
8/9/2019 100 PMI Questions
63/71
Justification :
JPerformance reiewsJ is a techni/ue used in Control &chedule process( It measures, compare
performance(
Reference: P%)FG Huide 5ourth Edition, Page *;0, figure ;-* and Page *;+
Pstudy(com comments:
)ption *$&chedule 2etwor! 8nalysis' is used in "eelop &chedule
)ption +$Pareto Chart' is used in Perform Ouality Control
)ption
-
8/9/2019 100 PMI Questions
64/71
-
8/9/2019 100 PMI Questions
65/71
Choice 2.our organi4ation is going through a slac! period, and some resources, who can prod
underutili4ed(
Choice 3The item under consideration is a proprietary or business critical product which is a p
company(
Choice 4The item under consideration is not part of your core business, but your company has
product in-house, if re/uired(
Correct Choice : 4
Justification :
If it is a non core item, it may ma!e sense to consider outsourcingas an option, as it may be c
house(
Reference: Pstudy(com comments
Question No : 194
In your project, you hae tocompletebuilding a prototype before testing can begin( This is an e
Choice 1 andatory dependency
Choice 2 "iscretionary dependency
Choice 3 E1ternal dependency
Choice 4 Preferred logic
http://www.pmstudy.com/2011PMP/sim1/193ans.asphttp://www.pmstudy.com/2011PMP/sim1/193ans.asphttp://www.pmstudy.com/2011PMP/sim1/193ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/193ans.asphttp://www.pmstudy.com/2011PMP/sim1/193ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asp -
8/9/2019 100 PMI Questions
66/71
CorrectChoice : 1
Justification :
andatory dependencies are those that are contractually re/uired or inherent in the nature of tdependencies often inole physical limitations, such as on aconstruction projectwhere it is im
superstructure until after the foundation has been built, or on an electronics project, where a pr
can be tested(
Reference: P%)FG Huide 5ourth Edition, Page *>
Question No : 195
.ou hae fifteen members in your project team( .ou hae called for a project status meeting wi
been too many sidebar conersations and arguments( 8s a result, you hae achieed nothing s
achiee orderliness in the meeting ne1t time, you should:
Choice 1 "ecrease the number of people in the meeting
Choice 2 Publish a meeting agenda
Choice 3 Ensure that you control the channels of communication
Choice 4 Hie incenties to team members for conforming to desired meeting norms
Correct Choice : 2
Justification :
Effectie Information "istribution includes((( meeting managementtechni/ues, preparing an ag
Reference: P%)FG Huide 5ourth Edition, Page +9
Pstudy(com comments:In order to conduct the meeting in an organi4ed way, you will hae to
meeting managementtechni/ues of preparing and publishing an agenda and to deal with confli
http://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/195ans.asphttp://www.pmstudy.com/2011PMP/sim1/195ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/194ans.asphttp://www.pmstudy.com/2011PMP/sim1/195ans.asphttp://www.pmstudy.com/2011PMP/sim1/195ans.asp -
8/9/2019 100 PMI Questions
67/71
)ption+: Preparing and publishing a meeting agenda is the best way to ensure that meetings a
fashion(
)ption *: "ecreasing the number of people may mean that we will not hae the re/uired sta!e
)ption : Controlling the channels of communication is not possible as the number of channels
determined by the formula 2 A $2-*' +(
)ption
-
8/9/2019 100 PMI Questions
68/71
Choice 2 Het approal from all your project team members
Choice 3
Try to preent this change, since you thin! it is unnecessary
Choice 4 Issue a change re/uest
Correct Choice : 1
Justification :
In this conte1t, the ne1t step to ta!e is to re-baseline the project scope, cost, and time(
)ption +: This is not re/uired, since the project fundingis not proided by the team members( I
)ption: This is not possible, since the change has already been approed by the change con
)ption
-
8/9/2019 100 PMI Questions
69/71
Choice 3 5
Choice 4
C
CorrectChoice : 3
Justification:
et us calculate the critical path for the diagram:
"ifferent possible paths are:
8%C"3: D < D D ? *
8%CH3: D < D + D < ? *
8EC"3: + D D D ? *
8ECH3: + D D + D < ? *
8E5H3: + D + D < D < ? *+
There are four critical paths, and all the tas!s that lie on the critical paths hae 4ero floa
any critical path and has a non-4ero float(
Reference: Pstudy(com comments
Question No : 199
#hich of the following is not the responsibility of a PP certificant=
Choice 1 Ensuring that there is no conflict of interest that can compromise the legitimate intere
Choice 2 Ensuring that technical specifications are appropriately defined
http://www.pmstudy.com/2011PMP/sim1/198ans.asphttp://www.pmstudy.com/2011PMP/sim1/198ans.asphttp://www.pmstudy.com/2011PMP/sim1/198ans.asphttp://www.pmstudy.com/2011PMP/sim1/198ans.asphttp://www.pmstudy.com/2011PMP/sim1/198ans.asphttp://www.pmstudy.com/2011PMP/sim1/198ans.asp -
8/9/2019 100 PMI Questions
70/71
Choice 3 "isseminatingPICode of Ethics and Professional Conduct to other PI members
Choice 4Cooperating with PI concerning ethics iolation related to PI andPP Certificatio
information
Correct Choice : 2
Justification :
The project manager need not be a technical e1pert /ualified to determine the accuracy of technical sp
8ll other responsibilities stated in options *, , and < find a place in the PI Code of Ethics and Profess
Reference: Pstudy(com comments
Question No : 200
#hich cost estimatingtechni/ue costs the least and saes the most time=
Choice 1 Parametric estimating
Choice 2 %ottom-up estimating
Choice 3 8nalogous estimating
Choice 4 Three-point estimates
CorrectChoice : 3
Justification:
8nalogous cost estimating is generally less costly and time consuming than other techni/ues
http://www.pmstudy.com/2011PMP/sim1/199ans.asphttp://www.pmstudy.com/2011PMP/sim1/199ans.asphttp://www.pmstudy.com/2011PMP/sim1/199ans.asphttp://www.pmstudy.com/2011PMP/sim1/199ans.asphttp://www.pmstudy.com/2011PMP/sim1/200ans.asphttp://www.pmstudy.com/2011PMP/sim1/200ans.asphttp://www.pmstudy.com/2011PMP/sim1/200ans.asphttp://www.pmstudy.com/2011PMP/sim1/199ans.asphttp://www.pmstudy.com/2011PMP/sim1/199ans.asphttp://www.pmstudy.com/2011PMP/sim1/200ans.asphttp://www.pmstudy.com/2011PMP/sim1/200ans.asphttp://www.pmstudy.com/2011PMP/sim1/200ans.asp -
8/9/2019 100 PMI Questions
71/71
accurate(
Reference: P%)FG Huide 5ourth Edition, Page 2umber:*M+