Shop Drawing Review Process

1. Log submittal with office clerk. Office clerk inputs job into “TES Shop Drawing Log” program.

2. Office Clerk scans drawings and places scan under shop drawing directory with received date, then returns drawings to reviewer.

3. Shop drawings must be processed within 5 business days

TES Engineering Review Process

04/12/23 2

Page 3: 120328 shop drawing review

X

Shop Drawing Review Process

TES Shop Drawing Program

04/12/23 3

Page 4: 120328 shop drawing review

X

Shop Drawing Review Process

1. Reviewer checks a hard copy against relevant construction documents.

2. TES is not responsible for means and methods.

3. Shop drawings received that were not specified to be submitted for review should be marked “not reviewed” on commentary submittal sheet.

4. Highlight conformance, mark red differences in red.

5. Discuss differences with PM and whether they are acceptable

Review Process

04/12/23 4

Page 5: 120328 shop drawing review

X

Shop Drawing Review Process

Check Conformance with design concept and the information shown

in the construction documents.

Do Not Check Accuracy or completeness of details, such as quantities,

dimensions, weights or gauges, fabrication processes, construction means or methods, coordination of the work with other trades or construction safety precautions, all of which are the sole responsibility of the contractor.

What to check and what not to check

04/12/23 5

Page 6: 120328 shop drawing review

X

Shop Drawing Review Process

Shop Drawing Review FormLocation: T:\Project Management

04/12/23 6

Page 7: 120328 shop drawing review

X

Shop Drawing Review Process

Shop Drawing Review FormLocation: T:\Project Management

04/12/23 7

Page 8: 120328 shop drawing review

X

Shop Drawing Review Process

1. After PM review, complete Shop Drawing Review Form to be sent back with shop drawings.

2. PM performs final review of shop drawing review form, corrections made, PM signs.

3. Review form copy sent with each copy of shop drawing being sent back (pdf if sent electronically).

4. Transmittal filled out and attached.

5. Inform OC of completion.

Shop Drawing Review Form

04/12/23 8

Page 9: 120328 shop drawing review

X

Shop Drawing Review Process

• Shop Drawings – drawings, diagrams, schedules, and other data specially prepared for work by the contractor

• Product data – illustrations, schedules, performance charts, instructions, brochures, diagrams, other information furnished by contractor

• Samples – physical examples which illustrate materials, equipment, workmanship

Types of Submittals

04/12/23 9

Page 10: 120328 shop drawing review

X

Shop Drawing Review Process

Routing of Submittals

04/12/23 10

Page 11: 120328 shop drawing review

X

Shop Drawing Review Process

• Submittals are prepared by contractor, architect prepares contract documents.

• Purpose of submittals is to demonstrate the way by which the contractor proposes to conform to the design concept.

• Contractor has reviewed and approved submittals.

• Submittals are required to do the work.

Contactor’s Role in Submittals

04/12/23 11

Page 12: 120328 shop drawing review

X

Shop Drawing Review Process

• Architect reviews and approves or takes appropriate action upon contractor’s submittals.

• Limited role of architect.

Additional Recommendations

• Log and track each submittal.

• Do not review submittals not required by the contract documents.

Architect’s Role in Submittals

04/12/23 12

Page 13: 120328 shop drawing review

X

Shop Drawing Review Process

• Inadequate submittal time in contract

• No submittal Schedule

• Late submittals

• Forced substitutions

Problems that Arise with Submittals

04/12/23 13

Page 14: 120328 shop drawing review

CRITICAL PATH METHOD (CPM)CONCLUSION . . .